9 Prov.

/ laying cement concrete


1:2:4 in lintel and slab
In Lintels
Door - D 2 1.35 0.40 0.15 0.16
Door - D 1 1.20 0.40 0.15 0.07
Door - D 1 1.05 0.40 0.15 0.06
Window - W 4 1.80 0.40 0.15 0.43
Ventilator - V 1 1.50 0.40 0.15 0.09
In Slab 1 x 8.1 6.65 0.1 = 5.39
1 x 7 1.9 0.1 = 1.33

Total :- 7.53 Cum

10 Stone Filling in Plinth


Store Room 1 x 1 x 3.00 4.50 0.15 = 2.03
Store Keeper Room 1 x 1 x 3.00 3.50 0.15 = 1.58
Chowkidar Room 1 x 1 x 3.00 2.50 0.15 = 1.13
Toilet 1 x 1 x 1.90 1.50 0.15 = 0.43

Total :- 5.17 Cum

11 Providing cement concrete 1:5:10 in Plinth


Store Room 1 x 1 x 3.00 4.50 0.10 = 1.35
Store Keeper Room 1 x 1 x 3.00 3.50 0.10 = 1.05
Chowkidar Room 1 x 1 x 3.00 2.50 0.10 = 0.75
Toilet 1 x 1 x 1.90 1.50 0.10 = 0.29

Total :- 3.44 Cum


12 15 mm cement plastering in
ceilling in cement mortar 1:3
Store Room 1 x 1 x 3.00 x 4.50 = 13.50
Store Keeper Room 1 x 1 x 3.00 x 3.50 = 10.50
Chowkidar Room 1 x 1 x 3.00 x 2.50 = 7.50
Toilet 1 x 1 x 1.90 x 1.50 = 2.85

Outside Projection
Front 1 x 1 x 8.10 x 0.90 = 7.29
Back 1 x 1 x 7.00 x 0.45 = 3.15
1 x 1 x 1.55 x 0.45 = 0.70
Left Side 1 x 1 x 7.20 x 0.45 = 3.24
Right Side 1 x 1 x 1.45 x 0.45 = 0.65
1 x 1 x 5.30 x 0.45 = 2.39
Bottom of Lintel
Door - D 2 x 1 1.05 0.275 = 0.58
Door - D 1 x 1 0.90 0.275 = 0.25
Door - D 1 x 1 0.75 0.275 = 0.21
Window - W 4 x 1 1.50 0.275 = 1.65
Ventilator - V 1 x 1 1.20 0.275 = 0.33

Total :- 54.79 Sqm.


13 20 mm cement plaster in single
coat on rough side of stone
masonry in cement mortar 1:6
Store Room 1 x 2 x( 3.00 + 4.50 )x 2.70 = 40.50
Store Keeper Room 1 x 2 x( 3.00 + 3.50 )x 2.70 = 35.10
Chowkidar Room 1 x 2 x( 3.00 + 2.50 )x 2.70 = 29.70
Toilet 1 x 2 x( 1.90 + 1.50 )x 2.70 = 18.36
123.66 Sqm.
Deduction for opening
Door - D 2 x 1.05 x 2.10 = 4.41
Door - D 1 x 0.90 x 2.10 = 1.89
Door - D 1 x 0.75 x 1.90 = 1.43
Window - W 4 x 1.50 x 1.65 = 9.90
Ventilator - V 1 x 1.20 x 0.45 = 0.54
Total Deduction :- 18.17 Sqm.

Net Quantity :- 105.49 Sqm.


14 Pointing on stone masonary with
cement mortar 1:3 ( 1 cement : 3
Sand)
Front and Back 1 x 2 x 7.20 x 3.20 = 46.08
Left and Right side 1 x 2 x 7.20 x 3.20 = 46.08
Total :- 92.16 Sqm.
Deduction for opening
Door - D 2 x 1.05 x 2.10 = 4.41
Door - D 1 x 0.90 x 2.10 = 1.89
Door - D 1 x 0.75 x 1.90 = 1.43
Window - W 4 x 1.50 x 1.65 = 9.90
Ventilator - V 1 x 1.20 x 0.45 = 0.54
Total Deduction :- 18.17 Sqm.
Net Quantity :- 73.99 Sqm.

