ESTIMATE AMETHI. CANOPYxlsx
ESTIMATE AMETHI. CANOPYxlsx
CORPORATION LTD.
LUCKNOW
G. TOTAL 60.63
TOTAL 53.66
ABSTRACT OF COST
5 Add for Internal W/S & Sewerage System Work @ 12 % of Rs 48.85 5.86
10 Add for carted earth filling in the campus (A.R 1200.00 CUM 356.50 4.28
TOTAL 82.38
PROJECT: PRELIMINARY ESTIMATE OF PROPOSED TOURISM DEVELOPMENT & BEAUTIFICATION
ABSTRACT OF COST
5 Add for Internal W/S & Sewerage System Work @ 12 % of Rs 108.46 13.01
10 Add for carted earth filling in the campus (A.R 1600.00 CUM 356.50 5.70
TOTAL 191.91
PROJECT: PRELIMINARY ESTIMATE OF PROPOSED TOURISM DEVELOPMENT & BEAUTIFICATION
OF PARAM HANS CANOPY ,AMETHI ( UTTAR PRADESH)
QTY.
S.N. DESCRIPTION DSR.14 UNIT RATE AMOUNT
RAIN WATER HARVESTING
RECHARGE PITS
1 Earth work in exacavation in trenches for
foundations and for pipes cables etc. in
ordinary soil(loam clay or sand) including
lift upto 1.5 m and dressing of sides and
ramming of bottom sand disposal of
surplus excavated earth as directed by
the Engineer i/c with in a lead of 50m.
In all kind of soil upto 1.5m depth (SOR 251) Cum 14.720 94.00 1383.68
In all kind of soil upto 1.5m to 3.0m. Cum 14.720 107.00 1575.04
depth
In all kind of soil upto 3.0m to 4.5m. Cum 14.72 120.00 1766.40
depth
2 Providing and laying in cement concrete
1:2:4 (1 cement :2 coarse sand :4
graded Stone aggregate 20 mm nominal
size) and curing complete,including cost
of form- work,in foundation and floors. (SOR
279B) Cum 0.925 6565.00 6072.63
1:3 (1 cement : 3 Coarse sand) (SOR 583) Sqm 46.185 156.00 7204.86
7 Providing M.S. foot rests including fixing
in manoholes with 20x20x10 cm cement
concrete blocks 1:3:6 (1cement : 3
coarse sand : 6 graded stone aggregate
20mm nominal size) as per standard
design:
19.15
With 20x20mm square bar 19.15.1 Nos. 12 275.50 3306.00
DRAINAGE NETWORK
15 Excavating trenches in all kinds of soil
of required width for pipes. including
excavation for sockets and dressing of
sides, ramming of bottoms, including
getting out the excavated soil & then
returning the soil as required, in layers
not exceeding 20 cm in depth including
consolidating each deposited layer by
ramming, watering, etc & disposing of
surplus excavated soil as directed within
uplead
a to 1.50 m depth
of 50m.
Pipes 80 mm to 300 mm diameter 2.10.1.2 metre 150.00 208.30 31245.00
Total 421980.35
ANALYSIS OF RATES
Carted
225.50
2 Cost of excavation 253 82.00
3 Cost of Earth L.S. 35.00
4 Cost of royality 14.00
SAY RS. 356.50 PER CUM
1 Constructing brick masonry
INSPECTION chamber 60x60x60
cm with bricks of class designation
50 in cement mortar 1:4 (1
cement : 4 coarse sand) including
CI cover with frame LIGHT
WEIGHT complete as per design. Qty. Unit Rate Amount
INSPECTION CHAMBER
Total 6400.39
Say 6400.39
ANALYSIS OF RATE FOR PAINTING OF EXISTING BITUMEN ROAD
AR-II
(ANALYSIS FOR 4.00 MT. WIDE & 10 MT. LENGTH)
MORTH DETAILS
S.NO. DESCRIPTION OF ITEM Ref. to NO. L B H QTY UNIT RATE AMOUNT
S.NO. MORTH Spec.
ABSTRACT OF COST
G. TOTAL 28970.04
(a) Cost of Brick work in fine sand in 1:4 cement & fine sand (PWD-305A) Rs. 5050.00
(b) Cost of Brick work in coarse sand in 1:4 cement & coarse sand (PWD- Rs. 5350.00
305B) Total Rs. 300.00
Rate of brick work in 1:6 Cement & fine Sand in foundation and plinth Rs. 4845.00
PWD-303
Add difference of Coarse sand & Fine Sand Rs. 300.00
Rate Per Cum 5145.00
CONSUMPTION OF MATERIALS (ADMINISTRATIVE)
ABSTRACT OF COST
(BASED ON U.P.P.W.D. S.O.R. - MATHURA w.e.f. 01/03/2013
(a) Fabrication of hold fast for door chaukhats and windows. #REF! KG 65.00 #REF!
36 Providing and fixing ball bearing for rollong (PWD-523) #REF! #REF! 750.00 #REF!
shutters. TOTAL #REF!
Say Rs. #REF! Lacs.
#REF!
#REF!
ABSTRACT OF COST
[ GODOWN 26.00 X 40.00]
#REF!
(a) Fabrication of hold fast for door chaukhats and windows. 19.20 KG 69.00 1324.80
31 Providing and fixing ball bearing for rollong (PWD-523) 4.000 NOS 304.00 1216.00
shutters.
32 Mild steel or iron work in heavy size such as
trusses, built up gates record rack, roof work,
gates etc. brought to required form including
drilling holes revitting or welding where
necessary and also including supply of steel
bolts, nuts, wastage etc and their fixing
require for proper completion of the work. (PWD 503) 10425.479 KG. 75.00 781910.96
0.00
33 Providing & Fixing TRACDEK-KLIPPON
0.65mm SMP coated galvaline steel AZ-150 (M.R.) 1114.872 SQM 1500.00 1672308.00
for roofing.
34 Painting two coat over priming coat (but
including cost of priming coat) on steel and
other metal surfaces up to 10 cm. width or
girth or small articles not exceeding 0.10sqm
in area white superior synthetic enamel such
as LUXOL3,Hi-gloss apcolite superlac,
DULUX specified brushing to give an even
shade and including cleaning the surface of
all dirt,dust and other foreign matter sand
papering and stoping including cost of all
materials, labour tools and plants etc.
required for proper completion of the work. (PWD-641+642)2249.600 SQM 87.00 195715.20
TOTA #REF!
DETAILS OF MEASUREMENT
[ GODOWN 26.00 X 40.00]
Page 28
INCLINED BEAM (SIDES) 4 12.000 0.300 0.450 6.480
TOTAL 48.787 CUM
8 R.C.C.work in raft foundation
F1 20 2.400 2.000 0.230 22.080
20*0.45/6*(2.4*2.0+0.40*0.70+4*1.40*1.35) 18.960
20 0.400 0.700 0.150 0.840
TOTAL 41.880 CUM
9 R.C.C.work in Column
C1 18 0.300 0.600 7.320 23.717
C1 2 0.300 0.600 11.520 4.147
TOTAL 27.864 CUM
10 B/W In foundation
UNDER PLATFORM 1 40.000 0.230 0.450 4.140
1 40.000 0.345 1.650 22.770
1 40.000 0.460 0.150 2.760
1 40.000 0.575 0.150 3.450
Page 29
2 26.000 0.150 7.800
2 40.000 0.150 12.000
TOTAL 39.327 SQM
16 15mm cement plaster (Interior surface)
GODOWN 2 25.550 5.000 255.500
2 39.540 5.000 395.400
INCLINED WALL 2 12.000 4.200 100.800
TOTAL 751.70 SQM
DEDUCTION
R.S. 2 2.500 2.550 12.750
FG 16 1.800 0.450 12.960
TOTAL 25.71 SQM
NET TOTAL 725.99 SQM
17 12 mm Thick plaster (outer side)
2 26.000 5.600 291.200
2 40.000 5.600 448.000
INCLINED WALL 2 12.000 4.200 100.800
TOTAL 840.000 SQM
18 25mm thick C.C. flooring .
APRON 2 40.750 0.750 61.125
2 26.750 0.750 40.125
TOTAL 101.250 SQM
19 Kota Stone Flooring .
GODOWN 1 25.550 39.540 1010.247
OPEN PLATFORM 1 40.000 1.500 60.000
ENTRANCE STEPS 2 1.800 0.900 3.240
TOTAL 1073.487 SQM
20 Kota Stone Skirting
GODOWN 1 130.180 0.150 19.527
OPEN PLATFORM 8 1.800 0.150 2.160
TOTAL 21.687 SQM
21 M.S.Work in D/W
(a) Hold fast
FG 16 2.000 0.600 19.200
TOTAL 19.200 KG
(b) M.S.Grill & Railing
FG. 16 1.800 0.450 20.000 259.200
TOTAL 259.200 KG.
(c) Z-Section Windows
FG. 16 1.800 0.450 20.000 259.200
TOTAL 259.200 KG.
22 Fixing D/W/V Chaukhats.
Fixed Glass Chaukhats 16.000 NOS
23 Glass panes
FG. 16 1.800 0.450 12.960
TOTAL 12.960 SQM
26 Steel painting
RS 2 2.500 2.550 2.000 25.500
FG. 16 1.800 0.450 3.000 38.880
TOTAL 64.380 SQM
Page 30
28 Rolling Shutter
R/S 2 2.500 2.550 12.750 SQM
34 Painting of Truss
RAFTER ISA 80X80X6 14 11.700 2.000 327.600
TIE - #2 7 24.000 2.000 336.000
WEB ISA 50X50X6 7 4.200 2.000 58.800
WEB ISA 75X75X6 14 6.000 2.000 168.000
WEB ISA 50X50X6 14 1.200 2.000 33.600
WEB ISA 65X65X6 14 3.000 2.000 84.000
WEB ISA 65X65X6 14 3.000 2.000 84.000
WEB ISA 65X65X6 14 3.000 2.000 84.000
WEB ISA 50X50X6 14 1.200 2.000 33.600
PURLIN ISMC 125 10 40.000 2.000 800.000
TIE RUNNER - #5 3 40.000 2.000 240.000
TOTAL 2249.600 SQM
Page 31
#REF!
#REF!
ABSTRACT OF COST
[ OPEN PLATFORM 15.00 X 42.00]
#REF!
TOTA #REF!
Say Rs. #REF! Lacs.
#REF!
#REF!
DETAILS OF MEASUREMENT
[ OPEN PLATFORM 15.00 X 42.00]
Page 35
1 15.000 42.000 630.000
STEPS 6 1.500 0.900 8.100
TOTAL 638.100 SQM
12 Kota Stone Skirting
STEPS 18 1.800 0.150 4.860
TOTAL 4.860 SQM
Page 36
#REF!
#REF!
ABSTRACT OF COST
[ 10 NOS. C-TYPE SHOPS]
[VEGETABLE AND FRUIT MARKET]
#REF!
(a) Fabrication of hold fast for door chaukhats and windows. 12.00 KG 69.00 828.00
35 Providing and fixing ball bearing for rollong (PWD-523) 20.000 #REF! 304.00 6080.00
shutters.
COST OF 10 NO SHOPS #REF!
COST OF 1 NO SHOP #REF!
HENCE COST OF 84 NO SHOP #REF!
DETAILS OF MEASUREMENT
[ 10 NOS. C-TYPE SHOPS]
[VEGETABLE AND FRUIT MARKET]
Page 42
B3 1 29.230 0.230 0.750 5.042
10 2.895 0.115 0.115 0.383
B4 2 9.030 0.230 0.450 1.869
Page 43
2 4.115 0.575 0.150 0.710
TOTAL 33.559 CUM
11 25mm thick D.P.C.
SHOPS 2 30.730 0.230 14.136
6 5.560 0.230 7.673
5 6.000 0.230 6.900
TOTAL 28.709 SQM
DEDUCTION (-)
R.S. 10 2.500 0.230 5.750
TOTAL 5.750 SQM
TOTAL 22.959 SQM
12 Bitumen Painting on D.P.C.
TOTAL 22.959 SQM
13 B/W In Superstructure (230 mm thick) 0.000
SHOPS 2 30.730 0.230 2.575 36.400
6 5.560 0.230 2.875 22.059
5 6.000 0.230 2.875 19.838
PARAPET 2 32.530 0.230 0.450 6.734
2 9.770 0.230 0.450 2.022
OFFSET 20 2.700 0.115 0.115 0.714
TOTAL 87.767 CUM
DEDUCTION (-)
R.S. 10 2.500 0.230 2.700 15.525
V1 10 0.900 0.230 0.450 0.932
TOTAL 16.457 CUM
NET TOTAL 71.310 CUM
14 M. S. work in R.C.C.
qty same as item no (6)*1.0*0.785 (Slab) 70.109
qty same as item no (7)*2.5.0*0.785 (Beam) 101.748
qty same as item no (8)*1.5*0.785 (Raft) 26.656
qty same as item no (9)*3.0*0.785 (Column) 37.727
TOTAL 236.240 QTL
15 15mm thick plinth plaster in 1:4
Below Plinth (Inside)
SHOPS 10 18.000 0.150 27.000
COVERED VERANDAH 2 32.530 0.150 9.759
2 4.000 0.150 1.200
Page 44
TOTAL 412.571 SQM
18 Ceiling Plaster .
SHOPS 10 3.000 6.000 180.000
COVERED VERANDAH 1 32.530 3.885 126.379
SLAB PROJECTION 2 34.030 0.750 51.045
2 10.230 0.750 15.345
CHAZZA 10 1.130 0.600 6.780
TOTAL 379.549 SQM
19 Making grooves .
SHOPS 10 18.000 180.000
COVERED VERANDAH 1 73.060 73.060
TOTAL 253.060 RM
20 25mm thick C.C. flooring .
APRON 2 34.030 0.750 51.045
2 14.460 0.750 21.690
TOTAL 72.735 SQM
25 Glass panes
V1 10 0.900 0.450 4.050
TOTAL 4.050 SQM
28 C.C. 1:2:4
HOLD FAST 20 0.150 0.100 0.100 0.030
PARAPET 2 32.530 0.380 0.150 3.708
2 9.770 0.380 0.150 1.114
TOTAL 4.852 CUM
29 Steel painting
Grills 0.000
V1 10 0.900 0.450 2.000 8.100
Z-SECTION 0.000
V1 10 0.900 0.450 2.000 8.100
Page 45
TOTAL 16.200 SQM
32 Rolling Shutter
R/S 10 2.500 2.700 67.500 SQM
Page 46
#REF!
#REF!
ABSTRACT OF COST
[ GODOWN 25.00 X 60.00]
#REF!
(a) Fabrication of hold fast for door chaukhats and windows. 24.00 KG 69.00 1656.00
31 Providing and fixing ball bearing for rollong (PWD-523) 8.000 NOS 304.00 2432.00
shutters.
32 Mild steel or iron work in heavy size such as
trusses, built up gates record rack, roof work,
gates etc. brought to required form including
drilling holes revitting or welding where
necessary and also including supply of steel
bolts, nuts, wastage etc and their fixing require
for proper completion of the work. (PWD 503) 15696.149 KG. 75.00 1177211.21
0.00
33 Providing & Fixing TRACDEK-KLIPPON
0.65mm SMP coated galvaline steel AZ-150 (M.R.) 1521.432 SQM 1500.00 2282148.00
for roofing.
34 Painting two coat over priming coat (but
including cost of priming coat) on steel and
other metal surfaces up to 10 cm. width or girth
or small articles not exceeding 0.10sqm in area
white superior synthetic enamel such as
LUXOL3,Hi-gloss apcolite superlac, DULUX
specified brushing to give an even shade and
including cleaning the surface of all dirt,dust
and other foreign matter sand papering and
stoping including cost of all materials, labour
tools and plants etc. required for proper(PWD-641+642)3438.800 SQM 87.00 299175.60
completion of the work.
TOTA #REF!
DETAILS OF MEASUREMENT
[ GODOWN 25.00 X 60.00]
Page 51
INCLINED BEAM (SIDES) 4 12.000 0.300 0.450 6.480
TOTAL 60.856 CUM
8 R.C.C.work in raft foundation
F1 28 2.400 2.000 0.230 30.912
28*0.45/6*(2.4*2.0+0.40*0.70+4*1.40*1.35) 26.544
28 0.400 0.700 0.150 1.176
TOTAL 58.632 CUM
9 R.C.C.work in Column
C1 26 0.300 0.600 7.320 34.258
C1 2 0.300 0.600 11.520 4.147
TOTAL 38.405 CUM
10 B/W In foundation
UNDER PLATFORM 1 60.000 0.230 0.450 6.210
1 60.000 0.345 1.650 34.155
1 60.000 0.460 0.150 4.140
1 60.000 0.575 0.150 5.175
Page 52
2 25.000 0.150 7.500
2 60.000 0.150 18.000
TOTAL 50.724 SQM
16 15mm cement plaster (Interior surface)
GODOWN 2 24.540 5.000 245.400
2 59.540 5.000 595.400
INCLINED WALL 2 12.000 4.200 100.800
TOTAL 941.60 SQM
DEDUCTION
R.S. 4 2.500 2.550 25.500
FG 20 1.800 0.450 16.200
TOTAL 41.70 SQM
NET TOTAL 899.90 SQM
17 12 mm Thick plaster (outer side)
2 25.000 5.600 280.000
2 60.000 5.600 672.000
INCLINED WALL 2 12.000 4.200 100.800
TOTAL 1052.800 SQM
18 25mm thick C.C. flooring .
