Professional Documents
Culture Documents
Notice Inviting Tender (Nit)
Notice Inviting Tender (Nit)
Page 1 of 8
NOTICE INVITING TENDER (NIT)
FOR
PROVIDING PLANT COST ESTIMATION OF PROCESS UNITS FOR
POLYPROPYLENE (PP) AT RASAYANI AND, PETRO RESID FCC
(PRFCC) & SULPHUR RECOVERY UNIT (SRU) AT MUMBAI
REFINERY INDIA (BIDDING DOCUMENT NO.: E-47522/ CRFQ-
1000316737)
1. INTRODUCTION
1.1. BPCL Mumbai Refinery has crude processing capacity of 12.0 Million Metric
Tonnes per Annum (MMTPA). The refining capacity has been augmented to
the present level through progressive revamps, addition of various process
units and incorporation of advanced refining technologies.
1.2. BPCL intends to diversify into Petrochemical products with major focus on
Propylene based derivatives to improve refinery profitability. BPCL has
recently carried out a Bottoms upgrading Study which recommended setting
up of a Petro Resid FCC (PRFCC) unit at Mumbai Refinery and
Polypropylene (PP) Unit at Rasayani, 50 km from MR. Also a new Sulphur
Recovery Unit (SRU) at Mumbai Refinery is proposed for processing
additional Sulphur load.
1.3. The following is the summary indicated in Table-1 of the new units proposed
under this project:
Table: 1
This tender document is issued to obtain firm offers for carrying out the plant
cost estimation for the above units
Page 2 of 8
3. SALIENT FEATURES OF BIDDING DOCUMENT ARE AS FOLLOWS:
Page 3 of 8
NO. SALIENT FEATURES DETAILS
Mr. Malpe VM
malpevm@bharatpetroleum.in
09820626345
3.1. If identified dates as (*) above happens to be a declared holiday / closed day
in BPCL, activity shall be conducted on next working day at 14:00 Hrs. IST.
3.2. All amendments, time extension, clarifications, etc. will be uploaded in the
websites only. Bidders should regularly visit the above website(s) to keep
themselves updated.
3.3. Request for extension or any queries received from any bidder with less
than two working days prior to bid due date shall generally be ignored, since
there will not be adequate time for consideration. Bidders shall submit the
bid directly and in their own name without involving any intermediaries
4.1. Consultant shall submit the documents containing the basis of cost
estimation to BPCL within one week from the date of award of job.
4.2. For Individual cost estimation, the completion period shall be 03 (Three)
weeks from the date of issue of LOA / FOA or issue of the required
information / input by BPCL for a process unit, whichever is later.
4.3. In the event of delay in delivery of the cost estimate by the Consultant, within
the time limit described above, LD clause of 0.5 % of the aggregate of the
award fee per week of delay or part thereof subject to maximum of 5% of
Page 4 of 8
contractual value.
4.4. The entire job is expected job to be spread over 09 (Nine) months from the
date of issue of LOA / FOA based on actual progress in each of the above
mentioned units submitted by the respective Licensors
5.1.1. Preparation of Feasibility report which includes +/- 30% estimates, or further
accuracy level.
Any of the job mentioned above should have been executed during last 10
Years (ending on last day of the month immediately previous to the month in
which last date of original bid submission falls).
5.2.2. The financial net worth of the bidder / vendor as per latest annual audited
balance sheet (FY: 2017-2018) shall be positive.
Page 5 of 8
5.3. DOCUMENTS TO BE SUBMITTED BY BIDDER
5.3.1. The bidder shall submit a declaration to the effect that they are not currently
serving Holiday Listing orders issued by BPCL or MoPNG debarring them
from carrying on business dealings with the BPCL / MoPNG or serving a
banning order by another Oil PSU.
