Abstract for Cost Analysis of Rock Bund Removing , Murrom filling & removing.
Say Rs : 3,200,000.00
NAVAYUGA ENGINEERING COMPANY LIMITED
PROJECT: CONSTRUCTION OF NRW 635M LONG MULTIPURPOSE BERTH AT KAKINADA.
COST ESTIMATION
ITEM NO: 01
BOULDER REMOVING AT OSV-II JETTY (NS-1 BUND)
Length : 140.00 M
Width : 5.50 M
Depth : 2.50 M
Volume of Boulder to be removed : 1925.00 Cu.m
Length : 140.00 M
Width : 3.00 M
Depth : 0.45 M
Volume of Boulder to be removed : 189.00 Cu.m
134.72
NAVAYUGA ENGINEERING COMPANY LIMITED
PROJECT: CONSTRUCTION OF NRW 635M LONG MULTIPURPOSE BERTH AT KAKINADA.
COST ESTIMATION
ITEM NO: 02
Cost Estimation for filling the removed area with Murrom.
Length : 140.00 M
Width : 10.00 M
Depth : 4.95 M (Considering filling upto -1.00 Level)
Compacted Volume of murrom to be : 6930.00 Cu.m Say = 7000.00Cu.m
filled
ITEM NO: 03
Cost Estimation for removing of the same murrom quantity
a) Removing quantity Calculation:
Length : 140.00 M
Width : 10.00 M
Depth
Compacted Volume of murrom to be : 5.95 M (Considering removal upto -2.00 Level)
filled : 8330.00 Cu.m Say =8500.00Cu.m
94.3670588
134.715156
300
529.082215
(Considering removal upto -2.00 Level)
NAVAYUGA ENGINEERING COMPANY LIMITED
PROJECT: CONSTRUCTION OF DIAPHRAGM WALL AT NS-1 BUND
Note : Cost Analysis for removing of Rock Bund , murrom filling & extraction of filled murrom is enclosed