Professional Documents
Culture Documents
Under Ground Cables: Southern Technical University
Under Ground Cables: Southern Technical University
Student name:
فاطمة عبد الصمد عيدان
Supervisor:
رشيد صباح.د
Stage/Study:
صباحي-أ-رابعة
Course:
TRANSMISSION AND DISTRIBUTION
Abstract
Governments and energy operators are often confronted with opposition to the
construction of new high-voltage overhead transmission lines and a lack of public
support. A frequently discussed strategy for enhancing support is to build underground
cables instead of overhead lines. So far, however, there is not much empirical evidence of
whether substituting overhead lines by underground cables actually reduces public
protest or affects public perceptions. This study contributes to filling this gap by
comparing local residents’ perceptions and protest behavior observed at two grid
expansion sites in Germany by means of a quasi-experiment. At the time when the data
were collected, both grid expansion projects–an overhead line project in Lower Saxony
and an underground cable project in Hesse–were at the same stage of the legally defined
planning and approval procedure. After controlling for various potential confounders, we
obtained results revealing that there are no differences in the perceptions, attitudes, and
protest behavior of residents interviewed at the two project sites, or only marginal ones.
Hence, our findings do not support the assumption that building underground cables
necessarily enhances public support for power grid expansion.
Introduction
This overview contains information about electric transmission lines which are installed
underground, rather than overhead on poles or towers. Underground cables have
different technical requirements than overhead lines and have different environmental
impacts. Due to their different physical, environmental, and construction needs,
underground transmission generally costs more and may be more complicated to
construct than overhead lines. Issues discussed in this pamphlet include:
-Types of Underground Electric Transmission Cables
-Ancillary Facilities
- Construction and Operation Considerations
- Costs
- Repairs
The design and construction of underground transmission lines differ from overhead lines
because of two significant technical challenges that need to be overcome. These are: 1)
providing sufficient insulation so that cables can be within inches of grounded material;
Transition Structures
For underground cables less than 345 kV, the connection from overhead to underground
lines require the construction of a transition structure, also known as a riser. Figures 6
depict sample transition structure designs. These structures are between 60 and 100 feet
tall. They are designed so that the three conductors are effectively separated and meet
electric code requirements. The insulated conductor of the overhead line is linked
through a solid insulator device to the underground cable. This keeps moisture out of the
cable and the overhead line away from the supporting structure.
Lightning arrestors are placed close to where the underground cable connects to the
overhead line to protect the underground cable from nearby lightning strikes. The
insulating material is very sensitive to large voltage changes and cannot be repaired. If
damaged, a completely new cable is installed.
Reliability of Service
In general, lower voltage underground transmission lines are very reliable. However, their
repairtimes are much longer than those for overhead lines. Repair Rates – Pipe-Type
Transmission Cables For pipe-type lines, the trouble rates historically, for about
2,536miles of line correspond to about:
- One cable repair needed per year for every 833 miles of cable.
- One splice repair needed per year for every 2,439 miles of cable.
- One termination repair needed per year for every 359 miles of cable. These trouble
rates indicate that there would be, at most, a 1:300 chance for the most common type of
repair to be needed in any one mile of pipe-type underground line over any one year.
Repair Rates - XLPE lines
There is less available documentation regarding XLPE trouble rates and very little
information for 345 kV transmission lines. However, the following estimates are generally
accepted.
- One cable repair needed per year for every 1,000 miles of cable.
- One splice repair needed per year for every 1,428 miles of cable.
- One termination repair needed per year for every 1,428 miles of cable.
These trouble rates indicate that there would be, at most, a 1:1,000 chance for the most
common type of repair to be needed in any one mile of XLPE underground line over any
one year.
- Airports.
• The conductor used in cables should be tinned stranded copper or aluminium of high
conductivity.
• The conductor size should be such that the cable carries the desired load current
without overheating and voltage drop within permissible limits.
• The cable must have proper thickness of insulation in order to give high degree of
safety and reliability at the voltage for which it is designed.
• The cable must be provided with suitable mechanical protection to withstand the rough
use in laying it.
• The materials used in manufacture of cables should be such that there is complete
chemical and physical stability throughout.
Classification of Cables
Cables for underground service may be classified in two ways according to
(i) the type of insulating material used in their manufacture
(ii) the voltage for which they are manufactured
(iii) the number of Cores
Conclusion
The soil analysis for medium and low voltage electrical cables will contribute to the
monitoring of study strategy of soil contamination with heavy metals and their
influence on polymeric insulating material. Also, it will contribute to the
development of knowledge in the field of analytical methods, which will be used to
determine certain heavy metals in the soil, before and during the exploitation. This study
will contribute, as well at the preparation of the remediation strategy of the
electrical cables defects in exploitation according to the contaminated soil with
heavy metals. The lifetime of the polymeric insulators depends by environmental local
factors and the physicochemical characteristics of the soil, where electric cables are
in exploitation. The presence of heavy metals including Pb, Cd, Cr, Ni, Co, Zn, Cu and Al
from soil can affect the buried electrical cables in exploitation.