Professional Documents
Culture Documents
Lean Manufacturing Implementation Using Value Stream Mapping As A Tool
Lean Manufacturing Implementation Using Value Stream Mapping As A Tool
www.emeraldinsight.com/2040-4166.htm
LM
Lean manufacturing implementation
implementation using value using VSM
stream mapping as a tool
89
A case study from auto components industry
Received 30 April 2012
Naga Vamsi Krishna Jasti and Aditya Sharma Revised 25 March 2013
Department of Mechanical Engineering, 1 September 2013
Birla Institute of Technology and Science (BITS), Pilani, India Accepted 4 September 2013
Abstract
Purpose – Value stream mapping (VSM) is a lean manufacturing (LM) tool used for analyzing
material and information flow on a specific product family. The purpose of this article is to address the
importance of VSM in LM environment in an Indian auto components industry.
Design/methodology/approach – The case study approach has been used to show the
applicability and importance of VSM in an Indian auto components company, in which the current
state of manufacturing is mapped with the help of VSM symbols. According to the current state
mapping, the study conducted analysis and identifies the area of improvement needed in terms of
work in process, lead time and cycle time. The study further implemented kaizen on the current state
map and developed future state map while including these kaizens.
Findings – The study clearly shows that the VSM brings out the positive impact on process ratio,
TAKT time, process inventory level, line speed, total lead and process time and reduced man power. It
is helping the company in satisfying their customers with respect to quality, cost and delivery.
Research limitations/implications – The main limitation of the study is the confined focus on a
single industry. The case should be extended to other industries in order to support the findings and
for the purpose of the wider generalization.
Practical implications – The results obtained from the study will help other industries and sectors
to implement VSM in LM environment.
Originality/value – The article deals with a real case study, which shows application of VSM for
implementing lean principles.
Keywords Lean manufacturing, Case study, Kaizen, Auto components, Value stream mapping
Paper type Case study
1. Introduction
India is becoming one of the major automotive vehicle manufacturing hubs in the world.
The growth of automotive industry is around 14-17 percentage noticed in every year
(Sharma and Kodali, 2008). Before the year 1990, Indian automotive organizations were
comfortable with a protectionist economy. In last decade of twentieth century, many
of the world class manufacturing organizations started to transform their location
preference to India and China. Indian manufacturing originations are struggling to International Journal of Lean Six
achieve better productivity in comparison with other developing country organizations. Sigma
Vol. 5 No. 1, 2014
Indian manufacturing organizations’ productivity growth rate is around 5 percent pp. 89-116
that was very low compared to 7.31 percent for China, 9.45 percent for Singapore q Emerald Group Publishing Limited
2040-4166
and 8.65 percent for Pakistan (Upadhye et al., 2010). In the current era of global DOI 10.1108/IJLSS-04-2012-0002
IJLSS competitiveness, Indian manufacturing organizations are facing enormous pressure
5,1 from their customers to reduce cost and improve quality so as to win the market share
(Dangayach and Deshmukh, 2001). The aforementioned factors are pushing the
companies either to reduce or eliminate waste so as to increase their efficiency, which
brings out the products with less cost, better quality and less lead time (George, 2002).
Hence, lean principles are not just an option for Indian manufacturing companies, but a
90 necessity for their survival. “Lean” is a philosophy that aims at elimination of non-value
added activities from the process and it treats the activities that do not add value to the
customer requirement as waste (Bhasin and Burcher, 2006). The concept of lean
manufacturing (LM) is widely known to the companies globally. However, there is a lack
of conceptual and practical knowledge about lean principles, lean tools and techniques
and the ways for its implementation among the Indian manufacturing industries. LM is
gaining importance with the trend of cutting down cost and reducing waste to gain
competitive advantage in Indian manufacturing sector. Due to implementation of LM
principles many manufacturing industries across the world have cut down their cost of
the product in manufacturing phase as well as rising their profits, which is a motivating
factor for majority of the Indian manufacturing organizations and hence they started
to implement LM concepts in their organization (Anand and Kodali, 2008). It is just a
beginning phase of lean principles in Indian manufacturing scenario. The present
study tries to identify the adoptability of LM tool and its implementation approach in
Indian auto-component industry.
The study considered case study approach to show the significance of value stream
mapping (VSM) tool in auto-component industry. The case study approach is generally
used to check any tool applicability and generate the complex relationships between
various variables to propose new theories (Wacker, 1998). The present case study (auto
component) organization is one of the suppliers to the automobile original equipment
manufacturers (OEM). The growth of automobile sector has broadened that helps to
improve the scope of the auto component industries. The study has applied VSM in the
Indian auto components company, so as to demonstrate how it can be perform better in
operational activities after implementing VSM. From this exercise, it emerges that LM
can help Indian auto component industry to eliminate wastes, improve process
stability, maintain better inventory control, reduce associated costs and increase
production efficiency.
The structure of the paper is as follows: Section 2 deals with literature review on
VSM. Section 3 introduces the background of the company under the study. Section 4 is
devoted to research methodology adopted in the study. The subsequent Section 5
contains information about the case study implementation, kaizen events and the
related calculations. Finally, in Section 6, the results and the conclusion of the present
research are presented.
2. Literature review
In the present scenario, automobile industry is considered one of the prime manufacturing
industries across globe. This industry plays vital role in terms of change our most basic
ideas and thoughts of manufacturing activities (Womack and Jones, 1996). In 1950s,
Japanese manufacturing industries have struggled with shortage of financial resources,
man power resources, and less availability of space. In the same period, the customer
demand in terms of variety, quality and service were in its peak. To satisfy the customer
requirements with minimum resources was a huge task in front of Japanese LM
manufacturing industries. To achieve the same object, Eiji Toyoda and Taiichi Ohno implementation
have developed a new production system called “Toyota Production System” with
combination of the knowledge of master craftsmen and the concept of standardization using VSM
with the help of teamwork thought. With that Japanese manufacturing industries have
fulfilled and satisfied the customer requirements with minimum resources and attracted
the attention of the western manufacturing competitors. Krafcik (1988) has reviewed 91
Toyota production system and introduced the famous term “lean production (LP) system”.
