QUESTION

A new well of a reservoir is placed on a production for a long test. The initial reservoir
pressure was measured using Drill Stem Test (DST) at 4325 psi. The well is produced at
a constant rate of 4000 b/d for 288 hours, and then shut-in for build-up for 72 hours.

The pressure data is given in Data*. Other estimated data are:

 = 0.23
 = 1.0 cp
rw = 0.3 ft
h = 33 ft
Bo = 1.4
Ct = 12.6 x 10-6 (psi)-1
Sw = 0.2

Analyze the results using both manual calculation and welltest software. Compare the
results.

No NAMA DATA
1 ABDUL ADL QAYYUM AL'NAFI BIN OTHMAN Data 01
2 ABDUL KHALIQ BIN ABDUL KADIR Data 02
3 AHMAD NUR IHSAN BIN MUHAMMAD NUR Data 03
4 ALVINE ACHAN ANAK JAIN Data 04
5 AWANG SHAHRIR BIN AWANG SULAIMAN Data 05
6 CHRISTOPHER LEONG HOCK TIONG Data 06
7 DARIUS TALU AUGUSTINUS KUDA Data 07
8 ELEANOR UNYANG HERBERT Data 08
9 FAZRUL AZHAR BIN ABDUL HARDY Data 09
10 GARA AK ANDREW EMPINI Data 10
11 GEOFFREY ALVIN AK TENNENT Data 11
12 JORGE-MYKEL GTIUMISS Data 12
13 KENNETH ANAK CLEMENT ETAN Data 13
14 MAZLIN BIN ALI Data 14
15 MOHAMMAD SAHREEN BIN ABDULLAH Data 15
16 MOHD MUAZZAM BIN SULIMAN Data 16
17 MOSHIN BIN ABD HALIM Data 17
18 NANDONG ANAK PANTING Data 18
19 NICHOLAS GAWAN ANAK TADONG Data 19
20 NOORAZILA BINTI ABDUL RAHIM Data 20
21 NOORIZAN BINTI HAMDAN Data 21
22 SITI BAIZURAH BINTI A.RAHMAN Data 22
23 ZAIRIL BIN ALI Data 23
24 SAPAWI OSMAN Data 24

Please submit by 20 April 2019.

You might also like