Professional Documents
Culture Documents
Sl. No FGD System Component Capital Cost Incremental Auxiliary Consumption Shut Down Period
Sl. No FGD System Component Capital Cost Incremental Auxiliary Consumption Shut Down Period
Sipat STPS
S No FGD System Capital Cost# Incremental Shut Down
Component Auxiliary Period
Consumption
1 FGD system `0.5 crore/MW 1.5% 180 days per
Unit
2 Chimney liner `18 crore/Unit
3 Reagent cost `2.75 lakh/ MW/
annum
4 De-Nox System 0.25 crore/MW 0.2% 90 days per Unit
(Combustion
Modification
and Installation
of SNCR)
5 Reagent cost `2.0 lakh/ MW/
annum
6 Other O&M 10% of equipment
cost- for cost
manpower and
maintenance of
addition
equipment
7 ESP Presently no The shutdown
modification period not
proposed, envisaged in
however, will case of schemes
approach not being done
Commission as presently.
and when However,
implemented. appropriate shut
8 Mercury Presently no down period
emission modification may also be
proposed, allowed, as and
however, will when such
approach schemes are
Commission as implemented.
and when
implemented.
Total `0.78 crore/ MW 1.7%
# This is estimated capital cost and same may change upon finalisation of technology supplier and lenders.
facilitate the smooth implementation of the revised emission norms under the
MOEFCC Notification for thermal power plants in the larger public interest. Section
“107 (1) In discharge its functions, the Central Commission shall be guided by such
directions as matter of policy involving public interest as the Central Government
may give to in writing.”
issued by the Central Government under section 107 of the 2003 Act in discharge
of its functions.
42. Para 5.4 of the Directions issued by MoP under Section 107 of the 2003 Act
provides as under:
“5.4 For the TPPs that are under the purview of the Central Commission, the
Commission shall develop appropriate regulatory mechanism to address the impact
on tariff, and certainty in cost recovery on account of additional capital and
operational cost, under concluded long term and medium term PPAs for this
purpose.”
43. MoP in its directions under section 107 of the 2003 Act has recognised that
Amendment Rules, 2015 dated 7th December, 2015 is of the nature of Change in
law event with two exceptions namely, where Power Purchase Agreements of such
TPPs whose tariff is determined under section 63 of the Electricity Act 2003 having
pollutions control system was mandated under the environment clearance of the
44. In our view, the MOEFCC Notification dated 7.12.2015 requiring the thermal