Deck Installation

Installation Vessel Subsea Structure


BOKALIFT Cargo Barge + Tug

Transit to location Mobilize Transport Spread

Check Deck Load-out & sea-fasten


Legs Bevel Deck on Cargo Barge

Jacket Installed Transit to installation site

Secure Cargo Barge


Berth Cargo Barge
alongside & transfer
alongside Installation
personnel on Cargo
Vessel
Barge Meteo check prior cutting
last 50% Sea fastening
Cut Deck Sea fastening
& Connect rigging
As built existing structure
availabe
Off-load Structure from
Lift Deck Off
Cargo Barge

Position Ship &


Orientate Crane

Unberth CB from Vessel


Release Cargo Barge
Side

Set down deck onto


Jacket
Transit to Port

Weld Deck on Jacket


(Transition Piece)
Demobilize Transport
Complete Deck Spread
Activities

Transfer Personnel (*)

Move next location

Deck Installation
Completed