Download as pdf or txt
Download as pdf or txt
You are on page 1of 9

CONS P&DB EPCT

information before each design and execution stage information before each design and execution stage information before each design and execution stage
is commenced. When any document of a technical is commenced. When any document of a technical is commenced. When any document of a technical
nature is issued to the Engineer, evidence of the nature is issued to the Engineer, evidence of the nature is issued to the Employer, evidence of the
prior approval by the Contractor himself shall be prior approval by the Contractor himself shall be prior approval by the Contractor himself shall be
apparent on the document itself. apparent on the document itself. apparent on the document itself.

CERTIFIED COPY – FOR EXCLUSIVE USE BY THE AMERICAN UNIVERSITY OF BEIRUT


Compliance with the quality assurance system shall Compliance with the quality assurance system shall Compliance with the quality assurance system shall
not relieve the Contractor of any of his duties, not relieve the Contractor of any of his duties, not relieve the Contractor of any of his duties,
obligations or responsibilities under the Contract. obligations or responsibilities under the Contract. obligations or responsibilities under the Contract.

OB 4.8

The Contractor is required to institute a quality assurance system in accordance it may be inappropriate for some Works or for work in some countries. If this Sub-
with the details stated in the Contract, unless no such details are so stated. The Clause is to apply, details of the quality assurance system should be included in
international standard ISO 9001 introduced the concept of quality assurance, but the Contract, and could have been proposed by tenderers.

4.10 Site Data

CONS P&DB EPCT


The Employer shall have made available to the The Employer shall have made available to the The Employer shall have made available to the
Contractor for his information, prior to the Base Contractor for his information, prior to the Base Contractor for his information, prior to the Base
Date, all relevant data in the Employer’s possession Date, all relevant data in the Employer’s possession Date, all relevant data in the Employer's possession
on sub-surface and hydrological conditions at the on sub-surface and hydrological conditions at the on subsurface and hydrological conditions at the
Site, including environmental aspects. The Employer Site, including environmental aspects. The Employer Site, including environmental aspects. The Employer
shall similarly make available to the Contractor all shall similarly make available to the Contractor all shall similarly make available to the Contractor all
such data which come into the Employer’s such data which come into the Employer’s such data which come into the Employer's
possession after the Base Date. The Contractor possession after the Base Date. The Contractor possession after the Base Date.
shall be responsible for interpreting all such data. shall be responsible for interpreting all such data.
To the extent which was practicable (taking account To the extent which was practicable (taking account The Contractor shall be responsible for verifying and
of cost and time), the Contractor shall be deemed of cost and time), the Contractor shall be deemed interpreting all such data. The Employer shall have
to have obtained all necessary information as to to have obtained all necessary information as to no responsibility for the accuracy, sufficiency or
risks, contingencies and other circumstances which risks, contingencies and other circumstances which completeness of such data, except as stated in
may influence or affect the Tender or Works. To the may influence or affect the Tender or Works. To the Sub-Clause 5.1 [ General Design Responsibilities ].
same extent, the Contractor shall be deemed to same extent, the Contractor shall be deemed to
have inspected and examined the Site, its have inspected and examined the Site, its

111 © FIDIC 2000


CONS P&DB EPCT

surroundings, the above data and other available surroundings, the above data and other available
information, and to have been satisfied before information, and to have been satisfied before
submitting the Tender as to all relevant matters, submitting the Tender as to all relevant matters,
including (without limitation): including (without limitation):
(a) the form and nature of the Site, including (a) the form and nature of the Site, including
sub-surface conditions, sub-surface conditions,

CERTIFIED COPY – FOR EXCLUSIVE USE BY THE AMERICAN UNIVERSITY OF BEIRUT


(b) the hydrological and climatic conditions, (b) the hydrological and climatic conditions,
(c) the extent and nature of the work and Goods (c) the extent and nature of the work and Goods
necessary for the execution and completion necessary for the execution and completion
of the Works and the remedying of any of the Works and the remedying of any
defects, defects,
(d) the Laws, procedures and labour practices of (d) the Laws, procedures and labour practices of
the Country, and the Country, and
(e) the Contractor’s requirements for access, (e) the Contractor’s requirements for access,
accommodation, facilities, personnel, power, accommodation, facilities, personnel, power,
transport, water and other services. transport, water and other services.
RB 11; YB 11.1; OB 4.9