15 40 mm Thick Cement concrete flooring in 1:2:4


Store Room 1 x 1 x 3.00 4.50 = 13.5
Store Keeper Room 1 x 1 x 3.00 3.50 = 10.5
Chowkidar Room 1 x 1 x 3.00 2.50 = 7.5
Toilet 1 x 1 x 1.90 1.50 = 2.85
Front Steps 1 x 1 x 3.40 1.20 = 4.08
Steps for Chowkidar Room 1 x 1 x 1.50 1.20 = 1.8
Steps for Toilet 1 x 1 x 1.35 1.20 = 1.62

Total :- 41.85 Cum

16 Wood work in Shutters of doors and windows


Door - D = Door 2 x 1 x 0.92 x 1.73 = 3.183
Door - D = Ventilator 2 x 1 x 0.92 x 0.32 = 0.589
Door - D1 = Door 1 x 1 x 0.77 x 1.73 = 1.332
Door - D1 = Ventilator 1 x 1 x 0.77 x 0.32 = 0.246
Door - D2 = Door 1 x 1 x 0.62 x 1.73 = 1.073
Window - Window 4 x 3 x 0.42 x 1.13 = 5.695
Window - Ventilator 4 x 4 x 0.42 x 0.32 = 2.150
Ventilator - 1 x 1 x 1.07 x 0.32 = 0.342
Total :- 14.610 Sqm.

17 Wood work in Wire gauge


Shutters of doors and windows
Door - D = Door 2 x 1 x 0.92 x 1.73 = 3.183
Door - D = Ventilator 2 x 1 x 0.92 x 0.32 = 0.589
Door - D1 = Door 1 x 1 x 0.77 x 1.73 = 1.332
Door - D1 = Ventilator 1 x 1 x 0.77 x 0.32 = 0.246
Window - Window 4 x 3 x 0.42 x 1.13 = 5.695
Window - Ventilator 4 x 4 x 0.42 x 0.32 = 2.150
Ventilator - 1 x 1 x 1.07 x 0.32 = 0.342
Total :- 13.537 Sqm.
18 White washing on ceilling
Store Room 1 x 1 x 3.00 x 4.50 = 13.50
Store Keeper Room 1 x 1 x 3.00 x 3.50 = 10.50
Chowkidar Room 1 x 1 x 3.00 x 2.50 = 7.50
Toilet 1 x 1 x 1.90 x 1.50 = 2.85

Outside Projection
Front 1 x 1 x 8.10 x 0.90 = 7.29
Back 1 x 1 x 7.00 x 0.45 = 3.15
1 x 1 x 1.55 x 0.45 = 0.70
Left Side 1 x 1 x 7.20 x 0.45 = 3.24
Right Side 1 x 1 x 1.45 x 0.45 = 0.65
1 x 1 x 5.30 x 0.45 = 2.39
Bottom of Lintel
Door - D 2 x 1 1.05 0.275 = 0.58
Door - D 1 x 1 0.90 0.275 = 0.25
Door - D 1 x 1 0.75 0.275 = 0.21
Window - W 4 x 1 1.50 0.275 = 1.65
Ventilator - V 1 x 1 1.20 0.275 = 0.33
Total :- 54.79 Sqm.
19 Distempering with primming coat on walls
Store Room 1 x 2 x( 3.00 + 4.50 )x 2.70 = 40.50
Store Keeper Room 1 x 2 x( 3.00 + 3.50 )x 2.70 = 35.10
Chowkidar Room 1 x 2 x( 3.00 + 2.50 )x 2.70 = 29.70
Toilet 1 x 2 x( 1.90 + 1.50 )x 2.70 = 18.36
123.66 Sqm.
Deduction for opening
Door - D 2 x 1.05 x 2.10 = 4.41
Door - D 1 x 0.90 x 2.10 = 1.89
Door - D 1 x 0.75 x 1.90 = 1.43
Window - W 4 x 1.50 x 1.65 = 9.90
Ventilator - V 1 x 1.20 x 0.45 = 0.54
Total Deduction :- 18.17 Sqm.
Net Quantity :- 105.49 Sqm.
20 Primming Coat on new wood
Door - D 2 x 1.05 x 2.10 = 4.41
Door - D 1 x 0.90 x 2.10 = 1.89
Door - D 1 x 0.75 x 1.90 = 1.43
Window - W 4 x 1.50 x 1.65 = 9.90
Ventilator - V 1 x 1.20 x 0.45 = 0.54
Total :- 18.17 Sqm.
Total :- 18.17 x 2.25 = 40.88 Sqm.

