Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

Annals of Nuclear Energy 94 (2016) 461–471

Contents lists available at ScienceDirect

Annals of Nuclear Energy


journal homepage: www.elsevier.com/locate/anucene

Technical note

HAZOP application for the nuclear power plants decommissioning


projects
Sigitas Rimkevičius, Mindaugas Vaišnoras ⇑, Egidijus Babilas, Eugenijus Ušpuras
Lithuanian Energy Institute, Breslaujos 3, LT-44403 Kaunas, Lithuania

a r t i c l e i n f o a b s t r a c t

Article history: Decommissioning of nuclear facilities involves different types of activities, tools, equipment and systems.
Received 9 October 2015 There is a potential for a wide range of radiological and industrial accidents during various stages of a
Received in revised form 11 April 2016 decommissioning project creating risk for workers and the environment. The occurrence of accidents is
Accepted 17 April 2016
possible due to many different operations involving movement and handling of large pieces of equipment
Available online 23 April 2016
and contaminated items. In addition, size reduction and decontamination processes are capable of
producing hazards. One of the first steps in developing a safety assessment for decommissioning activi-
Keywords:
ties is the identification of hazards that can affect workers, members of the public and the environment
Decommissioning
NPP
during decommissioning activities, and then to identify engineered and administrative control measures
HAZOP to prevent, eliminate or mitigate the hazards and their consequences. Fault and hazard identification can
ALARA be undertaken in several ways using a range of tools and techniques, including Hazard and Operability
Study (HAZOP).
The paper will mainly focus on the application of HAZOP technique for identification of the hazards
raised due to dismantling and decontamination activities at the Ignalina NPP, as well as at feasibility
study for the management of Bohunice V1 NPP primary circuit components.
Ó 2016 Elsevier Ltd. All rights reserved.

1. Introduction nationally prescribed safety criteria. Dismantling and decontami-


nation activities at any nuclear facilities significantly increase
The decommissioning of nuclear facilities requires adequate radiological and non-radiological hazards to workers, public and
planning and demonstration that dismantling and decontamina- the environment.
tion activities can be conducted safely. Existing safety standards All relevant hazards (e.g., sources of harm) to workers, the
require that an appropriate safety assessment be performed to public and the environment should be considered in the decom-
support any activities related to the sitting, operation, modifica- missioning safety assessment, including (International Atomic
tions and decommissioning of nuclear facilities. The main purpose Energy Agency, 2009):
of the safety assessment is to demonstrate that residual risks have
been reduced to As Low As Reasonably Achievable (ALARA) and to s Radiation exposures, for example, external exposure from direct
radiation and other radiation sources (including criticality),
internal exposure due to inhalation, ingestion or cuts and
Abbreviations: ALARA, As Low As Reasonably Achievable; AWT, annular water abrasions, and loss of containment leading to the uncontrolled
tank; D & D, dismantling and decontamination; ECCS, Emergency Core Cooling release of radionuclides.
System; EU, European Union; FEU, fume extract unit; HAZOP, hazards and s Toxic and other dangerous materials, for example, asbestos,
operability assessment procedure; HEPA, high efficiency particulate air filtration
flammable materials, carcinogens, chemicals used for decon-
system; IAEA, International Atomic Energy Agency; INPP, Ignalina Nuclear Power
Plant; LEI, Lithuanian Energy Institute; MFU, mobile filtering unit; MLW, medium tamination purposes.
level waste; NPP, nuclear power plant; PCC, primary circuit components; PPE, s Industrial hazards, for example, dropped loads, work at heights,
personal protection equipment; RIS, reactor internal structures; RPV, reactor fires, high temperatures, high pressures, noise, dust and
pressure vessel; SG, steam generator; SJR, Safety Justification Report; SQEP, suitably asbestos.
qualified and experienced personnel; VVER, from Russian: water–water energetic
reactor.
⇑ Corresponding author. According to IAEA safety guide WS-G-5.2 (International Atomic
E-mail address: mindaugas.vaisnoras@lei.lt (M. Vaišnoras). Energy Agency, 2009), a systematic approach should be taken for

http://dx.doi.org/10.1016/j.anucene.2016.04.027
0306-4549/Ó 2016 Elsevier Ltd. All rights reserved.
462 S. Rimkevičius et al. / Annals of Nuclear Energy 94 (2016) 461–471

the identification of hazards on the basis of the description of the 2. Hazard identification methodology used in NPP D & D
facility and decommissioning activities. The following steps should projects
be applied in an iterative manner to identify accident scenarios
that could lead to the exposure of workers and members of the The safety assessment process for decommissioning provides a
public or could have adverse consequences for the environment basis, on which the safety of workers and the public can be ensured
(International Atomic Energy Agency, 2009): through the evaluation of the consequences of potential hazards
and the identification of the ways they can be mitigated, so that
 Identification of hazards and initiating events: The activity and the associated residual risks are ALARA. The safety assessment
location of the radioactive source term at the facility should be should identify necessary preventive, protective and mitigating
considered together with any additional hazards, arising from measures and should justify that these will be suitable and suffi-
decommissioning activities or processes, and initiating events cient to ensure safety during decommissioning, in compliance with
that create the potential for causing harmful consequences for the relevant safety requirements and criteria (International Atomic
workers, the public or the environment should be identified. Energy Agency, 2009). The main steps of the harmonized safety
 Hazard screening: The hazards identified should be quantified assessment methodology for decommissioning are listed below:
and screened for in order to direct the safety efforts towards
all the significant and relevant hazards and initiating events (1) Safety assessment framework.
for a facility. (2) Description of facility and decommissioning activities.
 Identification of scenarios: The safety analysis should identify (3) Hazard analysis: identification and screening.
all relevant scenarios arising either from decommissioning (4) Hazard analysis: evaluation.
activities or accident situations, in which the screened hazards (5) Evaluation of results and identification of safety control
could be realized. measures.