The term LP initially got the popularity in western world with the book “The machine that
changed the World” written by Womack et al. (1990). Initially LM have projected as set of
principles, slowly converted as a manufacturing strategy and finally emerged as
manufacturing philosophy. The primary focus of LM philosophy is to reduce waste
activities from industry to enhance customer value and thus become more competitive
(Liker, 1998). Waste is an activity, which will not provide any value addition to the final
product or customer aspects (Russell and Taylor, 1999). According to Ohno’s, wastes could
be classified into seven categories. The seven categories of wastes are: over production,
waiting, transportation, inappropriate processing, unnecessary inventory, unnecessary
motions, and defects (Monden, 1993). The positive impact of LM principles in
manufacturing activities resulted that the principles have also applied across the product
development, supply chain management, administration activities (Womack and Jones,
1994). The benefits received by manufacturing industries with the implementation of LM
forced other sector industries like service, construction, health care and process industries
to implement LM principles in the respective organizations. In last two decades, many
studies like Jasti et al. (2012); Piercy and Rich (2009) have tried to use various tools,
techniques and principles to achieve excellence in the implementation of LM in various
organizations. Few researchers have proposed new elements of LM to implement in the
organization to get desired results (Anand and Kodali, 2010). Many researchers like
Pettersen (2009), Papadopoulou and Ozbayrak (2005) have performed review conceptually
on various aspects of LM.
Many researchers like Brown and Bessant (2003), Prince and Kay (2003),
Sharifi and Zhang (2001) started to argue agile manufacturing can provide better
results than LM due to its characteristics to respond promptly and efficiently as
per requirements of dynamic market place. Agile manufacturing is one of the
manufacturing strategies that rapidly entering the organizations and provide
solutions to the individual customer requirements. Where, LM provides high quality
products with low cost by elimination of waste to the customer in the manufacturing
processes (Maskell, 2001). Narasimhan et al. (2006) discussed agile manufacturing is
more useful manufacturing strategy in highly dynamic environments. But various
conditions of dynamic markets did not well-defined in the literature. However, the
same study also revealed that the performance perspective of agile organizations is
inferior to LM organizations. Hence, LM principles have strong base in literature and
have so many articles published in operations research journals as well as
implemented in many organizations to achieve excellence in manufacturing. LM uses
several tools and techniques like VSM, 5S, kaizen, total quality management (TQM),
kanbans, total preventive maintenance (TPM), poka yoke, etc. to identify and
remove the waste from any procedures (Shah and Ward, 2003, 2007; Singh and
Sharma, 2009).
IJLSS One of the main powerful tools used in LM is VSM (Abdulmalek and Rajgopal et al.,
5,1 2007; Braglia et al., 2006). Rother and Shook (1998) reported that wherever the product
is developing for customer, there should be a value stream. VSM is an important tool
that helps managers to understand the current operational conditions and recognize
improvement opportunities to improve the operational performance. VSM is a
language of symbol and is used as a technique for analyzing material and information
92 flow (Jones and Womack, 2000). It can be used within the factory in a particular
production family as well as beyond the boundaries of the organization. According to
Kalsaas (2002), VSM is a qualitative tool that reduces the inventory pipeline and leads
to reduction in throughput time. So far VSM has proved very effective in identifying
and eliminating waste. VSM is the technique that identifies all of the value-adding as
well as non-value-adding activities that materials are subjected to within the plant,
from raw material coming from the supplier into the plant converted to finished
product end-delivery to the customer (Rosentrater and Balamuralikrishna, 2006). It can
be implemented in any industry, to any activity and expanded downstream or
upstream (Seth et al., 2008). VSM has many sub-tools to carry out all the activities
involved in any system. Hines and Rich (1997) have proposed seven VSM tools that can
be effectively used – singularly or in combination, depending on the requirements of
the value stream.
The complex nature in manufacturing and business activities is mounting day by
day with that newer value stream tools are also emerging. It resulted that a huge
number of tools and techniques developed to fulfill different objectives and waste
reduction. Even though many researchers like New (1974, 1993), Forza et al. (1993),
Beesley (1994) and Jessop and Jones (1995) have used individual tools to identify
different value streams, regarding their overlapping nature and use much more
needs to be done. That is why newer classification and application areas are emerging.
Hines and Rich (1997) have proposed classification scheme about seven new mapping
tools that are: process activity mapping, supply-chain response matrix, production
variety funnel, quality filter mapping, demand amplification mapping, decision point
analysis and physical structure mapping. Pavnaskar et al. (2003) have proposed another
set of classification scheme for LM tools and allied. The classification scheme has
prepared with seven levels: system, object, operation, activity, resource, characteristic
and application. Each and every particular level has linked methodically. Hence the LM
tools and metrics, or manufacturing waste problems, have been classified in a
meaningful and systematical way. Lamming et al. (2000) have reported the classification
of supply networks using lean concepts. With that the application and scope of these
tools increases persistently to apply individually or in combination as per the value
streams requirements in diverse areas such as manufacturing, product development and
supply-chain management. Shen and Han (2006) mentioned about the VSM collaboration
tool and extended its application to connect value chains in both customer and supplier
ends. Numerous researchers have studied implementation of VSM in various phases
from collecting raw material to delivery finished products. Hines (1999) has presented
work on supply chain improvement using VSM tool. Brunt (2000) has made an attempt
to implement VSM across the whole supply chain. McDonald et al. (2002) have reported
an application of VSM enhanced through simulation on a particular production line in
one of the manufacturing industries. Lummus et al. (2006) have used VSM in physician’s
clinic to reduce waiting time of the patient as well as stress on the staff. Lian and
Van Landeghem (2007) have analyzed the effects of LM using a VSM-based simulation LM
generator. Lasa et al. (2008) have implemented VSM tool successfully in plastic industry implementation
and improved productivity, lead time, process inventory, etc. Solding and Gullander (2009)
have presented a simulation-based dynamic VSM to analyze more complex systems. using VSM
Only a few case studies have been reported from Indian manufacturing industry on
VSM application. Seth and Gupta (2005) describes VSM as the complete process of
mapping the raw material and information flows of all the processes in a value stream 93
that starts from suppliers to production process and distribution to the end customer.
