DCMA 14 Point Check - Assessment Report


_____________________________________________________________________________________________________________________________________________________________________________________________________________________________

Project : Template - Working Plan (initial version) Total Activity : 227 Start Date : Oct 1, 2018 Finish Date : Oct 18, 2022 Data Date : Oct 1, 2018

Schedule Metrics - Task

Total Task: 139 In Progress : 0 Not Started : 139 Total Links : 270
Invalid Invalid Invalid No BEI-
Missing Missing Total High Lags High Lags Negative FF/SS Hard Soft High Float High Float Negative High Invalid Planned Missed
FS Link SF Link Actual Forecast Forecast Assigned CPLI Actual
Predecessor Successor Lags >22 days >10 days Lags Link Constr. Constr >44 days >22 days Float Duration Actual Start Task Task
Finish Start Finish Resources Task

1 2 31 8 14 12 233 0 33 0 2 46 70 0 21 0 0 0 0 139 1.0 0 0 0.0

Assessment Results
Less than Less than Less than Less than Less then Less Less than Less than Less than Less than
Less than 5% 0 Task > =90% 0 Task 0 Task 0 Task 0 Task 0 Task 0 Task 0 Task CPLI Less than 5% BEI
5% 5% 5% 5% 10 % than 5% 5% 5% 5% 5%

0.7% 1.4% 11% 3% 5% 4.4% 86% 0.0% 12.2% 0% 1.4% 33% 50% 0% 15.1% 0% 0% 0% 0% 100% 1.0

Schedule Metrics - Milestones

Total Milestones : 60 In Progress : 0 Not Started : 60 Total Links : 69

Missing Missing Total High Lags High Lags Negative Hard Soft High Float High Float Negative
Predecessor Successor Lags >10 days >22 days Lags Constrains Constrains >44 days > 22 days Float

6 18 10 5 4 2 0 9 34 41 0

Assessment Results
Less than Less than Less than Less than Less than Equal to 0 Equal to 0 Less than Less than Less than Less than
5% 5% 5% 5% 5% Task Task 5% 5% 5% 5%

10.0% 30.0% 14.5% 7.2% 5.8% 2.9% 0.0% 15.0% 56.7% 68.3% 0.0%

Note for Assessment Criteria :


Hard Constraints- Mandatory Finish, Mandatory Start, Finish On or Before, Start On or Before
Soft Constraints- As Late As Possible, Start On or After, Finish On or After, Start On, Finish On
High Duration- Greater than 44 working days (2 Months)
Completed activities / LOE / WBS Summary type and Flag milestones are excluded in the assessment.