Dr. Martin E. Lipinski, Chair Department of Civil Engineering The University of Memphis Memphis, TN 38152

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

Reinforced Concrete Beam Project Reinforced Concrete Beam Project

ƒ Entry to the Herff College of Engineering 2003 ƒ Each team should prepare a full formal technical
Reinforced Concrete Competition requires:
report with a 5-minute presentation supported
by recent and relevant research
ƒ Letters of interest and writing plan are due Tuesday
March 18, 2003 to:
ƒ Final presentation and reports are due Sunday,
Dr. Martin E. Lipinski, Chair
Department of Civil Engineering April 13, 2003 -- 6:00 p.m. Engineering
The University of Memphis Auditorium
Memphis, TN 38152

ƒ A research-based progress report must be submitted to


Dr. Charles V. Camp, Contest Coordinator, by April 1,
2003.

Reinforced Concrete Beam Project Reinforced Concrete Beam Project

ƒ The cost of each beam will be estimated using


ƒ The objective of this project is to develop the the following data:
strongest reinforced concrete beam as
measured by the strength-to-weight ratio Material Cost

(SWR). Portland Type I cement $150/ton

Coarse aggregate $15/ton

Ultimate Load (lbs )


SWR =
Fine aggregate $12/ton

Beam Weight (lbs ) Steel reinforcement $500/ton

Admixtures - water reducer $10/gal

ƒ The strength of the beam is the ultimate load Admixture - silica flume $800/ton

recorded during testing. Fiber reinforcement Market value (see Dr. Camp)

Reinforced Concrete Beam Project Reinforced Concrete Beam Project


ƒ The concrete beam must be 30 inches long, 6 inches
ƒ A cost factor will be computed as follows: height, and have a prismatic cross-section.
Applied Load

$2.00
Cost Factor =
Beam Cost ($) width
6 in.
8 in. 8 in.

ƒ Using your cost factor, an adjusted SWR


computed as follows: 24 in.

30 in.

ƒ In designing the reinforced concrete beam groups may


SWRAdjusted = SWR × Cost Factor consider the use of admixtures, various types of
reinforcement, various types of cements and aggregates,
and non-rectangular cross-sections.

1
Reinforced Concrete Beam Project Reinforced Concrete Beam Project

ƒ The reinforced concrete beam problem poses ƒ The reinforced concrete beam project schedule:
several challenges to the student:
Date Activity
March 4-6 Introduction; concrete mix #1; concrete beam #1
1. selection of the shape and size of the cross-section
March 18 Letters of interest and writing plan
of the beam;
March 18-20
2. design of a concrete mix based on strength and Break mix #1 and beam #1; develop concrete beam #2

workability; March 25-27 Break mix #2 and beam #2; develop concrete beam #3

3. design of the reinforcement (type of reinforcement, April 1 Research-based progress report

amount, and position in the beam), and April 1-3 Break mix #3 and beam #3; develop final beam

4. the prediction of the SWR of the beam. April 8-10 Break final concrete beam

April 13 Reinforced concrete beam presentations - 6:00 p.m.

Reinforced Concrete Beam Project Reinforced Concrete Beam Project

ƒ The cost of steel may be estimated as follows: ƒ For example, if one #5 rebar in placed in
the beam the steel cost is estimated as:
As L  lb   $500   ton  Bar # Diameter (in) As (in2 )
Cost of steel =
Cost of steel =  490 ft 3   ton   2, 000 lb  1 0.125 0.0123

1,728 in
3
   
2
3
0.125
0.375
0.0245
0.11
ft
3
4 0.500 0.20 (0.31in 2 )(30in )  lb   $500   ton 
5 0.625 0.31 =  490 ft 3   ton   2, 000 lb 
1,728 in 3 
3
6 0.750 0.44
  
ƒ where As is the cross-sectional area of steel ft
7 0.875 0.60
8 1.000 0.79

rebars, L is the length of the steel rebars, and


9 1.128 1.00
10 1.270 1.27
11 1.410 1.56
= $0.66
490 lb/ft3 is the unit weight of steel.

Reinforced Concrete Beam Project Reinforced Concrete Beam Project

ƒ Consider the following mix for a yd3 of concrete ƒ The cost of the concrete required for a 4" by 6"
developed using the ACI mix design procedure. by 30" beam is estimated as:
Component Amount (lb)
4in (6in )30in  708 lb   $150   ton 
water 304 Cost of cement =  3   
1, 728in 3  27 ft   ton   2, 000 lb 
3

cement 708 ft
coarse aggregate 1,824 = $0.82
fine aggregate 1,131
4in (6in )30in  1,824 lb   $15   ton 
Cost of coarse aggregate =  3   
1,728 in 3  27 ft   ton   2, 000 lb 
3

ft

= $0.21

2
Reinforced Concrete Beam Project Reinforced Concrete Beam Project

ƒ The cost of the concrete required for a 4" by 6"


by 30" beam is estimated as: ƒ For example, if the unadjusted SWR for a beam
is 510 and the cost is $1.80, then the cost
Cost of fine aggregate =
4in (6in )30in  1,131 lb   $12   ton

 adjusted SWR is:
3   
1,728 in 3  27 ft   ton   2, 000 lb 
3

ft

= $0.10 SWRAdjusted = SWR × Cost Factor


The cost concrete is estimated as: $1.14
$2.00
The cost reinforced concrete beam is estimated SWRAdjusted = 510 × = 567
as: $1.80 $1.80

Reinforced Concrete Beam Project Reinforced Concrete Beam Project

Any questions?

You might also like