Sahoo et al. (2008) have implemented VSM tool in forging industry and improved
in all aspects of production system. Seth et al. (2008) have presented a case study on
VSM application in cottonseed oil industry and reduced their inventory as well as
increased the productivity of the organization. Vinodh et al. (2010) have reported a case
study on implementation of VSM in Indian automobile industry. The same study
reported that the effective implementation of VSM resulted in drastic reduction of idle
time, total cycle time, work-in-process inventory and defects of the products. Singh et al.
(2010) have implemented the VSM tool in one of the Indian manufacturing industries,
which clearly substantiates that lead time, process time, and work-in-process
inventory can be reduced drastically and productivity of the operator can be increased
more than 40 percent. Anand and Kodali (2011) have reported a case study using
simulator to overcome the shortcomings of the VSM physical method. However, there
are only few research case study articles published in the area of Indian auto
component industry. So, the present research tries to attempt how the VSM can be put
into practice in the auto components industry to improve the performance in all aspects
of production line.
Work cell
Table I.
VSM process symbols
Shipments Inventory
Table II.
VSM material symbols
4. Research methodology
The research methodology is based on case study strategy (Eisenhardt, 1989; Yin, 1994).
The importance of case research strategy discussed, carried out and published by
Voss et al. (2002). The same study revealed that case study strategy not only provides
answers to how and why questions, but it is also helpful to build up new concepts and
thoughts, and it can be useful to test the theory and refinement (Meredith, 1998;
IJLSS Snow and Thomas, 1994). The breakthrough concepts and theories in the field of
5,1 operational management have been developed from the field research. Many researchers
have discussed that the case study research helps not only enhance the theory and also
useful to the researchers to improve themselves (Dangayach and Deshmukh, 2001;
Voss et al., 2002). The main objective of study is to verify the application of VSM to
improve the production system performance. The research has been performed in
96 several stages. In the first stage, the study conducted literature review on LM and VSM.
In the second stage, performed study on existing production lines in the manufacturing
organization. The study has identified a particular crank shaft production line.
Currently, the organization has four similar production lines with the capacity of
producing around 20,000 crankshafts per annum. The production line has been
manufacturing crankshafts to a particular major customer. The demand from the
customer was very high but the organization was not able to deliver their customer
requirements. The main reason to select the machining production line was producing
less than planned capacity production. Hence the study concentrated on the particular
machining production line to improve overall productivity, quality and performance of
the manufacturing line.
In the third stage, the study collected the data related to the machining production
line, based on which, the study prepared current state of VSM. In the fourth stage, the
study performed analysis on current state of VSM and proposed various improvements
to the organization. Before making final improvements, the researchers of the study
also communicated production line leaders and managers to find out hurdles to
implement proposed improvements and work plan to implement future state of VSM in
the production line. Finally, the future state of VSM has been drawn-based upon
feedback given by organization executives. The future state of VSM contains all
possible improvements and suggestions proposed by the present study. The future
state of VSM has been implemented in the production line and performed data
collection for next six months to finalize the future state of VSM, which was later
successfully incorporated in the production line. Figure 1 shows the complete set of
VSM steps in flow chart. Once the current state mapping has been plotted, the analysis
of the production process had to be carried out for the scope of improvement. One of the
goals of LM is to achieve more value-added activities by cutting down the number of
wastes in the whole operation cycle. The study has suggested eliminating the wastes in
processes with the help of kaizen events to look for the opportunities where it can be
applied to cut down or check wasted time, lead time and thus making the complete
process streamlined. These findings of the study are supported by the findings of
Rosentrater and Balamuralikrishna (2006).
5. Case study
In order to perform the study, a team was formed with two members. The two members
have academic as well as consultancy experience in the organizations. To assist these
two team members, the organization provided one employee act as facilitator from the
manufacturing line under study (Rother and Shook, 1998). The main objective of
the facilitators is to provide required information as well as support to the team
members to conduct meetings with employees of the organization. The team member
spent one and a half month in the manufacturing line (crankshaft) to understand the
complete process. The study helped the team to understand the system followed by the
LM
Selection of implementation
product family
using VSM
97
Current state
mapping
Analyze the
waste &
possible
kaizen events
Future state
mapping
Make the
work plan & Figure 1.
achieve it Flowchart showing five
acheive steps of VSM
crankshaft production line completely. The operations division of the auto industry
is the major department that generally focuses on machining of crankshafts.
The supplier unit supplies the un-machined crankshafts to the operations division.
The operations division performs the primary inspection on few specifications
and performs necessary machining operations on crank shaft to make final product.
Table V shows the sequence of all the operations in operations division. The sequential
process flow diagram executed in the operations division is shown in Figure 2.
The study performed the earlier mentioned five steps as guidelines to implement VSM
tools and thus, carried out the following activities:
.
defined the current situation;
.
carry through the process flow;
.
current state mapping;
.
identified the wastes in the production cycle and NVA activities;
.
categorized them in seven kinds of wastes and kaizen;
.
challenged the necessity of each operation/activity;
5,1
98
IJLSS
Table V.
The sequence of
operations division
operations executed in
Operation No. Operation description Work center Machine type
(continued)
Figure 3.