For many types of Works, the Employer may have carried out many types of may find it difficult to anticipate their preferred locations.
investigations. The latter could include studies of feasibility (to verify the likelihood Tenderers require considerable data for the preparation of tenders for an EPCT
of the Works being economically advantageous), and various sub-surface, contract, under which the Contractor assumes much greater risks than under a
hydrological and environmental investigations. Tenderers typically need the factual CONS or P&DB contract. Since, for example, the risk of sub-surface conditions is
results of all these investigations, so that they can foresee the conditions in which allocated to the Contractor, each tenderer needs to assess how adverse the
the Works are to be constructed. actual conditions may be, both in terms of working in these conditions and in
Under a P&DB or EPCT contract, and also in the case of a CONS contract which terms of their effect on the design of the works. If the risk of sub-surface
includes a significant element of Contractor design, tenderers will require data in conditions is significant, taking account of the type of works, it may be in the
order to carry out pre-contract design and determine the details of the works for Employer's interests for the contract to allocate this risk to the Employer, either by
which costs are to be estimated (waiting until after award of the Contract amending EPCT 4.12 or by using P&DB.
enhances risk). Tenderers for Contractor-design works require as much data as In all Books, the Employer asserts that he has made available "all relevant data" in
that required by the Employer's designer under CONS. They may require more his possession, which would include:
data, because the Employer's designer would co-ordinate the pre-tender sub-
surface investigations to suit his preferred location of each pier of a multi-span - data which he obtained from investigations for the Works, and
bridge, for example. In contrast, when the Employer arranges for pre-tender - data obtained by others, including data which may be publicly available but
investigations in order to obtain the data needed by the tenderers' designers, he is in the Employer's possession.

112 © FIDIC 2000


The Employer should make as much information as possible available to his possession after the Base Date (in effect, between the Base Date and the
tenderers, although it would be unwise for him to state that no other information completion of the Works). Failure in this respect may have significant
was available. For a successful contract, it is in both Parties' interests for all of the consequences, under the Contract in general and under CONS/P&DB 4.12 in
tenderers and (subsequently) both of the Parties to have as much factual particular, including the extent to which conditions will be regarded as
information, relevant to the Site and Works, as is available. However, the "Unforeseeable". In some countries, negligent or intentional withholding of data
Employer's obligation is only to make "all relevant data … on sub-surface and may entitle the Contractor to termination, and consequential personal injury may
hydrological conditions" available. The Employer does not have to (although he result in private and/or criminal liability.

CERTIFIED COPY – FOR EXCLUSIVE USE BY THE AMERICAN UNIVERSITY OF BEIRUT


may) make available:
The Employer should endeavour to ensure that he obtains all his data as early as
- any data which is clearly not "relevant" to the Contractor's performance of possible: preferably before the tender documents are issued to prospective
obligations under the Contract, tenderers, so that they can study the data before they visit the Site for the first
time. The principle enshrined in the General Conditions is that the Employer
- information which is known to be incorrect and thus not "data" (but dubious makes data available by the Base Date at the latest, so that tenderers have up to
data must be made available, albeit with suitable explanations), 28 days within which to review the final items of data and finalise their Tenders. If
- experts' opinions and other non-factual interpretations, which are not important or unexpected data becomes available thereafter, such data must be
"data", made available, and it may be appropriate to consider postponing the date by
which the Tenders are to be submitted.
- information which is neither data on sub-surface conditions nor data on
hydrological conditions. Note that: The Contractor is responsible for the interpretation of the Site data, and for
obtaining other information, so far as was practicable. The practicability of
(i) "sub-surface conditions" are the conditions below the surface, including obtaining information will clearly depend upon the time allowed for the preparation
those within a body of water and those below the river-bed or sea-bed, of the Tender, and upon aspects such as the accessibility of the Site. Under EPCT,
(ii) "hydrological conditions" means the flows of water, including those in the Contractor is also responsible for verifying the data, and the Employer is only
rivers and the underwater currents in open seas, and responsible to the extent specified in the sub-paragraphs of EPCT 5.1.

