Download as pdf or txt
Download as pdf or txt
You are on page 1of 16

DATAS for Internal Water Supply & Sanitary Fittings. SSR 2017-18.

Supplying, laying, jointing and testimg of 110mm Dia. (S.16.5) unplasticized Non-pressure Polyvinyl Chloride (PVC-U)
Pipes of dark (any shade of Brown) for use in Underground Drainage & Sewerage System conforming to IS.15328/2003)
with Solvent Cement Jointing including transportation charges, loading, unloading, excise duty, cess & vat etc., and
including cost and conveyance of all materials to site of work and all labour charges such as laying, jointing including
excavation of trenches and socket pits in any soil (except rock required blasting) upto a depth of 3'-0" and refilling the same
after laying the pipe line with excavated soil etc., complete as directed by the department. (Pipe Series (S.25)

Unit -- One Rmt.


Cost of OD 110mm Dia. PVC-U (S16.5) P.No.64, PH SSR 1.00 201.00 201.00
Earth work excavation rate per Cum. P.No.304, Sl.No.1139, 0.68 89.42 60.81
TOTAL: 261.81
Overheads & Contractor's Profit @ 13.615% 35.64
TOTAL Rs.= 297.45 Rmt.
Supplying, laying, jointing and testimg of 160mm Dia. (S.16.5) unplasticized Non-pressure Polyviny Chloride (PVC-U)
Pipes of dark (any shade of Brown) for use in Underground Drainage & Sewerage System conforming to IS.15328/2003)
with Solvent Cement Jointing including transportation charges, loading, unloading, excise duty, cess & vat etc., and
including cost and conveyance of all materials to site of work and all labour charges such as laying, jointing including
excavation of trenches and socket pits in any soil(except rock required blasting)upto a depth of 3'-0" and refilling the same
after laying the pipe line with excavated soil etc., complete as directed by the department.

P.No.60, Code.(19) No.1, of Unit -- One Rmt.


Cost of OD 160mm Dia. PVC-U (S16.5) PH SSR Sl.No.1139, ELEC- 1.00
P.No.304, 424.00 424.00
Earth work excavation rate per Cum. 8.1.52, 0.72 89.42 64.38
TOTAL: 488.38
Overheads & Contractor's Profit @ 13.615% 66.49
TOTAL Rs.= 554.88 Rmt.
Supplying and fixing of 150mm x 100mm SWG Gully Trap1st class of approved ISI make confirming to ISI 651 & 4127 with
C.I. gratings of 6" x 6" and constructing intermediate brick masonry chamber of size 20"x14"x12" in CM (1:6) prop. over a
bed of CC (1:5:10) prop. 3" thick and plastering 12mm thick in CM (1:3) prop. both inside, outside & top with fine rendering
with neat cement and fitted with 12" x 9" C.I. frame and hinged cover etc., complete for finished item of work.

Unit -- Each
Cost of gully trap P.No.114, Sl.No.72 of BMW-A.72, Part-III. 1.00 485.00 485.00
Overheads & Contractor's Profit @ 13.615% 66.03
TOTAL Rs.= 551.03 Each
Construction of 3'-0" (904.0mm) Dia. Solid block Masonry INSPECTION CHAMBER as per IS.4111, Part-I-1986 with
CM(1:6)Prop. Fly-Ash blocks of 225mm thick from approved source having a minium crushing strength of 10 N/Sq. mm.
Including plastering with CM(1:3)Prop. 1/2" thick both inside and outside and fitted with 20" Dia. RCC Manhole Covers and
Frames including excavating pits upto a depth of 904.00 mm (3'-0") in all sorts of soils (excluding rock) and laying CC(1:4:8)
Prop. 150mm thick using 40mm HBG metal and PCC(1:2:4)Prop. benching and channel 100mm thick as per standard
specification and including cost and conveyance of all materials like cement, sand, bricks, water etc., to site of work,
seignorage on all materials and all operational, incidental, labour charges like mixing cement mortar, construcing masonry, lift
charges, curing etc., complete for finished item of work as per standard specification.

Unit -- Each

Rate as per Building SSR Part-III, P.No.114, Sl.No.78 of BMW-B.01. 1.00 5697.00 5697.00
Overheads & Contractor's Profit @ 13.615%. 775.65
TOTAL Rs.= 6472.65 Each
Construction of 457.20 mm x 457.20 mm (1-6"x1-6") Brick masonry INSPECTION CHAMBER with 9" thick brick masonry
work in C.M (1:6)prop. with necessary carbelling as per ISI standard upto a depth of 3'-0" over a bed of 4' thick CC(1:5:10)
prop. including plastering in CM(1:3)Prop. 1/2" thick to Inside, Outside & Top surfaces with fine rendering in neat cement and
making necessary C.C channelling with CC (1:2:4) prop. with smooth neat cement finishing, earth work excavation in all soils
(except rock required blastering) etc., and refilling with excavated soils as per SS and fixing with 1'-6"x1'-6" C.I frame and
cover of 20 Kg including cost and conveyance of all materials to site of work and labour charges, curing etc., complete for
finished item of work.
Unit -- Each

Rate as per Building SSR Part-III, P.No.115, Sl.No.83 of BMW-B.06. 1.00 3238.00 3238.00
Overheads & Contractor's Profit @ 13.615%. 440.85
TOTAL Rs.= 3678.85 Each
Supplying for fixing of 110mm Dia.3M Single Socket PVC/SWR pipes of approved make for 4kg./Sq.Cms. of single socket
pipe of ISI standard with air tight joints,fixing with clams and nails etc.,complete for (Vent Shaft) W.C.Connection inculding
cost and conveyance of all materials to work site labour charges etc for finished item of work inclusive all taxes etc complete.

Unit -- One Rmt.