Process flow chart of the
current state
Crank movement to M/c O-7 2.4 LM
Gear and flange end tapping and drilling on M/c O-7 14.2
Crank movement to inspection table 2
implementation
Gauge inspection 2.5 using VSM
Loading the crank on track 1.5
Crank travel on track 1
Crank movement to M/c O-8 1.5
Flange end finish boring on M/c O-8 Manual 101
Gauge inspection ---
Storage on pallet for next operation ---
Pallet movement to M/c O-10 34.5
Flange end finish grinding on M/c O-10 6.52
Gauge inspection ---
Storage on pallet for next operation ---
Pallet movement to M/c O-11 32.69
Gear end finish grinding on M/c O-11 6.1
Crank movement to M/c O-12 1
Magnetic (non-destructive) testing on M/c O-12 3.9
Crank movement to M/c O-13 1
Keyway milling on M/c O-13 7.6
Gauge inspection ---
Loading the crank on track 1
Crank travel on track 7
Crank movement to M/c O-14 2
Dynamic balancing on M/c O-14 9.6
Loading the crank on deburr table 1
Oil holes polish and webs deburr 4
Loading the crank on track 1
Crank travel on track 2
Crank movement to M/c O-16 1
Super-finishing of Jr. pin and thrust face on M/c O-
19.3
16
Loading the crank on inspection table 1
End inspection ---
Lapping and Polish on lathe machine 3.5
Loading the crank on track 1
Crank travel on track 3.5
Crank movement to M/c O-20 1
Final washing on M/c O-20 4.5
Crank movement to inspection table 1
Audit inspection ---
Storage on pallet for next operation Manual
Forklifts required for crank movement Manual
Loading the crank on track for final packaging 58
TOTAL 275.6 147.94
9 Figure 3.
5.1.1 Calculations from the current state map. Theory of constraint concept highlights
that every system has at least one constraint. Otherwise the organization will
make unlimited profits (Goldratt, 1990). In the present section of study, the bottleneck
operation in the production line is pin finish grinding on a machine M/c O-6,
which takes the maximum time of 21.7 min. The study identified the time spent
for non-value-added activities, which was 1,584.1 min per day. The reason for
5,1
102
IJLSS
Figure 4.
Current state map of
machining production line
PRODUCTION CONTROL
Crankshaft Machining Sceduling Order (as per
Sales Plan)
Orders
Production Monitoring
Planning
(Line Manager)
Facing &
Daily Shipment Schedule
Geometric Planning
centring
1
Shipping&
Despatch
I
Turning Module
Pin milling & finish
jour. turning Operation 11 Operation 12 Operation 13 Operation 14 Operation 15 Operation 16 Operation 17
Bottleneck time = 21.70
3 Magnetic (non- Super-finishing of
destructive) Oil holes polish & journals, pin &
Keyway milling Dynamic balancing End inspection Final washing Total process time =
inspection webs deburr thrust face
3 147.94 min.
I 2 2 2 2 2 2
Planning Cycle time: 3.90 Total lead time =
Cycle time: 7.60 Cycle time: 9.60 Cycle time: 4.00 Cycle time: 19.30 Cycle time: Manual Cycle time: 4.50
I I I I I I I 1,584 min.
Shot blasting
C/O time: 1 hr C/O time: 16 hrs C/O time: 4 hrs C/O time: --- C/O time: 4 hrs C/O time: --- C/O time: 8 hrs Process invetory = 73 Nos.
1
A B
High chance of
getting the Operator is doing
Operator takes 3-4 Distance travelled = 1,347 m
1 No. One operator is 1 No. job without 3 Nos. 1 No. Not enough space 1 No. 1 No. 1 No. washing twice. First
I involved in 3 carrying out for carrying min. to change the with kerosene for oil
Drilling Module operations that may Long distance from out this show of thrust hole cleaning & then
flange the last operation journal.
lead to operator operation. regular.
end finish boring.
fatigue
Web tapping & No inspection
drilling table
Process ratio = (Total
27.1 27.1 65.1 21.7 21.7 21.7 21.7 process time/Total lead
3 time)
309. 7.60 9.60 4.00 19.30 Manual 4.50 = (147.94/1,584)
= 9.34 %
I IH Module
Tempering &
induction
hardening 3
Operation 1 Operation 2 Operation 3 Operation 4 Operation 5 Operation 6 Operation 7 Operation 8 Operation 9 Operation 10
Both end rough Thrust journal Gear end & flange
Initial inspection boring & re- Semi-finish Thrust journal Pin finish grinding Flange end finish Flange end finish Gear end finish
turning of flange finish grinding finish grinding end tapping and grinding grinding
centering boring
3 3 outer dia 3 3 3 3 drilling 2 2 2 2
Cycle time: 2.55 Cycle time: Cycle time: 8.50 Cycle time:
I Cycle time: 20.47 Manual Cycle time: 8.50 Cycle time: 21.70 Cycle time : 14.20 Cycle time: 6.52 Cycle time: 6.10
I I I I I I I Manual I I
C/O time: --- C/O time: 8 hrs C/O time: 1 hr C/O time: 6 hrs
C/O time: 6 hrs C/O time: 12 hrs C/O time : 3 hrs C/O time : ..... C/O time: 7 hrs C/O time: 7 hrs
A
Manual butting is As it is performed
Manual operation Longest
manually operation It requires operator Long distance from
Job length is more carried out in gear Bottleneck backtracking
FI F O 11 Nos. 1 No. cycle time varies 8 Nos. Heavy oil leakages 5 Nos. Heavy oil leakages 10 Nos. 5 Nos. to bend upto 1-2 m 12 Nos. therfore it has less 7 Nos. 5 Nos. the last operation
than the inspection end counter dia. are observed are observed operation accuracy. Second of up to 36 m on
from operator for loading & thus require one
table length Lack of on machine on machine on the line backtracking on the the line. Third
to operator. unloading casual always
safety guards line Backtracking
First Backtracking
104
IJLSS
Table VI.
