Construction Activity Schedule 1

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

2020

Sl. May June July August September October


Percentage
Activity
No. of Work
1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4
Executed
0.0 PRE MACADAMIZATION PERIOD (Preparation of Surface)
0.1 Conduction of Various Tests for WBM at Quarry 100%
0.2 Gradation/Sieve Analysis of WBM G-III 100%
0.3 Laying & Spreading of WBM G-III at Site 100%
0.4 Comapction & Rolling of WBM G-III 100%
Checking of thickness of WBM G-III at various
0.5
RDs 100%
1.0 DURING MACADAMIZATION PERIOD Zero Date
1.1 Mobilization of Machinery 100%
1.2 Surface Correction 100%
Conduction of Various Tests for Bituminous
1.3
Concrete at Plant 100%

1.4 Applying Primer Coat with Bitumen Emulsion


100%
1.5 Laying of Bituminous Concrete at Site 100%
1.6 Compaction & Rolling of Bituminous Concrete
100%
1.7 Checking of thickness of BM at various RDs.
100%
1.8 Applying Tack Coat with Bitumen Emulsion
100%

1.9 Laying of Premix Carpet on Bituminous Macadam


100%
1.10 Comapction & Rolling of PC 100%
1.11 Applying Seal Coat to fill Voids 100%
1.12 Compaction of Bituminious Surface. 100%
2.0 POST MACADAMIZATION PERIOD
2.1 Construction of Berms. 100%

Other Allied Works/Fixing of Cautionary


2.1.1
Signs/Direction Signs/KM Stones etc
100%

a Inspection of works by Various officials.