The identification of initiating events and the analysis of their One of the first steps in developing a safety assessment for
evolution should be carried out using an appropriate technique. decommissioning activities is the identification of existing and
A wide range of different methods, such as Hazards and Operability future hazards (both radiological and non-radiological) that can
Study (HAZOP), Failure Mode and Effect Analysis (FMEA), Fault affect workers, members of the public and the environment during
Tree Analysis, are used for the hazards identification and analysis decommissioning activities, and then to identify engineered and
(Hashemi-Tilehnoee et al., 2010). In the nuclear industry HAZOP administrative control measures to prevent, eliminate or mitigate
method is used rather often (Jeong et al., 2008; John, 1988). The the hazards and their consequences. It is critical to the safety
HAZOP method is a formal, systematic, and critical approach to assessment that all reasonably foreseeable initiating events and
identifying the qualitative potential of hazards and operating prob- accident scenarios are identified (International Atomic Energy
lems associated with an existing or new system or piece of equip- Agency, 2013).
ment, caused by deviations from the design intent, and their Analysis of the possible hazards, raised by the proposed D & D
resulting consequential effects (Kletz, 1997; Hyatt, 2004). technology, starts before safety case development. A nuclear safety
The paper discusses hazard identification approach (HAZOP) case is a set of documents that describe the radiological and non-
used for decontamination and dismantling (D & D) projects at radiological hazards in terms of a facility or site and modes of oper-
the Ignalina NPP related to the dismantling and decontamination ation (including potential undesired modes) and the measures that
of the equipment located in buildings 117/1 and V1. Also, the prevent or mitigate the harm being incurred. The safety case
same HAZOP method was employed for hazard identification in should provide a coherent demonstration that relevant standards
feasibility study for management of Bohunice V1 NPP primary have been met and that risks to persons have been reduced to As
circuit components. The HAZOP study considered and reviewed Low As Reasonably Achievable. Safety assessment, an integral part
the available potential hazard management strategies for satisfy- of the safety case, is driven by a systematic assessment of these
ing the ALARA principle. Accumulated experience of the Lithua- hazards and is an important component of the safety case
nian Energy Institute experts in preparation of safety analysis for (International Atomic Energy Agency, 2012). The safety analysis
operating NPP (Ušpuras et al., 2010) was successfully adopted should identify all relevant scenarios arising either from decom-
for the development of D & D works safety assessment for NPP missioning activities or accident situations, in which the screened
decommissioning. hazards could be realized. It is a fundamental requirement that all
reasonably foreseeable faults are identified as a part of safety case
development. Hazard identification is a ‘‘comprehensive process to
Table 1
be applied systematically to the identification and review of the
List of nodes for HAZOP study for Ignalina NPP D & D projects.
hazards presented by a facility or operation and a consideration
Node Title of the ways in which risk to workers, the public and the environ-
1 Plant and building preparatory work (e.g., install barriers and transfer ment due to these hazards might be realized”.
systems, remove cladding and insulation) Fault and hazard identification can be undertaken in several
2 Remove small items and small bore pipe-work from accessible areas,
ways using a range of tools and techniques (including Hazard
drives/motors
3 Remove large items (vessels) and pipe-work, remove valves from
and Operability [HAZOP]), and it is this technique, which was
pipe-work applied for D & D projects at the Ignalina NPP, as well as at feasi-
4 Remove filter medium bility study for management of Bohunice V1 NPP primary circuit
5 Size reduce large pipe-work and vessels components.
6 Decontamination and monitoring of cut segments and pipe-work
7 Place all waste in containers/trolleys for removal
8 Remove steel platforms, redundant electrical cabinets and cables
9 Transfer waste from building 2.1. HAZOP procedure
10 Clean/decontaminate room
11 Monitor room A Hazard and Operability Study (HAZOP) can be used at varying
Further Ignalina NPP D & D HAZOP studies considered each element or sequence times during the life cycle of the process, from process develop-
(‘‘node”) of the design and involved the application of Keywords. ment through to the closure of the plant, including hazard
S. Rimkevičius et al. / Annals of Nuclear Energy 94 (2016) 461–471 463

assessment of any modifications proposed during its operational stand-point, there are a number of organizational requirements,
life span (Schlechter, 1995). which need to be built into the process to ensure consistency. The
The HAZOP objectives are to identify, as far as reasonably prac- procedure for performing the HAZOP study is presented in Fig. 1.
ticable, all accidents of safety significance, which could occur, i.e., The discussion is oriented by a Record Sheet, where every point
to produce a comprehensive fault set. The HAZOP process aims of every discussed item is recorded by the Team’s Secretary. It is
to produce a comprehensive fault set that will allow the develop- essential that detailed records of the HAZOP study are made.
ment of a fault and hazard schedule to demonstrate that the iden- Record tables are used for recording the following for each
tified hazards are controlled. The procedure identifies: keyword:

s Possible initiating events. s Contributory causes,


s Nature of accident consequences. s Consequences,
s Existing Engineered Safety Systems currently included within s Comments recorded,
the design. s Possible indications and protection/mitigation measures,
s Existing Operational Safety Systems, which are a current normal s Recommendations, actions placed on team members.
practice.
s Requirement for additional safety systems (engineered or 2.1.1. Nodes
managerial). In order to carry out a systematic study, it is necessary to divide
s Operability or functionality issues. the plant, modification design or procedure into individual items,
operational steps, or areas having a single functional intent. These
The HAZOP technique is normally a team based structured may be plant items or steps in procedures and are referred to as
method of identifying hazards, contributory causes and operability nodes. Each node is given a unique identifying number during
problems in plant and procedures. HAZOP is an effectively struc- the course of the study. The examples of nodes are as follows:
tured brainstorming workshop, i.e., a series of meetings involving
interested parties and relevant technical specialists to give differ-  Lines between major pieces of equipment.
ent viewpoints working as a group to stimulate creativity and  Equipment items (tanks/vessels, columns, reactors).
generate ideas. The advantages of this technique are that:  Packages (compressors, chemical injection).
 Utilities/services (Air, N2, steam, drains, vents, sewers, etc.).
s It is a comprehensive and systematic process.
s It is recognized and able to receive regulator acceptance. 2.1.2. Keywords
s It covers hazards and operability. Keywords are words, which are hazard based or fault initiating
s The use of brainstorming encourages lateral thinking and events which should stimulate identification of hazards when
‘thinking outside the box’. applied to nodes. The hazard-based keywords are used as the basis
for discussing the following:
In order that the HAZOP process delivers its objective of a
systematic evaluation of the design from a safety and operability s Credibility or possible cause of the hazard.
s Qualitative consequences to operators, on-site workers and the
general public.
Divide plant into nodes s Protection/mitigation measures, which could be provided to
either reduce the frequency of the hazardous event, mitigate
the consequences or manage the hazard.
Choose a node s Once the full list of keywords has been examined for a particu-
lar node, the study proceeds to the next node, repeating the pro-
cess until all relevant nodes have been examined.
Choose a keyword
Many companies have modified the keywords and parameters
they use during HAZOP to better define the process that is to be
investigated. This is especially true in the nuclear industry, where
Apply keyword to node
additional terms are required to evaluate the specific hazards due
to radiation (Gould et al., 2005). Examples of Hazard based
standard keywords:
Identify hazards
s Fire/explosion
s Radiation/loss of shielding
Identify protection/ s Airborne/surface contamination
mitigation measures
s Loss of containment
s Wounding
s Impact/dropped loads
Choose next keyword
s Loss of services – power, air, ventilation
s etc.

Choose next node 2.1.3. Protection/mitigation measures


During the HAZOP study, the team will identify and record
those protection/mitigation measures, which are currently built
End HAZOP Follow up and Review into the design or form normal practice at the NPP. The protec-
tion/mitigation measures will be divided into engineered
Fig. 1. HAZOP study. (e.g., structural, containment, shielding, cladding, glove boxes,
464 S. Rimkevičius et al. / Annals of Nuclear Energy 94 (2016) 461–471

secondary containment, control and instrumentation, alarms and Lithuanian Energy Institute participated in two projects
trips, suppression systems, etc.) and operational/managerial devoted to decontamination and dismantling (D & D) of the Igna-
protection/mitigation measures (e.g., procedures, training, supervi- lina NPP equipment:
sion, etc.).
The HAZOP team identifies engineered safety features, safety- s INPP building 117/1 decontamination and dismantling project
related equipment and safety management provisions for the plant development.
or modification. Recommendations are made to design or plant/ s INPP building V1 equipment decontamination and dismantling
decommissioning management to prevent or mitigate the conse- design development.
quences of a deviation through either design or procedural
changes. Actions may also be placed to ask for further information The objective of Ignalina NPP D & D Engineering Projects was
or separate assessments. the development of an optimal dismantling and decontamination
After completion of the HAZOP study, a list of the identified strategy of the equipment and preparation of all documentation
potential initiating events will be generated, and their outcome required for implementation of this strategy.
will be summarized in the Fault Schedule (Fig. 2).
A Fault Schedule should be included of all the hazards and fault/ 3.1. Ignalina NPP building 117/1 decontamination and dismantling
accident conditions that are applicable to the decommissioning
activities; these may be grouped appropriately to reduce the num- The function of building 117/1 is to house the Pressurized Tanks
ber of scenarios that require analysis. The Fault Schedule will be an of the Emergency Core Cooling System, Helium Storage Facility and
input for accident analysis of selected design option during prepa- auxiliary systems and equipment. After shutdown of the reactor of
ration of safety assessment report. Ignalina NPP Unit 1, the high pressure part of the Emergency Core
Cooling System (ECCS) and the Helium Make-up Station, located in
3. HAZOP application for the Ignalina NPP decommissioning building 117/1, have become redundant and are no longer needed,
and dismantling projects neither for safety nor for operational purposes; therefore, they
were dismantled.
Ignalina Nuclear Power Plant (INPP) was an important part of The dismantling and decontamination of the equipment within
Lithuania’s Energy Sector since 1983 (Unit 1 – started operation building 117/1 was heavily based on the experience in similar pro-
in 1983, Unit 2 – in 1987, design lifetime was envisage up to jects throughout Europe. For implementing the entire building
2013 for Unit 1 and up to 2017 for Unit 2). The Ignalina NPP Unit 117/1 dismantling and decontamination process, the following
1 was shutdown at the end of 2004, while Unit 2 was shut down tools and installations were required:
at the end of 2009. As a result of the political dialog leading up
to EU enlargement, Lithuania agreed to the early decommissioning s Workshop facility.
of its reactors. s Equipment for decontamination.
According to the INPP Final Decommissioning Plan, the INPP s Electric overhead crane.
decommissioning process is split into several dismantling and s Vessel cutting equipment.
decontamination (D & D) projects. Each of these D & D projects cov- s Pipe cutting equipment.
ers a particular field of activity, for example, initial primary circuit s Handling equipment.
decontamination or dismantling of equipment using ‘‘room by s Ventilation equipment & mobile filter unit.
room” or ‘‘system by system” approach (Babilas et al., 2015). s Monitoring equipment.

Divide system into nodes


HAZOP

Select the node

Record hazard/ YES Apply all keywords in NO


consequences, suggest turn. Any hazards/
mitigation measures operational problems
occurs?

NOT SURE

FAULT SCHEDULE

Fig. 2. HAZOP approach.


