# TASK PREDECESSOR O M P E

1 A: Clean the area 2 3 4 3


2 B: Earthworks A 5 6 7 6
3 C: Set the guide line using nylon A,B 1 2 3 2
4 D: Mix concrete C 3 4 5 4
5 E: Footing D 4 5 6 5
6 F: Set the CHB E 3 4 5 4
7 G: Apply concrete in CHB E,F 5 6 7 6
8 H: Even off concrete with a trowel G 6 7 8 7
9 I: Dry the concrete H 10 11 12 11

INSTALLATION OF CONCRETE HOLLOW BLOCKS

A B
0 3 3 3 6 9
0 0 3 3 0 9

C D E F
9 2 11 11 4 15 15 5 20 20 5 24
9 0 11 11 0 15 15 0 20 20 0 24

G H I
24 6 30 30 7 37 37 11 51
24 0 30 30 0 37 37 0 51

E
O
P

LEVEL 0 1 2 3 4 5 6 7 9
3

A B
3
6 2 4
3
C D E F
3 3 3

5 3 4

G H 3 I
3
EO
6 7
P

1. ABCDEFGHI = 48 HRS. (CRITICAL PATH METHOD)


2. ACDEFGHI = 42 HRS.
3. ABCDEGHI = 44 HRS. 11