1.00 Rmt cost of PVC pipe at Rs.476.00/3 Mts. length (476/3Mts.) 1.00 158.67 158.67
1 No. Pipe Clips vide P.No.105, SL.No.440. BMW-G.106 1.00 15.00 15.00
1 Rmt. Labour charges for laying & fixing, P.106,Sl.No.486, BMW-G-152. 1.00 70.00 70.00
Total 243.67
Overheads & Contractor's Profit @ 13.615% 33.18
TOTAL Rs.= 276.84 Rmt
Supplying & fixing of 110mm Dia. uPVC/SWR SINGLE TEE with Door of approved including cost and conveyance of all
materials to work site and all jointing materials, labour charges etc., complete for finished item of work.

Unit --- Each


110mm Dia. Single TEE with Door, vide P.No.126, Sl.No.406. BMW-G.72 1.00 110.00 110.00
Overheads & Contractor's Profit @ 13.615% 14.98
TOTAL Rs.= 124.98 Each
Supplying and fixing of 110mm Dia. UPVC/SWR 87.5 Degree Plain Bend of approved make including cost and conveyance
of all materials to work site and all jointing materials, labour charges etc., complete for finished item of work.

Unit --- Each


75mm Dia. 87.5 Degree Door Bend, P.No.129, Sl.No.391. BMW-G.57 1.00 70.00 70.00
Overheads & Contractor's Profit @ 13.615% 9.53
TOTAL Rs.= 79.53 Each

Supplying and fixing of 110mm Dia. UPVC/SWR VENT COWL of approved make including cost and conveyance of all
materials to work site and all jointing materials, labour charges etc., complete for finished item of work.

Unit --- Each


110mm dia. Vent Cowl vide P.No.131, Sl.No.434. BMW-G.100 1.00 16.00 16.00
Overheads & Contractor's Profit @ 13.615% 2.18
TOTAL Rs.= 18.18 Each
Supplying for fixing of 75mm Dia. 3M Single Socket UPVC/SWR pipes of approved make for 4kg/Sq.Cms. of single socket
pipe of ISI standard coonfirming to ISI 1352 with air tight joints,fixing with clams and nails etc.,complete for (Vent Shaft) W.C.
connection inculding cost and conveyance of all materials to work site labour charges etc for finished item of work inclusive
all taxes etc complete.
Unit -- One Rmt.
1.00 Rmt cost of PVC pipe at Rs.216.00/3 Mts. length as per SSR Part-III, 1.00 72.00 72.00
1 No. Pipe Clips vide P.No105, SL.No.438. BMW-G.104 1.00 13.00 13.00
1 Rmt. Labour charges for laying & fixing, P131,Sl.No.486, BMW-G-152. 1.00 70.00 70.00
155.00
Overheads & Contractor's Profit @ 13.615% 21.10
TOTAL Rs.= 176.10 Rmt

Supplying & fixing of 75mm Dia.PVC/SWR DOUBLE "Y" with Door of approved make including cost and conveyance of all
materials to work site and all jointing materials, labour charges etc., complete for finished item of work.

Unit --- Each


75mm Dia. Double 'Y' with Door vide P.No.129, Sl.No.422. BMW-G.88 1.00 112.00 112.00
Overheads & Contractor's Profit @ 13.615% 15.25
TOTAL Rs.= 127.25 Each
Supplying and fixing of 75mm Dia. UPVC/SWR VENT COWL of approved make including cost and conveyance of all
materials to work site and all jointing materials, labour charges etc., complete for finished item of work.
Unit --- Each
75mm Dia. Vent Cowl vide P.No.130, Sl.No.432. BMW-G.98 1.00 12.00 12.00
Overheads & Contractor's Profit @ 13.615% 1.63
TOTAL Rs.= 13.63 Each
Supplying and fixing of 75mm Dia. UPVC/SWR 87.5 Degree Door Bend of approved make including cost and conveyance of
all materials to work site and all jointing materials, labour charges etc., complete for finished item of work.

Unit --- Each


75mm Dia. 87.5 Degree Door Bend, P.No.129, Sl.No.392. BMW-G.55 1.00 57.00 57.00
Overheads & Contractor's Profit @ 13.615% 7.76
TOTAL Rs.= 64.76 Each
Supplying and fixing of 75mm Dia. UPVC/SWR PLAIN BEND 87.5 Degree of approved make including cost and
conveyance of all materials to work site and all jointing materials,labour charges etc.,complete for finished item of work.

Unit --- Each


110mm dia Door Brand 87.5 Degree, P.No.129, Sl.No.389. BMW-G.55 1.00 42.00 42.00
Overheads & Contractor's Profit @ 13.615% 5.71
TOTAL Rs.= 47.71 Each
Supplying and fixing of 76.2mm (3") Dia. NAHANY TRAP with Jali for UPVC/SWR pipe fittings of approved make including
cost and conveyance of all materials to work site and all jointing materials, labour charges etc., complete for finished item of
work.
Unit --- Each
76.2mm uPVC Nahany Trap, vide P.No.130, Sl.No.452. BMW-G.118 1.00 86.00 86.00
Overheads & Contractor's Profit @ 13.615% 11.70
TOTAL Rs.= 97.70 Each
Supplying and fixing of Europian Pan White Glazed W.C.of 1st quality conforming to IS:2556-Part-2-1973 of white
glazedwith 'S' trap of ISI Mark and using with plastic seat and lid for European water closets with rubber or plastic Buffers as
per IS 2548-1996 and also using with low down porcelain flushing tank 10 Lit Capacitywith internal components , 12.7 mm
NP stop cock Indian makeheavy duty including cost and conveyance of all materials to work site, labour charges etc for
finished item of work inclusive all taxes etc complete.

