Method Statement For Pile Hacking Works (Bored Piles at TR4 Project) PDF

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

METHOD STATEMENT CHIPPING OF BORED PILES

Title: Chipping of Bored Piles Document No.: C3INC-DOC-MS-004

1.0 Introduction

The preparation of piles for the next phase of construction involves demolition of excess concrete until the
desired cut-off elevation is reached. The process is often considered cumbersome if not given sufficient early
thought and planning. Despite the influx of new technologies in pile hacking, the traditional method is still
considered to be the most effective and economical approach. With skilled manpower with their sledge
hammers and chisels plus the assistance of heavy equipment such as backhoe or crane as the only
mechanism, pile hacking can be done fast, safe and efficient if proper technique was employed. The objective
of the document is to provide detailed instruction and direction for traditional method of breaking of
concrete piles.

2.0 Tools and Materials

 Sledge Hammers
 Rebar Chisels
 Spray Paint
 Oxygen and LPG/Acetylene Gas Tanks

3.0 Plant and Equipment

 Oxy-acetylene/LPG Cutting Set


 Survey Equipment
 Backhoe or Crane with Lifting Belt if needed
 Scaffolding if necessary
 Power Supply

4.0 Manpower

 Foreman
 Safety Officer
 Surveyor
 Heavy Equipment Operator
 Pile Hacking Operatives

Project : South Luzon Expressway Phase II Date : 22 Aug 19


Doc. Title: Chipping of Bored Piles Rev: 0
Doc. No.: C3INC-DOC-MS-004 Page: 1 of 2
METHOD STATEMENT CHIPPING OF BORED PILES

5.0 Work Method /Sequence

1. Excavate by using backhoe and expose the cut-off level (COL) of pile heads. Ensure the surrounding area
is suitable working condition. Provide scaffolding, dewatering and shoring system if necessary.
2. Survey the exposed pile heads and mark COL using a red spray paint.
3. Chipping will be done manually using sledge hammer and chisel. The objective is to expose firstly the
reinforcement bars by continuous breaking of concrete.
4. After all the steel bars are exposed, chip all loose concrete surrounding all the rebars.
5. If the COL is reached, chip the excess concrete and clean the pile top
6. Remove the excess spirals using oxygen-acetylene torch if necessary

6.0 Steel Reinforcement Photos

Photos above are actual assembly of reinforcing bars casted in-situ. The objective is to exposed 70cm of
rebars above cut-off level. The rebar congestion (two-layers and bended) on top of pile will make the
chipping of the bored pilee difficult.

7.0 OHS Requirements

All personnel will complete the project site induction before being allowed access to the works. Operator
competency will be recorded and equipment inspections will be undertaken prior to any activity
commencing. Daily start up meetings will be conducted to ensure all safety measures are in place for the
day’s activities.

 Scaffold as working platform for working at height shall be erected and certified safe for use
 Lighting and forced ventilation if necessary

Project : South Luzon Expressway Phase II Date : 22 Aug 19


Doc. Title: Chipping of Bored Piles Rev: 0
Doc. No.: C3INC-DOC-MS-004 Page: 2 of 2

You might also like