21 Painting in two coats on new wood


Door - D 2 x 1.05 x 2.10 = 4.41
Door - D 1 x 0.90 x 2.10 = 1.89
Door - D 1 x 0.75 x 1.90 = 1.43
Window - W 4 x 1.50 x 1.65 = 9.90
Ventilator - V 1 x 1.20 x 0.45 = 0.54
Total :- 18.17 Sqm.
Total :- 18.17 x 2.25 = 40.88 Sqm.

22 Under Layer
Front and Back 1 x 2 x 8.70 x 0.75 0.10 = 1.31
Left and Right side 1 x 2 x 8.70 x 0.75 0.10 = 1.31
Total :- 2.62 Cum

23 Plinth protetion in cement concrete 1:3:6


Front and Back 1 x 2 x 8.70 x 0.75 0.10 = 1.31
Left and Right side 1 x 2 x 8.70 x 0.75 0.10 = 1.31
Total :- 2.62 Cum
24 U- Shape drain
Front 1 x 8.7 = 8.7
Back 1 x 7.6 = 7.6
1 x 1.1 = 1.1
Left side 1 x 8.7 = 8.7
Right side 1 x 1.9 = 1.9
1 x 6.8 = 6.8
Total :- 34.80 Rmt
25 P/F anodised aluminium sliding door bolts
250mm x 16mm 4 x 1 = 4 Nos
26 Tower Bolts =
Doors = 150 mm x 10 mm 4 x 2 = 8
3 x 2 = 6
Total :- 14 Nos
Window = 100 mm x 10 mm 4 x 2 x 12 = 96
Ventilator = 100 mm x 10 mm 2 x 2 = 4
Total :- 100 Nos

27 Handles
Doors = 125 mm 4 x 2 8 Nos
Window = 100 mm 4 x 12 = 48
Ventilator = 100 mm 1 x 2 = 2
Total :- 50 Nos
ABSTRACT OF COTS
Annexure - Q
Name of Work :- Augumentation / Remodelling of GWSS G/O villages Sholi in G.P. Sholi Tehsil
Nankhari, Distt. Shimla (HP).
(SH: C/O Store for chemicals )

S.No Description of item Qty Rate Unit Amount

1 Excavation in foundations,trenches etc.in earth work,lift 56.37 Cum 351.85 Cum 19832.00
upto 1.5mt.stacking the excavated soil not more than 3mt
clear from the edge of the excavation & then returning the
stacked soil in 15cm layers,when required into plinths
sides,of fundations etc.,consolidating each deposited
layer by ramming and watering and then disposing of all
surplus excavated earth as directed with in a lead of
20mtr.

