ASSIGNMENT No.

3
Date for submission: 30/03/2020
Name: Amlan Khan
ID: 20180312026
Answer: Yellow color marked

Question: 1
Which of the following is not true?
(a) Every project is unique
(b) A project gives some output
(c) Projects are not repetitive
(d) Car manufacturing is an example of project

Question: 2
A person who is directly or indirectly involved with your project, or affected by your project or
its outcome, is known as:
(a) Customer
(b) Manager
(c) Team Member
(d) Stakeholder

Question: 3
Which of the following statement is true about a Program?
(a) A Program is a group of related projects
(b) A Program is group of unrelated projects
(c) A Program is a part of a big project
(d) None of the above

Question: 4
During a bidder conference you see that one bidder is your close friend. What should your next
step be?
(a) You will pass some confidential info to him
(b) You will disclose this relationship to your management
(c) You will resign immediately from the bidding process
(d) You will try not to give the contract to him to prove your integrity

Question: 5
How will you deal with the stakeholders with High Interest but Low Power?
(a) Keep them informed
(b) Monitor them
(c) Manage them closely
(d) Try to satisfy them

Question: 6
A subcontractor is delaying the delivery of the deliverables. Which of the following should you
do?
(a) Cancel the contract
(b) Schedule a meeting with contractor
(c) Inform management
(d) Delay the payment

Question: 7
In which of the following phases of the project will most of the money be spent?
(a) Initiating
(b) Planning
(c) Executing
(d) Closing

Question: 8
The most common cause of conflict within a project is:
(a) Schedule
(b) Personnel
(c) Procedures
(d) Resources

Question: 9
Whenever you receive a change request, what will be your next step?
(a) Process for approval
(b) Investigate it
(c) Reject it
(d) Ignore it

Question: 10
When should you update lessons learned?
(a) At the beginning of the project
(b) At the middle of the project
(c) Throughout the project
(d) At the end of the project

You might also like