S. Rimkevičius et al. / Annals of Nuclear Energy 94 (2016) 461–471 465

In order to allow the final size reduction and decontamination Most of building V1 equipment and components were not needed
processes to be carried out with minimal risk of airborne activity following the Reactor Final Shutdown and after Reactor Defuelling.
release and spread of contamination, a new containment structure For building V1 D & D, the preference was for manual cutting
within building 117/1 was constructed to house the size reduction, techniques that minimize secondary waste. The cold-cutting tech-
decontamination workshop and monitoring area. niques were favoured where appropriate to reduce the need for
According to the building 117/1 D & D Basic Design, the main Mobile filtration units and ventilation modifications as required
characteristics of the preferred D & D Strategy were identified as by hot cutting techniques. Combination of plasma arc and cold cut-
below: ting techniques were used to cut the large items (tanks, vessels,
etc.). For dismantling and subsequent size reduction of large
s In-situ size reduction followed by decontamination. (thicker walled) plant items (including vessels), a number of tech-
s ECCS vessel cutting by oxy-acetylene. niques have been considered in the development of options,
s Large pipe/valve cutting by ‘tool kit’ of techniques. namely plasma cutting, flame cutting, shears, diamond wire saws,
s Small pipes/fabrications cutting by ‘tool kit’ of techniques. circular saws and band saws. In line with previous building 117/1
s Decontamination by manually deployed vacuum abrasive D & D project, a ‘toolbox’ of standard techniques was used for some
blasting. items such as small pipes. Such a ‘toolbox’ would typically contain
the following techniques, e.g., hydraulic shears, reciprocating saws,
Details of the cutting process of ECCS vessels are shown in
electric nibblers, angle grinders, etc. Hot cutting was generally pre-
Fig. 3.
ferred for thick-walled materials, such as vessels, tanks and filters.
Whereas upper and lower dished end sections of the ECCS
vessels were cut manually and removed piece by piece, the cutting
of the cylindrical tank section was carried out using the remotely 3.3. Identifying and analyzing the hazards for D & D tasks of Ignalina
controlled torch/tractor system. Several ring sections were cut-off NPP buildings 117/1 and V1
sequentially in the same order.
Decommissioning of INPP buildings involved different types of
activities, tools, equipment and systems. There was a potential
3.2. Ignalina NPP building V1 decontamination and dismantling for a wide range of radiological and industrial hazards during
various stages of these buildings decommissioning projects creat-
One of the first buildings to undergo decommissioning was ing risk for workers and environment. The occurrence of hazards
Ignalina NPP building V1 (Fig. 4). Building V1 is dedicated to the was possible due to many different operations involving move-
location of significant sections of the reactor auxiliary systems ment and handling of large pieces of equipment and contaminated
including: the Reactor Gas Circuit, the Off-gas Clean-up System, items. In addition, size reduction and decontamination processes
the Main Circulation Circuit Maintenance Cooling Tank System, are capable of producing hazards. The main difference was that
different elements of the Ventilation Systems and part of the Emer- the main part of the equipment to be dismantled belonged to the
gency Core Cooling System as well as related auxiliary equipment. ECCS vessels and was located almost in one area of building

Fig. 3. ECCS vessel dismantling.


466 S. Rimkevičius et al. / Annals of Nuclear Energy 94 (2016) 461–471

Fig. 4. Panorama of the Ignalina NPP site and location of building V1.

117/1, while building V1 of INPP was a complex facility with over 3.4. INPP buildings D & D HAZOP steps (nodes)
200 rooms housing several auxiliary systems for Unit 1.
Accumulated experience of the Lithuanian Energy Institute The buildings V1 and 117/1 were assessed by separating the
experts in preparation of safety analysis for operating the NPP plant and equipment into functional nodes, each of which cover
was successfully adopted for the development of D & D works a subset of common issues and D & D strategy. These nodes were
safety assessment at the Ignalina NPP. In addition to the existing then analyzed in turn by the application of a set of keywords to
safety assessment practice, HAZOP method for the identification each node.
and evaluation of potential hazards, raised due to proposed D & The nodes considered in the INPP D & D HAZOP studies are
D activities in INPP buildings, was used. listed in Table 1.
It shall be justified that all worst emergency cases raised by the
proposed D & D technology are identified, and possible conse- 3.5. INPP buildings D & D HAZOP keywords
quences are analyzed. The HAZOP procedure was applied for this
purpose for the Ignalina NPP building 117/1 and V1 D & D projects. HAZOP studies for Ignalina NPP buildings D & D projects
HAZOP for Ignalina NPP D & D projects was organized in a series involved the application of defined keywords to the design in order
of meetings involving different experts related to the planned to prompt a discussion that identified principal hazards (initiating
activities and responsible for the radiation and industrial protec- events) and operability issues. This enabled their elimination and
tion, operational activities, etc. The basic concepts were relayed the specification of protective measures. The standard HAZOP
to the HAZOP team as presentations, supported by original system keywords conventionally used for decommissioning operating
drawings from the Ignalina NPP. tasks were used and are listed in Table 2.
The main objectives of these HAZOP Studies for Ignalina NPP D
& D projects were as follows:
3.6. INPP buildings D & D hazards identified at HAZOP studies
s Provide an identification of principal hazards.
The following main hazards with potentially significant conse-
s Identify potential hazard management strategies for addressing
quences associated with the Ignalina NPP building 117/1 and V1
the principal hazards.
D & D activities were identified by means of hazard and operability
s Identify operability issues, which need to be resolved.
(HAZOP) studies:
Buildings of Ignalina NPP are complex facilities with many
s Dropped heavy loads creating a risk of structural damage,
rooms housing several auxiliary systems for Unit 1. Therefore, it
airborne activity releases, worker injury or fatality, damage to
was proposed that the HAZOP studies would examine generic
live essential services.
aspects of the INPP buildings decontamination and dismantling,
s Dropped highly contaminated items, i.e., filters, waste drums
which are applicable to all the systems and to most of the rooms,
resulting in release of airborne contamination.
and specific aspects only relevant to certain systems. It was consid-
s Loss of ventilation. Mobile filtering units (MFUs) and fume
ered impractical to apply a HAZOP study to every room, as there
extract units (FEUs) are intended to maintain a safe working
are many common features both between the rooms and between
environment in localized containment areas during D & D oper-
the auxiliary systems. It is clearly impractical and unnecessary to
ations, removing combustion gases and minimizing the spread
consider operations in each individual room in the building, as this
of airborne contamination. Loss of ventilation can lead to oper-
would involve considerable time and much repetition.
ator asphyxiation, exceeding safe concentration limits for
The studies were carried out as a desk top by the HAZOP task
airborne toxic material, increased radiological internal dose
leader. The HAZOP studies have allowed performing a systematic,
and potential for spread of contamination.
comprehensive examination of potential hazards that may repre-
s Loss of containment, damage to local containment tenting,
sent risks to personnel and equipment. Reasonably foreseeable
failure to deploy temporary covers on pipe-work and vessels
hazards, initiating events and scenarios associated with planned
during cutting.
Ignalina NPP D & D activities were considered and identified.
S. Rimkevičius et al. / Annals of Nuclear Energy 94 (2016) 461–471 467