2 Prov.and laying cement concrete 1:6:12 ( 1cement: 8.11 Cum 5295.25 Cum 42918.00
6sand:1 2graded stone aggregate 40mm nominal
size)and curing complete excluding cost of centring and
shuttering in:Foundation and Plinth
3 Square rubble masonry(uncoursed/polygonal/brought to 39.65 Cum 9683.90 Cum 383979.00
courses) with hard stone of approved quality including
levelling up with cement concrete 1:6 (1 cement; 6 sand )
in foundation and plinth
4 Square rubble masonry(uncoursed/polygonal/brought to 34.31 Cum 9683.90 Cum 332255.00
courses) with hard stone of approved quality including
levelling up with cement concrete 1:6 (1 cement;6 sand )
in Super Structure
5 Providing wood work in frames of doors, windows,
clerestory windows and other frames wrought framed and
fixed in position.
2nd. Class deodar wood. 0.695 Cum 100058.05 Cum 69540.00

6 Providing Providing form work witt steel plate 3.15mm


thick welded with angle iron in frame 30x30x5mm so as
to give a fair finish i/c centering shuttering struting and
propping etc. with wooden batten and ballies height of
propping and centering below floor to ceiling not
exceeding 4 mtrs and removal of the same for insitu
reiforced concrete & plain concrete work in :-

a) In flat surfaces such as suspended floor roofs, bottom of 3.02 Sqm 399.55 Sqm 1207.00
beams, landing, softs and like floor etc.
b) In vertical surface such as sides od beem, limtels and 3.20 Sqm 271.10 Sqm 868.00
walls(any thickness)
c) In edges of slabs & breaks etc. 33.30 Sqm 123.15 Sqm 4101.00

7 Providing Providing form work witt steel plate 3.15mm


thick welded with angle iron in frame 30x30x5mm so as
to give a fair finish i/c centering shuttering struting and
propping etc. with wooden batten and ballies height of
propping and centering below floor to ceiling not
exceeding 4 mtrs and removal of the same for insitu
reiforced concrete & plain concrete work in :-

a) Flat surfaces such as soffits of suspended floors roofs 51.77 Sqm 399.55 Sqm 20683.00
landings and the like, Floors etc. upto 200mm in
thickness.
8 Prov tor steel reinforcement for RCC work /c 702.00 Kgs 71.20 Kg 49982.00
bending,binding placeing in position.

9 Prov.and laying cement concrete 1:2:4 (1cement: 2sand:


4graded stone aggregate 20mm nominal size) and curing
complete excluding cost of centring and shuttering in:

(a) Suspended floor roofs landing & shelves & their 7.53 Cum 7810.65 Cum 58814.00
supportsbalconies,beams, bressumers & cantilevers upto
floor two level.

10 Boulder filling dry hand packed tightly in plinth for soling 5.17 Cum 1748.60 Cum 9040.00

11 Providing & laying cement concrete 1:5:10 (1 cement : 5 3.44 Cum 5203.80 Cum 17901.00
Sand :10 graded stone aggregate 40 mm nominal size )
and curing complete excluding cost of centring &
shuttering in foundation & plinth.

12 15 mm cement plaster in single coat on rough side of 54.79 Sqm 188.65 Sqm 10335.00
brick/stone masonry for interior plastering upto floor two
level i/c arrises,internal rounded angles chamfers and/or
rounded angles not exceeding 80mm in girth & finished
even & smooth in C.M 1:3

13 20 mm cement plaster in single coat on rough side of 105.49 Sqm 252.70 Sqm 26657.00
brick/stone masonry for interior plastering upto floor two
level i/c arrises,internal rounded angles chamfers and/or
rounded angles not exceeding 80mm in girth & finished
even & smooth in C.M 1:3

14 Pointing on stone masonary with cement mortar 1:3 ( 1 73.99 Sqm 104.65 Sqm 7743.00
cement : 3 Sand)

15 Cement concrete flooring 1:2:4 41.85 Sqm 399.85 Sqm 16734.00


(1Cement:2Sand:4Graded stone agg.20mm nominal size)
laid in one layer finished with a floating coat of neat
cement.40mm thick

16 Providing & fixing panelled, glazed or panelled & glazed


shutters for doors, windows and cleristory windows
including black enamelled iron but hinges with necessary
screws.
40 mm thick 2nd. Class deodar wood. 14.610 Sqm 3979.20 Sqm 58136.00