(iii) "environmental aspects" include such matters as the (known or Under CONS or P&DB, the Contractor is deemed to have obtained all other
suspected) presence of pollutants. necessary information, to the extent which was practicable. This extent clearly
depends upon the cost and time necessary to obtain the information, within the
In this Sub-Clause, the Employer asserts that all his relevant data (on sub-surface prescribed tender period. No such provisions were considered necessary for
and hydrological conditions) were made available before the Base Date, and that inclusion in EPCT 4.10 because of the greater extent of the Contractor's
he shall similarly make available to the Contractor data which came or comes into responsibilities, particularly those under EPCT 4.12.

4.11 Sufficiency of the Accepted Contract Amount 4.11 Sufficiency of the Contract Price

CONS P&DB EPCT


The Contractor shall be deemed to: The Contractor shall be deemed to: The Contractor shall be deemed to have satisfied
himself as to the correctness and sufficiency of the
(a) have satisfied himself as to the correctness (a) have satisfied himself as to the correctness
Contract Price.
and sufficiency of the Accepted Contract and sufficiency of the Accepted Contract
Amount, and Amount, and

113 © FIDIC 2000


CONS P&DB EPCT

(b) have based the Accepted Contract Amount (b) have based the Accepted Contract Amount on
on the data, interpretations, necessary the data, interpretations, necessary information,
information, inspections, examinations and inspections, examinations and satisfaction as
satisfaction as to all relevant matters referred to all relevant matters referred to in Sub-Clause
to in Sub-Clause 4.10 [ Site Data ]. 4.10 [ Site Data ] and any further data relevant
to the Contractor's design.
Unless otherwise stated in the Contract, the Accepted Unless otherwise stated in the Contract, the Accepted Unless otherwise stated in the Contract, the Contract

CERTIFIED COPY – FOR EXCLUSIVE USE BY THE AMERICAN UNIVERSITY OF BEIRUT


Contract Amount covers all the Contractor’s Contract Amount covers all the Contractor's Price covers all the Contractor's obligations under the
obligations under the Contract (including those under obligations under the Contract (including those under Contract (including those under Provisional Sums, if
Provisional Sums, if any) and all things necessary for Provisional Sums, if any) and all things necessary for any) and all things necessary for the proper design,
the proper execution and completion of the Works the proper design, execution and completion of the execution and completion of the Works and the
and the remedying of any defects. Works and the remedying of any defects. remedying of any defects.

RB 12.1; YB 11.2; OB 4.10

Sub-Clause 4.11 confirms the Contractor's responsibility for the adequacy of based his Tender on various matters referred to in Sub-Clause 4.10. P&DB's
CONS/P&DB's Accepted Contract Amount or of EPCT's Contract Price. Accepted Contract Amount is also to have been based upon "any further data
Under CONS or P&DB, the Accepted Contract Amount is a fixed amount, and the relevant to the Contractor's design", because the information obtained by the
Contract Price is defined in Sub-Clause 14.1. Employer may have been based on design assumptions which were not wholly
identical to those made by the Contractor's designers. The Employer should not
Under EPCT, the Contract Price is largely referred to as being fixed, at least to a assume, for example, that all tenderers' designers will locate a bridge's piers, or
greater extent than under P&DB. However, EPCT's Contract Price may be align a tunnel, the same as the Employer's Personnel may have done.
adjusted, so:
No such provisions were considered necessary for inclusion in EPCT 4.11,
- the definition of Contract Price in EPCT 1.1.4.1 refers to the subsequent because of the greater extent of the Contractor's responsibilities, particularly
"adjustments in accordance with the Contract", and those under EPCT 4.12.
- the Particular Conditions should define the amount of Performance Unless otherwise stated in the Contract, the Accepted Contract Amount or
Security, advance payment, and limit of Retention Money as percentages EPCT's Contract Price is deemed to cover all the Contractor's obligations. Work
of the "Contract Price stated in the Contract Agreement". carried out under Provisional Sums (see Sub-Clause 13.5) must therefore be
Under CONS/P&DB's sub-paragraph (b), the Contractor is deemed to have included within the scope of insurance cover under Clause 18, for example.