Unit --- Each


Supplying and Fixing European Water Closet of 1st quality conforming to
IS:2556-Part-2-1973 ofwhite glazedwith 'S' trap 1.00 1703.00 1703.00
Supplying and Fixingbest Indian make plastic seat and lid for European water
closets with rubber or plastic Buffers as per IS 2548-1996 1.00 766.00 766.00
Supplying & Fixing low down porcelain flushing tank 10 Lit Capacitywith internal
components 1.00 2226.00 2226.00
S & F 12.7 mm NP stop cock Indian makeheavy duty 1.00 406.00 406.00
5101.00
Overheads & Contractor's Profit @ 13.615% 694.50
TOTAL Rs.= 5795.50 Each
Supplying and fixing of premium make of Ashirvad required Flowguard CPVC PIPES of 22.20mm OD Pipe SDR-11 and
fittings for Hot & Cold water confirming to IS.15778-2007 including fixing in walls, ceiling floors including cost and conveyance
of all materials to site of work and include for necessary excavation in all sorts of soils, chasing in the walls etc., refilling
consolidation with the excavated earth and making bores in walls ceiling etc., and making good the chased surface in cement
mortar and complete. When making a transition use metal threads fittings, including all taxes for finished item of work as
directed by the dept.
Unit --- One Rmt.
1.00 Rmt. Cost of 22.20 mm Dia. CPVC Pipes. 1.00 93.00 93.00
Overheads & Contractor's Profit @ 13.615% 12.66
TOTAL Rs.= 105.66 Rmt
Supplying and fixing of premium make of Ashirvad required Flowguard CPVC PIPES of 28.60mm OD Pipe SDR-11 and
fittings for Hot & Cold water confirming to IS.15778-2007 including fixing in walls, ceiling floors including cost and conveyance
of all materials to site of work and include for necessary excavation in all sorts of soils, chasing in the walls etc., refilling
consolidation with the excavated earth and making bores in walls ceiling etc., and making good the chased surface in cement
mortar and complete. When making a transition use metal threads fittings, including all taxes for finished item of work as
directed by the dept.
Unit --- One Rmt.
1.00 Rmt. Cost of 28.60 mm Dia. CPVC Pipes. 1.00 144.00 144.00
Overheads & Contractor's Profit @ 13.615% 19.60
TOTAL Rs.= 163.60 Rmt
Supplying and fixing of premium make of Ashirvad required Flowguard CPVC PIPES of 34.90mm OD Pipe SDR-11 and
fittings for Hot & Cold water confirming to IS.15778-2007 including fixing in walls, ceiling floors including cost and conveyance
of all materials to site of work and include for necessary excavation in all sorts of soils, chasing in the walls etc., refilling
consolidation with the excavated earth and making bores in walls ceiling etc., and making good the chased surface in cement
mortar and complete. When making a transition use metal threads fittings, including all taxes for finished item of work as
directed by the dept.
Unit --- One Rmt.
1.00 Rmt. Cost of 34.90 mm Dia. CPVC Pipes. 1.00 229.00 229.00
Overheads & Contractor's Profit @ 13.615% 31.17
Sundries
TOTAL Rs.= 260.17 Rmt
Supplying and fixing of premium make of Ashirvad required Flowguard CPVC PIPES of 54.00mm OD Pipe SDR-11 and
fittings for Hot & Cold water confirming to IS.15778-2007 including fixing in walls, ceiling floors including cost and conveyance
of all materials to site of work and include for necessary excavation in all sorts of soils, chasing in the walls etc., refilling
consolidation with the excavated earth and making bores in walls ceiling etc., and making good the chased surface in cement
mortar and complete. When making a transition use metal threads fittings, including all taxes for finished item of work as
directed by the dept.
Unit --- One Rmt.
1.00 Rmt. Cost of 54.00 mm Dia. CPVC Pipes. 1.00 483.00 483.00
Overheads & Contractor's Profit @ 13.615% 65.76
TOTAL Rs.= 548.76 Rmt
Supplying and fixing of 12.70mm Dia. N.P. Bib Tap Indian make heavy duty of approved make including cost and
conveyance of all materials to work site and all jointing materials, labour charges etc., complete for finished item of work.

Unit --- Each


Cost of 12.70mm Bib Tap vide P.No.97, Sl.No.180, BMW-E-07. 1.00 349.00 349.00
Overheads & Contractor's Profit @ 13.615% 47.51
TOTAL Rs.= 396.51 Each
Supplying and fixing of 19.05mm G.I.Union of 1st quality of any approved make including cost and conveyance of all
materials to work site and all jointing materials, labour charges etc., complete for finished item of work.
Unit --- Each

Cost of 19.05mm G.I.Union vide P.No.97, Sl.No.213, BMW-F-02 1.00 46.00 46.00
Overheads & Contractor's Profit @ 13.615% 6.25
TOTAL Rs.= 52.25 Each
Supplying and fixing of 40mm N.B. size Gunmetal Gate (G.M.Peet) Valve as per IS.778, Class-I of Indian make heavy
type including cost and conveyance of all materials to work site and all jointing materials, labour charges etc., complete for
finished item of work as directed by the department.
Unit --- Each
1 No. Cost of 50mm Gate valve vide P.No.98, Sl.No.236, BMW-F-25 1.00 2155.00 2155.00
Overheads & Contractor's Profit @ 13.615% 293.40
TOTAL Rs.= 2448.40 Each
Supplying and fixing of CP Long body bib cock fancy type deluxe heavy duty 12.70mm Dia. Indian make heavy duty of
approved make including cost and conveyance of all materials to work site and all jointing materials, labour charges etc.,
complete for finished item of work.
Unit --- Each
CP Long body bib cock fancy type deluxe heavy duty 12.70mm Dia vide 1.00 547.00 547.00
Overheads & Contractor's Profit @ 13.615% 74.46
TOTAL Rs.= 621.46 Each
DATAS FOR INTERNAL ELECTRICAL ITEM -- S.S.R. 2017-18.

Supplying and fixing of 25mm Outer Dia. medium (1.80mm thickness) grade with IS.9537, Part-3 regid
PVC Pipe of VIP/Besto plast/Goldmedal/Million plast/GM/Sudhakar/Polyline of ISI mark for CONCEALED IN
WALLS with all required accessories including chisiling the wall where ever necessary including masonry
work for Light/Fan Points and seperate plug point with junction boxes and bends of makes Gold
medal/Million plast/GM/Sudhakar/Polyline /Bestoplast including all labour chartges etc.
complete.

As per Standard Data-Sl.No.1.4.2(b) of BLD-ELEC-1-4,P.No.160. unit--One Rmt.


Amount in
Taking out put = 100 Mts. Unit Qty Rate in Rs
Rs.
A) MATERIAL:
25mm Dia.1.80m th. PVC pipe P.No.131, S.No.54.
ELEC-1.2.3 of Part-III. 1.00 100.00 27.00 2700.00

U' Nails P.No.222, Sl.No.1094, ELEC-8.1.7,Part-III 100 Nos 2.00 40.00 80.00
25mm PVC junction boxes, P.No.133,Sl.No.83, ELEC-
1.2.23 Each 12.00 17.00 204.00
25mm dia.1.5mm th. PVC Bends P.No.133, Sl.No.88,
ELEC-1.2.37, Part-III Each 12.00 5.00 60.00

Cement Kg. 50.00 3.882 194.10

B) LABOUR CHARGES
P.305,Sl.No.1161, ELEC-
Skilled Electrification 8.1.74, Part-3 Day 2.00 540.00 1080.00
P.305,Sl.No.1162, ELEC-
Semiskilled Electrification 8.1.75, Part-3 Day 2.00 420.00 840.00
P.305,Sl.No.1163, ELEC-
Helper (Electrical) 8.1.76, Part-3 Day 2.00 420.00 840.00
P.305,Sl.No.1164, ELEC-
Mason 8.1.77, Part-3 Day 2.00 465.00 930.00
Add. MPL @ 20% on Labour 738.00

7666.10

Overheads & Contractor's Profit @ 13.615%. 1043.74

Rate per 100 Rmt 8709.84

Rate per 1 Rmt 87.10


Supplying and fixing of 25mm Outer Dia. medium (1.80mm thickness) grade with IS.9537, Part-3 regid
PVC Pipe of VIP/Besto plast/Goldmedal/Million plast/GM/Sudhakar/Polyline of ISI mark for CONCEALED IN
ROOF SLAB with all required accessories including chisiling the wall where ever necessary including
masonry work for Light/Fan Points and seperate plug point with junction boxes including all labour chartges
etc. complete.
As per Standard Data-Sl.No.1.4.2(C) of BLD-ELEC-1-4,P.No.161. unit--One Rmt.
Amount in
Taking out put = 100 Mts. Unit Qty Rate in Rs
Rs.
A) MATERIAL:
25mm Dia.1.80m th. PVC pipe P.No.194, S.No.54.
ELEC-1.2.3 of Part-III. 100 M 1.00 27.00 2700.00
25mm PVC junction boxes, P.No.196,Sl.No.83, ELEC-
1.2.32 Each 12.00 17.00 204.00
25mm dia.1.5mm th. PVC Bends P.No.196, Sl.No.88,
ELEC-1.2.37, Part-III Each 12.00 5.00 60.00

B) LABOUR CHARGES

Skilled Electrification Day 2.00 540.00 1080.00

Semi skilled Electrification Day 2.00 420.00 840.00

Helper (Electrical) Day 2.00 420.00 840.00

Add. MPL @ 20% on Labour 552.00


6276.00
Overheads & Contractor's Profit @ 13.615%. 854.48

Rate per 100 Rmt 7130.48


Rate per 1 Rmt 71.30
Wiring with 2 runs of 14/0.3mm (1.00 Sq.mm) PVC insulated F.R flexible copper cable (ISI Mark) make of
Havells/KEI/Polycab/Bonton/Gold Medal/V-Guard/GM Million/HPL/Finecab/Orbit in the existing pipe with 6-
A/10-A 1 way 1 module switch make of Legrand Arteor/Schneider Zencelo/ Honeywell/Blenge plus, Ceiling
rose of make Anchore/Gold Medal Oliv`e/Million Zoom and 8 modular horizontal/vertical cover frame make of
Legrand Myrius/Cabtree Thames platinum/GM Four Five/Mullion Logus/Gold Medal Curve/CPL/Panasonic
vision/Salzer S.90,Series covering to module box including all labour charges etc., complete for LIGHT
POINTS, FAN POINTS & BELL POINTS in Residental Building.

As per Standard Data BLD-ELEC-2.1, Sl.No.2.1.2, P.No.163. Taking out put=7 Points.
Rate in Rs Amount in
Unit Qty
A. MATERIAL: Rs.
14/0.3mm PVC FRLS Flexible Copper Wire of make
Havells/KEI/Gold Medal/V-Guard/Finecab vide
P.No.199,Sl.No.127, ELEC-1.5.8, Part-III. 100 M 1 No. 837.00 837.00
6-A/10-A 1 way 1 module switch make of Legrand
Arteor/Schneider Zencelo/ Honeywell/Blenge plus vide
P.No.207,Sl.No.213,ELEC-1.8.1, Part-III. Each 7 Nos 83.00 581.00
3 plate Jumbo Ceiling Rose vide P.No.205,
SL.No.184, ELEC-1.7.13, Part-III. Each 7 Nos 19.00 133.00
Cost of 8 or 9 Module box horizontal/vertical vide
P.No.197, Sl.No.97, ELEC-1.3.5 Each 1 No 161.00 161.00
8 modular horizontal/vertical cover frame make of Legrand
Myrius/Cabtree Thames platinum/GM Four Five/Mullion
Logus/Gold Medal Curve/CPL/ Panasonic vision/Salzer
S.90,Series vide P.No.210, SL.No.255, ELEC-1.8.43. Each 1 No 124.00 124.00
B. LABOUR CHARGES:

Skilled Electrification Day 0.70 540.00 378.00

Semi skilled Electrification Day 1.40 420.00 588.00

Helper (Electrical) Day 0.70 420.00 294.00

Add. MPL @ 20% on Labour 252.00


Rate Rs 3348.00

Overheads & Contractor's Profit @ 13.615%. 455.83

Rate per 7 Points 3803.83

Rate per each point 543.40


Supplying and Run of U/S Circuit Mains by mean run of 2 of 56/0.3mm (4.00Sqmm) FRLS/HFFR/ ZHFR
PVC insulated 1100V grade as per IS.694/190 specification for Copper Wire make Havells/
KEI/Polycab/GM/Gold Medal/Million/HPL/Fine Cab/Vimal/Orbit in the existing metalic/Non metalic conduit
pipe for run of mains including all labour charges etc,complete.

As per Standard Data BLD-ELEC-3.1, Sl.No.3.1.5, P.No.169. Taking out put -100 Mts.

Unit Qty Rate in Rs Amount in


A. MATERIAL: Rs.
56/0.3mm (4 Sqmm) Copper Wire
vide P.No.199, SL.No.130, ELEC-1.5.11. 100 M 2 Nos 3045.00 6090.00
B. LABOUR CHARGES:

Skilled Electrification Day 1.00 540.00 540.00

Semi skilled Electrification Day 3.00 420.00 1260.00

Helper (Electrical) Day 1.00 420.00 420.00

Add. MPL @ 20% on Labour 444.00

TOTAL: 8754.00

Overheads & Contractor's Profit @ 13.615%. 1191.86

Rate per 100 Rmt 9945.86

Rate per 1 Rmt 99.46


Supplying and Run of U/S Circuit Mains by mean run of 2 of 36/0.3mm (2.5 Sqmm) FRLS/HFFR/ ZHFR pvc
insulated 1100V grade as per IS.694/190 specification for Copper Wire make Havells/ KEI/Polycab/GM/Gold
Medal/Million/HPL/Fine Cab/Vimal/Orbit in the existing metalic/Non metalic conduit pipe for run of mains
including all labour charges etc,complete.

As per Standard Data BLD-ELEC-3.1, Sl.No.3.1.4, P.No.168. Taking out put -100 Mts.

Unit Qty Rate in Rs Amount in


A. MATERIAL: Rs.
36/0.3mm (2.5Sqmm) Copper Wire vide P.No.199,
SL.No.129, ELEC-1.5.10. 100 M 2 Nos 1989.00 3978.00
B. LABOUR CHARGES:

Skilled Electrification Day 0.67 540.00 361.80

Semi skilled Electrification Day 2.00 420.00 840.00

Helper (Electrical) Day 0.67 420.00 281.40


Add. MPL @ 20% on Labour 296.64

TOTAL: 5757.84

Overheads & Contractor's Profit @ 13.615%. 783.93

Rate per 100 Rmt 6541.77

Rate per 1 Rmt 65.42


Supplying and Run of U/S Circuit Mains by mean run of 1 of 22/0.3mm (1.5 Sqmm) FRLS/HFFR PVC
insulated 1100V grade as per IS.694/1990 specification for Copper Wire make Havells/
KEI/Polycab/GM/Gold Medal/Million/HPL/Fine Cab/Vimal/Orbit in the existing metalic/Non metalic conduit
pipe for run of mains including all labour charges etc., complete.

As per Standard Data BLD-ELEC-3.1, Sl.No.3.1. 2, P.No.168. Taking out put - 100 M

Unit Qty Rate in Rs Amount in


A. MATERIAL: Rs.
22/0.3mm (1.5Sqmm) Copper Wire. P.No.199,
Sl.No.128, ELEC-1.5.9. 100 M 1 No 1231.00 1231.00

B. LABOUR CHARGES:

Skilled Electrification Day 0.34 540.00 183.60

Semi skilled Electrification Day 1.00 420.00 420.00

Helper (Electrical) Day 0.34 420.00 142.80

Add. MPL @ 20% on Labour 149.28

TOTAL: 2126.68

Overheads & Contractor's Profit @ 13.615%. 289.55

Rate per 100 Rmt 2416.23

Rate per 1 Rmt 24.16


Supply and fixing of Batten Holder/Slanting Holder of Anchor/Gold medal olive/Millon Zoom in lieu of
ceiling rose of light point complete with all connections and all labour charges etc., complete (for New
installation) without bulbs for finished item of work..

As per Standard Data BLD-ELEC-2.1, Sl.No.2.1.7, P.No.165. Taking out put - Each.

Unit Qty Rate in Rs Amount in


Rs.
A. MATERIAL:
PVC Batten Holder, P.No.205,Sl.No. 185,
ELEC.1.7.14. Each 1No 18.00 18.00
B. LABOUR CHARGES:

Skilled Electrification Day 0.050 540.00 27.00

Helper (Electrical) Day 0.050 420.00 21.00


Add. MPL @ 20% on Labour 9.60
TOTAL = 75.60

Overheads & Contractor's Profit @ 13.615%. 10.29

Each 85.89
Supply and fixing of 6-A/10-A 3/2 Pin 2 Module Modular Socket with shutter of make Legrand
Arteor/Schneider Zen celo/Honeywell Blenge plus with 6-A/10-A, 1 Way 1 Module Modular switch of make
Legrand Arteor/Schneider Zencelo/ Honeywell/Blenge plus 6-A Switch Control on a common switch board of
with earth continuity including wire leads, earth connections along with all labour charges etc., complete.

As per Standard Data BLD-ELEC-2.1, Sl.No.2.1.4, P.No.164. Taking out put - Each
Unit Qty Rate in Rs Amount in
A. MATERIAL: Rs.

6-A/10-A 3/2 Pin 2 Module Modular Socket with shutter


of make Legrand Arteor/Schneider Zen celo/Honeywell
Blenge plus vide P.No.207, Sl.No.216, ELEC-1.8.4. Each 1 No. 128.00 128.00
6-A/10-A 1 way 1 module switch make of Legrand
Arteor/Schneider Zencelo/ Honeywell/Blenge plus vide
P.No.207,Sl.No.213,ELEC-1.8.1, Part-III. Each 1 No 83.00 83.00
B. LABOUR CHARGES:

Skilled Electrification Day 0.067 540.00 36.18

Helper (Electrical) Day 0.067 420.00 28.14

Add. MPL @ 20% on Labour 12.86

TOTAL = 288.18

Overheads & Contractor's Profit @ 13.615%. 39.24

Each 327.42
Supply and fixing of 16-A/6A 1 way combi Socket with shutter make of Legrand Arteor/Schneider Zen
celo/Honeywell Blenge Plus duly recessed in module box including cost and conveyance of all materials to
work site and all labour charges etec.,complete.

Taking out put - Each

Unit Qty Rate in Rs Amount in


A. MATERIAL: Rs.

4 Module Box, P.197,Sl.No.95, ELEC-1.3.3. Each 1 No. 91.00 91.00


16-A/6A 1 way combi Socket with shutter make of
Legrand Arteor/Schneider Zen celo/Honeywell Blenge
Plus,vide P.No.208,Sl.No.224,ELEC-1.8.12. Each 1 No 178.00 178.00
B. LABOUR CHARGES: As per Standard Data BLD-ELEC-2.1, Sl.No.2.1.6, P.No.164.

Skilled Electrification Day 0.10 540.00 54.00


Semi skilled Electrification Day 0.10 420.00 42.00

Helper (Electrical) Day 0.10 420.00 42.00

Add. MPL @ 20% on Labour 27.60


TOTAL: 434.60

Overheads & Contractor's Profit @ 13.615%. 59.17

Each 493.77

Supply and fixing of 4 Way SPN Distribution Board with IP-43 Protection (Metal Door) as per 13032 and
suitable for Single Phase ECCB/RCCB/DP Isolator as Incomer Incommer of make of Gold Medal/GM/
Milltec/Sputnik/Benlo/Vimal/Fybros by Kundan cab and 6-32A 10KA SP MCB C/D curve as OUTGOING
make of Gold medal/Milltec/Sputnik/Benlo/GM/Vimal including internal connections and all labour charges for
surface/flush mounting etc., complete for finished item of work as directed by the department. (40A DP
Isolator/RCCB/ELCB=1 No. for Incomer {and} 10KA-6-32A SP MCBs = 4 Nos for Outgoing).

As per Standard Data of BLD-ELEC-4-4-2.(A), P.No.179 (Old Data)


40-A DP Isolator/RCCB/ELCB -- 1 No. for Incomer.
10KA-6-32.A SP MCBs -- 4 Nos. for Outgoing. Taking out put - Each.
Unit Qty Rate in Rs Amount in
Rs.
A. MATERIAL:

SPN 4 way DB with IP-43 protection vide P.No.225,


Sl.No.437, ELEC-2.12.16. Each 1.00 526.00 526.00

40-A DP Isolator/ECCB/RCCB make Gold


Medal/Milltec/Sputnik/Benlo/GM/Vimal vide P.No.222,
Sl.No.400, ELEC-2.10.18. Each 1.00 226.00 226.00
6-32-A 10-KA SP MCB C/D curve of make Gold
Medal/Milltec/Sputnik/Bentec, P.No.221, Sl.No.375,
ELEC-2.9.17. Each 4.00 106.00 424.00
B. LABOUR CHARGES:
Skilled Electrification Day 0.50 540.00 270.00
Semi skilled Electrification Day 0.50 420.00 210.00
Helper (Electrical) Day 1.00 420.00 420.00
Add. MPL @ 20% on Labour 180.00

Total 2256.00

Overheads & Contractor's Profit @ 13.615%. 307.14

Each 2563.14
Sypply, Trnsportatin, fabrication and erection of 14 SWG CRCA Sheet Steel enclosure for Power
Control Cubical Panel/Boxes etc., including cutting, bending, drilling, welding and reveting etc., with
cleaning 7 tank process and painting with powder coating including cost and conveyance of all materials to
site of work and all labour charges etc., complete as directed by the department.
AP.Standard Data of BLD-ELEC-14.1, SL.No.14.1.2, P.No.262.

Unit Qty Rate in Rs Amount in


Taking out put - One Sqm.
Rs.

14 SWG CRCA Sheet, P.292,Sl.974, ELEC-6.2.1 1 Sqm. 1 Sqm. 3593.00 3593.00

Overheads & Contractor's Profit @ 13.615%. 489.19

1 Sqmt 4082.19
Supply and Erection of 125-A, 4 Pole MCCB adjustable confirms to IS/IEC-60847-2 having breaking
capacity 25-KA with Thermal Magnetic setting release Panel Mounted. of make L&T/
Schneider/Siemens/Legrand/Hager based release arrangement with all connections etc., complete on
existing Panel Board including cost and conveyance of all materials to work site and all labour charges etc.,
complete as directed by the department.

As per Standard Data BLD-ELEC-4.3, Sl.No.4.3.4, P.No.176. Taking out put - Each.

Unit Qty Rate in Rs Amount in


Rs.

A. MATERIAL:

125-A, 4 Pole 25 KA Panel Mounting MCCB vide


P.No.216, Sl.No.323, ELEC-2.8.6. Each 1.00 8593.00 8593.00
B. LABOUR CHARGES:

Skilled Electrification Day 0.167 540.00 90.18

Semi skilled Electrification Day 0.167 420.00 70.14

Helper Day 0.333 420.00 139.86

Add. MPL @ 20% on Labour 60.04

8953.22

Overheads & Contractor's Profit @ 13.615%. 1218.98

Each 10172.20
Supply and erecting of 95 Sq.mm 3.50 Core XLPE insulated 1100.V Grade Armoured Alluminium Cable
of makeTorent/Universal/Unicab/Havells/KEI/Gloster/Polycab as per specification confirming to IS-7098 (Part-
I) with ISI mark making trench in soil upto 0.90 Mts. depth emeeding the cable with sand bed of 0.10 Mts.
thick layers and brick placed on top of the cable width wise all over the run and back filling the excavated
earth with stones are hard materials and making the surface proper with 15 Cm.crown on the top duly
providing route indicators inclduing including cost and conveyance of all materials to work site and all labour
charges etc.,complete for finished item of work.

Unit Qty Rate in Rs Amount in


Rs.
95Sq.mm 3.50 Core Alluminium U.G.Cable 1100.V
Grade. P.No.260, Sl.No.701, ELEC-4.1.31. 1.00 Mt. 1.00 503.00 503.00

Total 503.00

Overheads & Contractor's Profit @13.615%. 68.48

1 Rmt 571.48
Supplying and fixing of Crimping type Copper Lugs confirming to ISI specification suitable for cable of
95 Sq.mm. including nuts & bolts with connections. Evenly crimped with high pressure tool and connected
to switchgear terminals with brass/cadmium plated nut & bolts in an approved manner including cost and
conveyance of all materials to site of work, nuts & bolts and all labour charges for erection etc., complete.

As per Standard Data BLD-ELEC-15.4,Sl.No.15.4.6, P.No.270. Taking out put - Each.

Unit Qty Rate in Rs Amount in


Rs.
A: MATERIAL:

Copper Lugs P.No.263, Sl.No.733, ELEC-4.3.6. Each 1.00 58.00 58.00

B. LABOUR CHARGES:

Semi skilled Electrification Day 0.016 420.00 6.72

Helper (Electrical) Day 0.016 420.00 6.72

Add. MPL @ 20% on Labour 2.69


Total 74.13
Overheads & Contractor's Profit @ 13.615%. 10.09
Each 84.22
Supplying and fixing of Single compression Brass Cable Glands for 3.5 Core XLPE Armoured Cable from
70 Sq.mm. to 150 Sq.mm. with brass washers, rubber rings and errected with cable ends and leads
connected and including cost and conveyance of all materials to site of work and all labour charges etc.,
complete..

As per Standard Data BLD-ELEC-15.3,Sl.No.15.3.7, P.No.267. Taking out put - Each.

Unit Qty Rate in Rs Amount in


Rs.
A: MATERIAL:

Brass Cable Glands P..262,Sl.No.727,ELEC-4.2.7. Each 1.00 243.00 243.00


B. LABOUR CHARGES:

Semiskilled Electrification Day 0.066 420.00 27.72

Helper (Electrical) Day 0.066 420.00 27.72

Add. MPL @ 20% on Labour 11.09


TOTAL: 309.53
Overheads & Contractor's Profit @ 13.615%. 42.14

Each 351.67
Supply and erection of 0-415-V Volt Analog Meter on existing Box/Panel Board of make Conzerve
/Elmeasure/Legrand/Meco/HPL including cost and conveyance of all materials to work site and all labour
charges etc., complete as directed by the department.

Unit Qty Rate in Rs Amount in


Taking out put - Each
Rs.

0-415-V Volt Analog Meter, P.No.292, Sl.No.978,


ELEC-6.3.2. Each 1No 408.00 408.00

Overheads & Contractor's Profit @ 13.615%. 55.55

Each 463.55
Supply and erection of Led Indicator Lamps (Red, Yellow & Blue) of make L&T/C&S/ Salzar/HPL, on
existing Panel Board including cost and conveyance of all materials and all labour charges for fixing
charges etc., complete etc., as directed by the department for fixing Panel Board. (Make of
Conzerve/Elmeasure /MECO/HPL).

As per Standard Data BLD-ELEC-14.2, Sl.No.14.2.7, P.No.264. Taking out put - Each.

Unit Qty Rate in Rs Amount in


Rs.
A. MATERIAL:
Led Indicator Lamps vide P.No.293, Sl.No.985, ELEC-
6.3.9. Each 1 No. 122.00 122.00

B. LABOUR CHARGES:

Skilled Electrification (for 10 jobs/day) Day 0.010 540.00 5.40

Add. MPL @ 20% on Labour 1.08

128.48

Overheads & Contractor's Profit @ 13.615%. 17.49

Each 145.97
Supply and erection of Selector Switch for Voltmeter/Ammeter on the existing Box/Panel Board make of
L&T/C&S/Salzar/HPL including all connectionsand including cost and conveyance of all materials and all
labour charges for fixing charges etc., complete etc., as directed by the department.

As per Standard Data BLD-ELEC-14.2, Sl.No.14.2.6, P.No.264. Taking out put - Each.

Unit Qty Rate in Rs Amount in


Rs.
A. MATERIAL:
Selector Switch for Voltmeter, P.No.293, Sl.No.984,
ELEC-6.3.8. Each 1 No. 159.00 159.00

B. LABOUR CHARGES:
Skilled Electrification (for 5 jobs/day) Day 0.040 540.00 21.60

Add. MPL @ 20% on Labour 4.32

184.92

Overheads & Contractor's Profit @ 13.615%. 25.17

Each 210.09
Supplying, fabrication and erection of 25mmx6mm size 230-A in each bar of 1.00 Mt. length 4 Nos. of
Alluminium Bus Bars in the existing shet steel enclosure with resin cast insulator supports etc., including
cost and conveyance of all materials to site of work and cost of drilling holes, bolts & nuts, and all labour
charges for erection of Bus Bars etc., complete. (Weight per Mt. in Kg. = 0.402 Kgs.) As per Revised
Standard Data 12.2.1. (Standard Data P.No.305.d)

25 x 6mm size Bus bars Rate vide P.No.304,


Sl.No.1129, ELEC-8.1.42. @ Rs.225.00/Kg. 225.00 0.402

Cost of 1 Mt.x 4 Nos.x 0.402 Kg/Mt. 90.45

Overheads & Contractor's Profit @ 13.615%. 12.31

Total 102.76 per Rmt.


Supply and fixing of 32-A 240-V Porcelain rewirable FUSE UNITS make of GM/Sputnik/Million/ Gold
Medal/Vimal/Star Benlo/Fybros by jundan cab on existing Panel Board including cost and conveyance of all
materials and all labour charges for fixing charges etc., complete etc., as directed by the department for
fixing Panel Board.

A.P.Standard Data of BLD-ELEC-2.1.7 (Data taken as per Batten Holder )


Unit Qty Rate in Rs Amount in
Taking out put - Each
Rs.
A. MATERIAL:
Cost of 32-A, 240-V Rewirable Fuse Units. P.No.215,
Sl.No.308, ELEC-2.6.1.
Each 1No 88.00 88.00
B. LABOUR CHARGES:

Skilled Electrification Day 0.050 540.00 27.00

Helper (Electrical) Day 0.050 420.00 21.00

Add. MPL @ 20% on Labour 9.60


TOTAL = 145.60

Over Heads and Contractor's Profit @ 13.615 % 19.82

Each 165.42
Providing Independent Earthing from Main switch Board for earth continuity with No.8, G.I wire including
excavation of earth in hard gravel/hard desintegrated rock upto 2.10 Mts.' depth below ground level of
section 5'x2'x3' duly providing 40mm Dia G.I Pipe of 2.50 Mts. length using GI bolts and nuts and fixing earth
wire including supply and fixing 18''Dia., 2" thick hume pipe ring and refilling the pit with 5 Kgs hard coke,
20Kgs salt and excavated earth including all labour charges etc., complete for finished item of work.

As per Revised Standard Data of BLD-ELEC-5-1-1.


Unit Qty Rate in Rs Amount in
Rs.
Earth work excavation in all soils for trench, Pole Pit
and Earth Pit. P.No.304,Sl.No.1139,ELEC-8.1.52
Area = 1.50 x 0.60 x 0.90 = 0.81 cum Cum 0.81 99.00 80.19
40mm nominal bore light grade G.I pipe,
P.No.304,Sl.No.1144,ELEC-8.1.57. Rmt. 2.50 319.00 797.50
Drilling of 16 Nos. through holes of 12mm dia to
G.I.pipe, P.No.305, Sl.No.1146, ELEC-8.1.59. Each 16.00 5.00 80.00

G.I.Wire. P.No.304, Sl.No.1128, ELEC-8.1.41. Kg 1.00 61.00 61.00


G.I.Bolt & Nuts with washers
P.No.305, Sl.No.1147, ELEC-8.1.60. Set 4.00 10.00 40.00

Hard coke, P.No.303, Sl.No.1100, ELEC-8.1.13. Kg 40.00 18.00 720.00

Salt P.No.303, Sl.No.1101, ELEC-8.1.14. Kg 20.00 9.00 180.00


18" Dia. 2" th.Hume Pipe Ring,
P.No.305,Sl.No.1148,ELEC-8.1.61. Each 1.00 225.00 225.00

Semi skilled Electrification Nos. 0.50 420.00 210.00

Helper (Electrical) Nos. 0.50 420.00 210.00

Add. MPL @ 20% on Labour 84.00

2687.69

Overheads & Contractor's Profit @ 13.615%. 365.93

Each 3053.62
Earth work excavation of trench in hard ground soil, laying of U.G. Cables from 70 Sq.mm. to 400
Sq.mm. on sand cushion covering the cable with brick and back filling of trench duly providing route indicator
embedded in C.C. including cost and conveyance of all materials to work site and all labour charges etc.,
complete for finished item of work.

As per Standard Data BLD-ELEC-15.6, Sl.No.15.6.2, P.No.278. Taking out put -Rmt.

Unit Qty Rate in Rs Amount in


A. MATERIAL: Rs.
Earth work excavation 100x0.30x0.90 Mts. P.No.304,
Sl.No.1139, ELEC-8.1.52. Cum. 27 99.00 2673.00
Cost of Bricks. P.No.304, Sl.No.1141,ELEC-8.1.54
(3431/1000 = 3.431) 1000 Nos. 0.92 3431.00 3156.52

Sand Cum. 6.00 214.35 1286.10


Cable Route Indicator vide P.No.303, Sl.No.1114,
ELEC-8.1.27. Each 12.00 90.00 1080.00
B. LABOUR CHARGES:

Man Mazdoor for spreading the sand and back filling Day 2.50 370.00 925.00

Skilled Electrician Day 1.60 540.00 864.00

Helper (Electrical) Day 3.30 420.00 1386.00


Man Mazoor for concreting and embedding of
cable way indicators Day 2.00 370.00 740.00

Add. MPL @ 20% on Labour 783.00

Total 12893.62

Overheads & Contractor's Profit @ 13.615%. 1755.47

Total 14649.09

244.15

You might also like