17 Providing & fixing wire gauged shutters for doors,


windows and cleristory windows including black
enamelled iron but hinges with necessary screws.
40 mm thick 2nd. Class deodar wood. 13.537 Sqm 3635.50 Sqm 49214.00

18 White washing with lime on undecorated wall surfaces 54.785 Sqm 10.75 Sqm 589.00
two coats to give an even shade i/c thoroughly brooming
the surface to remove all dirt,dust,mortar dust & other
foreign matter.
19 Distempering two coats with oil bond washable distemper
of approved brand and manufacture and of required
shade on undecorated wall surfaces to give an even
shade over and including a priming coat with distemper
primer of approved brand and manufacture after
throughly brushing the surface brand and manufacture
after throughly brushing the surface free from mortar
droppings and other foreign matter and also including
preparing the surface even and sand papered smooth.

Primer coat with distemper primer 105.49 Sqm 72.65 Sqm 7664.00

20 Applying priming coats over new wood and wood based


surfaces after and including preparing the surface by
throughly cleaning oil, grease dirt and other foreign matter
sand papering and knotting
Ready mixed paint brushing wood primer pink 40.88 Sqm 37.15 Sqm 1519.00

21 Painting two coat (excluding priming coat) over new wood


and wood based surfaces with ready mixed paint,
brushing to give an even shade including cleaning of all
dirt, dust and other foreign matter and sand papering and
stopping
Ready mixed paint other than white 40.88 Sqm 79.60 Sqm 3254.00

22 Providing under layer for plinth protection 75 mm thick 2.62 Sqm 357.75 Sqm 937.00
unconsolidated) bed dry brick/ stone aggregate 40 mm
nominal size will rammed and consolidating and grouted
with fine sand including preparation of ground

23 Providing plinth protection 50 mm thick in cement 2.62 Sqm 347.05 Sqm 909.00
concrete 1:3:6 (1 cement : 3 sand : 6 graded stone
aggregate 20mm nominal size)

24 Constructing course rubble hammer dressed "U" shape 34.80 Rmt 1866.00 Rmt 64937.00
open surface drain with side wall 15x22 cm in cement
mortar 1:6 (1 cement : 6 sand) and inside plastering with
cement plaster 1:3 (1 cement : 3 sand) including earth
work and 10 cm cement concrete 1:5:10 (1 cement : 5
sand : 10 graded stone aggregate 40mm nominal size)
and 7.5 cm cement concrete 1:2:4 (1 cement : 2 sand : 4
graded stone aggregate 20mm nominal size) and finished
with a floating coat of neat cement complete as per
standard design

25 P/F anodised aluminium sliding door bolts anodised


colour and shade with bolts & nuts screws etc complete.

300mm x 16mm 4.00 Nos 190.50 Each 762.00

26 P/F bright finished brass tower bolts ( barrel type) with


screws etc complete
100 mm x 10 mm 14.00 Nos 83.10 Each 1163.00
150 mm x 10 mm 100.00 Nos 92.30 Each 9230.00

27 P/F aluminium handle anodised of dyed to required


shade and colour with screw etc. complete.
125 mm 8.00 Nos 10.60 Each 85.00
100 mm 50.00 Nos 9.00 Each 450.00

Total :- 1271438.00
Add 25% for site dev.approch road, Electricity and senitatry fitting 317860
G.Total :- 1589298.00

Executive Engineer,
I&PH Division,Rampur
ABSTRACT OF COTS
Annexure - Q
Name of Work :- Augumentation / Remodelling of GWSS G/O villages Sholi in G.P. Sholi Tehsil
Nankhari, Distt. Shimla (HP).
(SH: C/O Store for chemicals )

S.No Description of item Qty Rate Unit Amount

1 Excavation in foundations,trenches etc.in earth work,lift 56.37 Cum 351.80 Cum 19829.00
upto 1.5mt.stacking the excavated soil not more than 3mt
clear from the edge of the excavation & then returning the
stacked soil in 15cm layers,when required into plinths
sides,of fundations etc.,consolidating each deposited
layer by ramming and watering and then disposing of all
surplus excavated earth as directed with in a lead of
20mtr.