Table 2 s Protection of live cables and operational systems in cutting


Ignalina NPP D & D projects, HAZOP study keywords. areas to prevent damage.
1. External dose 14. Wastes s Control of equipment, tools and waste containers to ensure that
2. Internal dose 15. Corrosion and erosion they are certified, tested and adequately identified.
3. Shielding 16. Associated facilities s All activities were done according to approved procedures,
4. Containment 17. Extreme weather, wind,
temperature, flooding
under direct management of work supervisor.
5. Ventilation 18. Seismic
Also, it was assumed that the managerial protection and mitiga-
6. Fire 19. Toxicity
7. Explosion and overpressure 20. Dropped loads, impacts tion will include, but not be confined to, the following generic
8. Chemical reaction 21. Conventional hazards requirements:
9. Maintainability 22. Access
10. Remote handling 23. Environmental impact s Operator training.
11. Loss of services: power, steam, 24. Control and instrumentation
water, compressed air
s Use of suitably qualified and experienced personnel (SQEP).
12. Operator error 25. Communications s Use of approved procedures and site instructions.
13. Effluents: gaseous, liquid 26. Domino effects s Compliance with Lithuanian regulations.
The HAZOP team considered the issues and consequences in turn as appropriate. All
protection/mitigation measures required to prevent the hazard or mitigate the The purpose of the HAZOP studies was to identify faults and
consequences were recorded during INPP buildings D & D HAZOP meetings. consequent hazards in support of the Ignalina NPP buildings
117/1 and V1 equipment Decontamination and Dismantling
Design Development and Safety Justification Reports; therefore,
s Failure/malfunction of building ventilation system can lead to the identified potential initiating events and their outcome were
overpressure of building and potential uncontrolled release of qualitatively presented in the Fault Schedule of SJR. The Fault
airborne activity through building structural leakages into Schedule also includes events and faults having non-radiological
adjoining facilities and to the environment. consequences, e.g., the release of toxic fume, and identifies the
s Fire/explosion. Use of hot cutting technique potentially intro- safety measures to be provided. From the findings of the fault iden-
duces fire/explosion hazards. tification study, it was possible to identify the bounding case fault
Hazards arising from industrial accidents, loss of operational sequences, which can potentially lead to the worst case radiologi-
services, human error and organisational failures not resulting in cal consequences.
radiological consequences are controlled and mitigated by Ignalina
NPP site procedures and adequate work planning. 4. HAZOP application in feasibility study for the management of
Bohunice V1 NPP primary circuit components
3.7. INPP buildings D & D safety measures
The obtained experience of LEI experts in conduction of HAZOP
The emphasis of Ignalina NPP D & D HAZOP studies was on studies for the assessment of the proposed D & D methods for Igna-
consideration of practical measures to prevent, protect from and lina NPP building decommissioning was successfully adopted for
mitigate hazards identified in the study while addressing the exist- the development of Feasibility Study for the Management of Bohu-
ing protection/mitigation measures and potential for additional nice V1 NPP primary circuit components.
safety measures. Bohunice V1 nuclear power plant with two reactor units
A number of safety measures have been identified in order to (type VVER 440/V 230) (see Fig. 5) was constructed according to
satisfy the ALARA principle throughout the D & D operations in a Russian design in the period from 1973 to 1977. Initial criticality
buildings 117/1 and V1: at Units 1 and 2 was reached in 1978 and 1980, respectively. In the
90-s, an extensive reconstruction of the plant was performed
s The caps were welded on the open pipelines to avoid any aimed at increasing its nuclear and radiation safety with the
possibly of contaminated water leaking from the pipe-work. objective to reach the worldwide acceptable level of nuclear safety
s Improved sealing of existing bulkhead in the pipe tunnel in at the time. Nevertheless, afterwards in relation to Slovakia’s
order to minimize the concentration of airborne activity and access to the EU, the government of the Slovak Republic in its
control spread of contamination. resolution decided on the premature shutdown of the V1 NPP
s Polyethylene sheet and adhesive tape was used to seal openings and approved the dates for Units 1 and 2 shutdown (2006 and
into components to avoid contamination spread (e.g., floor 2008, respectively).
cleaning after dismantling work, use of tacky mats in entry The objective of Feasibility Study for the Management of V1 NPP
tents, etc.). primary circuit components was to identify, analyze, justify and
s Ventilation systems were provided the necessary air changes to rank alternative solutions towards the dismantling and manage-
reduce the risk of high concentrations of toxic gases, metallic ment of the large components of the two units of Bohunice V1
fume and airborne activity. Localized mobile ventilation NPP Primary Circuit included in the following list:
systems with HEPA filtration were used to supplement the
existing buildings 117/1 and V1 ventilation system. s Reactor pressure vessel (RPV)
s Catch pot at the bottom of the vessel to catch the hot cutting slag s Reactor internal structures (RIS)
and particulate falling inside the vessel and thus avoid blockage s Main circulation pipelines and main circulation pumps
of the ventilation flow route from the vessel were used. s Steam generators
s Personal dosimeters, portable area gamma alarms and portable air s Main gate valves
monitoring units for continuous monitoring of gas and airborne s Pressurizer and pressurized tank
activity at occupied work areas with alarm function were used. s Annular water tank (AWT)
s Appropriate use of personal protection equipment (respiratory s Mogilnik, etc.
protection and safety measures to protect the face and hands).
s Emergency access and egress routes (including revised signage, This Feasibility Study included the development and screening
emergency lighting, crash bar fire exit door to external area). of alternatives, and a detailed evaluation of alternative actions
468 S. Rimkevičius et al. / Annals of Nuclear Energy 94 (2016) 461–471