List of kaizens
O-2 Both end rough boring and re- Due to absence of door, burrs falls out Safety door should be introduced
centering of the machine
Manual butting is carried out in gear Auto indexing and automated butting
end counter diameter should be provided
O-3 Semi-finish turning of flange As it is performed manually In fixing it with re-centering
outer diameter operation cycle time varies from operation in M/c O-2 will save one
operator to operator operation
O-4 Other journal finish grinding Long distance of around 11-12 m from Change the layout to minimize this
the last operation distance
Table adjustment is done manually Couplings should be provided to
leading to operator fatigue adjust the table length
O-5 Thrust journal finish grinding Metal to metal contact is present on Table or proper rack should be
gauges leading to less accuracy, provided to keep the gauges
due to absence of rack or table to keep
gauges
O-6 Pin finish grinding Absence of track for the crank Track should be laid down between
movement from last operation the two operations
Gauges may get damaged as they are Rubber sheet or wooden tray should
kept on metal table be introduced
Accumulation of inventory due to Line speed and process time should
unmatched process time be set properly
Plastic cover of tackle found Proper hook should be used with
damaged, that may damage or leave provision of replacing the cover
mark on journal diameter periodically
Locating tooling and gauges is time Need for proper storing mechanism
consuming
Half bearing clamping pads are of Soft metal clamping pads should be
hard metal that may damage the used to reduce chances of damage
ground journal diameter
(continued)
M/c No. Operation Problem found Proposed changes KAIZEN
P Q C D S M
105
LM
Table VI.
5,1
106
IJLSS
Table VI.
M/c No. Operation Problem found Proposed changes KAIZEN
P Q C D S M
O-11 Gear end finish grinding Long distance from the last operation Change the layout to minimize
this distance
One operator is involved in three Need for thorough operation splitting
operations that may lead to operator
fatigue
No inspection table for dimensions Inspection table introduced
No proper place to keep the gauges. Rubber sheet or wooden tray should
Gauges may get damaged as they are be introduced
kept on outer table
O-13 Keyway milling High chance of getting the job Need to introduce sensors and nylon
without carrying out flange end finish pusher of flange end bore size in order
boring to avoid missing operation
O-14 Dynamic balancing Long distance from the last operation Change the layout to minimize this
distance
O-16 Super-finishing of journals, pin Magnetic separator is not functioning Need to repair it
and thrust face properly
Operator takes 3-4 min to change the Third arm should be introduced on
show of thrust journal the machine
Oil sucking and recycling mechanism Need to replace or repair it
not functioning properly
Absence of holder for emery paper Place holder should be introduced
Cotton and waste papers pile up on Need for dustbins to dump the waste
machine paper and cottons
Mix up of papers of pins and journals Visual indicators introduced
Oily and slippery platform Need for meshed type platform
Absence of light for visual display Proper lights for better visibility
modifications suggestion on current state of map based on analysis conducted in the LM
earlier section of the study. It also has the kaizen burst around the processes indicating implementation
improvement. The company XYZ has implemented the changes as proposed by the
present research. After applying those suggestions, the total number of activities came using VSM
down from 68 to 61 activities. Figure 6 shows the process flow chart of the future state.
The future state map is shown in Figure 7.
5.3.1 Calculations for the future state map. In the study the constraint of production 107
line is bottleneck operation of pin finish grinding on machine M/c o-6. After
implementing all proposed kaizens in the machining operations line, the research
identified that the bottleneck operation time remained same as that of current state
map for the pin finish grinding occurring on machine M/c O-6 and the value is 21.7 min.
The total process time had reduced to 142.18 min. The future state of map (Figure 8)
clearly shows that the sum of all the non-value-added time is 412.3 min that is equals to
total lead time. On implementing the changes as prescribed by the team, the production
increased to 40 units per day. The future state of map TAKT time was calculated and it
is 27.731 , 28 min.
6.2 Conclusion
Indian automobile industry is one of the fast developing industries with growth rate of
14-18 percent per year. However, the major automobile organizations are facing
problems to fulfill the customer requirements and to stay competition with the global
Morale, 2
Production,
11
Safety, 9 Production
Quality
Cost
Delivery
Safety
Morale Figure 5.
The distribution
Delivery, 4 of improvement
events (total of 39 events)
Quality, 9 in terms of PQCDSM
Cost, 4
IJLSS
5,1
Process Flow Chart 2: Future State
Activity Present Future Savings
Work: Manufacturing of the crankshaft
Operation 15 14 1
108
Transport 36 33 3
Method: Present/Future Delay 1 1 0
Inspection 11 11 0
Storage 5 2 3
Distance Time
Operation
(m) (min.)
Material input 75
Loading the crank on inspection table 1.5
Gauge inspection 2.55
Both end rough boring and re-centering on
20.47
M/c O-2
Crank movement to M/c O-4 3.2
Other journal finish grinding on M/c O-4 13
Crank movement to inspection table 1
Gauge inspection ---
Loading the crank on track 1
Crank travel on track 3
Crank movement to M/c O-5 1
Thrust journal finish grinding on M/c O-5 8.5
Crank movement to inspection table 1
Gauge inspection ---
Crank movement to M/c O-6 2.5
Pin finish grinding on M/c O-6 21.7
Crank movement to inspection table 1
Gauge inspection ---
Loading the crank on track 1
Crank travel on track 3
Crank movement to M/c O-7 1.3
Gear and flange end tapping and drilling on
14.2
M/c O-7
(continued)
Figure 6.
