Professional Documents
Culture Documents
A Tragic and Unpredictable Station Cavern Collapse During Construction of A Metro, Despite Extensive Drilling Investigations
A Tragic and Unpredictable Station Cavern Collapse During Construction of A Metro, Despite Extensive Drilling Investigations
net/publication/319188537
CITATIONS READS
0 195
1 author:
SEE PROFILE
Some of the authors of this publication are also working on these related projects:
All content following this page was uploaded by Nick Ryland Barton on 21 August 2017.
N. R. Barton
ABSTRACT
In January of 2007, seven people in a São Paulo street, four of them in a small bus, were
suddenly sucked into falling soil and saprolite, from a street elevation about 20 m above a metro
station cavern of 19 m span and 40 m length. Despite the evidence of four surrounding and one
central borehole, and six more boreholes around the adjacent station shaft, the assumed mean
rock cover of just 3 m above the 20 m deep cavern arch, proved locally to be more than 10 m in
error, due to a buried ridge of rock running high above the cavern arch, with one fateful low point
exactly where drilled on the cavern centre-line. Seven lanes of adjacent highway and twin railway
lines prevented viable seismic refraction, and a consistent drilling result had not proved this to be
necessary. Due to the assumed low rock cover, heavy lattice girders, embedded in 40 cm of S(fr)
were used as temporary support. The feet of the lattice girders were founded on broad ‘elephant’
footings. Due to the unknown adverse loading from a wedge-shaped, clay-bordered, giant ridge of
rock and saprolite, weighing some 15,000 tons, all forms of temporary support would eventually
have failed. Post-collapse, painstaking, police-supervised excavation of the entire 20 by 20 by 40
m of collapsed materials, taking some 15 months, finally revealed large remnants of the arch and
wall support, crushed and folded beneath the fallen gneiss, amphibolite, saprolite, sand and soil.
1 INTRODUCTION
1
2 BEFORE AND AFTER COLLAPSE FIGURES
2
3 RIDGE OF ROCK THAT WENT UNDETECTED 4 ROCK QUALITY LOGGING IN CAVERN
3
Figure 10: Part of the side of the smooth weathered ‘core’
exposed by excavation, here consisting of gneiss. It has
prominent cross-jointing, loosened by its rapid 9 to 10 m fall to
the floor of the cavern. The superficial UCS here may be as
low as 5 MPa, due to an original elevation about 9 m above the
arch, surrounded by the presumed saprolite of the Class IV
rock, as recorded at the lower level of the cavern.
Figure 8: Conceptual stages in the development of a high-
standing ridge-of-rock, with faster weathering of the lower Figure 10 is assumed to be a sample of ‘remnant’
quality surroundings. Parallels to ‘tor’ structures are apparent, Class III, but originating from a higher level (+10 m) than
as suggested in the next figure. when recorded by the geologist at the cavern face. Note
that the conceptual sketches in Figure 8 were created
before excavation had progressed to the level of this
fallen rock. The ridges could have been more rounded,
‘to aid’ (explain) the collapse, as a wedge phenomenon.
A photograph of part of the top of the exposed ridge is
reproduced in Figure 11. An original elevation of 705+2+
10 = 717 m is suggested, 11 m above the assumed rock
elevation of 706 m.
Figure 11: Part of the top of the ridge-of-rock, proving the high
Figure 9: The sketch is from Linton ( 1955). (‘The problem of original elevation (717 m). Remarkably, the investigating
tors’). Despite the much less massive nature of gneiss (as institute working on behalf of the police, missed or ignored this
compared to granites), the remnants of more jointed, and elevation discrepancy in their 3000 pages report to the
differentially weathered structures were clearly evident authorities.
throughout the stage-by-stage excavation. The arrow shows a
conceptual borehole 8704 location, between two towers, in this 6 THE COLLAPSE OF LATTICE GIRDER
case remnant towers or ‘tors’ of granite from SW England. SUPPORT
Figure 10 shows part of the flanks of the exposed In order to compare with subsequent collapse
ridge or ‘core’ that had a loosened appearance due to its photographs, the robust appearance of the lattice girder
fall of about 10 m. It exhibits a curved, smoothed surface, and S(fr) support is illustrated during a spraying cycle in
due to deep weathering.
4
S(fr), which in this case would need to be combined with
RRS, or rib-reinforced lattice girders, to take care of the
lowest quality rock mass. (Q was estimated from 0.1 to
4). It is the opinion of the writer that all conventional
methods of support would have failed in this special case.
Y Axis (m)
2.0 2.0
-0.5
1.0 1.0
0.5 0.5
-0.8
0 0
-0.9
-0.5 -0.5
-1.0
-1.0 -1.0
-1.1
-1.5 -1.5
-1.2
-2.0 -2.0
-1.3
-2.5 -2.5
-2.5 -2.0 -1.5 -1.0 -0.5 0 0.5 1.0 1.5 2.0 2.5 3.0 3.5 4.0 4.5 5.0 5.5 6.0
X Axis (m)
Figure 13.: Evidence of ‘plastic-hinge’ development in the Figure 15: A final stage of collapse with UDEC, stage 2 invert.
lattice girders. Note the remnants of pre-grouting tubes just
above the collapsed shotcrete (and lattice girder) support.