4.12 Unforeseeable Physical Conditions 4.12 Unforeseeable Difficulties

CONS P&DB EPCT


In this Sub-Clause, “physical conditions” means In this Sub-Clause, "physical conditions" means Except as otherwise stated in the Contract:

114 © FIDIC 2000


CONS P&DB EPCT

natural physical conditions and man-made and other natural physical conditions and man-made and other (a) the Contractor shall be deemed to have
physical obstructions and pollutants, which the physical obstructions and pollutants, which the obtained all necessary information as to risks,
Contractor encounters at the Site when executing Contractor encounters at the Site when executing contingencies and other circumstances which
the Works, including sub-surface and hydrological the Works, including sub-surface and hydrological may influence or affect the Works;
conditions but excluding climatic conditions. conditions but excluding climatic conditions.
(b) by signing the Contract, the Contractor

CERTIFIED COPY – FOR EXCLUSIVE USE BY THE AMERICAN UNIVERSITY OF BEIRUT


If the Contractor encounters adverse physical If the Contractor encounters adverse physical accepts total responsibility for having
conditions which he considers to have been Unfore- conditions which he considers to have been foreseen all difficulties and costs of
seeable, the Contractor shall give notice to the Unforeseeable, the Contractor shall give notice to successfully completing the Works; and
Engineer as soon as practicable. the Engineer as soon as practicable. (c) the Contract Price shall not be adjusted to
This notice shall describe the physical conditions, This notice shall describe the physical conditions, take account of any unforeseen difficulties or
so that they can be inspected by the Engineer, and so that they can be inspected by the Engineer, and costs.
shall set out the reasons why the Contractor shall set out the reasons why the Contractor
considers them to be Unforeseeable. The considers them to be Unforeseeable. The
Contractor shall continue executing the Works, Contractor shall continue executing the Works,
using such proper and reasonable measures as using such proper and reasonable measures as
are appropriate for the physical conditions, and are appropriate for the physical conditions, and
shall comply with any instructions which the shall comply with any instructions which the
Engineer may give. If an instruction constitutes a Engineer may give. If an instruction constitutes a
Variation, Clause 13 [ Variations and Adjustments ] Variation, Clause 13 [ Variations and Adjustments ]
shall apply. shall apply.
If and to the extent that the Contractor encounters If and to the extent that the Contractor encounters
physical conditions which are Unforeseeable, gives physical conditions which are Unforeseeable, gives
such a notice, and suffers delay and/or incurs Cost such a notice, and suffers delay and/or incurs Cost
due to these conditions, the Contractor shall be due to these conditions, the Contractor shall be
entitled subject to Sub-Clause 20.1 [ Contractor’s entitled subject to Sub-Clause 20.1 [ Contractor's
Claims ] to: Claims ] to:
(a) an extension of time for any such delay, if (a) an extension of time for any such delay, if
completion is or will be delayed, under Sub- completion is or will be delayed, under Sub-
Clause 8.4 [ Extension of Time for Clause 8.4 [ Extension of Time for
Completion ], and Completion ], and
(b) payment of any such Cost, which shall be (b) payment of any such Cost, which shall be
included in the Contract Price. included in the Contract Price.
After receiving such notice and inspecting and/or After receiving such notice and inspecting and/or
investigating these physical conditions, the Engineer investigating these physical conditions, the Engineer

115 © FIDIC 2000


shall proceed in accordance with Sub-Clause 3.5 shall proceed in accordance with Sub-Clause 3.5
[ Determinations ] to agree or determine (i) whether [ Determinations ] to agree or determine (i) whether
and (if so) to what extent these physical conditions and (if so) to what extent these physical conditions
were Unforeseeable, and (ii) the matters described were Unforeseeable, and (ii) the matters described
in sub-paragraphs (a) and (b) above related to this in sub-paragraphs (a) and (b) above related to this
extent. extent.

CERTIFIED COPY – FOR EXCLUSIVE USE BY THE AMERICAN UNIVERSITY OF BEIRUT


However, before additional Cost is finally agreed or However, before additional Cost is finally agreed or
determined under sub-paragraph (ii), the Engineer determined under sub-paragraph (ii), the Engineer
may also review whether other physical conditions may also review whether other physical conditions
in similar parts of the Works (if any) were more in similar parts of the Works (if any) were more
favourable than could reasonably have been favourable than could reasonably have been
foreseen when the Contractor submitted the Tender. foreseen when the Contractor submitted the Tender.
If and to the extent that these more favourable If and to the extent that these more favourable
conditions were encountered, the Engineer may conditions were encountered, the Engineer may
proceed in accordance with Sub-Clause 3.5 proceed in accordance with Sub-Clause 3.5
[ Determinations ] to agree or determine the [ Determinations ] to agree or determine the
reductions in Cost which were due to these reductions in Cost which were due to these
conditions, which may be included (as deductions) conditions, which may be included (as deductions)
in the Contract Price and Payment Certificates. in the Contract Price and Payment Certificates.
However, the net effect of all adjustments under However, the net effect of all adjustments under
sub-paragraph (b) and all these reductions, for all sub-paragraph (b) and all these reductions, for all
the physical conditions encountered in similar parts the physical conditions encountered in similar parts
of the Works, shall not result in a net reduction in of the Works, shall not result in a net reduction in
the Contract Price. the Contract Price.
The Engineer may take account of any evidence of The Engineer may take account of any evidence of
the physical conditions foreseen by the Contractor the physical conditions foreseen by the Contractor
when submitting the Tender, which may be made when submitting the Tender, which may be made
available by the Contractor, but shall not be bound available by the Contractor, but shall not be bound
by any such evidence. by any such evidence.

RB 12.2; YB 11.3; OB 4.11

Under EPCT, Sub-Clause 4.12 sets out EPCT's principles that risks lie with the for climatic events or other difficulties, unless they are so adverse and exceptional
Contractor, except where the contrary is expressly stated in the Contract: in as to constitute Force Majeure as defined in Sub-Clause 19.1. The remaining
Clause 19, for example. Therefore, the Contractor is not entitled to compensation comments on this Sub-Clause apply to CONS and P&DB only.

116 © FIDIC 2000


Under CONS or P&DB, Sub-Clause 4.12 entitles the Contractor to an extension of of conditions encountered at "any additional areas which may be obtained by the
time for delay, and to reimbursement of additional Cost, if he encounters Contractor", to which the first sentence of Sub-Clause 4.23 refers.
Unforeseeable physical conditions at the Site. As asserted in Sub-Clause 4.10, the
The Contractor's entitlement arises if such physical conditions are
Employer will have made available all information which he has, relating to the Site.
"Unforeseeable", which means "not reasonably foreseeable by an experienced
Sub-Clause 4.12 not only protects the Contractor if the actual conditions were not
contractor by the date for submission of the Tender", taking account (for example)
foreseeable. It also protects the Employer by providing a method of dealing with
of Sub-Clause 4.11(b) and of the data and matters mentioned in Sub-Clause 4.10.
the possibility of inaccuracies in the data referred to in Sub-Clause 4.10.

CERTIFIED COPY – FOR EXCLUSIVE USE BY THE AMERICAN UNIVERSITY OF BEIRUT


In Sub-Clause 4.10, the Employer asserts that all his relevant data (on sub-surface
The "physical conditions" are defined widely, so as to include natural sub-surface
and hydrological conditions) were made available before the Base Date, and that
conditions, natural and artificial physical obstructions, and the presence of
he shall similarly make available to the Contractor data which came or comes into
chemical pollutants, for example. The physical conditions are those which the
his possession after the Base Date. The Employer should have made data
Contractor "encounters at the Site", so they must be a type of condition which is
available by the Base Date at the latest, so that tenderers have 28 days within
physical in the sense that it is "encountered". Climatic conditions on the Site, such
which to review the final items of data and finalise their Tenders. If important or
as the direct effects of rainfall, are excluded. Note that:
unexpected data becomes available thereafter, such data must also be made
- "sub-surface conditions" are the conditions below the surface, including available. It may be appropriate to consider postponing the date by which the
those within a body of water and those below the river-bed or sea-bed, Tenders are to be submitted or, if data becomes available thereafter, to consider
what is to be regarded as "Unforeseeable".
- "hydrological conditions" means the flows of water, including those which
are attributable to off-Site climatic conditions, and Having encountered physical conditions which he considers may be both adverse
and Unforeseeable, the Contractor should promptly issue a notice, which could
- "physical conditions" exclude "climatic conditions" at the Site, and therefore also serve as the notice referred to in the first sentence of Sub-Clause 20.1 (to
exclude the hydrological consequences of climatic conditions at the Site. which Sub-Clause 4.21(f) refers). Failure to give notice within the period stated in
The adjective "Unforeseeable" is defined in Sub-Clause 1.1.6.8 as meaning "not Sub-Clause 20.1 deprives the Contractor of his entitlement to an extension of time
reasonably foreseeable by an experienced contractor by the date for submission and compensation. CONS/P&DB 1.3 requires the Contractor to send a copy of
of the Tender". The question whether hydrological conditions are Unforeseeable his notices to the Employer.
may be resolved by reference to the duration of the Time for Completion of the The notice should describe the physical conditions, state that it is issued under
Works and to the statistical frequency of the hydrological event, based upon Sub-Clauses 4.12 and 20.1, and be issued as soon as practicable so that the
historic records. For example, if the Time for Completion is three years, an Engineer:
experienced contractor might be expected to foresee an event which occurs (on
average) once in every six years, but an event which occurs only once in every ten - has the maximum opportunity to carry out an inspection and assess for
years might be regarded as Unforeseeable. If hydrological conditions are likely to himself whether the described conditions were Unforeseeable, taking
have a major effect on the execution of the Works, it may be desirable for the account of the Contractor's reasons set out in the notice, and
Contract to define Unforeseeable hydrological conditions and to clarify the - may consider initiating a Variation (although there is no obligation to do so),
consequences of extremely adverse hydrological conditions. in order to lessen the losses which might otherwise be suffered by the
Note the limitation to the "Site", which means "the places where the Permanent Employer.
Works are to be executed and to which Plant and Materials are to be delivered, Unless the physical conditions constitute Force Majeure and notice has been
and any other places as may be specified in the Contract as forming part of the given under Clause 19.2, the Contractor is required to continue executing the
Site". These places are those made available by the Employer under Sub-Clause Works, and not await instructions from the Engineer. When an experienced
2.1. Sub-Clause 4.12 does not entitle the Contractor to compensation in respect contractor encounters adverse physical conditions, he is expected to use his

117 © FIDIC 2000


expertise, overcome the conditions, and execute and complete the Works in Under the penultimate paragraph of Sub-Clause 4.12, the Engineer may review
accordance with the Contract. Although an experienced contractor should whether physical conditions in any other parts of the Works were more favourable
typically not require guidance on construction techniques, the Engineer should than could reasonably have been foreseen. This review is described as being
consider whether there is any need for Variations or other instructions. before "additional Cost is finally agreed or determined", the word "finally" confirming
Having given such prompt notice, the Contractor is entitled to an extension of time that there may well (and should) have been previous interim determinations of Cost
and reimbursement of the Cost attributable to the Unforeseeable physical for the purposes of Interim Payment Certificates. The Engineer should not delay or
withhold his interim determination and certification under Sub-Clause 4.12(a)&(b)

CERTIFIED COPY – FOR EXCLUSIVE USE BY THE AMERICAN UNIVERSITY OF BEIRUT


conditions, compared with the anticipated physical conditions which could
reasonably have been foreseen (which are deemed covered by the rates and whilst waiting to see if more-favourable conditions are going to be encountered.
prices contained in the Contract). In other words, the payment due should Sub-Clause 1.3 states that "determinations shall not be unreasonably withheld or
normally be the sum of: delayed"; and Sub-Clause 20.1 entitles the Contractor "to payment for such part
of the claim as he has been able to substantiate".
(a) the original contract value, namely of the work which would have been
required if he had only encountered foreseeable physical conditions, plus This penultimate paragraph concludes by preventing a net reduction for all
conditions encountered in similar parts of the Works, in order to impose a
(b) the additional Cost attributable to the extent to which the physical reasonable limitation on the Contractor's liability. The other parts of the Works,
conditions actually encountered are Unforeseeable. This is the Cost which where more-favourable conditions were encountered, must be "similar" to the parts
is in addition to the cost (deemed included in amounts (a)) which would where adverse Unforeseeable conditions were encountered. Parts of the Works will
have been incurred if he had encountered foreseeable physical conditions. be "similar" if their overall construction requirements are similar. For example:
The original contract value (a) of the work in foreseeable conditions is the various - the Works may comprise a number of similar elements, such as dwellings,
amounts stated in the Contract, typically for excavating the zone over which the pylons or pumping stations;
Unforeseeable conditions were encountered. The Contractor may consider that
he should be paid the total Cost of excavating Unforeseeable conditions, even if - a multi-span structure, such as a viaduct, may have many similar pier
they were only Unforeseeable to a limited degree. However, Sub-Clause 4.12 foundations;
states that his entitlement is payment of the Cost due to the extent to which the - a road cutting or tunnel may have similar section profiles at different locations.
conditions were Unforeseeable. Typically, it is therefore necessary to identify the
additional time and resources required, compared with those which would have Sub-Clause 4.12 concludes with a paragraph enabling the Engineer to take
been involved in the excavation of the zone if it had only comprised foreseeable account of any reliable evidence of the physical conditions which the Contractor
physical conditions. In the infrequent cases when the conditions are so adverse actually foresaw, although the possibility of misleading evidence having been
that it proves impossible to determine the costs which would have been incurred prepared for the purposes of this paragraph should not be overlooked. It may be
if he had encountered foreseeable physical conditions, it would be reasonable for appropriate for the Contractor to make such reliable evidence available (although
the Contractor to be paid his total Cost of excavating the adverse zone (in lieu of he is not obliged to do so) in order to avoid or resolve a dispute. If a dispute arises
the contract value (a) of excavating foreseeable conditions). and is referred to arbitration, the arbitrators may be given sight of such evidence,
may wish to question its authors, and may enquire why it was not made available
The original contract value (a) above would include the profit which the Contractor
to the Engineer under this paragraph.
would have earned if he had encountered foreseeable physical conditions. In
effect, the risk is shared, insofar as the Contractor loses the profit which he would Sub-paragraphs (a) and (b) describe the Contractor's entitlements in terms which are
have included in his Tender pricing if he had been aware of the existence of the used elsewhere in the General Conditions. See the Table in this Guide at the end of
adverse conditions. the commentary on Clause 3, and also the commentaries on Sub-Clauses 8.4 & 20.1.

118 © FIDIC 2000


4.13 Rights of Way and Facilities

CONS P&DB EPCT


The Contractor shall bear all costs and charges The Contractor shall bear all costs and charges The Contractor shall bear all costs and charges
for special and/or temporary rights-of-way which for special and/or temporary rights-of-way which for special and/or temporary rights-of-way which
he may require, including those for access to the he may require, including those for access to the he may require, including those for access to the

CERTIFIED COPY – FOR EXCLUSIVE USE BY THE AMERICAN UNIVERSITY OF BEIRUT


Site. The Contractor shall also obtain, at his risk Site. The Contractor shall also obtain, at his risk Site. The Contractor shall also obtain, at his risk
and cost, any additional facilities outside the Site and cost, any additional facilities outside the Site and cost, any additional facilities outside the Site
which he may require for the purposes of the which he may require for the purposes of the which he may require for the purposes of the
Works. Works. Works.

RB 42.3; OB 4.13

This Sub-Clause and Sub-Clause 4.15 assume that access to the Site is areas which may be obtained by the Contractor" mentioned in first sentence
physically practicable, but that the Contractor may need special or temporary of Sub-Clause 4.23.
rights-of-way or additional facilities. They may be located on the "additional

4.14 Avoidance of Interference

CONS P&DB EPCT

The Contractor shall not interfere unnecessarily or The Contractor shall not interfere unnecessarily or The Contractor shall not interfere unnecessarily or
improperly with: improperly with: improperly with:
(a) the convenience of the public, or (a) the convenience of the public, or (a) the convenience of the public, or
(b) the access to and use and occupation of all (b) the access to and use and occupation of all (b) the access to and use and occupation of all
roads and footpaths, irrespective of whether roads and footpaths, irrespective of whether roads and footpaths, irrespective of whether
they are public or in the possession of the they are public or in the possession of the they are public or in the possession of the
Employer or of others. Employer or of others. Employer or of others.
The Contractor shall indemnify and hold the The Contractor shall indemnify and hold the The Contractor shall indemnify and hold the
Employer harmless against and from all damages, Employer harmless against and from all damages, Employer harmless against and from all damages,
losses and expenses (including legal fees and losses and expenses (including legal fees and losses and expenses (including legal fees and
expenses) resulting from any such unnecessary or expenses) resulting from any such unnecessary or expenses) resulting from any such unnecessary or
improper interference. improper interference. improper interference.

RB 29

119 © FIDIC 2000

You might also like