Professional Documents
Culture Documents
Analysis of Rates: Name of Work:-Construction of 36 MTR Span Steel Girder Bridge in 1st KM of Dwari - Raithal Otor Raod
Analysis of Rates: Name of Work:-Construction of 36 MTR Span Steel Girder Bridge in 1st KM of Dwari - Raithal Otor Raod
Analysis of Rates: Name of Work:-Construction of 36 MTR Span Steel Girder Bridge in 1st KM of Dwari - Raithal Otor Raod
Total 1,653.60
Name of work:- Construction of 36 mtr span steel girder bridge in 1st km of dwari - Raithal otor Raod. Circle - 6th
Name of Contractor - M/s Hilways construction company C.B. No - 4 SE/2006-07 dated 26.12.2006
Sl No Items of Work Provision in Estimate Contractor's Claim AE / EE's Recommondation EE / SE' Sanction Remarks
Qty Rate Amount Qty Rate Amount Qty Rate Amount Qty Rate Amount
1 Reinforced cement vkx.ku esa
T.S.
concrete in proportion of M-20ddzhV dk
M-30 as per specification
and drawing including izkfo/kku fd;k
cost of material, labour, x;k gSA IIT
T&P etc. required for roorkee ls lsrq
proper completion of the design djkus ij
work. (MORT&H
Sr.no.12.8 G) RCC dk dk;Z M-
- - - 360.00 558.00 200880.00 360.00 558.00 200880.00 360.00 558.00 200880.00 30 ddzhV es djk;k
tkuk gS ftl dze
esa vfrfjDr en
Rs. 3151800-00
ek= dk Lohd`fr
gsrq izsf"kr gSA
Name of work:- Construction of 36 mtr span steel girder bridge in 1st km of dwari
- Raithal otor Raod.
e) overhead charges
add. 25% on cost of a+b+c+d 1520.46
f) contractor's profit
add. 10% on cost of a+b+c+d+e
760.23
cost for 15 cu.m 8362.52
Rate per cu.m 557.50
Say 558.00 per cum
0.00 26.32 26.32 Cement concrete with 40 mm gauge 2540.00 66852.80 66852.80 0.00
s/ballast, c/sand & cement in proportion
of 1:3:6 in foundation i/c s/o all m/l, t&p
etc complete.
3/4
0.00 18.33 18.33 RR stone masonary laid 1:4 cement, sand 1508.00 27641.64 27641.64 0.00
mortar i/c s/o all complete.
4/7
0.00 19.23 19.23 CC 1:2:4cement, c/sand & 20mm gauge 2921.00 56170.83 56170.83 0.00
s/ballast i/c s/o all complete.
5/5
0.00 4.318 4.318 Rcc work with cement, c/sand & 20mm 3600.00 15544.80 15544.80 0.00
gauge s/ballast in proportion of 1:1.5:3 in
rafts, bends & beams excluding cost of
steel.
6/8
14.52 162.12 176.64 Mild steel or iron work in plain work such 3800.00 671232.00 616056.00 55176.00
as in RCC brought to required size &
shape i/c bending for proper completion
of the work.
7/10
Supply & fabrication of 36.00m span
0.00 58.714 58.714 steel girder bridge as per detailed 67000.00 3933838.00 3933838.00 0.00
drawing.
8/22
24.55 78.400 102.950 Hand packed stone filling i/c s/o all 120.00 12354.00 9408.00 2946.00
material, labour, t&p etc all complete.
9/20
71.23 50.40 121.63 Excavation in foundation in all type of soil 44.00 5351.72 2217.60 3134.12
i/c s/o all m/l, t&p etc complete.
10/21
339.18 33.98 373.16 RR stone masonary laid 1:6 cement, sand 1094.00 408237.04 37174.12 371062.92
mortar i/c s/o all complete.
Total 5264773.28 4832454.24 432319.04
763392.13 700705.86 62686.26
Add 14.50% above as per bond condition
Total 6028165.41 5533160.10 495005.30
Extra Item
11/EI
1.66 594.62 596.28 Cement plum concrete with 40% plum & 4362.00 2600973.36 2593732.44 7240.92
60% CC 1:2:4 with cement, c/sand & 20
mm gauge s/ballast i/c s/o all m/l, t&p
etc all complete.
G. Total 11101182.55 10425866.80 675315.74
Royality Statement
7th Running bill
Name of Work :-C/o 36.00 m span steel girder bridge over Nahri gad in Ist km of Dwari - Raithal
Motor road.
Agency :- CB No 04/SE-6th/2006-07 dated 26.12.06 Name of Contractor :- M/s Hilways
Engineering company.
Sl no Item of Work Now to Stone Sand Stone / Ballast
pay Qty Norms Qty Norms Qty Norms Qty
Name of work :- Construction of 36.00 m span steel girder bridge at 1st km of Dwari-Raithal motor road.
C.B.N0.- 04/SE-6th dt.26.12.06
Date of Start : 27.12.2006
Actual Date of Completion : Work in progress
Detail of Recovery :
Month Explosive Detonator Fuse Detonating Remark
@ 86/kg @ 3.75/ Coils @ Fuse @
no 23/no 7.00/mtr
Page 7 of 8
oct-09 0.00 no transaction
nov-09 0.00 no transaction
dec-09 15.00 25.00 6.00 375.00 Issue against RMR of Pradeep mamgain (JE)
jan-10 0.00 no transaction
jan-10 0.00 no transaction
feb-10 0.00 no transaction
feb-10 0.00 no transaction
Mar-10 0.00 no transaction
Total qty 240.00 770.00 42.00 2500.00
Amount 20640.00 2887.50 966.00 17500.00
Total 41993.50
amount to
be
recovered
Rs.
Page 8 of 8