2 Prov.and laying cement concrete 1:6:12 ( 1cement: 8.11 Cum 6938.10 Cum 56233.00
6sand:1 2graded stone aggregate 40mm nominal
size)and curing complete excluding cost of centring and
shuttering in:Foundation and Plinth
3 Square rubble masonry(uncoursed/polygonal/brought to 39.65 Cum 19127.04 Cum 758411.00
courses) with hard stone of approved quality including
levelling up with cement concrete 1:6 (1 cement; 6 sand )
in foundation and plinth
4 Square rubble masonry(uncoursed/polygonal/brought to 34.31 Cum 19127.04 Cum 656249.00
courses) with hard stone of approved quality including
levelling up with cement concrete 1:6 (1 cement;6 sand )
in Super Structure
5 Providing wood work in frames of doors, windows,
clerestory windows and other frames wrought framed and
fixed in position.
2nd. Class deodar wood. 0.695 Cum 103658.30 Cum 72043.00

6 Providing Providing form work witt steel plate 3.15mm


thick welded with angle iron in frame 30x30x5mm so as
to give a fair finish i/c centering shuttering struting and
propping etc. with wooden batten and ballies height of
propping and centering below floor to ceiling not
exceeding 4 mtrs and removal of the same for insitu
reiforced concrete & plain concrete work in :-

a) In flat surfaces such as suspended floor roofs, bottom of 3.02 Sqm 443.90 Sqm 1341.00
beams, landing, softs and like floor etc.
b) In vertical surface such as sides od beem, limtels and 3.20 Sqm 241.90 Sqm 774.00
walls(any thickness)
c) In edges of slabs & breaks etc. 33.30 Sqm 120.30 Sqm 4006.00

7 Providing Providing form work witt steel plate 3.15mm


thick welded with angle iron in frame 30x30x5mm so as
to give a fair finish i/c centering shuttering struting and
propping etc. with wooden batten and ballies height of
propping and centering below floor to ceiling not
exceeding 4 mtrs and removal of the same for insitu
reiforced concrete & plain concrete work in :-

a) Flat surfaces such as soffits of suspended floors roofs 51.77 Sqm 443.90 Sqm 22978.00
landings and the like, Floors etc. upto 200mm in
thickness.
8 Prov tor steel reinforcement for RCC work /c 702.00 Kgs 61.30 Kg 43033.00
bending,binding placeing in position.

9 Prov.and laying cement concrete 1:2:4 (1cement: 2sand:


4graded stone aggregate 20mm nominal size) and curing
complete excluding cost of centring and shuttering in:

(a) Suspended floor roofs landing & shelves & their 7.53 Cum 8670.50 Cum 65289.00
supportsbalconies,beams, bressumers & cantilevers upto
floor two level.

10 Boulder filling dry hand packed tightly in plinth for soling 5.17 Cum 4344.50 Cum 22461.00

11 Providing & laying cement concrete 1:5:10 (1 cement : 5 3.44 Cum 7093.20 Cum 24401.00
Sand :10 graded stone aggregate 40 mm nominal size )
and curing complete excluding cost of centring &
shuttering in foundation & plinth.

12 15 mm cement plaster in single coat on rough side of 54.79 Sqm 298.60 Sqm 16359.00
brick/stone masonry for interior plastering upto floor two
level i/c arrises,internal rounded angles chamfers and/or
rounded angles not exceeding 80mm in girth & finished
even & smooth in C.M 1:3

13 20 mm cement plaster in single coat on rough side of 105.49 Sqm 360.20 Sqm 37997.00
brick/stone masonry for interior plastering upto floor two
level i/c arrises,internal rounded angles chamfers and/or
rounded angles not exceeding 80mm in girth & finished
even & smooth in C.M 1:3

