Weekly Report As of 30th Dec'18

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

Project: Industrial Support Facility Building

Location: Jazan Economic City


Contractor: Al Yamama Company

Weekly Progress Update (Rev.09)


Data as of: 30th Dec'18
Procurement Progress (%) Construction Progress (%) Overall Progress (%)
Description
Planned Actual Difference Planned Actual Difference Planned Actual Difference

Last week 0.10% 0.00% -0.10% 0.42% 0.41% -0.01% 0.27% 0.22% -0.05%
Original Scope

This week 0.11% 0.00% -0.11% 0.43% 0.40% -0.03% 0.26% 0.21% -0.04%

Total 96.78% 96.51% -0.27% 78.81% 78.86% 0.05% 87.12% 87.02% -0.10%

Change order work progress % 0.14%

TOTAL ACTUAL CURRENT WEEK 0.54%

Planned Vs Actual Histogram - Original Scope


0.50%

0.45%
0.43%
0.40%
0.40%

0.35%

0.30%

0.26%
0.25%
0.21%
0.20%

0.15%
0.11%
0.10%

0.05%

0.00%
0.00%
Planned Actual Planned Actual Planned Actual
Procurement Progress (%) Construction Progress (%) Overall Progress (%)