This document outlines the timeline and progress of a macadamization road project from May to October 2020. It lists 12 activities during the macadamization period including mobilizing machinery, applying primer coat, laying bituminous concrete, and applying a seal coat. Each activity shows it has been 100% completed by the given dates. The document also notes pre-macadamization and post-macadamization activities including various tests, spreading base materials, and construction of berms have similarly been fully executed according to the schedule.
This document outlines the timeline and progress of a macadamization road project from May to October 2020. It lists 12 activities during the macadamization period including mobilizing machinery, applying primer coat, laying bituminous concrete, and applying a seal coat. Each activity shows it has been 100% completed by the given dates. The document also notes pre-macadamization and post-macadamization activities including various tests, spreading base materials, and construction of berms have similarly been fully executed according to the schedule.
This document outlines the timeline and progress of a macadamization road project from May to October 2020. It lists 12 activities during the macadamization period including mobilizing machinery, applying primer coat, laying bituminous concrete, and applying a seal coat. Each activity shows it has been 100% completed by the given dates. The document also notes pre-macadamization and post-macadamization activities including various tests, spreading base materials, and construction of berms have similarly been fully executed according to the schedule.
This document outlines the timeline and progress of a macadamization road project from May to October 2020. It lists 12 activities during the macadamization period including mobilizing machinery, applying primer coat, laying bituminous concrete, and applying a seal coat. Each activity shows it has been 100% completed by the given dates. The document also notes pre-macadamization and post-macadamization activities including various tests, spreading base materials, and construction of berms have similarly been fully executed according to the schedule.
Percentage Activity No. of Work 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 Executed 0.0 PRE MACADAMIZATION PERIOD (Preparation of Surface) 0.1 Conduction of Various Tests for WBM at Quarry 100% 0.2 Gradation/Sieve Analysis of WBM G-III 100% 0.3 Laying & Spreading of WBM G-III at Site 100% 0.4 Comapction & Rolling of WBM G-III 100% Checking of thickness of WBM G-III at various 0.5 RDs 100% 1.0 DURING MACADAMIZATION PERIOD Zero Date 1.1 Mobilization of Machinery 100% 1.2 Surface Correction 100% Conduction of Various Tests for Bituminous 1.3 Concrete at Plant 100%
1.4 Applying Primer Coat with Bitumen Emulsion
100% 1.5 Laying of Bituminous Concrete at Site 100% 1.6 Compaction & Rolling of Bituminous Concrete 100% 1.7 Checking of thickness of BM at various RDs. 100% 1.8 Applying Tack Coat with Bitumen Emulsion 100%
1.9 Laying of Premix Carpet on Bituminous Macadam
100% 1.10 Comapction & Rolling of PC 100% 1.11 Applying Seal Coat to fill Voids 100% 1.12 Compaction of Bituminious Surface. 100% 2.0 POST MACADAMIZATION PERIOD 2.1 Construction of Berms. 100%