Process flow chart of the
future state
LM
implementation
using VSM
Crank movement to inspection table 1
Gauge inspection 2.5
Loading the crank on track 0.5
Crank travel on track 3 109
Crank movement to M/c O-8 0.5
Flange end finish boring on M/c O-8 Manual
Gauge inspection ---
Crank movement to M/c O-10 1.5
Flange end finish grinding on M/c O-10 6.52
Gauge inspection ---
Crank movement to M/c O-11 4
Gear end finish grinding on M/c O-11 6.1
Crank movement to M/c O-12 1
Magnetic (non-destructive) testing on M/c
3.9
O-12
Crank movement to M/c O-13 1
Keyway milling on M/c O-13 7.6
Gauge inspection ---
Loading the crank on track 1
Crank travel on track 5
Crank movement to M/c O-14 2
Dynamic balancing on M/c O-14 9.1
Loading the crank on deburr table 1
Oil holes polish and webs deburr 4
Loading the crank on track 1
Crank travel on track 2
Crank movement to M/c O-16 1
Super-finishing of Jr. pin and thrust face
on M/c O-16 14.24
Loading the crank on inspection table 1
End inspection ---
Lapping and Polish on lathe machine 3.3
Loading the crank on track 1
Crank travel on track 3.5
Crank movement to M/c O-20 1
Final washing on M/c O-20 4.5
Crank movement to inspection table 1
Audit inspection ---
Storage on pallet for next operation Manual
Forklifts required for crank movement Manual
Loading the crank on track for final packaging 56
TOTAL 184.5 142.18
Figure 6.
IJLSS
5,1
110
Figure 7.
The sample of
improvement
implemented in the
production line
players in terms of cost, quality and services. Some of the notable automobile
industries are able to meet the customer requirements in the aspect of delivery time
and demand. One of the reasons why most of the Indian manufacturing organizations
or auto-component industries are still not able to implement advanced manufacturing
systems (like LM) is due to lack of knowledge and information. Hence most of the
auto-component industries are spending much of their resources to fulfill the
customer requirements. The objective of the research is to check the application of
VSM in Indian auto component industry. The study clearly shows that VSM is
important LM tool, which can be used to identify various wastes in the
production system of Indian manufacturing industries. The study results clearly
proved that all types of lean wastes can be identified with the help of VSM. Currently, it
is in improvement phase and giving commitment for its uninterrupted efforts in
elevating technological frame and quality improvement. The results obtained from the
study may help other companies to find methodology to implement the LM tools like
VSM.
6.2.1 Limitations. To implement any philosophy or tools in any industry, the top
management of the organization should be involved to implement the tool in
that organization successfully. LM is one of the long-term manufacturing
philosophies, which can take time and cost to get the desired results to any
organization. One of the limitations of the study is the application of VSM tool
restricted to a specific production line in an Indian auto-component industry. Before
generalizing the results of the study, researchers need to conduct similar study across
the industry sectors.
PRODUCTION CONTROL
Crankshaft Machining Sceduling Order (as per Sales
Plan)
Orders
I Kaizen Burst
IH Module c = 1, s = 2
Tempering & Kaizen Burst
Kaizen Burst P = 4, Q = 3, Kaizen Burst Kaizen Burst
induction Kaizen Burst P = 2, C = 1, D = 1 Kaizen Burst
D = 1, M = 1 Q=1 C = 1, S = 5 P = 1, Q = 1
hardening 3 Q = 2, D = 1, M = 1
Operation 1 Operation 2 Operation 3 Operation 4 Operation 5 Operation 6 Operation 7 Operation 8 Operation 9 Operation 10
Both end rough Semi-finish turning Gear end & flange
Initial inspection Other journal finish Thrust journal finish Pin finish grinding Flange end finish Flange end finish Gear end finish
boring & re- of flange outer end tapping and
grinding grinding boring grinding grinding
3 centering 3 dia 3 3 3 3 drilling 2 2 2 2
I Cycle time: 2.55 I Cycle time: 20.47 I Cycle time: Manual I Cycle time: 13.00
I Cycle time: 8.50 I Cycle time: 21.70 I Cycle time: 14.20 I Cycle time: Manual I Cycle time: 6.52 I Cycle time: 6.10
C/O time: --- C/O time: 8 hrs C/O time: 1 hr C/O time: 6 hrs C/O time: 6 hrs C/O time: 12 hrs C/O time: 3 hrs C/O time: --- C/O time: 7 hrs C/O time: 7 hrs
A
111
LM
IJLSS
Description Current Future
5,1
Production planned by planning department 30 Nos per day 40 Nos per day
Number of operations 15 14
Transport 36 33
Delay 1 1
112 Inspection 11 11
Storage 5 2
Total distance travelled by crankshaft in the
production line (m) 275.69 184.5
Total process time (min) 147.94 142.18
TAKT time (min) 36.975 , 37 27.731 , 28
Table VII. Process inventory (Nos) 73 19
Comparison of the results Total lead time (min) 1,584 412.3
obtained Process ratio (%) 9.34 34.48
References
Abdulmalek, F.A. and Rajgopal, J. (2007), “Analyzing the benefits of lean manufacturing and
value stream mapping via simulation: a process sector case study”, International Journal
of Production Economics, Vol. 107 No. 1, pp. 223-236.
Anand, G. and Kodali, R. (2008), “Selection of lean manufacturing systems using the
PROMETHEE”, Journal of Modelling in Management, Vol. 3 No. 1, pp. 40-70.
Anand, G. and Kodali, R. (2010), “Development of a framework for implementation of lean
manufacturing systems”, International Journal of Management Practice, Vol. 4 No. 1,
pp. 95-116.
Anand, G. and Kodali, R. (2011), “Design of lean manufacturing systems using value stream
mapping with simulation: a case study”, Journal of Manufacturing Technology
Management, Vol. 22 No. 4, pp. 444-473.
Beesley, A. (1994), “A need for time based process mapping and its application in procurement”,
Proceedings of 3rd Annual IPSERA Conference, University of Glamorgan, Pontypridd,
pp. 41-56.
