Professional Documents
Culture Documents
Sl. No FGD System Component Capital Cost Incremental Auxiliary Consumption Shut Down Period
Sl. No FGD System Component Capital Cost Incremental Auxiliary Consumption Shut Down Period
Sipat STPS
S No FGD System Capital Cost# Incremental Shut Down
Component Auxiliary Period
Consumption
1 FGD system `0.5 crore/MW 1.5% 180 days per
Unit
2 Chimney liner `18 crore/Unit
3 Reagent cost `2.75 lakh/ MW/
annum
4 De-Nox System 0.25 crore/MW 0.2% 90 days per Unit
(Combustion
Modification
and Installation
of SNCR)
5 Reagent cost `2.0 lakh/ MW/
annum
6 Other O&M 10% of equipment
cost- for cost
manpower and
maintenance of
addition
equipment
7 ESP Presently no The shutdown
modification period not
proposed, envisaged in
however, will case of schemes
approach not being done
Commission as presently.
and when However,
implemented. appropriate shut
8 Mercury Presently no down period
emission modification may also be
proposed, allowed, as and
however, will when such
approach schemes are
Commission as implemented.
and when
implemented.
Total `0.78 crore/ MW 1.7%
# This is estimated capital cost and same may change upon finalisation of technology supplier and lenders.
Petition shall be issued by the Chairperson and three Members of the Commission
who heard the matter. Accordingly, we proceed to adjudicate the disputes raised
23. Based on the above submissions of the parties, following are the issues which
(a) Issue No.1: Whether the prayer for in-principle approval in the petition is
maintainable in the absence of such provisions in the 2014 Tariff Regulations
and in the light of the orders of the Commission dated 14.10.2009 and dated
20.3.2017 in Petition No.153 of 2009 and Petition No.72/MP/2016
respectively?
(b) Issue No.2: Whether the MOEFCC Notification dated 7.12.2015 requiring
the thermal generating stations to implement the revised environmental
norms amounts to Change in Law in terms of the provisions of the 2014 Tariff
Regulations?
(c) Issue No.3: Whether the Commission can issue directions providing for
broad guidelines for implementation of the ECS and incremental expenditure
on auxiliary consumption and O&M expenses on ECS and other facilities?
Issue No.1: Whether the prayer for in-principle approval in the petition is
maintainable in the absence of such provisions in the 2014 Tariff Regulations
and in the light of the orders of the Commission dated 14.10.2009 and dated
20.3.2017 in Petition No. 153 of 2009 and Petition No.72/MP/2016
respectively?
24. MOEFCC, GoI vide Notification dated 7.12.2015 has notified the Environment
revised. Since the Central Government has revised the standards of emissions of
Protection Act, 1986, the said notification is covered under Change in Law in terms
of Regulation 3(9)(ii) of the 2014 Tariff Regulations. The revised standards are
39. Ministry of Power, GOI, in exercise of its powers conferred under Section 107
of the 2003 Act has issued directions to the Commission vide letter dated
No.23/22/2018- R & R
Government of India
Ministry of Power
Shram Shakti Bhawan, Rafi Marg
New Delhi, 30th May, 2018
To
The Chairperson,
Central Electricity Regulatory Commission
Chanderlok Building,
Janpath, New Delhi-110001
Ministry of Environment, Forest and Climate Change (MoEFCC) has notified the
Environment (Protection) Amendment Rules, 2015 on 7th December, 2015 thereby
introducing revised emission standards for Thermal Power Plants (TPPs). The
revised emission standards are applicable to existing as well as upcoming TPPs. To
meet the revised emission standards, the TPPs would have to install or upgrade
various emission control systems like Flue-gas desulfurization (FGD) system,
Electro-Static Precipitators (ESP) system etc.
2. As per implementation plan prepared by Central Electricity Authority (CEA), the
existing TPPs are required to comply with the new emission standards by the year
2022.
3. Implementation of revised emission standards would face challenges relating to
stringent timelines, availability of suppliers and technology, shut down for longer
periods, and revenue loss during shutdown. It would also have significant
implications on the tariff agreed under the long term and medium term power
Yours faithfully
Ghanshyam Prasad
Chief Engineer
facilitate the smooth implementation of the revised emission norms under the
MOEFCC Notification for thermal power plants in the larger public interest. Section
“107 (1) In discharge its functions, the Central Commission shall be guided by such
directions as matter of policy involving public interest as the Central Government
may give to in writing.”
issued by the Central Government under section 107 of the 2003 Act in discharge
of its functions.
42. Para 5.4 of the Directions issued by MoP under Section 107 of the 2003 Act
provides as under:
“5.4 For the TPPs that are under the purview of the Central Commission, the
Commission shall develop appropriate regulatory mechanism to address the impact
on tariff, and certainty in cost recovery on account of additional capital and
operational cost, under concluded long term and medium term PPAs for this
purpose.”
43. MoP in its directions under section 107 of the 2003 Act has recognised that
Amendment Rules, 2015 dated 7th December, 2015 is of the nature of Change in
law event with two exceptions namely, where Power Purchase Agreements of such
TPPs whose tariff is determined under section 63 of the Electricity Act 2003 having
pollutions control system was mandated under the environment clearance of the
44. In our view, the MOEFCC Notification dated 7.12.2015 requiring the thermal
Policy directions issued by the MoP under section 107 of the Act.
Issue No.3: Whether the Commission should issue directions providing for broad
guidelines for implementation of the ECS and incremental expenditure on
auxiliary consumption and O&M expenses on ECS and other facilities?
law‟ in terms of Regulation 3(9)(ii) of the 2014 Tariff Regulations. The relief under
Xxxxx
46. Existing generating project has been defined as a „project‟ which has been
declared under commercial operation on a date prior to 1.4.2014 and new project
has been defined as the project achieving COD or anticipated to be achieving COD
Notification dated 7.12.2015 shall be admissible after due prudence check, under
47. The compliance of the revised norms specified under the MOEFCC Notification
depending upon location of plant and existing level of emission from such plant.
Moreover, the scope of work would also differ from plant to plant, depending upon
the type of technology to be adopted. The Petitioner in its prayers (b) to (h) has
(ii) Incremental O&M cost for installation of ECS and other associated
facilities.
(iv) Expenditure on water cost required for operation of ECS and other
associated facilities
(vi) Expenditure on procurement cost of lime stones and other reagents like
urea and ammonia etc.
48. Therefore, a mechanism needs to be devised for addressing the issues like
identification of suitable technology for each plant for implementation of ECS, its
(a) Suitable technology with model specification for each plant, with regard
to implementation of new norms;
49. Based on the guidelines and operational parameters decided by CEA, the
Commission shall undertake prudence check and grant the tariff for the capital and
this regard.
50. The treatment of shut down period required for installation and commissioning
referred to in para 49 above will address this aspect also. The Petitioner may