5.3.2. Bidders shall furnish any of the following documents evidence in support of
the above:
5.3.2.1. Details of Work Order experience and other criteria along with relevant
documents, such as copies of Work Order, Covering letter, Schedule of rates
and Completion Certificate containing executed value of work.
5.3.4. In case, the job is a part of major project activities, the bidder shall submit
documents for the same as a proof.
5.3.5. In case of Sub contract works, the bidder is also required to submit a
Certificate from the end user / Owner / Consultant of the Owner stating that
the main contractor has intimated them about the engagement of sub-
contracting OR have been allowed / permitted as a sub-contractor.
Page 6 of 8
Petroleum Corporation Limited” payable at Mumbai or Bank Guarantee
(BG). BG shall be submitted from any Indian scheduled bank which includes
Indian branch of foreign bank recognized as scheduled bank by RBI. Bids
without the requisite EMD as mentioned above shall be rejected.
EMD exemption will be applicable to the following Bidders:
b) The above document submitted by the bidder shall be duly certified (in
original) by Notary or the Statutory Auditor of the bidder or a practicing
Chartered Accountant (not being an employee or a Director or not
having any interest in the bidder’s company/firm) where audited
accounts are not mandatory as per law or duly notarized by any Notary
Public in the bidder’s country.
c) If the bidder does not provide the appropriate document or any evidence
to substantiate the above, then it will be presumed that they do not
qualify for any preference admissible in the Public Procurement Policy,
2012.
There will be no waiver of EMD for Public Sector Undertaking of
Central/State Government Undertakings. EMD shall be valid for a period of
06 (Eight) months from the final bid due date for submission of Bids.
Page 7 of 8
The Bank Guarantee in lieu of EMD shall be furnished on non-judicial
stamp paper of Rs. 500/- value and in the prescribed Performa given
in the Tender Document.
Bank Guarantee (BG) shall be executed by any Scheduled Bank
approved by Reserve Bank of India as per the proforma. The BG shall
remain valid for a period of six months from the due date of opening
the tender.
Original DD/ Banker's Cheque or BG as the case may be, towards
EMD shall be sent separately to CPO (Head), CPO-Refineries, BPCL.
Copy the DD/ Banker's cheque/ BG as the case may be, along with
proof of dispatch to be uploaded along with "Prequalification Bid".
Bids without EMD are liable to be rejected.
EMD can be also submitted through electronic fund transfer to the
Account as detailed below;
Details of Bank for Electronic Fund Transfer:
Beneficiary-Bharat Petroleum Corporation Limited
Name of the Bank- Standard Chartered Bank, M G Road,
Address-90, M G Road, Fort, Mumbai-400 001,
IFSC Code-SCBL0036001,
MICR Code-400036002,
Type of Account-11(Current),
Account No:22205020115.
EMD of other unsuccessful bidders shall be released after issuance of
FOA/LOA/contract Order against this tender. However, in case of
successful bidder the EMD shall be released on receipt of
performance bank guarantee.
Forfeiture of EMD - A tenderer who has submitted their bid shall not
be permitted to alter/ amend or withdraw the bid, not withstanding that
the bid(s) has/ have not yet been opened/ finalized. A tenderer who
purports to alter/ modify withdraw their offer after submission, within
the validity of the offer shall be liable to have their offer rejected and
their EMD forfeited/ encashed.
The Earnest Money deposited by successful tenderer shall be
forfeited if the successful tenderer fails to honour the offer terms prior
to ordering and Contractual terms after issuance of FOA/LOA/
contract Order.
Offers received without scan copy of EMD (DD/BG/Valid NSIC
Certificate/Bank transfer details) in the e-tender and physically not
received within 7 days after “Prequalification Bid” opening date (as
indicated in the NIT or corrigendum thereof) are liable to be rejected.
EMD shall be valid for a period of 6 (Six) Months from the due date
and in compliance with the terms provided in General Conditions of
Contract (GCC) for the same. EMD format provided in GCC shall be
complied.
Page 8 of 8