Z21 MORTARS
To be read in conjunction with Section A and other related sections of the Specification, Preliminaries
and Contract Conditions.
Z21.2000 MATERIALS/PRODUCTS
Z21.2100 MATERIALS
Z21.2101 Mortar Generally
a) Mortar mix proportions shall be cement, lime and sand as specified, with nominal mix
proportions to BS 5628: Part 3.
b) Sand for mortar:
i) All sand shall comply with, and be from one source, to BS EN 13139BS 1199 and BS
1200, unless specified otherwise. It shall be well graded from 5mm in accordance with
Table 1 therein.
ii) Where a range is specified (e.g. 1:1:5-6) the lower proportion for grade ‘g’ sands and
higher proportion for grade 's' sands shall be used.
iii) Marine sand shall not be used with sulphate resisting or super sulphated cement.
c) Portland cements shall conform to BS EN 197: Part 1. Unless otherwise stated the cement
shall be of Ordinary Portland Cement and be delivered in the original sealed bags of the
manufacturer or in acceptable bulk containers.
d) All cement used shall be obtained from a supplier capable of complying with the requirements
of the Specification.
e) Lime shall conform to BS EN 459: Part 1 and be hydrated lime Type (i), (ii) or (iii).
f) Any mortar plasticiser used shall be agreed with the Engineer prior to commencement of any
work, and used in the proportions recommended in writing by the manufacturer. Mortar mixes
shall also be altered in accordance with the manufacturer's written recommendations. The
suitability of the mixture for use in any particular mortar shall be demonstrated.
g) Admixtures shall not be used in mortar unless agreed. Calcium chloride, or any admixtures
containing calcium chloride, shall not be used. Admixtures, if specified, shall be to BS EN 934:
Part 3.
Z21.2200 WORKMANSHIP
Z21.2201 General
a) Mixing plant, tools and banker boards shall be kept clean at all times.
b) Materials shall be measured accurately by volume using clean gauge boxes. Proportions of
mixes shall be for dry sand making allowance for bulking if it is damp.
c) Ingredients shall be mixed thoroughly to a consistency suitable for the work and free from
lumps. Mortars containing air-entraining admixtures shall be mixed by machine, but not
overmixed.
d) Retarded mortar shall be used within the time recommended in writing by the manufacturer
relative to the extreme temperatures that may be experienced on Site. Mortar shall be
retempered to restore workability, but only within these time limits.
e) The required amount of water shall be determined to achieve a workable mix.
f) If pre-mixed mortars are used, the characteristics, product data, and testing criteria shall be
submitted to the Engineer for review.
Z21.2300 TESTING
Z21.2301 Mortar Testing
a) Tests:
i) Testing of mortars shall be carried out in accordance with BS 5628: Part 1, BS 4551 and
BS EN 1015, or to equal standards acceptable to the Engineer.
End of Section
F10.2300 MORTARS
F10.2301 Mortar for Walling
In addition to the requirements of Section Z21 the following shall apply:
a) Block Mortar:
i) Generally: Select all mortar types to provide a compressive strength of 13.2 N/mm² to
comply with BS EN 998: Part 2 and the requirements of the Structural Engineer.
ii) Submit details of all mortar mixes for agreement with the CAEngineer.
b) Mortar to be colour matched with blockwork for all fair-faced work.
c) Sand for facework mortar shall be from one source to ensure consistency of colour and texture.
Submit samples of sand proposed in accordance with the requirements of the Specification
and identify:
i) Name of supplier.
ii) The pit the material came from.
iii) Sieve analysis.
iv) Maximum aggregate size: To be agreed with the CAEngineer.
d) Ready-mix mortar may be submitted as an alternative to that specified, subject to the
acceptance of the CAEngineer.
F10.3100 INSTALLATION
F10.3101 Site Control
a) Site installation shall be carried out in accordance with BS 5628 and BS 8000: Part 3.
b) Materials shall be clean and built uniform and level within the tolerances specified.
c) Quoins and jambs shall be plumbed as the work proceeds. The head of all walls shall be laid