APRON 2 60.750 0.750 91.125
2 25.750 0.750 38.625
TOTAL 129.750 SQM
19 Kota Stone Flooring .
GODOWN 1 24.540 59.540 1461.112
OPEN PLATFORM 1 60.000 1.500 90.000
ENTRANCE STEPS 4 1.800 0.900 6.480
TOTAL 1557.592 SQM
20 Kota Stone Skirting
GODOWN 1 168.160 0.150 25.224
OPEN PLATFORM 16 1.800 0.150 4.320
TOTAL 29.544 SQM
21 M.S.Work in D/W
(a) Hold fast
FG 20 2.000 0.600 24.000
TOTAL 24.000 KG
(b) M.S.Grill & Railing
FG. 20 1.800 0.450 20.000 324.000
TOTAL 324.000 KG.
(c) Z-Section Windows
FG. 20 1.800 0.450 20.000 324.000
TOTAL 324.000 KG.
22 Fixing D/W/V Chaukhats.
Fixed Glass Chaukhats 20.000 NOS
23 Glass panes
FG. 20 1.800 0.450 16.200
TOTAL 16.200 SQM
26 Steel painting
RS 4 2.500 2.550 2.000 51.000
FG. 20 1.800 0.450 3.000 48.600
TOTAL 99.600 SQM
Page 53
28 Rolling Shutter
R/S 4 2.500 2.550 25.500 SQM
34 Painting of Truss
RAFTER ISA 80X80X6 22 10.700 2.000 470.800
TIE - #2 11 25.000 2.000 550.000
WEB ISA 50X50X6 11 4.200 2.000 92.400
WEB ISA 75X75X6 22 6.000 2.000 264.000
WEB ISA 50X50X6 22 1.200 2.000 52.800
WEB ISA 65X65X6 22 3.000 2.000 132.000
WEB ISA 65X65X6 22 3.000 2.000 132.000
WEB ISA 65X65X6 22 3.000 2.000 132.000
WEB ISA 50X50X6 22 1.200 2.000 52.800
PURLIN ISMC 125 10 60.000 2.000 1200.000
TIE RUNNER - #5 3 60.000 2.000 360.000
TOTAL 3438.800 SQM
Page 54
#REF!
#REF!
#REF!
(b) Providing & fixing of door / windows grill. 43.200 KG #REF! #REF!
Page 60
NET TOTAL 11.072 CUM
9 B/W in super-structure(115 thick)
PARAPET 2 3.960 0.115 0.900 0.820
2 3.000 0.115 0.900 0.621
2 3.960 0.075 0.150 0.089
2 3.000 0.075 0.075 0.034
1 2.985 0.115 0.350 0.120
1 2.990 0.075 0.150 0.034
1 2.990 0.075 0.075 0.017
1 3.945 0.115 0.350 0.159
1 3.945 0.075 0.150 0.044
1 3.945 0.075 0.075 0.022
TOTAL 1.960 CUM
10 D.P.C.
PLINTH BAND 2 3.960 0.230 1.822
2 3.000 0.230 1.380
TOTAL 3.202 SQM
24 Snowcem painting
SAME AS ITEM NO. (16) TOTAL 95.813 SQM
26 Glass panes
W 2 0.900 1.200 2.160
TOTAL 2.160 SQM
27 Glass strips
SAME AS ITEM NO. (20)*6 TOTAL 70.884 RM
Page 62
#REF!
#REF!
5 Anti-termite treatment
PL. AREA+APRON AREA TOTAL 68.400 SQM
6 R.C.C.work in Lintel
PLINTH BAND
BATH 2 1.430 0.230 0.150 0.099
2 0.635 0.230 0.150 0.044
W.C. 2 1.360 0.230 0.150 0.094
2 1.200 0.230 0.150 0.083
KITCHEN 2 0.585 0.230 0.150 0.040
2 1.830 0.230 0.150 0.126
2 2.400 0.230 0.150 0.166
DRG. ROOM 2 3.525 0.230 0.150 0.243
2 4.710 0.230 0.150 0.325
2 3.465 0.230 0.150 0.239
BED ROOM 2 2.930 0.230 0.150 0.202
1 3.310 0.230 0.150 0.114
BATH 2 1.200 0.230 0.150 0.083
2 1.430 0.230 0.150 0.099
2 0.750 0.230 0.150 0.052
2 1.430 0.230 0.150 0.099
W.C. 2 1.015 0.230 0.150 0.070
2 1.200 0.230 0.150 0.083
LINTAL BAND 0.000
BATH 2 1.430 0.230 0.150 0.099
2 0.635 0.230 0.150 0.044
W.C. 2 1.360 0.230 0.150 0.094
2 1.200 0.230 0.150 0.083
KITCHEN 2 0.585 0.230 0.150 0.040
2 1.830 0.230 0.150 0.126
2 2.400 0.230 0.150 0.166
DRG. ROOM 2 3.525 0.230 0.150 0.243
2 4.710 0.230 0.150 0.325
2 3.465 0.230 0.150 0.239
BED ROOM 2 2.930 0.230 0.150 0.202
1 3.310 0.230 0.150 0.114
BATH 2 1.200 0.115 0.150 0.041
2 1.430 0.115 0.150 0.049
2 0.750 0.115 0.150 0.026
2 1.430 0.115 0.150 0.049
W.C. 2 1.015 0.115 0.150 0.035
2 1.200 0.115 0.150 0.041
TOTAL 4.277 CUM
10 D.P.C.
BATH 2 1.430 0.254 0.726
2 0.635 0.254 0.323
W.C. 2 1.360 0.254 0.691
2 1.200 0.254 0.610
KITCHEN 2 0.585 0.254 0.297
2 1.830 0.254 0.930
2 2.400 0.254 1.219
DRG. ROOM 2 3.525 0.254 1.791
2 4.710 0.254 2.393
2 3.465 0.254 1.760
BED ROOM 2 2.930 0.254 1.488
1 3.310 0.254 0.841
BATH 2 1.200 0.139 0.334
2 1.430 0.139 0.398
2 0.750 0.139 0.209
2 1.430 0.139 0.398
W.C. 2 1.015 0.139 0.282
2 1.200 0.139 0.334
TOTAL 15.021 SQM
DEDUCT 0.000
D1 4 1.000 0.254 1.016
D2 4 0.900 0.254 0.914
D3 4 0.750 0.139 0.417
TOTAL 2.347 SQM
NET TOTAL 12.674 SQM
12 B/W in super-structure
BATH 2 1.430 0.230 2.880 1.894
2 0.635 0.230 2.880 0.841
W.C. 2 1.360 0.230 2.880 1.802
2 1.200 0.230 2.880 1.590
KITCHEN 2 0.585 0.230 2.880 0.775
2 1.830 0.230 2.880 2.424
2 2.400 0.230 2.880 3.180
DRG. ROOM 2 3.525 0.230 2.880 4.670
2 4.710 0.230 2.880 6.240
2 3.465 0.230 2.880 4.590
BED ROOM 2 2.930 0.230 2.880 3.882
1 3.310 0.230 2.880 2.193
PARAPET WALL 1 36.880 0.230 0.500 4.241
TOTAL 38.322 CUM
DEDUCT
D1 4 1.000 0.230 2.100 1.932
D2 2 0.900 0.230 2.100 0.869
W1 2 1.800 0.230 1.200 0.994
W2 2 1.500 0.230 1.200 0.828
W3 2 0.900 0.230 1.050 0.435
V 4 0.600 0.230 0.600 0.331
TOTAL 5.389 CUM
NET TOTAL 32.933 CUM
13 B/W in super-structure(115 thick)
BATH 2 1.200 0.115 2.880 0.795
2 1.430 0.115 2.880 0.947
2 0.750 0.115 2.880 0.497
2 1.430 0.115 2.880 0.947
W.C. 2 1.015 0.115 2.880 0.672
2 1.200 0.115 2.880 0.795
TOTAL 4.653 CUM
DEDUCTION
D2 2 0.900 0.115 2.100 0.435
D3 4 0.750 0.115 2.100 0.725
TOTAL 1.159 CUM
NET TOTAL 3.494 CUM
21 15 mm plinth plaster
OUTER 2 4.244 0.150 1.273
2 10.900 0.150 3.270
2 3.385 0.150 1.016
INNER
BATH 2 4.800 0.150 1.440
W.C. 2 4.200 0.150 1.260
2 3.460 0.150 1.038
KITCHEN 2 8.000 0.150 2.400
BED ROOM 2 11.560 0.150 3.468
2 0.900 0.150 0.270
2 4.200 0.150 1.260
DRG. ROOM 2 11.350 0.150 3.405
2 0.970 0.150 0.291
LOBBY 1 9.630 0.150 1.445
TOTAL 21.835 SQM
22 12 mm cement plaster G.F. (Outer face)
OUTER 2 12.380 3.600 89.136
2 7.005 3.600 50.436
2 0.485 3.600 3.492
PARAPET WALL 1 36.880 1.530 56.426
TOTAL 199.490 SQM
23 15 mm cement plaster G.F. (Inner face)
BATH 2 4.800 3.030 29.088
W.C. 2 4.200 3.030 25.452
2 3.460 3.030 20.968
KITCHEN 2 8.000 3.030 48.480
BED ROOM 2 11.560 3.030 70.054
2 0.900 3.030 5.454
2 4.200 3.030 25.452
DRG. ROOM 2 11.350 3.030 68.781
2 0.970 3.030 5.878
LOBBY 1 9.630 3.030 29.179
TOTAL 328.785 SQM
DEDUCT
D1 4 1.000 2.100 8.400
D2 4 0.900 2.100 7.560
D3 4 0.750 2.100 6.300
W1 2 1.800 1.200 4.320
W2 2 1.500 1.200 3.600
W3 2 0.900 1.050 1.890
V 4 0.600 0.600 1.440
TOTAL 33.510 SQM
NET TOTAL 295.275 SQM
33 Glass panes
W1 2 1.800 1.200 4.320
W2 2 1.500 1.800 5.400
W3 2 0.900 1.200 2.160
V 4 0.600 0.700 1.680
TOTAL 13.560 SQM
37 Glass Strip
SAME AS ITEM NO. (27)*6 TOTAL 455.479 RM
#REF!
#REF!
Page 78
14 Brick koba treatment on roofs. 135.18 SQM #REF! #REF!
Page 79
measured upto floor two level. (PWD- 504) 23.39 QTL. #REF! #REF!
Page 80
exceeding 0.10sqm in area white superior 0.00
synthetic enamel such as LUXOL3,Hi-gloss 0.00
apcolite superlac, DULUX specified 0.00
brushing to give an even shade and 0.00
including cleaning the surface of all 0.00
dirt,dust and other foreign matter sand 0.00
papering and stoping including cost of 0.00
all materials, labour tools and plants 0.00
etc. required for proper completion of
the work. 59.71 SQM #REF! #REF!
Page 81
37 Providing and laying water proofing treatment in
sunken portion of WCs, bathroom etc., by applying
cement slurry mixed with water proofing cement
compound consisting of applying : a) First layer of
slurry of cement @ 0.488 kg/sqm mixed with water
proofing cement compound @ 0.253 kg/sqm. This
layer will be allowed to air cure for 4 hours. b) Second
layer of slurry of cement @ 0.242 kg/sqm mixed with
water proofing cement compound @ 0.126 kg/sqm.
This layer will be allowed to air cure for 4 hours
followed with water curing for 48 hours. The rate
includes preparation of surface, treatment and sealing
of all joints, corners, junctions of pipes and masonry
with polymer mixed slurry. (DSR-22.5)
G. TOTAL #REF!
Page 82
#REF!
#REF!
0.00
ABSTRACT OF COST (2 NOS. TYPE -II RESIDENCES)
2 Filling of sand
UNDER FLOOR 0.000
DRAWING ROOM 2 3.450 3.500 0.150 3.623
VERANDAH 2 1.230 1.270 0.150 0.469
BED ROOM 2 3.000 3.500 0.150 3.150
2 0.600 0.935 0.150 0.168
DINNING HALL 2 2.710 3.300 0.150 2.683
BATH 2 1.200 1.500 0.150 0.540
WASH AREA 2 0.750 1.380 0.150 0.311
W.C. 2 1.220 0.900 0.150 0.329
2 2.710 1.000 0.150 0.813
CORRIDOR 2 3.175 1.000 0.150 0.953
STAIR LOBBY 1 3.474 1.735 0.150 0.904
TOTAL 13.942 CUM
Page 85
9 B/W In foundation.
1-1 SECTION 2 1.450 0.230 0.775 0.517
2 1.450 0.345 0.630 0.630
2 1.450 0.460 0.075 0.100
2 1.450 0.575 0.150 0.250
4 1.015 0.230 0.775 0.724
4 1.015 0.345 0.630 0.882
4 1.015 0.460 0.075 0.140
4 1.015 0.575 0.150 0.350
2 0.845 0.230 0.775 0.301
2 0.845 0.345 0.630 0.367
2 0.845 0.460 0.075 0.058
2 0.845 0.575 0.150 0.146
2 1.050 0.230 0.775 0.374
2 1.050 0.345 0.630 0.456
2 1.050 0.460 0.075 0.072
2 1.050 0.575 0.150 0.181
12 D.P.C.
DRAWING/ STAIR 2 3.225 0.230 1.484
DRAWING/ LOBBY 2 1.039 0.230 0.478
2 3.175 0.230 1.461
BED / DRAWING ROOM 2 3.730 0.230 1.716
DRAWING 2 3.450 0.230 1.587
4 0.600 0.230 0.552
BED ROOM 2 3.230 0.230 1.486
4 0.600 0.230 0.552
2 4.330 0.230 1.992
2 1.050 0.230 0.483
BATH 2 1.015 0.230 0.467
2 0.845 0.230 0.389
W.C 2 0.785 0.230 0.361
2 1.680 0.230 0.773
VERANDAH 2 2.940 0.230 1.352
KITCHEN 2 0.885 0.230 0.407
1 3.715 0.230 0.854
KIT/ LOBBY 1 3.945 0.230 0.907
STAIRCASE 1 2.005 0.230 0.461
FOR 115MM THICK WALL
BATH / BED ROOM 2 1.315 0.115 0.302
2 0.485 0.115 0.112
BATH/ WASH 2 1.385 0.115 0.319
WASH/ DINNING 2 2.070 0.115 0.476
W.C/ BATH 2 1.220 0.115 0.281
KIT/ DINNING 2 2.070 0.115 0.476
KITCHEN 1 2.955 0.115 0.340
TOTAL 20.066 SQM
DEDUCT
D1 6 1.000 0.230 1.380
D2 2 0.900 0.230 0.414
D2 2 0.900 0.115 0.207
D3 4 0.750 0.115 0.345
DRAWING ROOM OPENING 2 1.200 0.230 0.552
TOTAL 2.898 SQM
NET TOTAL 17.168 SQM
13 Painting on DPC
Page 88
SAME AS ITEM NO. 12 17.168 SQM
15 Flush door
D1 7 1.000 2.100 14.700
D2 4 0.900 2.100 7.560
D3 4 0.750 2.100 6.300
TOTAL 28.560 SQM
16 M.S.Work in D/W
(a) Hold fast
DOORS 15 6.000 0.600 54.000
WINDOWS 10 6.000 0.600 36.000
VENTILATORS 4 4.000 0.600 9.600
TOTAL 99.600 KG
(b) M.S.Grill & Stair Railing
W 2 1.800 1.200 20.000 86.400
W1 2 1.350 1.200 20.000 64.800
W2 2 1.200 1.050 20.000 50.400
W3 2 0.450 1.050 20.000 18.900
W4 2 1.500 1.200 20.000 72.000
V 4 0.600 0.600 20.000 28.800
STAIR RAILING 1 5.800 0.900 20.000 104.400
TOTAL 425.700 KG
c. Z-Section steel window
W 2 1.800 1.200 20.000 86.40
W1 2 1.350 1.200 20.000 64.80
W2 2 1.200 1.050 20.000 50.40
W3 2 0.450 1.050 20.000 18.90
W4 2 1.500 1.200 20.000 72.00
V 4 0.600 0.600 20.000 28.80
TOTAL 321.30 KG
d. Angle Iron door chaukhats
D1 7 5.200 3.000 109.200
D2 4 5.100 3.000 61.200
D3 4 4.950 3.000 59.400
TOTAL 229.800 KG
19 Plinth plaster
Below G.L. 2 16.285 0.150 4.886
2 8.375 0.150 2.513
4 0.600 0.150 0.360
Below plinth
DRG.ROOM 2 13.900 0.150 4.170
BED ROOM 2 13.000 0.150 3.900
2 0.600 0.150 0.180
DINNING/ LOUNG 2 7.650 0.150 2.295
BATH 2 5.400 0.150 1.620
W.C. 2 4.240 0.150 1.272
WASH 2 2.770 0.150 0.831
KITCHEN 2 9.510 0.150 2.853
PASSAGE 2 1.000 0.150 0.300
2 3.175 0.150 0.953
LOBBY 2 1.039 0.150 0.312
1 3.474 0.150 0.521
TOTAL 26.964 SQM
20 12 mm cement plaster ( outer side)
2 16.285 3.600 117.252
2 8.375 3.600 60.300
4 0.600 3.600 8.640
MUMTY 2 3.873 2.800 21.689
2 2.465 2.800 13.804
PARAPET 1 48.095 2.000 96.190
MUMTY PARAPET 2 3.873 1.130 8.753
2 2.000 1.130 4.520
TOTAL 331.148 SQM
21 12 mm cement plaster (IN SIDE)
