Sir,
You were awarded the Construction of Karnam Malleswari National Weight Lifting and Power Lifting
High Performance Training and Coaching center at Village Chahron, Yamuna Nagar, Haryana vide
agreement dated 28.03.2019 entered into pursuant to tender.
The said Center would cater to the needs and aspiration of young sportsmen who want to excel and
bring pride to the nation and the said center would be their second home.
As per the terms of the tender / agreement, the work awarded to you must be completed in stipulated
time i.e. at the end of March 2020. However,inspite of completing the work within stipulated time you
are making the excuses Bid later dated…
3
· Performances guarantee amounting RS. 32, 27,620/- was
submitted on 26/03/2019 in accordance of the contract.
4
· Work order was issued on 26/03/2019 with contract value 5, 76,
36,075/- without GST. Being GST payable extra.
5
· Date of start commencing 15 days from letter of allotment i.e.
10/04/2019 with stipulated date of completion being 10/02/2020.
6
· Concrete design Mix was got approved from NABL approved lab
Omega test house on 04/04/2019 as per tender item.
7
· We wrote a letter on 01/04/2019 requesting structure as well as
architecture drawings.
8
· On 15/04/2019 again letter was submitted requesting the
drawings. It was also requested in letter to consider the date of
start only when required drawings are issued.
9
· On 28/04/19 again letter was mailed with CC to architect
regarding issue of drawings as the drawings for hostel block was
issued and in the drawings it was observed that the design mix is
given M30 instead of M25 item in tender.
10
· Design mix report was again has to be got done as per the new
item introduced in drawings i.e. is M30.
11
· As on 06/05/2019 meeting was held in New Delhi regarding the
work and we have been instructed to use M30 instead of tender
item M25 and we were instructed to submit M30 rate analysis as
extra item.
12
· Design mix as per M30 was issued by Omega test house on
11/05/2019.
13
· Rate analysis was submitted by us for M30 concrete on
23/05/2019.
14
· Meeting was held at site including architect on 02/06/2019. The
foundation work was started after getting the final nod from your
side on 10/06/2019.
15
· On 14/06/2019 final 28 days report was issued by Omega test
house regarding the M30 concrete.
16
· Routine testing used to be carried out at site besides testing from
a government lab in Jagadhari was being done for concrete cubes
17
· Later water and concrete cubes were sent from your side for
testing in NIT, Kurukshetra where all the reports were found
satisfactory.
19
· On 08/08/2019 we were abruptly asked to stop the work vide e
mail mentioning about test conducted by ShriRam test house for
which we were totally unaware about the sampling.
20
· We requested for elaborate and more decisive tests at site with
our presence and duly signed samples by both parties.
21
· Tests were conducted by ShriRam test house on 03/09/2019.
Hammer rebound test and core cut sample test were conducted
by the testing agency.
22
· Reports were released by ShriRam test house on 11/09/2019
which was provided to us on 13/09/2019.
23
· Again the reports were actually satisfactory but misread from your
side besides our plea that reports are within the parameters, we
were told that the samples are failed.
24
· The work was kept stalled from your side whereas our recurring
expenses were going down the drain.
25
· The architect was replaced b
The work was kept stalled from your side whereas our recurring
expenses were going down the drain.
26
· The architect was replaced by a new one for reasons beyond our
knowledge and the new architect started the redesigning the
project.
28 · The concrete design mix was now again changed back to M25 and
worth mentioning that our rates of M30 were never approved
besides we did huge quantity of concreting.
31
· Besides our repeated requests our payments were not got
released from KMF at the same time we were told to expedite the
work.
42 · The institute block was also revised and revised drawings were
issued on 05/03/2020 with extension of block and other changes.
Thanking you.
Yours Truly
Chairperson
Karnam Malleswari Foundation
To DATED: 08/05/2020
The Chairperson,
320/321,Sector-18,HUDA,Jagadhri,
YamunaNagar,Haryana-135003
Sub: Construction of Karnam Malleswari National Weight Lifting and Power Lifting High Performance
Training and Coaching Centre at Village Chahron, Distt.YamunaNagar, Haryana.
Respected Madame,
Regarding the above said work we hereby wish to submit the date wise events or time line of
the project as under up till now:
As evident with the timeline stated above and various situational issues and where the drawings were
being issued at plinth level on 01/02/2020 and basement roof slab on 15/02/2020 and other issues
stated the timely completion i.e. 10/02/2020, was practically impossible.
We request you to extend the time limit of the project adequately at least upto 31/12/2020 as even
now, due to ongoing pandemic where labour are running away to their home state and the material
supply chains are very adversely affected the progress of works all over the nation are very badly hit and
there is situation of uncertainty. We shall spare no effort from our side to expedite the work with the
available resources and submit the revised bar chart/ completion schedule of the work as soon as the
situation normalizes occurred due to Covid pandemic.
We again pray to release our pending payment as we are in deep trouble and we are unable to carry on
the work in shortage of cash flow/funds. We have huge amount invested at your site in shape of
material lying at site along with our tools and plants and balance pending payments we request you to
do the needful at earliest please.
Warm Regards,
Yours Truly,
Anuj Aggarwal
Partner