REPLY TO WSP SITE MEMO

REF : M805 / REPLY TO SITE MEMO / C-007


DATE : 04/09/2018
TO : WSP
FROM : KEC INTERNATIONAL LTD.
CONTRACT : N-15284
PROJECT: 400kV OHL BAB/DHAFRAH & 400kV OHL WORKSAROUND HARAH AND FAYA
SUBJECT: POINTS TO BE IMPLEMENTED –SITE MEMO C-007 dt 01.09.2018

Dear Sir,
Reference to the site memo C-007 dt 01.09.18 , We have taken necessary corrective measures and
implemented all points notified in the site memo as under

1) Barricading around Machinaries


Reply: Noted and complied

2) Storing of Tools and Equipments


Reply: Noted and complied

3) Welfare facilities for workers


Reply: Noted and complied

4) Mobile Toilets
Reply: Noted and complied

This is for your information and record please

KEC INTERNATIONAL LTD.

Signature
You are advised take necessary action and requested send us the report for the action taken up on the
above issues.

1) Warning tape shall be placed around any operated machines.


Reply: Noted and complied (Evidence photo attached)
2) Tent to be maintained.
Reply: Noted and complied (Evidence photo attached).
3) Provide sufficient space between steel members
Reply: Noted, will be followed in the future.
4) Welfare facilities without water
Reply: Noted and will be complied.
5) Workers shall work in safe place not near to access road.
Reply: Noted and will be followed in future.
6) Communication device is required between the supervisor and workers
Reply: Noted and will be followed.

7) Concrete block to be protected at the side near to access road.


Reply: Noted and will be followed in future.
8) Shed to be maintained
Reply: Noted and will be followed.
9) Leveling the ground allow workers work in safe condition.
Reply: Noted, will be followed.
10) Loading of steel casing was done without supervision.
Reply: Noted and will be followed.
11) Unwanted material to be removed.
Reply: Noted and complied
12) Unsafe support for rebar cage .
Reply: Noted and will be followed in future.
13) Oil drums shall be placed away from the access road.
Reply: Noted and will be followed.
14) Fire extinguishers to be maintained.
Reply: Noted and will be followed.
15) Machine to be maintained
Reply: Noted, will be followed.
16) Container used as worker area which is very hot.
Reply: Noted and complied (Evidence photo attached).
17) The container stored with flammable material.
Reply: Noted and complied

KEC INTERNATIONAL LTD.