DRG.ROOM 2 13.900 3.030 84.234
BED ROOM 2 13.000 3.030 78.780
2 0.600 3.030 3.636
DINNING/ LOUNG 2 7.650 3.030 46.359
BATH 2 5.400 1.530 16.524
W.C. 2 4.240 1.530 12.974
WASH 2 2.770 3.030 16.786
KITCHEN 2 9.510 3.030 57.631
PASSAGE 2 1.000 3.030 6.060
2 3.175 3.030 19.241
LOBBY 2 1.039 3.030 6.296
1 3.474 3.030 10.526
MUMTY 1 11.066 2.680 29.657
TOTAL 388.704 SQM
DEDUCT
D1 7 1.000 2.100 14.700
D2 2 0.900 2.100 3.780
D3 4 0.750 2.100 6.300
W 2 1.800 1.200 4.320
W1 2 1.350 1.200 3.240
W2 2 1.200 1.050 2.520
W3 2 0.450 1.050 0.945
W4 2 1.500 1.200 3.600
V 4 0.600 0.600 1.440
TOTAL 40.845 SQM
NET TOTAL 347.859 SQM
22 Ceiling plaster
DRG.ROOM 2 3.450 3.500 24.150
Page 90
BED ROOM 2 3.000 3.500 21.000
2 0.600 0.935 1.122
DINNING/ LOUNGE 2 3.300 2.710 17.886
BATH 2 1.200 1.500 3.600
W.C. 2 1.220 0.900 2.196
WASH 2 1.385 0.750 2.078
KITCHEN 2 1.800 2.955 10.638
LOBBY 1 3.474 1.735 6.027
STAIRCASE 1 3.225 2.005 6.466
1 2.465 0.990 2.440
PROJECTION 2 2.735 0.600 3.282
VERANDAH 2 1.520 1.830 5.563
2 2.835 1.125 6.379
MUMTY 1 4.215 2.465 10.390
CHAZZA
W2 2 1.430 0.600 1.716
W4 2 1.500 0.600 1.800
V 4 0.600 0.715 1.716
D1 1 1.460 0.600 0.876
TOTAL 129.325 SQM
23 Making grooves.
DRG.ROOM 2 13.900 27.800
BED ROOM 2 13.000 26.000
2 0.600 1.200
DINNING/ LOUNG 2 7.650 15.300
BATH 2 5.400 10.800
W.C. 2 4.240 8.480
WASH 2 2.770 5.540
KITCHEN 2 9.510 19.020
PASSAGE 2 1.000 2.000
2 3.175 6.350
LOBBY 2 1.039 2.078
1 3.474 3.474
MUMTY 1 11.066 11.066
TOTAL 139.108 RM
24 Ceremic tiles flooring & dado
FLOOR TILES
W.C 2 1.220 0.900 2.196
BATH 2 1.200 1.500 3.600
KIT 2 1.800 2.955 10.638
WALL TILES
W.C 2 4.240 1.500 12.720
BATH 2 5.400 1.500 16.200
KIT 2 9.590 0.150 2.877
2 3.555 0.600 4.266
TOTAL 52.497 SQM
25 40 mm thk cement conc. Flooring
DRAWING ROOM 2 3.450 3.500 24.150
VERANDAH 2 1.230 1.270 3.124
2 2.835 1.125 6.379
BED ROOM 2 3.000 3.500 21.000
2 0.600 0.935 1.122
DINNING HALL 2 2.710 2.230 12.087
BATH 2 1.200 1.500 3.600
WASH AREA 2 0.750 1.380 2.070
W.C. 2 1.220 0.900 2.196
CORRIDOR 2 3.175 1.000 6.350
STAIR LOBBY 1 3.474 1.735 6.027
STAIRCASE STEP 16 0.978 0.250 3.912
LANDING 1 2.235 1.215 2.716
APRON 2 18.085 0.900 32.553
2 8.975 0.900 16.155
TOTAL 143.440 SQM
Page 91
26 C.C. Skirting up to two floor level.
DRG.ROOM 2 13.900 0.150 4.170
BED ROOM 2 13.000 0.150 3.900
2 0.600 0.150 0.180
DINNING/ LOUNG 2 7.650 0.150 2.295
BATH 2 5.400 0.150 1.620
W.C. 2 4.240 0.150 1.272
WASH 2 2.770 0.150 0.831
KITCHEN 2 9.510 0.150 2.853
PASSAGE 2 1.000 0.150 0.300
2 3.175 0.150 0.953
LOBBY 2 1.039 0.150 0.312
1 3.474 0.150 0.521
STAIR CASE STEP 18 0.978 0.175 3.081
TOTAL 22.287 SQM
27 Steel painting
D1 7 1.000 2.100 0.600 8.820
D2 4 0.900 2.100 0.600 4.536
D3 4 0.750 2.100 0.600 3.780
W 2 1.800 1.200 2.000 8.640
W1 2 1.350 1.200 2.000 6.480
W1 2 1.200 1.050 2.000 5.040
W3 2 0.450 1.050 2.000 1.890
W4 2 1.500 1.200 2.000 7.200
V 4 0.600 0.600 2.000 2.880
STAIR RAILING 1 5.800 0.900 2.000 10.440
TOTAL 59.706 SQM
28 Painting on wood.
SAME AS ITEM NO. 16*2 57.120 SQM
29 Snowcem painting
SAME AS ITEM NO.(20) 331.148 SQM
31 Glass panes
W 2 1.800 1.200 4.320
W1 2 1.350 1.200 3.240
W2 2 1.200 1.050 2.520
W3 2 0.450 1.050 0.945
W4 2 1.500 1.200 3.600
V 4 0.600 0.600 1.440
TOTAL 16.065 SQM
32 Glass strips
SAME AS ITEM NO. (25)*6 860.643 RM
36 Cinder filling
BATH 2 1.200 1.500 0.450 1.620
W.C. 2 1.220 0.900 0.450 0.988
2 1.385 0.750 0.450 0.935
TOTAL 3.543 CUM
37 Water proofing
KIT 2 2.955 1.800 10.638
2 9.510 0.150 2.853
BATH 2 1.200 1.500 3.600
Page 92
2 5.400 0.450 4.860
W.C 2 1.220 0.900 2.196
2 4.240 0.450 3.816
2 4.270 0.450 3.843
2 1.385 0.750 2.078
TOTAL 33.884 SQM
Page 93
#REF!
#REF!
16a Providing & fixing 30mm thick wire gauge shutters using
galvanised M.S. wire gauge of average width of aperture 1.4mm
with wire of dia 0.63mm for doors, windows and clerestory
windows including ISI marked bright finished or/and black
enamelled M.S. butt hinges with necessary screws. Second class
teak wood. (DSR-9.30.1)
Page 101
1 2.152 0.850 0.150 0.274
1 3.220 0.850 0.150 0.411
1 2.723 0.850 0.150 0.347
1 2.535 0.850 0.150 0.323
1 3.270 0.850 0.150 0.417
1 5.590 0.850 0.150 0.713
1 3.455 0.850 0.150 0.441
3 0.600 0.850 0.150 0.230
Page 102
1 3.500 0.230 0.150 0.121
1 1.155 0.230 0.150 0.040
1 0.850 0.230 0.150 0.029
1 0.600 0.230 0.150 0.021
TOILET 2 1.695 0.230 0.150 0.117
1 2.200 0.230 0.150 0.076
LOUNGE 1 2.515 0.230 0.150 0.087
1 4.685 0.230 0.150 0.162
KITCHEN 1 2.000 0.230 0.150 0.069
1 3.380 0.230 0.150 0.117
1 2.348 0.230 0.150 0.081
STORE 1 2.345 0.230 0.150 0.081
TOILET 2 2.365 0.230 0.150 0.163
1 1.350 0.230 0.150 0.047
TOILET 1 2.200 0.230 0.150 0.076
STORE 1 0.880 0.230 0.150 0.030
1 0.600 0.230 0.150 0.021
LINTEL BAND 0.000
DRAWING ROOM 2 5.290 0.230 0.150 0.365
2 3.225 0.230 0.150 0.223
BED ROOM / TOILET 1 4.695 0.230 0.150 0.162
BED ROOM 1 3.965 0.230 0.150 0.137
1 0.600 0.230 0.150 0.021
BED ROOM 1 4.560 0.230 0.150 0.157
1 3.500 0.230 0.150 0.121
1 1.155 0.230 0.150 0.040
1 0.850 0.230 0.150 0.029
1 0.600 0.230 0.150 0.021
TOILET 2 1.695 0.230 0.150 0.117
1 2.200 0.230 0.150 0.076
LOUNGE 1 2.515 0.230 0.150 0.087
1 4.685 0.230 0.150 0.162
KITCHEN 1 2.000 0.230 0.150 0.069
1 3.380 0.230 0.150 0.117
1 4.695 0.230 0.150 0.162
STORE 1 4.690 0.230 0.150 0.162
TOILET 2 2.365 0.115 0.150 0.082
1 1.350 0.115 0.150 0.023
TOILET 1 2.200 0.115 0.150 0.038
STORE 1 0.880 0.115 0.150 0.015
1 0.600 0.115 0.150 0.010
TOTAL 4.794 CUM
Page 103
V1 1 1.060 0.450 0.100 0.048
W3 1 2.115 0.600 0.100 0.127
TOTAL 12.370 CUM
8. R.C.C.work in beams
B1 2 2.595 0.155 0.300 0.241
B2 1 2.890 0.230 0.300 0.199
TOTAL 0.441 CUM
9. B/W In foundation.
1-1 SECTION 1 2.430 0.230 1.125 0.629
1 2.430 0.345 1.650 1.383
1 2.430 0.460 0.075 0.084
1 2.430 0.575 0.150 0.210
Page 104
1 2.955 0.230 1.050 0.714
1 2.955 0.345 1.575 1.606
1 2.955 0.460 0.150 0.204
1 2.955 0.575 0.075 0.127
1 2.955 0.690 0.150 0.306
1 0.723 0.230 1.050 0.175
1 0.723 0.345 1.575 0.393
1 0.723 0.460 0.150 0.050
1 0.723 0.575 0.075 0.031
1 0.723 0.690 0.150 0.075
1 2.152 0.230 1.050 0.520
1 2.152 0.345 1.575 1.169
1 2.152 0.460 0.150 0.148
1 2.152 0.575 0.075 0.093
1 2.152 0.690 0.150 0.223
1 3.220 0.230 1.050 0.778
1 3.220 0.345 1.575 1.750
1 3.220 0.460 0.150 0.222
1 3.220 0.575 0.075 0.139
1 3.220 0.690 0.150 0.333
1 2.723 0.230 1.050 0.658
1 2.723 0.345 1.575 1.480
1 2.723 0.460 0.150 0.188
1 2.723 0.575 0.075 0.117
1 2.723 0.690 0.150 0.282
1 2.535 0.230 1.050 0.612
1 2.535 0.345 1.575 1.377
1 2.535 0.460 0.150 0.175
1 2.535 0.575 0.075 0.109
1 2.535 0.690 0.150 0.262
1 1.635 0.230 1.050 0.395
1 1.635 0.345 1.575 0.888
1 1.635 0.460 0.150 0.113
1 1.635 0.575 0.075 0.071
1 1.635 0.690 0.150 0.169
1 5.590 0.230 1.050 1.350
1 5.590 0.345 1.575 3.037
1 5.590 0.460 0.150 0.386
1 5.590 0.575 0.075 0.241
1 5.590 0.690 0.150 0.579
1 3.455 0.230 1.050 0.834
1 3.455 0.345 1.575 1.877
1 3.455 0.460 0.150 0.238
1 3.455 0.575 0.075 0.149
1 3.455 0.690 0.150 0.358
3 0.600 0.230 1.050 0.435
3 0.600 0.345 1.575 0.978
3 0.600 0.460 0.150 0.124
3 0.600 0.575 0.075 0.078
3 0.600 0.690 0.150 0.186
Page 105
1 1.973 0.345 1.575 1.072
1 1.973 0.460 0.150 0.136
1 1.523 0.230 0.575 0.201
1 1.523 0.345 1.575 0.828
1 1.523 0.460 0.150 0.105
1 1.465 0.230 0.575 0.194
1 1.465 0.345 1.575 0.796
1 1.465 0.460 0.150 0.101
1 1.605 0.230 0.575 0.212
1 1.605 0.345 1.575 0.872
1 1.605 0.460 0.150 0.111
1 0.622 0.230 0.575 0.082
1 0.622 0.345 1.575 0.338
1 0.622 0.460 0.150 0.043
1 1.780 0.230 0.575 0.235
1 1.780 0.345 1.575 0.967
1 1.780 0.460 0.150 0.123
TOTAL 67.416 CUM
10. D.P.C
DRAWING ROOM 2 5.290 0.230 2.433
2 3.225 0.230 1.484
BED ROOM / TOILET 1 4.695 0.230 1.080
BED ROOM 1 3.965 0.230 0.912
1 0.600 0.230 0.138
BED ROOM 1 4.560 0.230 1.049
1 3.500 0.230 0.805
1 1.155 0.230 0.266
1 0.850 0.230 0.196
1 0.600 0.230 0.138
TOILET 2 1.695 0.230 0.780
1 2.200 0.230 0.506
LOUNGE 1 2.515 0.230 0.578
1 4.685 0.230 1.078
KITCHEN 1 2.000 0.230 0.460
1 3.380 0.230 0.777
1 2.348 0.230 0.540
STORE 1 2.345 0.230 0.539
OFFSET 3 0.600 0.230 0.414
TOILET 2 2.365 0.115 0.544
1 1.350 0.115 0.155
TOILET 1 2.200 0.115 0.253
STORE 1 0.880 0.115 0.101
1 0.600 0.115 0.069
3 1.200 0.115 0.414
TOTAL 15.708 SQM
DEDUCT
D1 6 0.900 0.230 1.242
D2 1 0.750 0.230 0.173
D2 2 0.750 0.115 0.173
TOTAL 1.587 SQM
NET TOTAL 14.121 SQM
11. Bitumen Painting on D.P.C.
QTY SAME AS ITEM NO. 10 14.121 SQM
TOTAL 14.121 SQM
12. B/W in super-structure
DRAWING ROOM 2 5.290 0.230 2.875 6.996
2 3.225 0.230 2.875 4.265
BED ROOM / TOILET 1 4.695 0.230 2.875 3.105
BED ROOM 1 3.965 0.230 2.875 2.622
1 0.600 0.230 2.875 0.397
BED ROOM 1 4.560 0.230 2.875 3.015
1 3.500 0.230 2.875 2.314
1 1.155 0.230 2.875 0.764
1 0.850 0.230 2.875 0.562
Page 106
1 0.600 0.230 2.875 0.397
TOILET 2 1.695 0.230 2.875 2.242
1 2.200 0.230 2.875 1.455
LOUNGE 1 2.515 0.230 2.875 1.663
1 4.685 0.230 2.875 3.098
KITCHEN 1 2.000 0.230 2.875 1.323
1 3.380 0.230 2.875 2.235
1 2.348 0.230 2.875 1.552
STORE 1 2.345 0.230 2.875 1.551
OFFSET 3 0.600 0.230 2.875 1.190
PARAPET 1 40.720 0.230 0.900 8.429
TOTAL 49.174 CUM
DEDUCTION
D1 6 0.900 0.230 2.100 2.608
D2 1 0.750 0.230 2.100 0.362
W1 2 1.500 0.230 1.200 0.828
W2 2 1.200 0.230 1.200 0.662
W3 1 1.200 0.230 1.050 0.290
V 2 0.750 0.230 0.600 0.207
TOTAL 4.958 CUM
NET TOTAL 44.216 CUM
Page 107
W3 1 1.200 1.050 1.260
V 2 0.750 0.600 0.900
TOTAL 8.640 Sqm
16a Fly mesh shutters in outer doors
D1 3 0.900 2.100 5.670
TOTAL 5.670 SQM
17. M. S. work in R.C.C.
qty same as item no (6)*1.0*0.785 (Lintel) 3.764
qty same as item no (7)*1.00*0.785 (Slab) 9.711
qty same as item no (8)*2.5*0.785 (Beam) 0.865
TOTAL 14.339 QTL
18. Fixing D/W/V Chaukhats.
Door chaukhats 9.000 NOS
Window chaukhats 5.000 NOS
Ventilator chaukhats 2.000 NOS
Page 108
KITCHEN 2 2.000 3.025 12.100
2 2.550 3.025 15.428
STORE 2 1.515 3.025 9.166
4 1.200 3.025 14.520
TOTAL 249.820 SQM
DEDUCTION
D1 6 0.900 2.100 11.340
D2 3 0.750 2.100 4.725
W1 2 1.500 1.200 3.600
W2 2 1.200 1.200 2.880
W3 1 1.200 1.050 1.260
V 2 0.750 0.600 0.900
TOTAL 24.705 SQM
NET TOTAL 225.115 SQM
21 6mm thick plaster on Ceiling in 1:3
DRAWING ROOM 1 3.255 4.230 13.769
FRONT VERANDAH 1 1.800 1.230 2.214
BED ROOM 1 3.365 3.000 10.095
1 2.985 3.500 10.448
1 1.270 0.600 0.762
1 0.600 1.290 0.774
LOUNGE 1 3.615 3.445 12.454
1 0.600 1.200 0.720
TOILET 1 2.250 1.465 3.296
1 2.200 1.350 2.970
REAR VERANDAH 1 2.515 1.150 2.892
KITCHEN 1 2.000 2.550 5.100
STORE 1 1.515 1.200 1.818
LOBBY 1 3.730 1.730 6.453
CHAZZA
W1 / V1 1 2.965 0.600 1.779
W2 1 1.385 0.600 0.831
V1 1 1.060 0.450 0.477
W3 1 2.115 0.600 1.269
TOTAL 78.120 SQM
22 Making grooves.
DRG. ROOM 2 3.225 6.450
2 4.230 8.460
BED ROOM 2 3.365 6.730
2 3.000 6.000
2 0.600 1.200
TOILET 2 2.250 4.500
2 1.465 2.930
BED ROOM 2 2.985 5.970
2 3.500 7.000
2 0.600 1.200
TOILET 2 1.350 2.700
2 2.200 4.400
LOUNGE 2 3.615 7.230
2 3.445 6.890
2 0.600 1.200
KITCHEN 2 2.000 4.000
2 2.550 5.100
STORE 2 1.515 3.030
4 1.200 4.800
TOTAL 89.790 RM
23 Ceremic tiles flooring & dado
BED ROOM TOILET 1 2.250 1.465 3.296
2 2.250 1.500 6.750
2 1.465 1.500 4.395
BED ROOM TOILET 1 2.200 1.350 2.970
2 2.200 1.500 6.600
2 1.350 1.500 4.050
KITCHEN 1 2.000 0.600 1.200
Page 109
1 2.550 0.600 1.530
TOTAL 30.791 SQM
DEDUCTION
D3 3 0.750 1.500 3.375
TOTAL 3.375 SQM.