Bhasin, S. and Burcher, P. (2006), “Lean viewed as a philosophy”, Journal of Manufacturing
Technology Management, Vol. 17 No. 1, pp. 56-72.
Braglia, M., Carmignani, G. and Zammori, F. (2006), “A new value stream mapping approach for
complex production systems”, International Journal of Production Research, Vol. 44 No. 18,
pp. 3929-3952.
Braglia, M., Frosolini, M. and Zammori, F. (2009), “Uncertainty in value stream mapping
analysis”, International Journal of Logistics Research and Applications, Vol. 12 No. 6,
pp. 435-453.
Brown, S. and Bessant, J. (2003), “The manufacturing strategy-capabilities links in mass
customization and agile manufacturing – an exploratory study”, International Journal of
Operations and Production Management, Vol. 23 No. 7, pp. 707-730.
Brunt, D. (2000), “From current state to future state: mapping the steel to component supply
chain”, International Journal of Logistics: Research and Applications, Vol. 3 No. 3,
pp. 259-271.
Dangayach, G.S. and Deshmukh, S.G. (2001), “Manufacturing strategy: experiences from Indian
manufacturing companies”, Production Planning Control, Vol. 12 No. 8, pp. 775-786.
Eisenhardt, K.M. (1989), “Building theories from case study research”, Academy of Management LM
Review, Vol. 14, pp. 532-550.
implementation
Forza, C., Vinelli, A. and Filippini, R. (1993), “Telecommunication services for quick response in
the textile-apparel industry”, Proceedings of the 1st International Symposium on Logistics, using VSM
University of Nottingham, Nottingham, pp. 119-126.
George, M. (2002), Lean Six Sigma: Combining Six Sigma Quality with Lean Speed, McGraw-Hill,
New York, NY. 113
Goldratt, E.M. (1990), What is this Thing Called Theory of Constraints and How Should it be
Implemented?, North River Press, New York, NY.
Hines, P. (1999), “Value stream management: next frontier in supply chain”, Logistics Focus,
Vol. 1 No. 3, pp. 36-39.
Hines, P. and Rich, N. (1997), “The seven value stream mapping tools”, International Journal of
Operations and Production Management, Vol. 17 No. 1, pp. 46-64.
Hines, P., Rich, N. and Esain, A. (1998), “Creating a lean supplier network: a distribution
industry case”, European Journal of Purchasing and Supply Management, Vol. 4,
pp. 235-246.
Jasti, N.V.K., Sharma, A. and Kodali, R. (2012), “Lean to green supply chain management:
a case study”, Journal of Environmental Research and Design, Vol. 6 No. 3A, pp. 890-899.
Jessop, D. and Jones, O. (1995), “Value stream process modelling: a methodology for creating
competitive advantage”, Proceedings of 4th Annual IPSERA Conference, University of
Birmingham, Birmingham.
Jones, D. and Womack, J. (2000), Seeing the Whole: Mapping the Extended Value Stream,
Lean Enterprise Institute, Cambridge, MA.
Kalsaas, B.T. (2002), “Value stream mapping: an adequate method for going lean?”, Proceedings
of the 14th International Conference NOFOMA 2002, Trondheim, Norway.
Krafcik, J.F. (1988), “Triumph of the lean production system”, Sloan Management Review, Vol. 30
No. 1, pp. 41-52.
Lamming, R., Johnsen, T., Zheng, J. and Harland, C. (2000), “An initial classification of supply
networks”, International Journal of Operations and Production Management, Vol. 20,
pp. 675-691.
Lasa, I.S., Laburu, C.O. and de Vila, R.C. (2008), “An evaluation of the value stream mapping
tool”, Business Process Management Journal, Vol. 14 No. 1, pp. 39-52.
Lian, Y.H. and Van Landeghem, H. (2007), “Analysing the effects of lean manufacturing using a
value stream mapping-based simulation generator”, International Journal of Production
Research, Vol. 45 No. 13, pp. 3037-3058.
Liker, J.K. (1998), Becoming Lean, Productivity Press, Portland, OR.
Lummus, R.R., Vokurka, R.J. and Rodeghiero, B. (2006), “Improving quality through value
stream mapping: a case study of a physician’s clinic”, Total Quality Management and
Business Excellence, Vol. 17 No. 8, pp. 1063-1075.
McDonald, T., Aken, E.M.V. and Rentes, A.F. (2002), “Utilising simulation to enhance value
stream mapping: a manufacturing case application”, International Journal of Logistics
Research Application, Vol. 5 No. 2, pp. 213-232.
Marchwinski, C. and Shook, J. (2003), Lean Lexicon: A Graphical Glossary for Lean Thinkers,
The Lean Enterprise Institute, Cambridge, MA.
Maskell, B. (2001), “The age of agile manufacturing”, Supply Chain Management, Vol. 6 No. 1,
pp. 5-11.
IJLSS Meredith, J. (1998), “Building operations management theory through case and field research”,
Journal of Operations Management, Vol. 16, pp. 441-454.
5,1
Monden, Y. (1993), Toyota Production System: An Integrated Approach to Just-In Time, 2nd ed.,
Industrial Engineering and Management Press, Institute of Industrial Engineers,
Norcross, GA.
Narasimhan, R., Swink, M. and Kim, S.W. (2006), “Disentangling leanness and agility:
114 an empirical investigation”, Journal of Operations Management, Vol. 24 No. 5, pp. 440-457.
New, C. (1974), “The production funnel: a new tool for operations analysis”, Management
Decisions, Vol. 12, pp. 167-178.
New, C. (1993), “The use of throughput efficiency as a key performance measure for the new
manufacturing era”, International Journal of Logistics Management, Vol. 4, pp. 95-104.