14 Pointing on stone masonary with cement mortar 1:3 ( 1 73.99 Sqm 104.10 Sqm 7702.00
cement : 3 Sand)

15 Cement concrete flooring 1:2:4 41.85 Sqm 396.60 Sqm 16598.00


(1Cement:2Sand:4Graded stone agg.20mm nominal size)
laid in one layer finished with a floating coat of neat
cement.40mm thick

16 Providing & fixing panelled, glazed or panelled & glazed


shutters for doors, windows and cleristory windows
including black enamelled iron but hinges with necessary
screws.
40 mm thick 2nd. Class deodar wood. 14.610 Sqm 4810.20 Sqm 70277.00

17 Providing & fixing wire gauged shutters for doors,


windows and cleristory windows including black
enamelled iron but hinges with necessary screws.
40 mm thick 2nd. Class deodar wood. 13.537 Sqm 3635.50 Sqm 49214.00

18 White washing with lime on undecorated wall surfaces 54.785 Sqm 9.00 Sqm 493.00
two coats to give an even shade i/c thoroughly brooming
the surface to remove all dirt,dust,mortar dust & other
foreign matter.
19 Distempering two coats with oil bond washable distemper
of approved brand and manufacture and of required
shade on undecorated wall surfaces to give an even
shade over and including a priming coat with distemper
primer of approved brand and manufacture after
throughly brushing the surface brand and manufacture
after throughly brushing the surface free from mortar
droppings and other foreign matter and also including
preparing the surface even and sand papered smooth.

Primer coat with distemper primer 105.49 Sqm 41.00 Sqm 4325.00

20 Applying priming coats over new wood and wood based


surfaces after and including preparing the surface by
throughly cleaning oil, grease dirt and other foreign matter
sand papering and knotting
Ready mixed paint brushing wood primer pink 40.88 Sqm 34.20 Sqm 1398.00

21 Painting two coat (excluding priming coat) over new wood


and wood based surfaces with ready mixed paint,
brushing to give an even shade including cleaning of all
dirt, dust and other foreign matter and sand papering and
stopping
Ready mixed paint other than white 40.88 Sqm 33.80 Sqm 1382.00

22 Providing under layer for plinth protection 75 mm thick 2.62 Sqm 819.40 Sqm 2147.00
unconsolidated) bed dry brick/ stone aggregate 40 mm
nominal size will rammed and consolidating and grouted
with fine sand including preparation of ground

23 Providing plinth protection 50 mm thick in cement 2.62 Sqm 401.60 Sqm 1052.00
concrete 1:3:6 (1 cement : 3 sand : 6 graded stone
aggregate 20mm nominal size)

24 Constructing course rubble hammer dressed "U" shape 34.80 Rmt 1866.00 Rmt 64937.00
open surface drain with side wall 15x22 cm in cement
mortar 1:6 (1 cement : 6 sand) and inside plastering with
cement plaster 1:3 (1 cement : 3 sand) including earth
work and 10 cm cement concrete 1:5:10 (1 cement : 5
sand : 10 graded stone aggregate 40mm nominal size)
and 7.5 cm cement concrete 1:2:4 (1 cement : 2 sand : 4
graded stone aggregate 20mm nominal size) and finished
with a floating coat of neat cement complete as per
standard design

25 P/F anodised aluminium sliding door bolts anodised


colour and shade with bolts & nuts screws etc complete.

300mm x 16mm 4.00 Nos 190.50 Each 762.00

26 P/F bright finished brass tower bolts ( barrel type) with


screws etc complete
100 mm x 10 mm 14.00 Nos 83.10 Each 1163.00
150 mm x 10 mm 100.00 Nos 92.30 Each 9230.00

27 P/F aluminium handle anodised of dyed to required


shade and colour with screw etc. complete.
125 mm 8.00 Nos 10.60 Each 85.00
100 mm 50.00 Nos 9.00 Each 450.00

Total :- 2032619.00
Add 25% for site dev.approch road, Electricity and senitatry fitting 508155
G.Total :- 2540774.00