Steel Structure Building Construction Procedure: Download Method Statement
Steel Structure Building Construction Procedure: Download Method Statement
This procedure is useful for building construction Aluminium & Glass Work Methods (9)
based upon the steel structure erection work. Based
Building Management System (24)
on the design and speci cation, this document
provides a proper step wise procedure and quality and Civil Engineering Methods (127)
safety management of the steel structure work.
Civil SWMS Downloads (35)
Chalk line
Steel measuring tapes 30m and 8m
Recent Articles
Utility knife
Staple applicator Project Approvals – Statutory and Regulatory
Oxy-Acetylene cutting out t Requirements for Construction Projects
Welding hood
General Sequence of Works in Preparation of
Hard hats
Building Foundation Up To The Level Of Blinding
Safety belts – Bolt bags
Concrete
Masonry drill bits 12mm
Extension ladders Aluminium HVAC Duct Installation Method
Statement
Step Ladders
Sca olding System Possible Causes of Road Crack and Defect – Road
Hilti gun, cartridges and nails Maintenance Inspection Guide
Each workers shall be physically quali ed to perform the duties to which he is assigned. Popular Tags
Workers shall always wear hard helmets, shoes, uniforms and gloves. Access Control System AHU Air Balancing Air Handling
Unit Aluminium Work bms bms system BMS Testing
Workers working at height shall always wear safety belts.
Procedure Building Management System CAPACITOR
Goggles, face masks shields or helmets are required for scaling, grinding, cutting, and welding BANK cctv camera checklist Checklists Civil Method
operations.
Maintenance of machines used in the steel structure erection work shall be done properly. Download
Statements
Setting of safety rope is mandatory on Roof when carry out the roo ng work.
Setting of signboard, and barricade by ropes around working area, do not permit any person
Method Statement
Electrical Method Statement fahu FIRE ALARM SYSTEM Fire
without duty to enter the working area.
Suppression System installation Installation Method
The crane condition (including machine parts, wire rope) must be checked everyday.
Safety meeting shall be done everyday before starting work. Statement iso 9001 ITP mcc mdb method
Cleaning of concrete column top surface. Operation SMDB statement swms T&C Method
Project Plans
Project Management
HSE Procedures
Step 3: Set form for starting column and support them carefully.
Step 5: Set template with anchor bolts. The template position is higher than concrete surface level.
Marking line of bolt-group-center and each bolt must be matched on the template.
Adjust position of the template according to marking line on footing by plum bob.
Step 6: Welding diagonal supporting bar to column rebar and anchor bolt.
Step 10: After casting concrete, re-check anchor bolt position. Adjust the template if necessary.
Step 1:
Set up 2 side columns of braced bay (between Grid 4 and Grid 5), including bracing beams.
Erect interior columns (along grid C1-4 and C1-5) with temporary bracing.
Tighten anchor bolts and nuts su ciently to prevent columns from rocking.
Assemble rafter components of Grid 4 on the ground into connection.
Install all bolts in rafter splices to proper tension, using turn-o -nut method and torque wrench.
Raise the rst assembled rafter on top of column by cranes.
Install bolts of rafter through column connection and tighten to snug position.
Secure all temporary, wire ropes bracings, plumb and align the column and rafter before releasing
the crane.
Step 2:
Using same procedure to assemble other parts of the rafter of Grid 5 (A – F).
Place it on top of interior columns.
Bolt to column connections and tighten.
Secure temporary bracings.
Step 3:
Assemble the rafter of Grid 6 (same as the rst erected rafters). Connect and bolted to column
splices. The crane has to keep holding the rafter in position until su cient purlins ( 1/3 of total
purlins at that area ) have installed to provide rigid support for the bay. The crane can release if
having temporary bracing cables for both sides at interval of maximum 10 m.
Continue erecting the next rafters of the brace bay.
Completing purlins, ange braces, roof bracings.
Plumb and align before proceeding to erect the next bays.
After checking the alignment and squareness, tighten again anchor bolts, column connection, girts
bolts, and eave strut bolts to required tension by torque wrench.
Step 4:
Step 5:
Fabrication and installation of roo ng panels. (See “Erection Procedure for roof Panel”)
Step 6:
Inspection is necessary at all steps of erection process, from the times materials are rst received until
the structure is completely installed. Inspection during the steel erection process shall be continuous in
order to prevent the occurrence of possible damage and to require the maintenance of high standard
workmanship. Inspection shall include members, painting, connection, alignment, bracings, roo ng and
wall cladding, equipment and false work.
Inspection of Members
a. Anchor bolts:
– Check the tolerance of dimensions between anchor bolts to meet the required tolerance (5mm).
b. Bolts connection:
– The supervisor has to assure himself that the wrenches used are calibrated properly so that bolts are
tightened the proper amount. Also the proper lengths of bolts shall be checked.
– After connecting, all bolts shall be tightened to obtain the required tension values
Using turn-o nut method: Tighten more 120o+/-30o for bolt diameter >12mm, tighten more 60o-
0+30o for bolt diameter = 12mm.
Torque wrench: the actual value must be within the recommended value +/-5_10%.
– Every connection point shall be inspected with the inspection record that is made by the team leader,
with the con rmation of responsible engineers and Site Manager. The actual value of tension or torque
moment of every bolt in the connection shall be shown on the record.
D N M
mm KN N.m
12.7 53 136
15.9 84 271
After the rst bay (braced bay) is erected, the columns shall be made plumb and the rafters shall
be straight.
After completing the erection of main frames the alignment check shall be done again, before
continuing the erection of the successive bays.
The tolerance of column plumb must be within the value of 1/500 of column height, but can not
be more than 25mm.
The tolerance of Rafter alignment (from straight rafter – line) must be within the value of 1/300 of
Span.
After completing the erection of main frames, the nal check of alignment (plumbing and
straightness) for the all columns and rafters of whole building shall be done.
Adjustment of bracing
Adjustable diagonal bracing is xed after all parts of the structure are in place. In bolted structures
having diagonal bracing, wall bracings are adjusted after the columns are plumbed, and roof bracing are
adjusted when rafters are in straight line.
All screws must be perpendicular to panels, and rubber washer thickness must be from 1.00 to 1.20 mm.
After completing all trims and accessories, a nal inspection of the building shall be done:
All bracings in position and tightened.
All bolts in place and high strength bolts tightened to correct tension value.
Check that roof and gutters are clear of debris and ferrous metals.
Check improper drilled screws.
Check opening for joinery.
Touch up any damaged paint
Below is comprehensive list of additional tools and tackles that you may need for doing the steel
structure construction works.
3 Seamer
6 Uncoiler
7 Crimper
1 Combination Wrench
4 Screw Driver
6 Wrench
7 Sweeping Broom
10 Goggles
11 Fire Extinguisher
12 Nibbler
14 Hack Saw
17 Screw Gun
18 Drill machine
19 Grinder (small)
20 Nylon Rope
23 Vice Grip 8″
24 Utility Knife
27 Side Cutter 8″
32 Feller Gauge mm
35 Level
38 Oiler
40 Torch
41 Tape 8 meters
42 Tape 30 meters
43 Tape 5 meters
Supporting
6 Spreader bar
9 Electrical box
10 Stand Conveyor
Safety Gears
1 Safety Clothes
5 Helmet
Category: Construction Method Statements Stainless Steel Fabrication Tags: building construction , metal
building homes , steel deck , steel structure method statement