TOTAL 27.416 SQM.
24 Kota Stone flooring
KITCHEN 1 2.000 2.550 5.100
TOTAL 5.100 SQM.
25 Kota Stone skirting
KITCHEN 1 9.100 0.150 1.365
KITCHEN PLATFORM 1 3.950 0.600 2.370
TOTAL 3.735 SQM.
26 Plain C.C. for hold fast
HOLD FAST 78 0.150 0.100 0.100 0.117
TOTAL 0.117 CUM
27 Glass panes
W1 2 1.500 1.200 3.600
W2 2 1.200 1.200 2.880
W3 1 1.200 1.050 1.260
V 2 0.750 0.600 0.900
TOTAL 8.640 SQM
28 C.C. Flooring
DRAWING ROOM 1 3.225 4.230 13.642
FRONT VERANDAH 1 2.550 1.230 3.137
BED ROOM 1 3.365 3.000 10.095
1 0.600 1.270 0.762
LOUNGE 1 3.615 3.445 12.454
1 0.600 1.200 0.720
STORE 1 1.515 1.200 1.818
STAIRCASE LOBBY/STAIRCASE 1 2.200 5.290 11.638
LOBBY 1 2.700 1.130 3.051
REAR VERANDAH 1 2.515 1.150 2.892
APRON 2 10.620 0.900 19.116
2 11.500 0.900 20.700
TOTAL 100.024 SQM
29 C.C. Skirting
DRAWING ROOM 1 14.910 0.150 2.237
FRONT VERANDAH 1 4.830 0.150 0.725
BED ROOM 1 12.730 0.150 1.910
LOUNGE 1 14.120 0.150 2.118
STORE 1 5.430 0.150 0.815
LOBBY 1 2.700 0.150 0.405
5 1.130 0.150 0.848
REAR VERANDAH 1 4.815 0.150 0.722
5 2.630 0.150 1.973
TOTAL 11.750 SQM
30 Glass strips 0.000
Qty same as Item No. 28 x 6) TOTAL 600.145 RM
31 Steel painting
M.S.Grill & Stair Railing /Z-Section windows
W1 2 1.500 1.200 3.000 10.800
W2 2 1.200 1.200 3.000 8.640
W3 1 1.200 1.050 3.000 3.780
V 2 0.750 0.600 3.000 2.700
Angle iron chaukhat 0.000
D1 6 0.900 2.100 0.600 6.804
D2 3 0.750 2.100 0.600 2.835
TOTAL 35.559 Sqm
32 Painting on wood.
CUP BOARD SHUTTERS
BED ROOM 1 1.270 1.200 2.000 3.048
BED ROOM 1 1.290 1.200 2.000 3.096
Page 110
Flush door
D1 6 0.900 2.100 2.000 22.680
D2 3 0.750 2.100 2.000 9.450
TOTAL 38.274 SQM
33 Oil bound distemper
Same as Inside plaster TOTAL 225.115 SQM
35 Snowcem painting
Same as outside plaster TOTAL 220.914 SQM
39 Cinder filling
TOILET 1 2.250 1.465 0.450 1.483
TOILET 1 2.200 1.350 0.450 1.337
KITCHEN 1 2.000 2.550 0.150 0.765
TOTAL 3.585 CUM
40 Water proofing of Sunken portion
TOILET 1 2.250 1.465 3.296
2 2.250 0.450 2.025
2 1.465 0.450 1.319
TOILET 1 2.200 1.350 2.970
2 2.200 0.450 1.980
2 1.350 0.450 1.215
KITCHEN 1 2.000 2.550 5.100
2 2.000 0.150 0.600
2 2.550 0.150 0.765
TOTAL 19.270 SQM
41 BRICK KOBA TREATMENT
DRAWING ROOM 1 3.685 4.690 17.283
BED ROOM 1 3.595 3.460 12.439
1 3.445 3.960 13.642
1 1.730 0.600 1.038
1 0.600 1.750 1.050
LOUNGE 1 3.615 3.445 12.454
TOILET 1 2.595 1.235 3.205
1 2.660 1.465 3.897
REAR VERANDAH 1 3.300 1.380 4.554
KITCHEN 1 2.345 2.895 6.789
STORE 1 2.345 1.430 3.353
LOBBY 1 3.730 1.730 6.453
FRONT VERANDAH 1 1.800 1.230 2.214
TOTAL 88.370 SQM
42 P/F of Curtain rods
D1 6 1.130 6.780
D2 3 0.980 2.940
W1 2 1.730 3.460
W2 2 1.430 2.860
W3 1 1.430 1.430
V 2 0.980 1.960
TOTAL 19.430 RM
Page 111
BILL OF QUANTITY OF PROPOSED PROPOSED GATE COMPLEX 1 NOS. 18.0 MT. WIDE
TOTAL #REF!
10 M.S. Work
GATE 1 18.000 3.000 50.000 2700.000
1 1.500 1.800 50.000 135.000
TOTAL 2835.000 KG
11 M.S. Painting
GATE 1 18.000 3.000 2.000 108.000
1 1.500 1.800 2.000 5.400
TOTAL 113.400 sqm
BILL OF QUANTITY OF PROPOSED FLOWER MARKET
AT SUB MARKET YARD,VRINDAVAN (U.P.)
ABSTRACT OF COST
(BASED ON U.P.P.W.D. S.O.R. - MATHURA w.e.f. 01/03/2013
DETAILS OF MEASUREMENT
Page 121
A.C. PLANT ROOM 4 3.335 4.500 0.150 9.005
SHOPS 16 3.300 4.500 0.150 35.640
ELECTRICAL ROOM 1 3.300 4.500 0.150 2.228
AIR-LOCK 1 6.830 4.500 0.150 4.610
2 4.500 6.000 0.150 8.100
STAIRCASE 1 3.300 4.500 0.150 2.228
SIDE ENT 4 4.500 1.800 0.150 4.860
LOADING/UNLOADING PLATFORM 1 20.950 6.000 0.150 18.855
CORRIDOR 2 42.200 4.500 0.150 56.970
2 6.000 4.000 0.150 7.200
AUCTION PLATFORM 1 34.200 6.000 0.150 30.780
TOTAL 180.475 CUM
5 Anti-termite treatment
TOTAL 1124.000 SQM
6 R.C.C. work in Lintel
D 6 2.300 0.230 0.200 0.635
D1 4 2.100 0.230 0.150 0.290
D2 4 1.800 0.230 0.200 0.331
D3 18 1.300 0.230 0.150 0.807
D4 2 1.300 0.230 0.150 0.090
W 6 2.700 0.230 0.200 0.745
W1 13 2.100 0.230 0.150 0.942
W2 26 1.800 0.230 0.150 1.615
W3 4 1.500 0.230 0.150 0.207
FG 19 2.100 0.230 0.150 1.377
TOTAL 7.038 CUM
7 R.C.C. work in slab
SHOPS 1 35.530 4.960 0.120 21.147
1 17.915 4.960 0.120 10.663
1 10.820 4.960 0.120 6.440
AIR-LOCK 2 6.900 4.960 0.140 9.583
2 3.250 0.600 0.120 0.468
AUCTION PLATFORM 1 42.660 6.450 0.120 33.019
2 42.660 4.505 0.140 53.811
PROJECTION OF SLAB 1 35.070 0.600 0.120 2.525
1 10.360 0.600 0.120 0.746
1 20.950 0.600 0.120 1.508
A.C. PLANT ROOM 4 3.830 5.180 0.120 9.523
MUMTY 1 4.960 6.160 0.120 3.666
STAIRCASE ON TERRACE
LANDING 4 1.230 0.980 0.150 0.723
FLIGHT 4 3.059 1.230 0.150 2.258
CHAZZA
W2 22 1.960 0.300 0.100 1.294
44 1.960 0.530 0.100 4.571
W 4 2.860 0.300 0.100 0.343
8 2.860 0.530 0.100 1.213
W 2 3.700 0.600 0.100 0.444
2 4.276 0.830 0.100 0.710
D 4 4.090 0.335 0.100 0.548
STAIRCASE FLIGHT 1 0.768 1.430 0.150 0.165
1 1.104 1.430 0.150 0.237
1 2.459 1.430 0.150 0.527
STAIRCASE LANDING 1 1.730 1.430 0.150 0.371
3 1.430 1.430 0.150 0.920
1 1.430 0.600 0.150 0.129
R.C.C. LOADING/UNLOADING PLATFORM 1 21.410 6.230 0.120 16.006
AUCTION PLATFORM 1 34.200 6.000 0.120 24.624
TOTAL 208.182 CUM
8 R.C.C.work in beams
GRADE BEAMS 0.000
PB1 5 6.460 0.230 0.450 3.343
PB2 1 27.040 0.230 0.450 2.799
Page 122
3 6.760 0.230 0.450 2.099
PB3 2 40.560 0.230 0.450 8.396
5 6.000 0.230 0.450 3.105
10 4.050 0.230 0.450 4.192
PB1A 5 6.460 0.230 0.600 4.457
5 6.460 0.230 0.100 0.743
PB2A 1 27.040 0.230 0.600 3.732
1 27.040 0.230 0.100 0.622
3 6.760 0.230 0.600 2.799
3 6.760 0.230 0.100 0.466
PB4A 4 4.060 0.230 0.600 2.241
4 4.060 0.230 0.100 0.374
4 4.050 0.230 0.600 2.236
4 4.050 0.230 0.100 0.373
2 6.000 0.230 0.600 1.656
2 6.000 0.230 0.100 0.276
4 4.090 0.230 0.600 2.258
4 4.090 0.230 0.100 0.376
PB4 15 4.060 0.230 0.450 6.303
4 6.000 0.230 0.450 2.484
PB5 7 4.500 0.230 0.450 3.260
BEAMS
B1 10 6.460 0.230 0.450 6.686
B2 2 27.040 0.230 0.450 5.597
2 7.760 0.230 0.450 1.606
2 13.520 0.230 0.450 2.799
B3 2 22.220 0.230 0.450 4.600
4 6.000 0.230 0.450 2.484
4 4.090 0.230 0.450 1.693
15 4.060 0.230 0.450 6.303
B4 7 4.500 0.230 0.600 4.347
0.000
B1 4 3.230 0.230 0.450 1.337
B2 5 6.460 0.230 0.450 3.343
7 14.100 0.230 0.450 10.215
1 3.230 0.230 0.450 0.334
B3 1 27.040 0.230 0.450 2.799
1 6.760 0.230 0.450 0.700
1 13.520 0.230 0.450 1.399
2 4.060 0.230 0.450 0.840
B4 2 40.560 0.230 0.600 11.195
B5 6 6.150 0.230 0.450 3.819
B6 8 4.060 0.230 0.450 3.362
MUMTY 0.000
B1 2 3.230 0.230 0.450 0.669
2 4.060 0.230 0.450 0.840
TOTAL 135.556 CUM
9 R.C.C.work in raft foundation
F-1 7 2.100 2.100 0.150 4.631
7*0.15/6*(2.1*2.1+0.50*0.65+4*1.30*1.375) 2.080
7 0.500 0.650 0.150 0.341
Page 123
F-5 4 2.900 2.900 0.150 5.046
4*0.25/6*(2.90*2.90+0.50*0.65+4*1.70*1.775) 3.468
4 0.500 0.650 0.150 0.195
TOTAL 85.259 CUM
10 R.C.C.work in Column
C3 IN F1 4 0.300 0.450 4.550 2.457
C2 IN F2 6 0.300 0.450 4.500 3.645
C2 IN F3 3 0.300 0.450 4.500 1.823
AUCTION PLATFORM
Column in F-2 10 0.300 0.450 6.750 9.113
Column in F-3 9 0.300 0.450 6.750 8.201
Column in F-5 4 0.300 0.450 6.700 3.618
TOTAL 47.642 CUM
11 B/W In foundation
LOADING/UNLOADING PLATFORM 7 6.000 0.230 0.600 5.796
7 6.000 0.345 0.150 2.174
7 6.000 0.460 0.150 2.898
7 6.000 0.575 0.150 3.623
1 21.410 0.230 0.600 2.955
1 21.410 0.345 0.150 1.108
1 21.410 0.460 0.150 1.477
1 21.410 0.575 0.150 1.847
TOTAL 21.876 CUM
12 25mm thick D.P.C.
SHOPS 2 39.960 0.230 18.382
2 39.660 0.230 18.244
18 4.060 0.230 16.808
7 4.500 0.230 7.245
CORRIDOR 4 4.050 0.230 3.726
AIR LOCK 4 4.090 0.230 3.763
4 6.000 0.230 5.520
DUCTS 8 0.600 0.230 1.104
16 0.450 0.230 1.656
DUCT 2 0.740 0.115 0.170
TOTAL 76.618 SQM
DEDUCTION (-)
D 6 2.000 0.230 2.760
D1 4 1.800 0.230 1.656
D2 4 1.500 0.230 1.380
D3 18 1.000 0.230 4.140
D4 2 1.000 0.230 0.460
TOTAL 10.396 SQM
TOTAL 66.222 SQM
13 Bitumen Painting on D.P.C.
Same as Item No. 12 TOTAL 66.222 SQM
Page 124
7 4.500 0.230 2.850 20.648
CORRIDOR 4 4.050 0.230 2.850 10.619
AIR LOCK 4 4.090 0.230 2.850 10.724
4 6.000 0.230 2.850 15.732
DUCTS 8 0.600 0.230 2.850 3.146
A.C. PLANT 8 3.230 0.230 1.800 10.698
8 4.060 0.230 1.800 13.447
MUMTY 2 3.230 0.230 2.850 4.235
2 4.060 0.230 2.850 5.323
AUCTION PLATFORM 4 3.230 0.230 1.800 5.349
1 27.040 0.230 1.800 11.195
1 6.760 0.230 1.800 2.799
1 19.980 0.230 1.800 8.272
2 14.100 0.230 1.800 11.675
OFFSET 52 0.300 0.230 2.350 8.432
4 0.300 0.230 2.550 0.704
16 0.450 0.230 6.030 9.986
Page 125
2 2.400 0.115 1.400 0.773
D1 2 2.630 0.115 0.130 0.079
DUCT 2 0.740 0.115 3.780 0.643
8 0.115 0.115 5.170 0.547
TOTAL 6.742 CUM
16 M. S. work in R.C.C.
qty same as item no (6)*1.0*0.785 (Lintel) 5.525
qty same as item no (7)*1.0*0.785 (Slab) 163.423
qty same as item no (8)*1.5.0*0.785 (Beam) 266.029
qty same as item no (9)*1.0*0.785 (Raft) 100.393
qty same as item no (10)*2.0*0.785 (Column) 112.196
TOTAL 647.565 QTL
17 12mm thick plinth plaster in 1:4
Inside (below plinth)
A.C. PLANT ROOM 4 15.670 0.150 9.402
SHOPS 16 15.600 0.150 37.440
ELECTRICAL ROOM 1 15.600 0.150 2.340
AIR-LOCK 1 22.490 0.150 3.374
2 21.000 0.150 6.300
STAIRCASE/MUMTY 1 15.600 0.150 2.340
AUCTION PLATFORM 1 114.400 0.150 17.160
Outside (below G.L.)
2 53.320 0.150 15.996
2 24.920 0.150 7.476
TOTAL 101.828 SQM
18 15mm cement plaster (Interior surface)
A.C. PLANT ROOM 4 15.670 5.430 340.352
SHOPS 16 15.600 3.180 793.728
ELECTRICAL ROOM 1 15.600 3.180 49.608
AIR-LOCK 1 22.490 3.180 71.518
2 21.000 3.180 133.560
STAIRCASE/MUMTY 1 15.600 6.480 101.088
AUCTION PLATFORM 1 114.400 5.430 621.192
TOTAL 2111.05 SQM
DEDUCTION
D 6 2.000 2.550 30.600
D1 4 1.800 2.550 18.360
D2 4 1.500 2.550 15.300
D3 18 1.000 2.550 45.900
D4 2 1.000 2.100 4.200
W 6 2.400 1.650 23.760
W1 13 1.800 1.650 38.610
W2 26 1.500 1.650 64.350
W3 4 1.200 1.650 7.920
FG 19 1.800 0.600 20.520
TOTAL 269.520 SQM
NET TOTAL 1841.53 SQM
19 12 mm Thick plaster (outer side)
2 42.660 6.150 524.718
2 24.920 6.150 306.516
6 4.960 1.050 31.248
MUMTY 2 4.960 1.050 10.416
2 3.760 1.050 7.896
PARAPET 1 35.000 1.430 50.050
1 10.290 1.430 14.715
1 20.880 1.430 29.858
2 3.250 1.430 9.295
4 0.370 1.430 2.116
4 4.730 2.630 49.760
4 2.022 2.630 21.271
TOP PARAPET 1 34.265 1.430 48.999
2 5.180 1.430 14.815
Page 126
4 3.370 1.430 19.276
2 25.820 1.430 73.845
2 5.410 1.430 15.473
1 19.315 1.430 27.620
1 8.750 1.430 12.513
MUMTY 2 6.160 1.430 17.618
2 4.500 1.430 12.870
DUCTS 8 0.600 3.300 15.840
DUCT 2 0.740 3.900 5.772
8 0.115 5.170 4.756
TOTAL 1327.256 SQM
20 Ceiling Plaster .
A.C. PLANT ROOM 4 3.335 4.500 60.030
SHOPS 16 3.300 4.500 237.600
ELECTRICAL ROOM 1 3.300 4.500 14.850
AIR-LOCK 1 6.830 4.500 30.735
2 4.500 6.000 54.000
STAIRCASE 1 3.300 4.500 14.850
CORRIDOR 2 42.200 4.500 379.800
2 6.000 4.000 48.000
AUCTION PLATFORM 1 34.200 6.000 205.200
MUMTY 1 3.300 4.500 14.850
PROJECTION OF SLAB 1 35.070 0.600 21.042
1 10.360 0.600 6.216
1 20.950 0.600 12.570
CHAZZA
W2 88 1.960 0.300 51.744
W 12 2.860 0.300 10.296
6 3.700 0.600 13.320
D 4 3.860 0.335 5.172
TOTAL 1180.275 SQM
21 Making grooves .
A.C. PLANT ROOM 4 15.670 62.680
SHOPS 16 15.600 249.600
ELECTRICAL ROOM 1 15.600 15.600
AIR-LOCK 1 22.490 22.490
2 21.000 42.000
STAIRCASE/MUMTY 1 15.600 15.600
AUCTION PLATFORM 1 114.400 114.400
TOTAL 522.370 RM
22 40mm thick C.C. flooring .
APRON 2 52.120 0.900 93.816
2 32.950 0.900 59.310
TOTAL 153.126 SQM
23 Kota Stone Flooring .
A.C. PLANT ROOM 4 3.335 4.500 60.030
SHOPS 16 3.300 4.500 237.600
ELECTRICAL ROOM 1 3.300 4.500 14.850
AIR-LOCK 1 6.830 4.500 30.735
2 4.500 6.000 54.000
STAIRCASE 1 3.300 4.500 14.850
SIDE ENT 4 4.730 2.700 51.084
LOADING/UNLOADING PLATFORM 1 21.410 6.230 133.384
CORRIDOR 2 42.200 4.500 379.800
2 6.000 4.000 48.000
AUCTION PLATFORM 1 34.200 6.000 205.200
ENT. STEPS 2 3.000 2.200 13.200
TOTAL 1242.733 SQM
24 Kota Stone Skirting
A.C. PLANT ROOM 4 15.670 0.150 9.402
SHOPS 16 15.600 0.150 37.440
ELECTRICAL ROOM 1 15.600 0.150 2.340
AIR-LOCK 1 22.660 0.150 3.399
2 21.000 0.150 6.300
Page 127
STAIRCASE/MUMTY 1 15.600 0.150 2.340
AUCTION PLATFORM 1 114.400 0.150 17.160
1 77.820 0.200 15.564
SIDE ENT. STEPS 20 4.730 0.150 14.190
REAR STEPS 8 3.000 0.150 3.600
PLATFORM 1 21.410 0.150 3.212
STAIRCASE STEPS 22 1.200 0.150 3.960
1 15.600 0.150 2.340
TOTAL 121.247 SQM
25 M.S.Work in D/W
(a) Hold fast
DOORS 34 6.000 0.600 122.400
WINDOWS 49 4.000 0.600 117.600
VENTILATORS 19 2.000 0.600 22.800
TOTAL 262.800 KG
(b) M.S.Grill & Railing
D 6 2.000 0.450 20.000 108.000
D1 4 1.800 0.450 20.000 64.800
D2 4 1.500 0.450 20.000 54.000
D3 18 1.000 0.450 20.000 162.000
W 6 2.400 1.650 20.000 475.200
W1 13 1.800 1.650 20.000 772.200
W2 26 1.500 1.650 20.000 1287.000
W3 4 1.200 1.650 20.000 158.400
FG 19 1.800 0.600 20.000 410.400
STAIRCASE RAILING 1 0.768 0.900 30.000 20.736
1 1.104 0.900 30.000 29.808
1 2.459 0.900 30.000 66.393
TOTAL 3608.937 KG.
(c) Z-Section Windows
W 6 2.400 1.200 20.000 345.600
W1 13 1.800 1.200 20.000 561.600
W2 26 1.500 1.200 20.000 936.000
W3 4 1.200 1.200 20.000 115.200
TOTAL 1958.400 KG.
(d) Angle iron
D 6 9.550 3.600 206.280
D1 4 9.150 3.600 131.760
D2 4 8.550 3.600 123.120
D3 18 7.100 3.600 460.080
D4 2 5.200 3.600 37.440
TOTAL 958.680 KG.
26 Flush Door
(a) Single Leaf
D3 18 1.000 2.100 37.800
D4 2 1.000 2.100 4.200
TOTAL 42.000 SQM
(b) Double Leaft
D 6 2.000 2.100 25.200
D1 4 1.800 2.100 15.120
D2 4 1.500 2.100 12.600
TOTAL 52.920 SQM
27 Fixing D/W/V Chaukhats.
Door chaukhats 34.000 NOS
Window chaukhats 49.000 NOS
Ventilator chaukhats 19.000 NOS
28 Glass panes
D 6 2.000 0.450 5.400
D1 4 1.800 0.450 3.240
D2 4 1.500 0.450 2.700
D3 18 1.000 0.450 8.100
W 6 2.400 1.650 23.760
Page 128
W1 13 1.800 1.650 38.610
W2 26 1.500 1.650 64.350
W3 4 1.200 1.650 7.920
FG 19 1.800 0.600 20.520
TOTAL 174.600 SQM
31 White washing
(Same as ceiling plaster) TOTAL 1180.275 SQM
35 C.C. 1:2:4
HOLD FAST 438 0.150 0.100 0.100 0.657
Page 129
D1 4 1.800 2.100 0.600 9.072
D2 4 1.500 2.100 0.600 7.560
D3 18 1.000 2.100 0.600 22.680
D4 2 1.000 2.100 0.600 2.520
TOTAL 609.788 SQM
Page 130
CONSUMPTION OF MATERIALS (FLOWER MARKET)
ABSTRACT OF COST
(BASED ON U.P.P.W.D. S.O.R. - MATHURA w.e.f. 01/03/2013
(a) Fabrication of hold fast for door chaukhats and windows. 12.00 KG 65.00 780.00
36 Providing and fixing ball bearing for rollong (PWD-523) 20.000 NOS 750.00 15000.00
shutters. TOTAL #REF!
HENCE COST OF 20 NOS. SHOPS Say Rs. #REF! Lacs.
DETAILED MEASUREMENTS OF PROPOSED 20 NOS. C-TYPE SHOPS
AT SUB MARKET YARD,VRINDAVAN (U.P.)
DETAILS OF MEASUREMENT
Page 139
B2 1 30.730 0.230 0.750 5.301
Page 140
C4 IN F4 4 0.300 0.450 4.550 2.457
C3 IN F3A 2 0.300 0.450 4.550 1.229
TOTAL 12.074 CUM
10 B/W In foundation
UNDER PLATFORM 0.000
LOADING/UNLOADING PLATFORM 1 32.300 0.230 0.450 3.343
1 32.300 0.345 0.150 1.672
1 32.300 0.460 0.150 2.229
1 32.300 0.575 0.150 2.786
14 M. S. work in R.C.C.
qty same as item no (6)*1.0*0.785 (Slab) 70.109
qty same as item no (7)*2.5.0*0.785 (Beam) 101.748
qty same as item no (8)*1.5*0.785 (Raft) 27.837
qty same as item no (9)*3.0*0.785 (Column) 28.433
TOTAL 228.126 QTL
15 15mm thick plinth plaster in 1:4
Below Plinth (Inside)
SHOPS 10 18.000 0.150 27.000
COVERED VERANDAH 2 32.530 0.150 9.759
2 4.000 0.150 1.200
Page 141
V1 10 0.900 0.450 4.050
OPENING 10 2.665 2.700 71.955
2 3.240 2.700 17.496
TOTAL 161.001 SQM
NET TOTAL 648.791 SQM
17 12 mm Thick plaster (outer side)
OUTER SIDE 1 10.230 4.150 42.455
2 32.530 4.150 269.999
OFFSET 9 0.415 3.600 13.446
PARAPET 2 32.530 1.580 102.795
2 9.770 1.580 30.873
OPENING -10 2.665 2.700 -71.955
-1 3.240 2.700 -8.748
TOTAL 378.865 SQM
18 Ceiling Plaster .
SHOPS 10 3.000 6.000 180.000
COVERED VERANDAH 1 32.530 3.885 126.379
SLAB PROJECTION 2 34.030 0.750 51.045
2 10.230 0.750 15.345
CHAZZA 10 1.130 0.600 6.780
TOTAL 379.549 SQM
19 Making grooves .
SHOPS 10 18.000 180.000
COVERED VERANDAH 1 73.060 73.060
TOTAL 253.060 RM
20 40mm thick C.C. flooring .
APRON 2 34.030 0.750 51.045
1 14.460 0.750 10.845
TOTAL 61.890 SQM
25 Glass panes
V1 10 0.900 0.450 4.050
TOTAL 4.050 SQM
Page 142
27 Water proof cement paint
(Same as Outside plaster) TOTAL 378.865 SQM
29 C.C. 1:2:4
HOLD FAST 20 0.150 0.100 0.100 0.030
PARAPET 2 32.530 0.380 0.150 3.708
1 9.770 0.380 0.150 0.557
TOTAL 4.295 CUM
30 Steel painting
Grills 0.000
V1 10 0.900 0.450 2.000 8.100
Z-SECTION 0.000
V1 10 0.900 0.450 2.000 8.100
TOTAL 16.200 SQM
33 Rolling Shutter
R/S 10 2.500 2.700 67.500 SQM
Page 143
CONSUMPTION OF MATERIALS (20 NOS. C-TYPE SHOPS)
ABSTRACT OF COST
(BASED ON U.P.P.W.D. S.O.R. - MATHURA w.e.f. 01/03/2013
TOTAL #REF!
DETAILS OF MEASUREMENT
Page 148
TOTAL 24.945 CUM
11 M. S. work in R.C.C.
qty same as item no (6)*2.5.0*0.785 (Beam) 25.160
qty same as item no (7)*1.5*0.785 (Raft) 10.598
qty same as item no (8)*3.0*0.785 (Column) 32.022
TOTAL 67.779 QTL
12 15 mm Thick plaster (outer side)
FRONT SIDE 1 41.310 0.750 30.983
LEFT SIDE 1 9.000 0.750 6.750
REAR SIDE 1 41.310 0.750 30.983
RIGHT SIDE 1 9.000 0.750 6.750
RAT PROTECTION LEDGE 2 41.770 0.560 46.782
2 9.460 0.560 10.595
TOTAL 132.843 SQM
13 40mm thick C.C. flooring .
APRON 2 42.810 0.750 64.215
2 9.000 0.750 13.500
TOTAL 77.715 SQM
14 Kota Stone Flooring .
AUCTION PLATFORM 1 41.310 9.000 371.790
ENTRANCE STEPS 16 3.100 0.450 22.320
TOTAL 394.110 SQM
0.000
15 Making drain alongwith apron 2 42.810 85.620
2 9.000 18.000
TOTAL 103.620 RM
Page 149
CONSUMPTION OF MATERIALS (AUCTION PLATFORM)
ABSTRACT OF COST
#REF!
(a) Fabrication of hold fast for door chaukhats and windows. 55.20 KG #REF! #REF!
TOTAL #REF!
DETAILS OF MEASUREMENT
Page 158
GB2 2 4.592 0.380 0.075 0.262
1 3.600 0.380 0.075 0.103
1 4.027 0.380 0.075 0.115
1 3.546 0.380 0.075 0.101
1 7.873 0.380 0.075 0.224
1 4.027 0.380 0.075 0.115
1 3.600 0.380 0.075 0.103
1 3.444 0.380 0.075 0.098
1 2.541 0.380 0.075 0.072
Page 159
1 50.814 1.000 0.120 6.098
1 9.173 1.000 0.120 1.101
DEDUCTIONS ( - ) -1 29.823 1.000 0.130 -3.877
CANTEEN'S UPPER SLAB 1 34.571 1.000 0.110 3.803
CANTEEN'S UPPER SLAB PROJECTION 1 12.028 1.000 0.120 1.443
CHAZZA
D/W/W 5 4.400 0.715 0.100 1.573
CANTEEN - W 4 3.460 0.600 0.100 0.830
W/W 1 7.872 0.600 0.113 0.531
V/D1 1 3.505 0.600 0.113 0.237
TOTAL 36.377 CUM
8 R.C.C.work in beams
GRADE BEAMS 0.000
GB1 6 4.592 0.230 0.450 2.852
1 2.541 0.230 0.450 0.263
1 3.444 0.230 0.450 0.356
1 3.546 0.230 0.450 0.367
GB2 2 4.592 0.230 0.450 0.951
1 3.600 0.230 0.450 0.373
1 4.027 0.230 0.450 0.417
1 3.546 0.230 0.450 0.367
1 7.873 0.230 0.450 0.815
1 4.027 0.230 0.450 0.417
1 3.600 0.230 0.450 0.373
1 3.444 0.230 0.450 0.356
1 2.541 0.230 0.450 0.263
GB3 2 3.600 0.230 0.450 0.745
GB4 1 1.376 0.230 0.300 0.095
1 2.388 0.230 0.300 0.165
1 1.344 0.230 0.300 0.093
1 1.096 0.230 0.300 0.076
SECTION AT S0-S0
DUCTS 4 1.650 0.675 0.200 0.891
2 0.675 0.675 0.200 0.182
BEAMS
B1 8 2.917 0.300 0.500 3.500
B2 4 1.220 0.300 0.500 0.732
2 2.541 0.300 0.500 0.762
2 3.546 0.300 0.500 1.064
B3 8 4.631 0.300 0.450 5.001
B4 2 3.600 0.300 0.450 0.972
B5 1 20.380 0.300 0.500 3.057
B6 2 3.062 0.230 0.450 0.634
B7 2 3.989 0.230 0.450 0.826
B8 1 7.781 0.230 0.450 0.805
B9 5 5.966 0.230 0.300 2.058
BEAM OF TOP SLAB
B9 1 20.644 0.230 0.300 1.424
B10 2 6.000 0.230 0.300 0.828
2 5.540 0.230 0.300 0.765
B11 4 5.328 0.230 0.300 1.471
TOTAL 34.315 CUM
9 R.C.C.work in raft foundation
F1 4 2.700 2.700 0.150 4.374
4*0.2/6*(2.7*2.7+0.55*0.8+4*1.625*1.75) 2.547
4 0.550 0.800 0.150 0.264
0.000
F2 6 2.050 2.050 0.150 3.782
6*0.1/6*(2.05*2.05+0.50*0.50+4*1.275*1.275) 1.096
6 0.500 0.500 0.150 0.225
0.000
CF1 4 2.900 1.800 0.150 3.132
4*0.1/6*(2.90*1.80+2.90*0.55+4*2.90*1.175) 1.363
Page 160
4 2.900 0.550 0.350 2.233
TOTAL 19.016 CUM
10 R.C.C.work in Column
UPTO PLINTH LVL.
F1
C1 4 0.350 0.600 1.200 1.008
F2
C3 4 0.300 0.300 1.300 0.468
C4 2 0.300 0.300 1.300 0.234
CF1
C1 4 0.350 0.600 1.300 1.092
C2 4 0.350 0.450 1.300 0.819
UPTO LOWER SLAB LVL.
C1 8 0.350 0.600 3.370 5.662
C2 4 3.143 0.031 3.370 1.298
C3 4 0.300 0.300 3.370 1.213
C4 2 0.300 0.300 3.370 0.607
UPTO UPPER SLAB LVL. 0.000
C5 8 3.143 0.016 1.690 0.664
TOTAL 13.064 CUM
11 B/W In foundation
DWARF WALL 0.000
GB1 6 4.592 0.230 0.600 3.802
1 2.541 0.230 0.600 0.351
1 3.444 0.230 0.600 0.475
1 3.546 0.230 0.600 0.489
Page 161
1 1.923 0.230 0.442
TOILET 1 3.444 0.230 0.792
1 2.541 0.230 0.584
DUCTS 10 0.715 0.230 1.645
HAND WASH 1 1.376 0.115 0.158
W.C. 1 1.382 0.115 0.159
2 1.100 0.115 0.253
DUCTS 4 0.971 0.115 0.447
2 0.344 0.115 0.079
TOTAL 21.348 SQM
DEDUCTION (-)
D 1 2.000 0.230 0.460
D1 1 1.500 0.230 0.345
D2 1 1.000 0.230 0.230
D3 1 0.750 0.230 0.173
1 0.750 0.115 0.086
TOTAL 1.294 SQM
TOTAL 20.054 SQM
13 Bitumen Painting on D.P.C.
Same as above Item No. 12 TOTAL 20.054 SQM
Page 162
2 0.670 0.115 0.900 0.139
DUCTS 5 0.971 0.115 3.050 1.703
2 0.344 0.115 3.050 0.241
PARAPET UPPER SLAB 8 2.676 0.115 0.525 1.293
TOTAL 5.363 CUM
DEDUCTION (-)
D3 1 0.750 0.115 2.100 0.181
TOTAL 0.181 CUM
NET TOTAL 5.182 CUM
16 M. S. work in R.C.C.
qty same as item no (6)*1.0*0.785 (Lintel) 1.543
qty same as item no (7)*1.0*0.785 (Slab) 28.556
qty same as item no (8)*2.5.0*0.785 (Beam) 67.343
qty same as item no (9)*1.5*0.785 (Raft) 22.391
qty same as item no (10)*3.0*0.785 (Column) 30.765
qty same as item no (41)*0.6*0.785 (Thin Shelves) 16.019
TOTAL 166.619 QTL
17 12mm thick plinth plaster in 1:4 (Inside Outer walls)
DWARF WALL 0.000
GB1 6 4.592 0.300 8.266
1 2.541 0.300 0.762
1 3.444 0.300 1.033
1 3.546 0.300 1.064
0.000
GB2 2 4.592 0.300 2.755
1 3.600 0.300 1.080
1 4.027 0.300 1.208
1 3.546 0.300 1.064
1 7.873 0.300 2.362
1 4.027 0.300 1.208
1 3.600 0.300 1.080
1 3.444 0.300 1.033
1 2.541 0.300 0.762
0.000
GB3 2 3.600 0.300 2.160
0.000
GB4 1 1.376 0.300 0.413
1 2.388 0.300 0.716
1 1.344 0.300 0.403
1 1.096 0.300 0.329
SECTION AT S0-S0 0.000
DUCTS 2 0.767 0.300 0.460
2 0.600 0.300 0.360
0.000
8 0.600 0.300 1.440
8 0.956 0.300 2.294
TOTAL 32.253 SQM
18 15mm cement plaster (Interior surface)
CANTEEN 8 4.751 3.050 115.924
8 2.485 1.690 33.597
HAND WASH 1 2.530 3.050 7.717
1 1.376 3.050 4.197
1 1.252 3.050 3.819
1 2.203 3.050 6.719
1 2.700 3.050 8.235
STORE 1 10.800 3.050 32.940
KITCHEN 1 7.703 3.050 23.494
1 4.069 3.050 12.410
1 6.124 3.050 18.678
1 3.600 3.050 10.980
1 2.388 3.050 7.283
WASH 1 2.151 3.050 6.561
Page 163
1 1.971 3.050 6.012
1 1.923 3.050 5.865
PANTRY 1 1.746 3.050 5.325
1 2.510 3.050 7.656
1 3.600 3.050 10.980
1 1.800 3.050 5.490
1 2.153 3.050 6.567
TOILET 1 2.930 0.950 2.784
1 1.852 0.950 1.759
1 1.777 0.950 1.688
1 1.214 0.950 1.153
1 1.344 0.950 1.277
1 1.215 0.950 1.154
TOTAL 350.26 SQM
DEDUCTION
D 1 2.000 2.550 5.100
D1 1 1.500 2.550 3.825
D2 1 1.000 2.100 2.100
D3 2 0.750 2.100 3.150
W 8 1.500 1.650 19.800
WK 3 1.800 1.500 8.100
W1 1 1.200 1.650 1.980
W2 1 0.900 1.650 1.485
V 1 0.900 0.600 0.540
V1 4 0.600 0.600 1.440
V2 8 1.800 0.600 8.640
TOTAL 56.160 SQM
NET TOTAL 294.10 SQM
19 12 mm Thick plaster (outer side)
CANTEEN 1 77.706 4.100 318.595
8 2.676 1.800 38.534
PARAPET - LOWER SLAB 1 60.819 1.580 96.094
PARAPET UPPER SLAB 8 2.676 1.465 31.363
PLANTER 1 3.740 0.900 3.366
1 3.280 0.900 2.952
TOTAL 490.904 SQM
20 Ceiling Plaster .
CANTEEN'S (CENTRAL AREA) 1 110.221 1.000 110.221
HAND WASH 1 6.429 1.000 6.429
STORE 1 6.480 1.000 6.480
KITCHEN 1 28.161 1.000 28.161
WASH / PANTRY 1 11.282 1.000 11.282
TOILET 1 4.835 1.000 4.835
W.C. 1 1.321 1.000 1.321
DEDUCTIONS ( - ) -1 29.823 1.000 -29.823
PROJECTION 5 9.014 1.000 45.070
2 61.772 0.150 18.532
CANTEEN'S UPPER SLAB 1 29.823 1.000 29.823
PROJECTION 1 12.028 1.000 12.028
CHAZZA 0.000
D/W/W 5 4.400 0.715 15.730
CANTEEN - W 4 3.460 0.600 8.304
W/W 1 7.872 0.600 4.723
V/D1 1 3.505 0.600 2.103
UNDER THIN SHELVES
HAND WASH 1 2.530 0.600 1.518
STORE 1 3.600 0.600 2.160
2 1.200 0.600 1.440
2 3.600 0.450 3.240
4 1.200 0.450 2.160
KITCHEN 1 7.798 0.600 4.679
1 5.095 0.600 3.057
Page 164
WASH 1 1.971 0.600 1.183
PANTRY 1 3.600 0.600 2.160
TOTAL 296.815 SQM
21 Making grooves .
CANTEEN 8 4.751 38.008
8 2.485 19.880
HAND WASH 1 2.530 2.530
1 1.376 1.376
1 1.252 1.252
1 2.203 2.203
1 2.700 2.700
STORE 1 10.800 10.800
KITCHEN 1 7.703 7.703
1 4.069 4.069
1 6.124 6.124
1 3.600 3.600
1 2.388 2.388
WASH 1 2.151 2.151
1 1.971 1.971
1 1.923 1.923
PANTRY 1 1.746 1.746
1 2.510 2.510
1 3.600 3.600
1 1.800 1.800
1 2.153 2.153
TOILET 1 2.930 2.930
1 1.852 1.852
1 1.777 1.777
1 1.214 1.214
1 1.344 1.344
1 1.215 1.215
TOTAL 130.819 RM
22 40mm thick C.C. flooring .
APRON 1 64.422 0.750 48.317
TOTAL 48.317 SQM
23 Kota Stone Flooring .
CANTEEN 1 110.221 1.000 110.221
HAND WASH 1 6.429 1.000 6.429
STORE 1 6.480 1.000 6.480
KITCHEN 1 28.161 1.000 28.161
WASH / PANTRY 1 11.282 1.000 11.282
CANTEEN'S OUTER WALK - WAY/ENT 5 9.014 1.000 45.070
ENTRANCE STEPS CANTEEN 8 2.100 0.450 7.560
ENTRANCE STEPS KITCHEN 4 1.500 0.450 2.700
TOTAL 217.903 SQM
24 Kota Stone Skirting
CANTEEN 8 4.751 0.150 5.701
HAND WASH 1 2.530 0.150 0.380
1 1.376 0.150 0.206
1 1.252 0.150 0.188
1 2.203 0.150 0.330
1 2.700 0.150 0.405
STORE 1 10.800 0.150 1.620
KITCHEN 1 7.703 0.150 1.155
1 4.069 0.150 0.610
1 6.124 0.150 0.919
1 3.600 0.150 0.540
1 2.388 0.150 0.358
WASH 1 2.151 0.150 0.323
1 1.971 0.150 0.296
1 1.923 0.150 0.288
PANTRY 1 1.746 0.150 0.262
1 2.510 0.150 0.377
Page 165
1 3.600 0.150 0.540
1 1.800 0.150 0.270
1 2.153 0.150 0.323
TOTAL 15.091 SQM
25 Ceremic tiles in toilet
FLOOR
TOILET 1 4.835 1.000 4.835
W.C. 1 1.321 1.000 1.321
WALLS
TOILET 1 2.930 2.100 6.153
1 1.852 2.100 3.889
1 1.777 2.100 3.732
1 1.344 2.100 2.822
1 1.250 2.100 2.625
W.C. 2 1.100 2.100 4.620
2 1.200 2.100 5.040
PANTRY 1 3.600 0.600 2.160
WASH 1 1.971 0.600 1.183
HAND WASH 1 2.530 0.600 1.518
TOTAL 39.898 SQM
26 M.S.Work in D/W
(a) Hold fast
DOORS 5 6.000 0.600 18.000
WINDOWS 13 4.000 0.600 31.200
VENTILATORS 5 2.000 0.600 6.000
TOTAL 55.200 KG
(b) M.S.Grill & Railing
D 1 2.000 0.450 20.000 18.000
D1 1 1.500 0.450 20.000 13.500
W 8 1.500 1.650 20.000 396.000
WK 3 1.800 1.500 20.000 162.000
W1 1 1.200 1.650 20.000 39.600
W2 1 0.900 1.650 20.000 29.700
V 1 0.900 0.600 20.000 10.800
V1 4 0.600 0.600 20.000 28.800
V2 8 1.800 0.600 20.000 172.800
TOTAL 871.200 KG.
(c) Z-Section Windows
W 8 1.500 1.200 20.000 288.000
WK 3 1.800 1.050 20.000 113.400
W1 1 1.200 1.200 20.000 28.800
W2 1 0.900 1.200 20.000 21.600
V 1 0.900 0.600 20.000 10.800
V1 4 0.600 0.600 20.000 28.800
V2 8 1.800 0.600 20.000 172.800
TOTAL 664.200 KG.
(d) Angle iron door chaukhats
D 1 9.550 3.600 34.380
D1 1 8.550 3.600 30.780
D2 1 5.200 3.600 18.720
D3 2 4.950 3.600 35.640
119.520 KG.
27 Flush Door
(a) Single Leaf
D2 1 1.000 2.100 2.100
D3 2 0.750 2.100 3.150
TOTAL 5.250 SQM
(b) Double Leaf
D 1 2.000 2.100 4.200
D1 1 1.500 2.100 3.150
TOTAL 7.350 SQM
28 Fixing D/W/V Chaukhats.
Page 166
Door chaukhats 5.000 NOS
Window chaukhats 13.000 NOS
Ventilator chaukhats 5.000 NOS
29 Glass panes
D 1 2.000 0.450 0.900
D1 1 1.500 0.450 0.675
W 8 1.500 1.650 19.800
WK 3 1.800 1.500 8.100
W1 1 1.200 1.650 1.980
W2 1 0.900 1.650 1.485
V 1 0.900 0.600 0.540
V1 4 0.600 0.600 1.440
V2 8 1.800 0.600 8.640
TOTAL 43.560 SQM
36 C.C. 1:2:4
HOLD FAST 92 0.150 0.100 0.100 0.138
PARAPET - LOWER SLAB 1 60.819 0.305 0.075 1.391
PARAPET UPPER SLAB 8 2.676 0.190 0.075 0.305
TOTAL 1.834 CUM
37 Steel painting
Grills 0.000
D 1 2.000 0.450 2.000 1.800
D1 1 1.500 0.450 2.000 1.350
W 8 1.500 1.650 2.000 39.600
WK 3 1.800 1.500 2.000 16.200
W1 1 1.200 1.650 2.000 3.960
W2 1 0.900 1.650 2.000 2.970
V 1 0.900 0.600 2.000 1.080
V1 4 0.600 0.600 2.000 2.880
V2 8 1.800 0.600 2.000 17.280
Z-SECTION 0.000
W 8 1.500 1.200 2.000 28.800
WK 3 1.800 1.050 2.000 11.340
W1 1 1.200 1.200 2.000 2.880
W2 1 0.900 1.200 2.000 2.160
V 1 0.900 0.600 2.000 1.080
V1 4 0.600 0.600 2.000 2.880
V2 8 1.800 0.600 2.000 17.280
DOOR CHAUKHATS
D2 1 1.000 2.100 0.600 1.260
D3 2 0.750 2.100 0.600 1.890
D 1 2.000 2.100 0.600 2.520
D1 1 1.500 2.100 0.600 1.890
TOTAL 161.100 SQM
Page 167
38 Painting on wood. 25.200
Same as Item No. (27)X2 TOTAL 25.200 SQM
41 Thin shelves
HAND WASH 1 2.875 0.830 2.386
STORE 1 4.060 0.830 3.370
2 1.430 0.830 2.374
2 4.060 0.680 5.522
4 1.430 0.680 3.890
KITCHEN 1 8.028 0.830 6.663
1 5.325 0.830 4.420
WASH 1 2.431 0.830 2.018
PANTRY 1 4.060 0.830 3.370
TOTAL 34.012 SQM
42 Granite Top .
HAND WASH 1 2.530 0.600 1.518
STORE 1 3.600 0.600 2.160
2 1.200 0.600 1.440
2 3.600 0.450 3.240
4 1.200 0.450 2.160
KITCHEN 1 7.798 0.600 4.679
1 5.095 0.600 3.057
WASH 1 1.971 0.600 1.183
PANTRY 1 3.600 0.600 2.160
TOTAL 21.596 SQM
Page 168
CONSUMPTION OF MATERIALS (CANTEEN BLOCK)
ABSTRACT OF COST
#REF!
(a) Fabrication of hold fast for door chaukhats and windows. 60.00 KG 65.00 3900.00
40 Same as item 38 above but on new wood surf #REF! 39.900 SQM 55.00 2194.50
TOTAL #REF!
DETAILS OF MEASUREMENT
Page 177
Under Apron
APRON 2 10.520 0.750 0.075 1.184
2 8.900 0.750 0.075 1.001
TOTAL 15.241 CUM
3 Sand filling
Under Floor
VERANDAH 1 3.530 2.740 0.150 1.451
LOBBY 1 5.030 2.510 0.150 1.894
MALE TOILET 1 3.665 3.530 0.150 1.941
W.C. 2 1.250 1.100 0.150 0.413
JANITOR 1 1.250 1.215 0.150 0.228
FEMALE TOILET 1 1.935 3.530 0.150 1.025
W.C. 3 1.250 1.100 0.150 0.619
STAIRCASE VERANDAH 1 1.950 0.900 0.150 0.263
STAIRCASE 1 5.035 1.950 0.150 1.473
TOTAL 9.305 CUM
4 Anti-termite treatment
TOTAL 72.672 SQM
5 R.C.C. work in Lintel
(a) Ground Floor
LINTEL
D 3 1.460 0.230 0.150 0.151
W 3 1.660 0.230 0.150 0.172
W1 1 1.660 0.230 0.150 0.057
V 6 0.910 0.230 0.150 0.188
V1 1 1.360 0.230 0.150 0.047
PLINTH BAND
MALE TOILET 2 1.250 0.230 0.150 0.086
1 0.700 0.230 0.150 0.024
FEMALE TOILET 2 1.250 0.230 0.150 0.086
1 0.920 0.230 0.150 0.032
LINTEL BAND
MALE TOILET 1 3.645 0.115 0.150 0.063
2 1.250 0.115 0.150 0.043
1 0.700 0.115 0.150 0.012
FEMALE TOILET 1 3.530 0.115 0.150 0.061
2 1.250 0.115 0.150 0.043
1 0.920 0.115 0.150 0.016
TOTAL 1.082 CUM
(b) First Floor
LINTEL
D 2 1.460 0.230 0.150 0.101
W2 1 1.960 0.230 0.150 0.068
TOTAL 0.168 CUM
6 R.C.C. work in slab
(a) G. F.
TOILET BLOCK 1 5.490 6.730 0.120 4.434
1 3.530 6.730 0.120 2.851
STAIR FIRST FLIGHT 1 3.305 1.180 0.150 0.585
STAIR SECOND FLIGHT 1 2.995 1.780 0.150 0.800
STAIR FIRST LANDING 1 1.280 2.410 0.150 0.463
STAIR SECOND LANDING 1 1.980 2.410 0.150 0.716
CHAZZA
STAIRCASE - D 1 2.180 0.750 0.113 0.184
STAIRCASE - W1 1 1.660 0.600 0.113 0.112
LOBBY - W 1 1.660 0.600 0.113 0.112
MALE TOILET - V/V/V 1 2.960 0.600 0.113 0.200
MALE TOILET - W 1 1.660 0.600 0.113 0.112
MALE TOILET - V1 1 1.360 0.600 0.113 0.092
FEMALE TOILET - W 1 1.430 0.600 0.113 0.097
FEMALE TOILET - V/V/V 1 2.960 0.600 0.113 0.200
Page 178
TOTAL 10.956 CUM
(b) F. F.
STAIRCASE / VERANDAH / ROOM 1 5.490 8.910 0.120 5.870
CHAZZA
ROOM - W2 1 1.960 0.600 0.113 0.132
TOTAL 6.002 CUM
7 R.C.C.work in beams
(a) GROUND FLOOR
GRADE BEAMS
GB1 4 4.590 0.230 0.450 1.900
2 3.230 0.230 0.450 0.669
2 3.390 0.230 0.450 0.702
GB2 2 1.880 0.230 0.450 0.389
1 1.950 0.230 0.450 0.202
1 3.230 0.230 0.450 0.334
3 2.440 0.230 0.450 0.758
1 3.390 0.230 0.450 0.351
1 3.530 0.230 0.450 0.365
1 1.878 0.230 0.450 0.194
BEAMS
B1 2 4.590 0.230 0.450 0.950
1 3.390 0.230 0.450 0.351
Page 179
(a) G.F.
BELOW PLINTH LVL.
F-1
C1 4 0.300 0.450 1.300 0.702
C2 3 0.300 0.300 1.300 0.351
F-2 0.000
C1 3 0.300 0.450 1.250 0.506
F-3 0.000
C1 1 0.300 0.450 1.200 0.162
ABOVE PLINTH LVL.
C1 8 0.300 0.450 3.380 3.650
C2 3 0.300 0.300 3.380 0.913
TOTAL 6.284 CUM
(b) FIRST FLOOR
C1 8 0.300 0.450 3.380 3.650
TOTAL 3.650 CUM
10 B/W In foundation
GB1 4 4.590 0.230 0.600 2.534
2 3.230 0.230 0.600 0.891
2 3.390 0.230 0.600 0.936
GB2 2 1.880 0.230 0.600 0.519
1 1.950 0.230 0.600 0.269
1 3.230 0.230 0.600 0.446
3 2.440 0.230 0.600 1.010
1 3.390 0.230 0.600 0.468
1 3.530 0.230 0.600 0.487
1 1.878 0.230 0.600 0.259
FOR 0.115 THICK WALLS
W.C. / JANITOR 2 1.250 0.230 0.225 0.129
2 1.250 0.345 0.075 0.065
2 1.250 0.460 0.150 0.173
Page 180
2 1.250 0.115 0.288
1 0.700 0.115 0.081
FEMALE TOILET 1 3.530 0.115 0.406
2 1.250 0.115 0.288
1 0.920 0.115 0.106
TOTAL 11.059 SQM
DEDUCT
D 3 1.000 0.230 0.690
D1 6 0.750 0.230 1.035
TOTAL 1.725 SQM
NET TOTAL 9.334 SQM
12 Bitumen Painting on D.P.C.
MALE TOILET 1 4.590 0.230 1.056
2 3.390 0.230 1.559
1 2.145 0.230 0.493
FEMALE TOILET 1 3.390 0.230 0.780
2 3.230 0.230 1.486
LOBBY 2 2.440 0.230 1.122
STAIRCASE 2 1.880 0.230 0.865
2 4.590 0.230 2.111
MALE TOILET 1 3.645 0.115 0.419
2 1.250 0.115 0.288
1 0.700 0.115 0.081
FEMALE TOILET 1 3.530 0.115 0.406
2 1.250 0.115 0.288
1 0.920 0.115 0.106
TOTAL 11.059 SQM
DEDUCT
D 3 1.000 0.230 0.690
D1 6 0.750 0.230 1.035
TOTAL 1.725 SQM
TOTAL 9.334 SQM
13 B/W in super-structure (230 mm thick)
(a) G.F.
MALE TOILET 1 4.590 0.230 3.050 3.220
2 3.390 0.230 3.050 4.756
1 2.145 0.230 3.050 1.505
FEMALE TOILET 1 3.390 0.230 3.050 2.378
2 3.230 0.230 3.050 4.532
LOBBY 2 2.440 0.230 3.050 3.423
STAIRCASE 2 1.880 0.230 3.050 2.638
2 4.590 0.230 3.050 6.440
VERANDAH ENTRANCE STEPS 1 2.510 0.900 0.300 0.678
1 2.510 0.600 0.150 0.226
1 2.510 0.300 0.150 0.113
STAIRCASE ENTRANCE STEPS 1 1.950 0.900 0.300 0.527
1 1.950 0.600 0.150 0.176
1 1.950 0.300 0.150 0.088
ENTRANCE STEPS PARAPET 2 0.900 0.230 0.600 0.248
1 1.800 0.230 0.600 0.248
TOTAL 31.194 CUM
DEDUCTION (-)
D 3 1.000 0.230 2.550 1.760
W 3 1.200 0.230 1.650 1.366
W1 1 1.200 0.230 1.650 0.455
V 6 0.450 0.230 0.450 0.279
V1 1 0.900 0.230 0.450 0.093
TOTAL 2.194 CUM
NET TOTAL 29.000 CUM
(b) F.F.
STAIRCASE 2 1.880 0.230 3.050 2.638
2 4.590 0.230 3.050 6.440
ROOM 2 4.590 0.230 3.050 6.440
Page 181
2 3.390 0.230 3.050 4.756
TERRACE PARAPET 1 6.730 0.230 0.950 1.471
2 3.300 0.230 0.950 1.442
UPPER TERRACE PARAPET 2 8.910 0.230 0.350 1.435
2 5.030 0.230 0.350 0.810
TOTAL 25.430 CUM
DEDUCTION
D 2 1.000 0.230 2.550 1.173
W2 1 1.500 0.230 1.650 0.569
TOTAL 1.742 CUM
NET TOTAL 23.688 CUM
14 B/W in super-structure(115 thick)
(a) G.F.
MALE TOILET 1 3.645 0.115 2.100 0.880
2 1.250 0.115 2.100 0.604
1 0.700 0.115 2.100 0.169
FEMALE TOILET 1 3.530 0.115 2.100 0.852
2 1.250 0.115 2.100 0.604
1 0.920 0.115 2.100 0.222
TOTAL 3.331 CUM
DEDUCTION
D1 6 0.750 0.115 2.100 1.087
TOTAL 1.087 CUM
NET TOTAL 2.245 CUM
(b) F.F.
VERANDAH PARAPET 1 2.440 0.115 0.950 0.267
NET TOTAL 0.267 CUM
15 M. S. work in R.C.C.
(a) GROUND FLOOR
qty same as item no (5a)*1.0*0.785 (Lintel) 0.849
qty same as item no (6a)*1.0*0.785 (Slab) 8.600
qty same as item no (7a)*2.5*0.785 (Beam) 21.644
qty same as item no (8)*1.5*0.785 (footing) 13.809
qty same as item no (9a)*3.0*0.785 (Column) 14.799
qty same as item no (41)*0.6*0.785 (Thin Shelves) 2.277
TOTAL 61.979 QTL
(b) FIRST FLOOR
qty same as item no (5b)*1.0*0.785 (Lintel) 0.132
qty same as item no (6b)*1.0*0.785 (Slab) 4.712
qty same as item no (7b)*2.5*0.785 (Beam) 6.861
qty same as item no (9b)*3.0*0.785 (Column) 8.597
TOTAL 20.302 QTL
16 12mm cement plinth plaster in 1:4
Inside (Below Plinth Lvl.)
MALE TOILET LOBBY 1 5.035 0.150 0.755
2 2.510 0.150 0.753
1 2.365 0.150 0.355
1 1.365 0.150 0.205
MALE TOILET 1 2.365 0.150 0.355
2 3.530 0.150 1.059
1 3.665 0.150 0.550
2 0.750 0.150 0.225
W.C. 2 4.700 0.150 1.410
JANITOR 1 4.930 0.150 0.740
FEMALE TOILET 2 1.935 0.150 0.581
2 3.530 0.150 1.059
2 0.920 0.150 0.276
W.C. 3 4.700 0.150 2.115
Outside (Below Ground Lvl.)
FRONT SIDE 1 5.490 0.150 0.824
LEFT SIDE 1 8.910 0.150 1.337
REAR SIDE 1 9.020 0.150 1.353
RIGHT SIDE 1 3.990 0.150 0.599
Page 182
1 3.530 0.150 0.530
1 4.920 0.150 0.738
TOTAL 15.815 SQM
17 15mm cement plaster (Interior surface)
(a) G.F.
MALE TOILET 1 5.030 1.280 6.438
2 3.530 1.280 9.037
1 2.370 1.280 3.034
FEMALE TOILET 2 3.300 1.280 8.448
2 3.530 1.280 9.037
LOBBY 2 2.510 1.280 6.426
1 5.035 1.280 6.445
1 2.365 1.280 3.027
1 1.365 1.280 1.747
STAIRCASE 2 5.035 3.380 34.037
2 1.950 3.380 13.182
TOTAL 100.857 SQM
DEDUCTION
D 3 1.000 0.450 1.350
V 6 0.450 0.450 1.215
V1 1 0.900 0.450 0.405
TOTAL 2.970 SQM
NET TOTAL 97.887 SQM
(b) F.F.
STAIRCASE 2 5.035 3.380 34.037
2 1.950 3.380 13.182
VERANDAH 2 5.375 3.380 36.335
ROOM 2 5.030 3.380 34.003
2 3.530 3.380 23.863
TOTAL 141.419 SQM
DEDUCTION (-)
D 2 1.000 2.550 5.100
W2 1 1.500 1.650 2.475
TOTAL 7.575 SQM
NET TOTAL 133.844 SQM
18 12mm thick plaster (outer side)
(a) GROUND FLOOR
FRONT SIDE 1 5.490 4.100 22.509
LEFT SIDE 1 8.910 4.100 36.531
REAR SIDE 1 9.020 4.100 36.982
RIGHT SIDE 1 3.990 4.100 16.359
1 3.530 4.100 14.473
1 4.920 4.100 20.172
ENTRANCE STEP PARAPET 1 1.800 1.430 2.574
2 0.900 1.430 2.574
TOTAL 152.174 SQM
(b) FIRST FLOOR
FRONT SIDE 1 5.490 3.500 19.215
LEFT SIDE 1 8.910 3.500 31.185
REAR SIDE 1 5.490 3.500 19.215
RIGHT SIDE 1 3.990 3.500 13.965
1 2.480 3.500 8.680
VERANDAH PARAPET 1 2.440 2.015 4.917
TERRACE PARAPET 1 6.730 2.015 13.561
2 3.300 2.015 13.299
UPPER TERRACE PARAPET 2 8.910 0.930 16.573
2 5.030 0.930 9.356
TOTAL 149.965 SQM
19 6mm thick plaster on Ceiling in 1:3
(a) G.F.
VERANDAH 1 3.530 2.740 9.672
LOBBY 1 5.030 2.510 12.625
MALE TOILET 1 5.030 3.530 17.756
Page 183
FEMALE TOILET 1 3.300 3.530 11.649
STAIRCASE VERANDAH 1 1.950 0.750 1.463
STAIRCASE 1 5.030 1.950 9.809
CHAZZA
STAIRCASE - D 1 2.180 0.750 1.635
STAIRCASE - W1 1 1.660 0.600 0.996
LOBBY - W 1 1.660 0.600 0.996
MALE TOILET - V/V/V 1 2.960 0.600 1.776
MALE TOILET - W 1 1.660 0.600 0.996
MALE TOILET - V1 1 1.360 0.600 0.816
FEMALE TOILET - W 1 1.430 0.600 0.858
FEMALE TOILET - V/V/V 1 2.960 0.600 1.776
TOTAL 72.822 SQM
(b) F.F.
STAIRCASE 1 5.030 1.950 9.809
VERANDAH 1 5.375 2.510 13.491
ROOM 1 5.030 3.530 17.756
CHAZZA 0.000
ROOM - W2 1 1.960 0.600 1.176
TOTAL 42.232 SQM
20 Making grooves.
G.F.
VERANDAH 1 6.270 6.270
LOBBY 1 15.080 15.080
MALE TOILET 1 22.600 22.600
FEMALE TOILET 1 13.660 13.660
STAIRCASE 1 13.970 13.970
F.F.
STAIRCASE 1 13.970 13.970
VERANDAH 1 15.770 15.770
ROOM 1 17.120 17.120
TOTAL 118.440 RM
21 Kota Stone Flooring
(a) G.F.
VERANDAH/STEPS 1 4.430 2.740 12.138
STAIRCASE (BELOW FLIGHT/LANDING) 1 5.030 1.950 9.809
STAIR ENTRANCE STEPS 1 2.180 1.726 3.763
TOTAL 25.709 SQM
(b) F.F.
VERANDAH 1 5.375 2.510 13.491
STAIRCASE 1 5.030 1.950 9.809
TOTAL 23.300 SQM
22 Kota Stone Skirting
(a) G.F.
VERANDAH 1 6.270 0.150 0.941
STAIRCAE 1 13.960 0.150 2.094
STAIR STEPS 21 0.900 0.150 2.835
ENT STEPS 4 2.180 0.150 1.308
4 2.510 0.150 1.506
TOTAL 8.684 SQM
(b) F.F.
VERANDAH 1 13.260 0.150 1.989
TOTAL 1.989 SQM
23 Ceremic tiles flooring & dado
(a) G.F.
FLOOR TILES
MALE TOILET LOBBY 1 5.030 2.510 12.625
MALE TOILET 1 3.665 3.530 12.937
W.C. 2 1.250 1.100 2.750
JANITOR 1 1.250 1.215 1.519
FEMALE TOILET 1 1.935 3.530 6.831
W.C. 3 1.250 1.100 4.125
Page 184
WALL TILES
MALE TOILET LOBBY 1 5.035 2.100 10.574
2 2.510 2.100 10.542
1 2.365 2.100 4.967
1 1.365 2.100 2.867
MALE TOILET 1 2.365 2.100 4.967
2 3.530 2.100 14.826
1 3.665 2.100 7.697
2 0.750 2.100 3.150
W.C. 2 4.700 2.100 19.740
JANITOR 1 4.930 2.100 10.353
FEMALE TOILET 2 1.935 2.100 8.127
2 3.530 2.100 14.826
2 0.920 2.100 3.864
W.C. 3 4.700 2.100 29.610
TOTAL 186.895 SQM
DEDUCTION (-)
D2 2 1.000 2.100 4.200
D3 6 0.750 2.100 9.450
TOTAL 13.650 SQM
TOTAL 173.245 SQM
24 C.C. Flooring
ROOM 1 5.030 3.530 17.756
APRON 2 10.520 0.750 15.780
2 8.900 0.750 13.350
TOTAL 46.886 SQM
25 C.C. skirting
ROOM 1 17.120 0.150 2.568
TOTAL 2.568 SQM
26 P/L glass strip
ROOM 1 5.030 3.530 4.000 71.024
TOTAL 71.024 RM
27 Flush door
D 5 1.000 2.100 10.500
D1 6 0.750 2.100 9.450
TOTAL 19.950 SQM
28 Fixing D/W/V Chaukhats.
Door chaukhats 11.000 NOS
Window chaukhats 5.000 NOS
Ventilator chaukhats 7.000 NOS
29 M.S.Work in D/W
(a) Hold fast
DOORS 11 6.000 0.600 39.600
WINDOWS 5 4.000 0.600 12.000
VENTILATORS 7 2.000 0.600 8.400
TOTAL 60.000 KG
(b) M.S.Grill & Railing
D 5 1.000 0.450 20.000 45.000
W 3 1.200 1.650 20.000 118.800
W1 1 1.200 1.650 20.000 39.600
W2 1 1.500 0.450 20.000 13.500
V 6 0.450 0.450 20.000 24.300
V1 1 0.900 0.450 20.000 8.100
STAIR RAILING 1 3.305 0.900 20.000 59.490
1 2.995 0.900 20.000 53.910
TOTAL 362.700 KG.
(c) Z-Section Windows
W 3 1.200 1.650 20.000 118.800
W1 1 1.200 1.650 20.000 39.600
W2 1 1.500 0.450 20.000 13.500
Page 185
V 6 0.450 0.450 20.000 24.300
V1 1 0.900 0.450 20.000 8.100
TOTAL 204.300 KG.
(d) Angle iron
D 5 7.100 3.600 127.800
D1 6 4.950 3.600 106.920
234.720 KG.
30 Glass panes
D 5 1.000 0.450 2.250
W 3 1.200 1.650 5.940
W1 1 1.200 1.650 1.980
W2 1 1.500 0.450 0.675
V 6 0.450 0.450 1.215
V1 1 0.900 0.450 0.405
TOTAL 12.465 SQM
31 Oil bound distemper (Inner walls)
Qty Same as Inside plaster TOTAL 231.73 SQM
33 Snowcem painting
Qty Same as outer plaster TOTAL 302.14 SQM
41 Thin shelves
MALE TOILET 1 3.080 0.830 2.556
FEMALE TOILET 1 2.745 0.830 2.278
TOTAL 4.835 SQM
42 Granite Top .
Page 186
MALE TOILET 1 2.850 0.600 1.710
FEMALE TOILET 1 2.400 0.600 1.440
TOTAL 3.150 SQM
43 C.C. 1:2:4
HOLD FAST 100 0.150 0.100 0.100 0.150
TERRACE PARAPET 1 6.730 0.330 0.100 0.222
2 3.300 0.330 0.100 0.218
UPPER TERRACE PARAPET 2 8.910 0.330 0.100 0.588
2 5.030 0.330 0.100 0.332
NET TOTAL 1.510 CUM
Page 187
CONSUMPTION OF MATERIALS (TOILET BLOCK)
ABSTRACT OF COST
#REF!
(a) Fabrication of hold fast for door chaukhats and windows. 12.00 KG 65.00 780.00
36 Same as item 35 above but on new wood surf #REF! 4.200 SQM 55.00 231.00
TOTAL #REF!
DETAILES OF MEASUREMENT
Page 194
1 1.800 0.230 0.230 0.095
TOTAL 0.164 CUM
8 R.C.C.work in raft foundation
FT1 1 0.900 0.900 0.150 0.122
1*0.15/6*(0.9*0.9+0.38*0.38+4*0.64*0.64) 0.065
1 0.380 0.380 0.200 0.029
TOTAL 0.215 CUM
9 R.C.C.work in Column
C1 1 0.230 0.230 4.425 0.234
TOTAL 0.234 CUM
10 B/W In foundation
SECTION 1-1
1 0.875 0.230 0.675 0.136
1 0.875 0.345 0.075 0.023
1 0.875 0.460 0.150 0.060
SECTION 2-2 0.000
2 4.030 0.230 0.675 1.251
2 4.030 0.345 0.150 0.417
2 4.030 0.460 0.075 0.278
2 4.030 0.575 0.150 0.695
2 3.830 0.230 0.675 1.189
2 3.830 0.345 0.150 0.396
2 3.830 0.460 0.075 0.264
2 3.830 0.575 0.150 0.661
2 1.650 0.230 0.675 0.512
2 1.650 0.345 0.150 0.171
2 1.650 0.460 0.075 0.114
2 1.650 0.575 0.150 0.285
1 1.830 0.230 0.675 0.284
1 1.830 0.345 0.150 0.095
1 1.830 0.460 0.075 0.063
1 1.830 0.575 0.150 0.158
STEPS 1 1.800 0.600 0.300 0.324
1 1.800 0.300 0.150 0.081
TOTAL 7.457 CUM
11 25mm thick D.P.C
2 4.260 0.230 1.960
2 3.600 0.230 1.656
2 1.800 0.230 0.828
1 3.200 0.230 0.736
TOTAL 5.180 SQM
DEDUCTION (-)
D 2 1.000 0.230 0.460
TOTAL 0.460 SQM
TOTAL 4.720 SQM
12 Bitumen Painting on D.P.C.
PLINTH BAND 2 4.260 0.230 1.960
2 3.600 0.230 1.656
2 1.800 0.230 0.828
1 3.200 0.230 0.736
TOTAL 5.180 SQM
DEDUCTION (-)
D 2 1.000 0.230 0.460
TOTAL 0.460 SQM
TOTAL 4.720 SQM
13 B/W In Superstructure (230 mm thick) 0.000
2 4.260 0.230 3.175 6.222
2 3.600 0.230 3.175 5.258
2 1.800 0.230 3.175 2.629
1 3.200 0.230 3.175 2.337
Page 195
TOTAL 16.445 CUM
DEDUCTION (-)
D 2 1.000 0.230 2.100 0.966
W 2 1.500 0.230 1.200 0.828
TOTAL 1.794 CUM
NET TOTAL 14.651 CUM
14 B/W In Superstructure (115 mm thick) 0.000
PARAPET WALL 2 6.090 0.115 0.300 0.420
2 4.260 0.115 0.300 0.294
TOTAL 0.714 CUM
15 M. S. work in R.C.C.
qty same as item no (5)*1.0*0.785 (Lintel) 1.269
qty same as item no (6)*1.0*0.785 (Slab) 2.565
qty same as item no (7)*2.0*0.785 (Beam) 0.258
qty same as item no (8)*1.0*0.785 (Raft) 0.169
qty same as item no (9)*3.5*0.785 (Column) 0.643
TOTAL 4.903 QTL
16 12mm thick plinth plaster in 1:4
Inside (Below Plinth Lvl.)
PUMP ROOM 1 14.800 0.150 2.220
CHLORINATOR ROOM 1 6.800 0.150 1.020
VERANDAH 1 3.400 0.150 0.510
Outside (Below Ground Lvl.)
OUTER 2 6.090 0.150 1.827
2 4.260 0.150 1.278
TOTAL 6.855 SQM
17 15mm cement plaster (Interior surface)
PUMP ROOM 1 14.800 3.325 49.210
CHLORINATOR ROOM 1 6.800 3.325 22.610
VERANDAH 1 3.400 3.325 11.305
TOTAL 83.125 SQM
DEDUCTION
D 2 1.000 2.100 4.200
W 2 1.500 1.200 3.600
TOTAL 7.800 SQM
NET TOTAL 75.325 SQM
18 12 mm Thick plaster (outer side)
OUTER 2 6.090 3.900 47.502
2 4.260 3.900 33.228
PARAPET WALL 2 6.090 0.715 8.709
2 4.260 0.715 6.092
TOTAL 95.531 SQM
19 6mm thick plaster (ceiling) in 1:3
1 3.600 3.800 13.680
1 1.800 1.600 2.880
1 1.800 1.140 2.052
W 2 1.96 0.60 2.352
TOTAL 20.964 SQM
20 Making grooves
PUMP ROOM 1 14.800 14.800
CHLORINATOR ROOM 1 6.800 6.800
VERANDAH 1 3.400 3.400
TOTAL 25.000 RM
Page 196
22 C.C. Skirting
PUMP ROOM 1 14.800 0.150 2.220
CHLORINATOR ROOM 1 6.800 0.150 1.020
VERANDAH 1 3.400 0.150 0.510
TOTAL 3.750 SQM
25 Flush Door
D 1 1.000 2.100 2.100
TOTAL 2.100 SQM
26 Fixing D/W/V Chaukhats.
Door chaukhats 2.000 NOS
Window chaukhats 2.000 NOS
27 Glass panes
W 2 1.500 1.200 3.600
TOTAL 3.600 SQM
0.000
34 Plain C.C. for hold fast
HOLD FAST 20 0.150 0.100 0.100 0.030
TOTAL 0.030 CUM
35 Steel painting
Angle iron
D 2 1.000 2.100 0.600 2.520
Grills
W 2 1.500 1.200 2.000 7.200
Z-SECTION
Page 197
W 2 1.500 1.200 2.000 7.200
TOTAL 16.920 SQM
36 Painting on wood.
Same as Item No. (25)X2 4.200
TOTAL 4.200 SQM
Page 198
CONSUMPTION OF MATERIALS (PUMP ROOM)
ABSTRACT OF COST
#REF!
TOTAL #REF!
DETAILS OF MEASUREMENT
5 Anti-termite treatment
PL. AREA+APRON AREA TOTAL 68.400 SQM
6 R.C.C.work in Lintel
PLINTH BAND
BATH 2 1.430 0.230 0.150 0.099
2 0.635 0.230 0.150 0.044
W.C. 2 1.360 0.230 0.150 0.094
2 1.200 0.230 0.150 0.083
KITCHEN 2 0.585 0.230 0.150 0.040
2 1.830 0.230 0.150 0.126
2 2.400 0.230 0.150 0.166
DRG. ROOM 2 3.525 0.230 0.150 0.243
2 4.710 0.230 0.150 0.325
2 3.465 0.230 0.150 0.239
BED ROOM 2 2.930 0.230 0.150 0.202
1 3.310 0.230 0.150 0.114
BATH 2 1.200 0.230 0.150 0.083
2 1.430 0.230 0.150 0.099
2 0.750 0.230 0.150 0.052
2 1.430 0.230 0.150 0.099
W.C. 2 1.015 0.230 0.150 0.070
2 1.200 0.230 0.150 0.083
LINTAL BAND 0.000
BATH 2 1.430 0.230 0.150 0.099
2 0.635 0.230 0.150 0.044
W.C. 2 1.360 0.230 0.150 0.094
2 1.200 0.230 0.150 0.083
KITCHEN 2 0.585 0.230 0.150 0.040
2 1.830 0.230 0.150 0.126
2 2.400 0.230 0.150 0.166
DRG. ROOM 2 3.525 0.230 0.150 0.243
2 4.710 0.230 0.150 0.325
2 3.465 0.230 0.150 0.239
BED ROOM 2 2.930 0.230 0.150 0.202
1 3.310 0.230 0.150 0.114
BATH 2 1.200 0.115 0.150 0.041
2 1.430 0.115 0.150 0.049
2 0.750 0.115 0.150 0.026
2 1.430 0.115 0.150 0.049
W.C. 2 1.015 0.115 0.150 0.035
2 1.200 0.115 0.150 0.041
TOTAL 4.277 CUM
8 R.C.C.work in beams
BEAM
B1 1 2.180 0.230 0.300 0.150
HB2 2 1.430 0.230 0.135 0.089
2 1.130 0.230 0.135 0.070
TOTAL 0.309 CUM
9 R.C.C.work in thinselves
KITCHEN 2 1.600 0.600 1.920
2 1.800 0.600 2.160
DRG. ROOM 2 0.895 0.600 1.074
BED ROOM 2 0.750 0.600 0.900
TOTAL 6.054 SQM
10 B/W in foundation
SECTION 1-1
LOBBY 1 1.950 0.230 0.450 0.202
1 1.950 0.345 0.300 0.202
1 1.950 0.460 0.150 0.135
SECTION 2-2 0.000
BATH 1 2.180 0.230 0.450 0.226
1 2.180 0.345 0.300 0.226
1 2.180 0.460 0.150 0.150
2 1.200 0.230 0.450 0.248
2 1.200 0.345 0.300 0.248
2 1.200 0.460 0.150 0.166
2 1.200 0.230 0.450 0.248
2 1.200 0.345 0.300 0.248
2 1.200 0.460 0.150 0.166
1 0.900 0.230 0.450 0.093
1 0.900 0.345 0.300 0.093
1 0.900 0.460 0.150 0.062
TOILET 2 1.200 0.230 0.450 0.248
2 1.200 0.345 0.300 0.248
2 1.200 0.460 0.150 0.166
1 2.180 0.230 0.450 0.226
1 2.180 0.345 0.300 0.226
1 2.180 0.460 0.150 0.150
1 1.200 0.230 0.450 0.124
1 1.200 0.345 0.300 0.124
1 1.200 0.460 0.150 0.083
SECTION 3-3 0.000
KITCHEN 2 2.860 0.230 0.450 0.592
2 2.860 0.345 0.675 1.332
2 2.860 0.460 0.150 0.395
2 2.860 0.575 0.075 0.247
2 2.860 0.690 0.150 0.592
4 1.600 0.230 0.450 0.662
4 1.600 0.345 0.675 1.490
4 1.600 0.460 0.150 0.442
4 1.600 0.575 0.075 0.276
4 1.600 0.690 0.150 0.662
BATH 2 1.430 0.230 0.450 0.296
2 1.430 0.345 0.675 0.666
2 1.430 0.460 0.150 0.197
2 1.430 0.575 0.075 0.123
2 1.430 0.690 0.150 0.296
2 1.200 0.230 0.450 0.248
2 1.200 0.345 0.675 0.559
2 1.200 0.460 0.150 0.166
2 1.200 0.575 0.075 0.104
2 1.200 0.690 0.150 0.248
BED ROOM 4 2.700 0.230 0.450 1.118
4 2.700 0.345 0.675 2.515
4 2.700 0.460 0.150 0.745
4 2.700 0.575 0.075 0.466
4 2.700 0.690 0.150 1.118
1 3.540 0.230 0.450 0.366
1 3.540 0.345 0.675 0.824
1 3.540 0.460 0.150 0.244
1 3.540 0.575 0.075 0.153
1 3.540 0.690 0.150 0.366
DRG. ROOM 4 3.470 0.230 0.450 1.437
4 3.470 0.345 0.675 3.232
4 3.470 0.460 0.150 0.958
4 3.470 0.575 0.075 0.599
4 3.470 0.690 0.150 1.437
2 2.925 0.230 0.450 0.605
2 2.925 0.345 0.675 1.362
2 2.925 0.460 0.150 0.404
2 2.925 0.575 0.075 0.252
2 2.925 0.690 0.150 0.605
TOTAL 32.709 CUM
11 D.P.C.
BATH 2 1.430 0.254 0.726
2 0.635 0.254 0.323
W.C. 2 1.360 0.254 0.691
2 1.200 0.254 0.610
KITCHEN 2 0.585 0.254 0.297
2 1.830 0.254 0.930
2 2.400 0.254 1.219
DRG. ROOM 2 3.525 0.254 1.791
2 4.710 0.254 2.393
2 3.465 0.254 1.760
BED ROOM 2 2.930 0.254 1.488
1 3.310 0.254 0.841
BATH 2 1.200 0.139 0.334
2 1.430 0.139 0.398
2 0.750 0.139 0.209
2 1.430 0.139 0.398
W.C. 2 1.015 0.139 0.282
2 1.200 0.139 0.334
TOTAL 15.021 SQM
DEDUCT 0.000
D1 4 1.000 0.254 1.016
D2 4 0.900 0.254 0.914
D3 4 0.750 0.139 0.417
CD 1 2.000 0.254 0.508
TOTAL 2.855 SQM
NET TOTAL 12.166 SQM
12 Painting on DPC
4.100 TOTAL 12.166 SQM
13 B/W in super-structure
BATH 2 1.430 0.230 2.790 1.835
2 0.635 0.230 2.790 0.815
W.C. 2 1.360 0.230 2.790 1.745
2 1.200 0.230 2.790 1.540
KITCHEN 2 0.585 0.230 2.790 0.751
2 1.830 0.230 2.790 2.349
2 2.400 0.230 2.790 3.080
DRG. ROOM 2 3.525 0.230 2.790 4.524
2 4.710 0.230 2.790 6.045
2 3.465 0.230 2.790 4.447
BED ROOM 2 2.930 0.230 2.790 3.760
1 3.310 0.230 2.790 2.124
TOTAL 33.015 CUM
DEDUCT
D1 4 1.000 0.230 2.100 1.932
D2 2 0.900 0.230 2.100 0.869
CD 1 2.000 0.230 2.100 0.966
W1 2 1.800 0.230 1.200 0.994
W2 2 1.500 0.230 1.200 0.828
W3 2 0.900 0.230 1.050 0.435
V 4 0.600 0.230 0.600 0.331
TOTAL 6.355 CUM
NET TOTAL 26.661 CUM
14 B/W in super-structure(115 thick)
BATH 2 1.200 0.115 2.790 0.770
2 1.430 0.115 2.790 0.918
2 0.750 0.115 2.790 0.481
2 1.430 0.115 2.790 0.918
W.C. 2 1.015 0.115 2.790 0.651
2 1.200 0.115 2.790 0.770
PARAPET WALL 2 12.150 0.115 0.900 2.515
2 6.290 0.115 0.900 1.302
TOTAL 8.325 CUM
DEDUCTION
D2 2 0.900 0.115 2.100 0.435
D3 4 0.750 0.115 2.100 0.725
TOTAL 1.159 CUM
NET TOTAL 7.166 CUM
20 M. S. work in R.C.C.
qty same as item no (6)*1.0*0.785 (LINTEL) 3.358
qty same as item no (7)*1.0*0.785 (SLAB) 7.343
qty same as item no (8)*2*0.785 (BEAM) 0.486
qty same as item no (9)*0.6*0.785 (THIN SHELVES) 2.851
TOTAL 14.037 QTL
21 Fixing D/W/V Chaukhats.
Door chaukhats 12.000 NOS
Window chaukhats 6.000 NOS
Ventilator Chaukhats 6.000 NOS
22 12 mm plinth plaster
OUTER 2 4.244 0.150 1.273
2 10.900 0.150 3.270
2 3.385 0.150 1.016
INNER 0.000
BATH 2 4.800 0.150 1.440
W.C. 2 4.200 0.150 1.260
2 3.460 0.150 1.038
KITCHEN 2 8.000 0.150 2.400
BED ROOM 2 11.560 0.150 3.468
2 0.900 0.150 0.270
2 4.200 0.150 1.260
DRG. ROOM 2 11.350 0.150 3.405
2 0.970 0.150 0.291
LOBBY 1 9.630 0.150 1.445
TOTAL 21.835 SQM
23 12 mm cement plaster G.F. (Outer face)
OUTER 2 4.244 3.050 25.888
2 10.900 3.050 66.490
2 3.385 3.050 20.649
PARAPET WALL 4 12.150 0.900 43.740
4 6.250 0.900 22.500
TOTAL 179.267 SQM
32 Snowcem painting
SAME AS ITEM NO. (23) 179.267 SQM
34 White washing
SAME AS ITEM NO.(25) 67.532 SQM
35 Glass panes
W1 2 1.800 1.200 4.320
W2 2 1.500 1.800 5.400
W3 2 0.900 1.200 2.160
V 4 0.600 0.700 1.680
TOTAL 13.560 SQM
36 Sliding bolt. 12.000 NOS
39 Glass Strip
SAME AS ITEM NO. (28)*6 TOTAL 494.584 RM
CONSUMPTION OF MATERIALS (CHECK POST)
-
A.R.-I
ANALYSIS OF RATES
Carted
197.00
Carted
197.00
(A) MATERIALS
(a) CIDF Swing type Non Return Valve as per IS
5312 (Part 1 & 2) PN 1.6 CI Body, Door Bronze
to Rubber rings/SS 410 Hinge Pin construction
NO. 10.000 30180.00 301800.00
(b) Carriage of C.I. fittings Tonne 0.44 94.80 41.71
(c) Labour for laying valve (Rate as per Item No.
18.24 of SH : Water supply (DSR-2013) Qtl 4.430 221.27 980.23
(d) Providing glanged joints to sluice valves with
bolts, nuts and rubber insertion etc. (Rate as
per Item No. 18.30.2 of SH: Water supply)
Each 20.000 181.38 3627.60
TOTAL 306449.54
Add 1 % for water charges except Item No. C & @ 1% of Rs. ### 3018.42
TOTAL 309467.96
Add 10% for contractor’s profit Except Item No. @ 10% of Rs ### 30486.01
C & Dof 10.00 Nos.
Cost TOTAL 339953.97
Cost of 1.0 No. SAY RS. 33995.00
Analysis of Rate for C.I. Sluice Valve 65mm dia for fire hydrant
(A) MATERIALS
(a) CIDF Non Rising Spindle Sluice Valve PN 1.6 IS
14846, CI Body/ Wedge/Bronze rings/ SS 410
Shaft Construction & SS IS : 6603 Gr 12 Cr 12 IN
(ISI Marked) Body, Door Bronze to Rubber
rings/SS 410 Hinge Pin construction
NO. 10.00 ### 127550.00
(b) