Site Labour V205

Monday Tuesday Wednesday Thursday Friday Saturday Sunday


Day/Date 4-May-20 5-May-20 6-May-20 7-May-20 8-May-20 9-May-20 10-May-20

2 13 14 13 18 20 0

SGB03-SGB04a : install rebar n formwork for rc kerb SGB03-SGB04a : install rebar n formwork for rc SGB03-04a : install rebar & formwork station SGB03-04a : install rebar & formwork station SGB03-04 : concreting fire seal kerb station
TNE36-37 : parapet stitching finishing rectification 2 3 2 2 3 5 No activity 0
Section 1 extension lhs kerb extension lhs platform kerb RHS platform kerb RHS platform RHS
Sungai Besi
TNE37 : Housekeeping n hacking conc debris at 1 TNE35 : Dismantling jacks 3 TNE35 : Dismantle hydraulic jack on pier head 2 SGB06-07 : tendon grouting 6 SGB07-08 : tendon grouting 6
stitching area

TNE38 : Dismantling trestle 9 TNE38 : Dismantling trestle 9 TNE38 :Dismantle trestle 9 TNE38 : Dismantle trestle 9 TNE38 : Dismantle trestle 9

27 38 42 37 28 28 3

LSC B LSC B LSC B LSC B LSC B LSC B SGB 10


5 6 Bearing tightening works at SGB10 - UC - LHS 4 preparation for tendon grouting, installation of 5 4 5 3
Cropping tendons at SGB 10-13 Cropping tendons at SGB 10-13 grouting recess top cantilever tendon at SGB 10-12) housekeeping dismantling Peri's working platform
(plinth no. 2) inlet pipe for grouting at SGB 11-12

LG3 SGB 36-TP 02


7 7 LG3 6 LG3 6 SGB 10 5 SGB 10 3
installation formwork for lifting holes on SBG span grouting for lifting holes on SBG span SGB 36 - TP
SGB 36 - TP 02 02 grouting lifting holes on SBG span TP 02-04 grouting lifting holes on SBG span TP 02-04 dismantling working platform dismantling working platform

SGB 36 - TP 04 SGB 11-TP 04


lifting up parapet wall at span TP 03-04 LSC B
parapet 10 15 TP 02-04 10 5 LSC B 5 LSC B 5
dismantle formwork of stitching beam at SGB 36 - TP installation parapet span TP 03-04 LHS installation rebar & fwk for stitching beam at TP preparation for tendon grouting, installation of preparation for grouting tendons span SGB 10-12 preparation for grouting tendons span SGB 10-12
installation bracket & UPVC pipe for RWDP span inlet pipe for grouting at SGB 11-12
02
SGB 11-12

Section 2
Technology Park RWDP SGB 10-11
3 SGB 11-12 3 4 LG3 6 SGB 33 - TP 03 10 SGB 36 - TP 03 10
installation bracket & UPVC pipe for RWDP span TP installation bracket & UPVC pipe for RWDP span
02-04 preparation for cable hanger installation SGB 10-11 grouting lifting holes on SBG span TP 02-04 housekeeping works of parapet material and debris housekeeping

SGB 35-TP 04
TP 03-04 SGB 11-12 SGB 11-12
housekeeping works at LSC B at SGB 10-12 2 Installation of parapet at SGB 35-36 & TP 02-04 7 SGB 36- TP 02 5 final inspection & concreting for parapet 10 installation bracket & UPVC pipe for RWDP span 4 installation bracket & UPVC pipe for RWDP span 5
Fixing rebar for parapet stitching at SGB 35-36 & TP housekeeping works at SGB 36- TP 02
stitching at TP 03-04 SGB 11-12 SGB 11-12
02-04

SGB 32 - TP 04
6 SGB 11-12 5
housekeeping works & grouting lifting holes on
precast parapet walls transfer pipe fitting to SGB 11-12

TP 02-03 7
concreting parapet stitching at TP 02-03

18 21 21 26 39 25 0

TP04 - TP08 TP04 - TP08 TP04 - TP08 TP05 - TP06 TP05 TP05 - TP06
- preparation work for tendon grouting 3 - preparation work for tendon grouting 6 - preparation work for tendon grouting 6 11 13 13 No activity 0
- de-tension tendon -unload parapet wall on top deck - Pt work
- install protection cap - install protection cap - install protection cap
Section 3
Serdang
1) TP04 1) TP04 1) TP04-TP05
-housekeeping on top deck -housekeeping on top deck -housekeeping on top deck
TP04 15 TP04 15 15 15 TP05 - TP06 11 8
-housekeeping on top deck -housekeeping on top deck 2) SRN25 2) SRN25 - Pt work 2) SRN25 - SRN27
- cutting slope & prepare platform for drainage - cutting slope & prepare platform for drainage - cutting slope & prepare platform for drainage
works works works

1) TP04-TP05
-housekeeping on top deck
2) SRN25 - SRN27 15 TP08 4
- Install bearing plate
- cutting slope & prepare platform for drainage
works

Total (Day) 47 72 77 76 85 73 Total (Day) 3