Fig. 5. The view on objects at Bohunice site.

towards the dismantling and waste management of V1 large  Alternative A3: Fragmentation of activated equipment, separa-
components. Description of V1 NPP primary circuit equipment tion and decay storage of MLW.
management alternatives is presented in Section 4.1.  Alternative C1: Dismantling of whole contaminated equipment
Application of HAZOP study to the management of Bohunice V1 and disposal in whole.
NPP primary circuit components was used in assessment of each  Alternative C2: Dismantling of whole contaminated equipment
alternative with respect to overall protection of human health with subsequent fragmentation and decontamination in a sepa-
and the environment criterion. Methods of alternatives assessment rate facility.
and results of HAZOP Study formed the framework for alternatives  Alternative C3: Dismantling of contaminated equipment in
analysis. large fragments with subsequent fragmentation and decontam-
ination in a separate facility.
4.1. Identifying and analyzing the hazards for decommissioning tasks  Alternative C4: Complete in-situ fragmentation of contami-
of Bohunice V1 NPP nated equipment and decontamination using other facilities.

A detailed analysis of V1 NPP primary circuit equipment man- Individual analysis included evaluation of each alternative
agement alternatives was performed, which comprised individual against a set of criteria. The following criteria for alternatives
and comparative analysis of the alternatives. Highly activated assessment have been identified:Criterion 1. Short and long-term
and contaminated waste requires completely different treatment Client’s Policy and Criteria.Criterion 2. Overall Protection of Human
and final disposal (storage); therefore, its management alternatives Health and the Environment.Criterion 3. Compliance with Applica-
are developed separately. V1 NPP primary circuit includes the ble or Relevant and Appropriate Requirements.Criterion 4. Long-
following activated equipment, such as RPV, reactor internals, term effectiveness and permanence.Criterion 5. Reduction of
shielding assemblies, annular water tank. Contaminated equip- volume.Criterion 6. Short-term effectiveness.Criterion 7. Technical
ment consists of steam generators, main circulation pumps, main and administrative implementability.Criterion 8. Cost.
circulation circuit pipes, etc. This kind of equipment does not con- The alternatives have been individually analyzed against each
tain activated metal but only surface contamination. criterion and then compared against one another to determine
Alternatives for management of primary circuit components their respective strengths and weaknesses and to identify the key
were developed based on high-level scenarios and technical trade-offs that must be balanced for the site. For each criterion,
options. Alternatives were compiled using uniform approach to an evaluation method including qualitative and quantitative
combination of feasible options and scenarios for different kind parameters was developed. The evaluation was performed using
of equipment. After screening, three alternatives remained for the developed method. Evaluation results included both numerical
activated equipment. Four alternatives developed for contami- values, like volume, dose, cost, and qualitative estimates using five-
nated equipment cover full range of feasible waste management grade ‘‘low–fair–medium–good–excellent” scale. Comparative
possibilities. These three alternatives for activated equipment analysis included mapping scores of the alternatives to the numer-
management (Alternatives A) and four alternatives for contami- ical 1–100 scale, weighting the criteria and final calculation. The
nated waste management (Alternatives C) were analyzed: results of final calculation are provided in Table 3 and Fig. 6 below.
Detailed analysis of alternatives was a final step in developing
 Alternative A1: Dismantling of whole activated equipment, of alternative solutions for the management of Large Components
placement of the RIS into the RPV, decay storage. of Primary Circuits of two Units of V1 NPP and providing the
 Alternative A2: Dismantling of whole activated equipment, decision-makers with sufficient information on high ranked alter-
placement of the RIS partly into the RPV, partly into shielding native solutions, resulting from their comparative analysis, in order
containers, decay storage. to justify their acceptance for implementation.
S. Rimkevičius et al. / Annals of Nuclear Energy 94 (2016) 461–471 469

Table 3 There is a risk of external and internal exposures for the opera-
Results of comparative analysis. tion personnel when handling the radioactive materials; therefore,
Alternative A1 A2 A3 C1 C2 C3 C4 non-presence of personnel at the reactor hall during activated
Total benefit 65.7 63.5 81.3 57.9 73.4 84.8 90.7 equipment (e.g., RPV, RIS) handling and transfer is required. Spread
of contamination, asphyxiation, drop of loads, pipe whip, heat and
sparks, both of which are potential fire or burn hazards during acet-
ylene cutting, structural failures are additional potential hazards.
As barriers for preventing human exposure and/or spread of
radioactive materials to the environment under management of
V1 NPP PCC protective shields with varying wall thickness (depends
on the dose rate), portable screens, heavy protective containers,
weld-on metal stoppers (plugs), double protective lids, etc. are
employed.
Other precautions for mitigating the hazards associated with a
PCC dismantling operations are listed below:

s Crane, hoisting units and a special lifting traverse to be


employed for lifting heavy components (e.g., RPV) and for open-
ing apertures. Remote control for crane for exact positioning as
well as additional crane load capacity check are needed to
decrease the risk of working environment hazards.
s Lifting systems must have auxiliary power or protections in
case of power loss.
Fig. 6. Results of comparative analysis.
s Remotely controlled mechanical cutting to be used to avoid
high dose rate.
HAZOP study in Feasibility Study for the Management of V1 NPP s Use of high-resolution cameras for remote monitoring of dis-
primary circuit components (PCC) was applied in the assessment mantling operations shall be required. Visual system of position-
and ranking of individual alternatives with respect to overall pro- ing, visual control of stropping after cutting, visual control on the
tection of human health and the environment criterion. Overall work with manipulator decrease working environment hazards.
protection of human health and the environment addresses s The welding operation must be carried out in accordance with
whether the alternative provides adequate protection and this safety procedures. The work must be carried out under close
criterion describes how risks are eliminated, reduced, or controlled supervision.
through treatment, engineering controls, or institutional controls. s Fire alarms and firefighting equipment are fully operational.
HAZOP workshop with a team consisting of consortium experts, s Fume extraction unit with spark arrester shall be employed for
plant operators, engineers, managers and others, some of whom extraction and filtration of welding fume.
were familiar with the facilities, was prepared and conducted in s HEPA filtered vacuum cleaners were used to collect cutting
the initial assessment phase of the Feasibility Study. The main waste, dust and dirt.
hazards, their contributory causes and appropriate safety measures s As a result of building ventilation system with additional MFU,
were identified by means of HAZOP studies during INPP buildings suitable conditions were created for work of operational
D & D projects. personnel and equipment, prevention of contamination spread-
HAZOP study considered each element or sequence (‘‘Node”) of ing, provision of air filtration, check-up and organized discharge
the alternative and involved the application of Keywords in order of air, which could be contaminated by radioactive aerosols.
to identify and evaluate problems that may represent risks to per- s Protective tent connected to the ventilation system was
sonnel or equipment. List of nodes for each alternative in HAZOP arranged to prevent concrete dust from spreading.
study for the Management of V1 NPP PCC is provided in Table 4. s Temporary coverings (tents) for building door opening were
For each Node under consideration, the appropriate keyword employed to reduce spread of airborne contamination.
(Table 5) was applied to prompt discussion of the alternative s Proper personnel protective equipment (eye protection; long-
intent. The team considered the issues and consequences in turn sleeved clothing; sturdy, full length pants; steel-toed boots or
as appropriate. shoes; hearing protection; and safety gloves) must be used to
A summary of Individual Analysis results was developed based avoid exposure to workers during the handling of impacted
on the performed assessments and the results of HAZOP study. The materials.
acceptability and performance of each node against the Overall s Personal air samplers were issued to personnel working on dust
protection of human health and the environment criterion were producing tasks.
evaluated individually so that relative strengths and weaknesses
are identified. Any protection/mitigation measures required to Conventional safety is highly significant during PCC dismantling
prevent the hazard or mitigate the consequences were recorded. operations, e.g., apertures in walls have to be closed; fixing pipes to
prevent their inadvertent shifting; marking cutting lines; checking
4.1.1. Hazards and Safety Measures from ‘‘Nodes” of the alternatives welding points; no people in cutting area during tank cutting into
with respect to overall protection of human health and the fragments using a cable saw (entering the shaft only when cutting
environment criterion is stopped); no work underneath suspended loads; collection of
Individual Evaluation of Nodes of the alternatives against asbestos in a special box, etc.
overall protection of human health and the environment criterion Specific precautionary measures for working at height must be
is presented in this chapter. Assessment against the criterion of ensured, e.g., workers shall be required to wear suitably anchored
Overall Protection of Human Health is categorized as a threshold lanyards with harnesses and fall arrestors. Double- checking work
criterion. This threshold criterion must be satisfied in order for operations will be used as a proactive principle for decreasing the
an alternative to be eligible for selection. risk of human errors.
470 S. Rimkevičius et al. / Annals of Nuclear Energy 94 (2016) 461–471

Table 4
List of nodes for each alternative in HAZOP study for the management of V1 NPP PCC.

Alternative Node Node short description


Alternative A1 – Dismantling of whole activated equipment, RPV-1 Disconnection of the RPV from all process communications
placement of the RIS into the RPV, decay storage RPV-2 The RPV is slung and transferred to the transport corridor and anchored in the
vertical position on the platform
RPV-3 Cutting upper part of Protective Tube Unit
RPV-4 The RIS are emplaced inside the RPV
RPV-5 The RPV is lowered onto the platform with the aid of additional hoisting
mechanisms
AWT-1 Fixation of the AWT
AWT-2 In-situ fragmentation of the AWT
Alternative A2 – Dismantling of whole activated equipment, RPV-1 Disconnection of the RPV from all process communications
placement of the RIS partly into the RPV, partly into shielding RPV-2 The RPV is slung and transferred to the transport corridor and anchored in the
containers, decay storage vertical position on the platform
RPV-4 The RIS are emplaced inside the RPV
AWT-1 Fixation of the AWT
AWT-2 In-situ fragmentation of the AWT
Alternative A3 – Fragmentation of activated equipment, separation RPV-1 Disconnection of the RPV from all process communications
and decay storage of MLW RPV-2* The RPV is slung and transferred into the SG-MCP bay
RPV-6 RPV and RIS fragmentation into fragments
AWT-1 Fixation of the AWT
AWT-2 In-situ fragmentation of the AWT
Alternative C1 – Dismantling of whole contaminated equipment and SG-1 Disconnection of SG from process communications
disposal in whole SG-2 SG is dragged under the aperture
SG-3 SG is removed through an aperture and transferred to the transport corridor and
anchored on the platform
MG-1 Demolishing of concrete
MG-2 Dismantling of pipes
Alternative C2 – Dismantling of whole contaminated equipment with SG-1 Disconnection of SG from process communications
subsequent fragmentation and decontamination in a separate SG-2 SG is dragged under the aperture
facility SG-3 SG is removed through an aperture and transferred to the transport corridor and
anchored on the platform
Alternative C3 – Dismantling of contaminated equipment in large SG-1 Disconnection of SG from process communications
fragments with subsequent fragmentation and decontamination in SG-5 Cutting SG at their regular position into large fragments
a separate facility
Alternative C4 – Complete in-situ fragmentation of contaminated SG-1 Disconnection of SG from process communications
equipment and decontamination using other facilities SG-6 Cutting SG at their regular position into small fragments
*
Difference for node RPV-2 in Alternative A3 is that in case of A3, the RPV is transferred into the SG-MCP bay instead of the transport corridor (Alternatives A1 and A2).

Table 5
D7.1 project, HAZOP study keywords.
decommissioning project, creating risk for workers and environ-
ment. The identification of the hazards and the analysis of their
Direct radiation Contamination evolution should be carried out using an appropriate technique.
Dispersion Fire
Explosion Gas generation
In the nuclear industry, HAZOP method is used rather often.
Flooding Handling The paper presented the application of HAZOP technique at two
Missiles Chemical/toxic different decommissioning stages:
Utilities Degradation/aging
Maintenance faults Operational faults
- for identification of the hazards raised due to dismantling and
Interfacing (Domino effect) Extreme weather
External fire Seismic decontamination activities in Ignalina NPP buildings after justi-
Communication – fication of the preferred D & D Strategy and
- in feasibility study for the management of Bohunice V1 NPP
primary circuit components.

The purpose of the INPP building D & D HAZOP studies was to


The adherence to the ALARA principles of restricted time for
identify faults and consequent hazards in support of the SJR devel-
operation; distance and shielding will underpin dismantling oper-
opment. Identified potential initiating events and their outcome
ations of V1 NPP primary circuit components and will protect
were qualitatively presented in the Fault Schedules of SJR. Poten-
workers (PPE, monitoring of activity levels). Environmental
tial hazard management strategies have been determined. A num-
impacts, which may result in the uncontrolled release of radioac-
ber of safety measures have been identified in order to prevent
tive material to the environment, are not expected under V1 NPP
undue routine radiation exposures to the facility staff, public and
PCC dismantling operations. There is no evidence of contaminated
the environment according to the ALARA principle throughout
effluents or leakage of radioactive material.
the INPP building D & D operations. These safety measures are
largely of a passive nature, i.e., controlled access, reduced exposure
5. Conclusions times, provision of localized ventilated containments with HEPA
filters, continuous gas and airborne activity monitoring, shielding,
Decommissioning of NPPs involves different types of activities, operational measures to reduce operator error and personal pro-
tools, equipment and systems. There is a potential for a wide range tection equipment, decontamination equipment preventing spread
of radiological and industrial hazards during various stages of NPPs of contaminated dust, etc.
S. Rimkevičius et al. / Annals of Nuclear Energy 94 (2016) 461–471 471

Application of HAZOP study to the management of Bohunice V1 the EBRD-managed Ignalina International Decommissioning Sup-
NPP primary circuit components was used in assessment of each port Fund (IIDSF).
alternative with respect to overall protection of human health
and the environment criterion. Methods of alternatives assessment References
and results of HAZOP Study formed the framework for alternatives
analysis. According to HAZOP study, the major risks to come are International Atomic Energy Agency, 2009. Safety Assessment for the
Decommissioning of Facilities Using Radioactive Material Safety Guide, IAEA
those resulting from the activities of dismantling and removal of Series No. WS-G-5.2, Vienna.
large-size and highly activated and contaminated primary circuit Hashemi-Tilehnoee, M., Pazirandeh, A., Tashakor, S., 2010. HAZOP-study on heavy
components from their current protective structures, the relevant water research reactor primary cooling system. Ann. Nucl. Energy 37, 428–433.
Jeong, K., Lee, D., Lee, K., Lim, H., 2008. A qualitative identification and analysis of
doses and potential releases to the environment, as well as indus- hazards, risks and operating procedures for a decommissioning safety
trial hazards related to the operations with the heavy components, assessment of a nuclear research reactor. Ann. Nucl. Energy 35 (10), 1954–1962.
including their handling and transportation. John, B., 1988. Garrick. The approach to risk analysis in three industries: nuclear
power, space systems, and chemical process. Reliab. Eng. Syst. Saf. 23 (3), 195–
The adherence to the ALARA principles of time, distance and 205.
shielding underpins operations of V1 NPP primary circuit equip- Kletz, T.A., 1997. HAZOP-past and future. Reliab. Eng. Syst. Saf.
ment management alternatives and protects workers (PPE, moni- Hyatt, N., 2004. Guidelines for Process Hazards Analysis. Hazards Identification and
Risk Analysis. CRC Press in corporation by DYADEM Press.
toring of activity levels, etc.). Environmental impacts, which may
Ušpuras, E., 2010. State of the Art of the Ignalina RBMK-1500 Safety. Hindawi
result in the uncontrolled release of radioactive material to the Publishing Corporation. Science and Technology of Nuclear Installations. vol.
environment, are not expected under these operations. There is 2010, Article ID 102078. doi:10.1155/2010/102078.
International Atomic Energy Agency, 2013. Safety Assessment for
no evidence of contaminated effluents or leakage of radioactive
Decommissioning, IAEA Safety Reports Series. No. 77, Vienna.
material. Schlechter, W., 1995. Process risk assessment – Using science to ‘‘Do It Right”. Int. J.
Individual and comparative analysis of alternatives for manage- Press. Vessels Pip. 61 (n2–3), 479–494.
ment of Bohunice V1 NPP primary circuit components provided a Gould, J., Glossop, M., Ioannides, A., 2005. Review of Hazard Identification
Techniques. Health and Safety Laboratory, 2005/58.
well-grounded basis for decision makers to choose the best Babilas, E., Uspuras, E., Rimkevicius, S., Dundulis, G., Vaisnoras, M., 2015. Safety
solution for decommissioning of V1 NPP. assessment of low-contaminated equipment dismantling at nuclear power
plants. In: Sci. Technol. Nucl. Install., 1687-6075 2015, 1–11. http://dx.doi.org/
10.1155/2015/650810 650810.
Acknowledgement International Atomic Energy Agency, 2012. Safety Standards Series No. SSG-23, The
Safety Case and Safety Assessment for the Disposal of Radioactive Waste,
Dismantling and Decontamination projects B9-0 and B9-2 at Vienna.
the Ignalina NPP referred to in the paper were grant funded by

You might also like