Özkan, K., Birgün, S., Kiliçogullari, P. and Akman, G. (2005), “Responding to customer
requirements with value stream mapping: an automotive industry application”,
Proceedings of the 35th International Conference on Computers & Industrial
Engineering, Turkey.
Papadopoulou, T.C. and Ozbayrak, M. (2005), “Leanness: experiences from the journey to date”,
Journal of Manufacturing Technology Management, Vol. 16 No. 7, pp. 784-807.
Pavnaskar, S.J., Gershenson, J.K. and Jambekar, A.B. (2003), “Classification scheme for lean
manufacturing tools”, International Journal of Production Research, Vol. 41, pp. 3075-3090.
Pettersen, J. (2009), “Defining lean production: some conceptual and practical issues”, The TQM
Journal, Vol. 21 No. 2, pp. 127-142.
Piercy, N. and Rich, N. (2009), “Lean transformation in the pure service environment: the case of
the call service center”, International Journal of Operations & Production Management,
Vol. 29 No. 1, pp. 54-76.
Prince, J. and Kay, J.M. (2003), “Combining lean and agile characteristics: creation of virtual
groups by enhanced production flow analysis”, International Journal of Production
Economics, Vol. 85 No. 3, pp. 305-318.
Rosentrater, K.A. and Balamuralikrishna, R. (2006), “Value stream mapping – a tool for
engineering and technology education and practice”, Proceedings of the 2006 ASEE IL/IN
Conference, Fort Wayne, IN, USA.
Rother, M. and Shook, J. (1998), Learning to See: Value Stream Mapping to Add Value and
Eliminate Muda, Lean Enterprise Institute, Cambridge, MA.
Russell, R.S. and Taylor, B.W. (1999), Operations Management, 2nd ed., Prentice-Hall,
Upper Saddle River, NJ.
Sahoo, A.K., Singh, N.K., Shankar, R. and Tiwari, M.K. (2008), “Lean philosophy: implementation
in a forging company”, International Journal of Advanced Manufacturing Technology,
Vol. 36 Nos 5/6, pp. 451-462.
Seth, D. and Gupta, V. (2005), “Application of value stream mapping for lean operations and
cycle time reduction: an Indian case study”, Production Planning and Control, Vol. 16 No. 1,
pp. 44-59.
Seth, D., Seth, N. and Goel, D. (2008), “Application of value stream mapping (VSM) for
minimization of wastes in the processing side of supply chain of cottonseed oil industry in
Indian context”, Journal of Manufacturing Technology Management, Vol. 19 No. 4,
pp. 529-550.
Shah, R. and Ward, P.T. (2003), “Lean manufacturing: context, practice bundles, and
performance”, Journal of Operations Management, Vol. 21 No. 2, pp. 129-149.
Shah, R. and Ward, P.T. (2007), “Defining and developing measures of lean production”, LM
Journal of Operations Management, Vol. 25, pp. 785-805.
Sharifi, H. and Zhang, Z. (2001), “Agile manufacturing in practice: application of a methodology”,
implementation
International Journal of Operations and Production Management, Vol. 21 Nos 5/6, using VSM
pp. 772-794.
Sharma, M. and Kodali, R. (2008), “Validity and reliability of applying manufacturing excellence
frameworks to Indian industries”, Proceedings of the Institution of Mechanical Engineers, 115
Part B: Journal of Engineering Manufacture, Vol. 222 No. 6, pp. 723-739.
Shen, S.X. and Han, C.F. (2006), “China electrical manufacturing services industry value stream
mapping collaboration”, International Journal Flexible Manufacturing System, Vol. 18
No. 4, pp. 285-303.
Singh, B. and Sharma, S.K. (2009), “Value stream mapping as a versatile tool for lean
implementation: an Indian case study of a manufacturing firm”, Measuring Business
Excellence, Vol. 13 No. 3, pp. 58-68.
Singh, B., Garg, S.K., Sharma, S.K. and Grewal, C. (2010), “Lean implementation and its
benefits to production industry”, International Journal of Lean Six Sigma, Vol. 1 No. 2,
pp. 157-168.
Snow, C.C. and Thomas, J.B. (1994), “Field research methods in strategic management:
contributions to theory building and testing”, Journal of Management Studies, Vol. 31
No. 4, pp. 457-480.
Solding, P. and Gullander, P. (2009), “Concepts for simulation based value stream mapping”,
Proceedings of the 2009 Winter Simulation Conference, Piscataway, NJ, USA.
Upadhye, N., Deshmukh, S.G. and Garg, S. (2010), “Lean manufacturing system for medium size
manufacturing enterprises: an Indian case”, International Journal of Management Science
and Engineering Management, Vol. 5 No. 5, pp. 362-375.
Vinodh, S., Arvind, K.R. and Somanaathan, M. (2010), “Application of value stream mapping in
an Indian camshaft manufacturing organization”, Journal of Manufacturing Technology
Management, Vol. 21 No. 7, pp. 888-900.
Voss, C., Tsikriktsis, N. and Frohlich, M. (2002), “Case research in operations management”,
International Journal of Operations and Production Management, Vol. 22, pp. 195-219.
Wacker, J.G. (1998), “A definition of theory: research guidelines for different theory-building
research methods in operations management”, Journal of Operations Management, Vol. 16
No. 4, pp. 361-385.
Womack, J.P. and Jones, D.T. (1994), “From lean production to lean enterprise”, Harvard Business
Review, March/April, pp. 93-103.
Womack, J.P. and Jones, D.T. (1996), Lean Thinking, Banish Waste and Create Wealth in Your
Corporation, Simon & Schuster, New York, NY.
Womack, J.P., Jones, D.T. and Roos, D. (1990), The Machine that Changed the World,
Rawson Associates, New York, NY.
Yin, R.K. (1994), Case Study Research, Design and Methods, 2nd ed., Sage, Thousand Oaks, CA.