Professional Documents
Culture Documents
Figure 2-1: Overview of Sitakunda Terminal
Figure 2-1: Overview of Sitakunda Terminal
Bangladesh has planned to construct an Economic Zone in the Feni-Mirasarai area, some 60-80 km north of
Chittagong. In order to improve the supply chain efficiency for production, distri- bution and trade it is considered
important that a Port/Terminal is established with adequate port facilities near the Economic Zone. The proposed
location of this new Sitakunda Terminal is in the Sandwip Channel, in and around Sitakunda Upazila near Mirasarai,
and opposite of the Sandwip Island.
The market is expected to be predominantly captive. By year 2025 container traffic is already expected to reach 2.6
million TEU per year, assuming operations start in year 2021.
Vessels with larger capacity can call the Terminal in partly loaded condition, provided that the draught does not
exceed 9.5m. Hence, there are no general limitations for the LOA of the vessels. The platform in the future Sitakunda
Terminal will have a length of 1,980m corresponding to 10 berths for 1,300 TEU vessels with LOA=165m. Since cargo
handling can be performed efficiently with two cranes working simultaneously on a 1,300 TEU vessel, it is proposed to
install 20 STS cranes with a 100 ft. span. Sitakunda Terminal with this can handle maximum 2.7 million TEU per year.
Loaded container groups in the container yard will have a width of seven stacks and a maximum height of five
containers. The stacking height of one over five containers is selected as it provides the best compromise between
storage capacity and operational efficiency. The stacks are operated by diesel powered Rubber Tire Gantry (RTG)
cranes and MTS. A total of 42 RTG cranes are required to operate the container yard. An overview of the Sitakunda
Terminal is shown in the figure below.
Table below provides an overview of the annual operating costs for Sitakunda Terminal. The total operating costs,
when the terminal is fully operational, will be approximately 44,592,000 USD per year and a non-recurrent cost of
353,000 USD is encountered.
OPEX estimate for Sitakunda Terminal – Annual operating costs.
Total Cost (USD)
Personnel 7,381,000
Energy and Operations 12,122,000
Maintenance and Repair 20,237,000
General Costs (Recurrent) 4,852,000
General Costs (Non-recurrent) 353,000
OPEX TOTAL (rounded) (excl. non-recurrent costs) 44,592,000
The investment plan summarizes the development of the total capital and operating expenditures at
Sitakunda Terminal throughout a forecasting period of 20 years.
More detailed elaborations of the CAPEX and OPEX estimates are included in the following.
Table 2-8: Sitakunda Terminal initial equipment investment costs. Replacement costs are included as-
suming a project lifetime of 20 years.
Life
Equipment Span Unit Price Initial Investment Replacement
(Years) (USD) Costs (USD) Costs (USD)
STS Crane 20 11,650,000 233,000,000 -
STS Rails and Related Sys- 20 1,200 2,101,600 -
tems
RTG 20 1,750,000 73,500,000 -
Multi Trailer 15 43,500 23,925,000 23,925,000
Trucks 15 187,000 20,570,000 20,570,000
Empty Container Handler 10 292,000 2,920,000 2,920,000
IT and Terminal Operation 10 1,285,500 1,285,500 1,285,500
System
Fuel Tank, Capacity 45m3 20 58,500 175,700 -
Service Cars 10 76,000 228,000 228,000
Fuelling Truck 10 87,500 175,000 175,000
Gate/Security Arrangement 15 1,169,000 1,169,000 1,169,000
Fence 20 300 1,200,000 -
Various Transport Equipment 10 350,500 350,500 350,500
Buoys 10 46,500 139,500 139,500
Light Tower High (incl. light) 30 128,500 128,500 -
Light Tower Low (incl. light) 30 70,000 70,000 -
Minibus/Bus 20 Persons 10 47,000 470,000 470,000
Bus 10 76,000 532,000 532,000
Spare Parts Inventory 10 3,506,000 3,506,000 3,506,000
Pilot Boats 20 1,052,000 2,104,000 -
Mooring Boats 20 584,500 1,169,000 -
Tug Boats 30 11,104,500 22,209,000 -
Building Equipment (IT equip- 10 877,000 877,000 877,000
ment etc.)
Additional Works - - 11,754,153 1,684,425
Unforeseen Expenses - - 26,231,352 3,759,075
Design - - 3,008,534 431,137
TOTAL (rounded) 432,800,000 62,022,000
For calculation of the economic feasibility, the Consultant used the following key assumptions:
Cargo destined for domestic consumption 50% of total cargo hauled by land
Average price decrease for domestic consumers 1%
Average value of container contents 50,000 US$ per TEU
Value-added through "just-in-time” delivery 2% of value per TEU
1,300 TEU container-vessel operating costs US$ 15,000 per day
Berth occupancy at Bay Terminal in "without-Project" case 80%
Reduction of average dwell time compared to Bay Terminal 1 day
Return on equity FIRR, FNPV (15%)
A Build-Operate-Transfer (BOT) contract would offer the main advantage that CPA would have limited
commercial risk, and that the concessionaire would be doing his utmost effort to offer a satisfactory
service. A concession contract would be used whenever the terminal needs huge funds to be prepared
and ready to put in service.
Container Charges
Discharged Containers
han- dled 36.8 117.6 155.9 206.6 273.9
Loaded Containers 48.7 154.8 205.2 272.0 360.6
Full Containers stored 15.6 49.9 66.2 87.7 116.3
Empty Containers stored 7.1 22.2 29.4 39.0 51.7
Total Revenues 114.1 363.3 481.4 638.2 846.0
Above-listed revenues from Sitakunda Terminal comprise only calculable revenues to CPA, whereas
additional operating revenues (form shifting containers, hiring equipment, etc.) are not included. The
Consultant therefore sees a potential for rather higher revenues.
The Consultant calculated the pre-tax FIRR as 11.52% which lies slightly below the preferred dis- count
rate of 15%. Considering that the water-side tariff has not been calculated to increase, and that revenues
from additional services have not been included, this FIRR demonstrates the finan- cial viability of the
Project. When applying the preferred discount rate of 15%, the pre-tax FNPV stands at US$ -307.0 million
and the after-tax FNPV at US$ -411.7 million. Residual value at the end of the Project period amounts to
about US$ 1,427 million. The pre-tax benefit/cost ratio (ra- tio between net present values of expenses
and revenues) stands at 0.86, whereas the after-tax BCR stands at 0.79.
Indicator Base
EIRR Economic Internal Rate of Return (%) 18.91%
ENPV Economic Net Present Value (US$
million, i=15%) 272.2
BCR Benefit/Cost Ratio 4.62
Consequently, the ENPV will be positive with US$ 272.2 million, and the benefit/cost ratio will stand at
4.62, proving the economic viability of Sitakunda Terminal. The Consultant subjected uncertainties to
sensitivity calculations to test the effect of changes in their levels on the EIRR,
ENPV and BCR indicators.
31 of
37
32 of
37
Changed
Variable
33 of
37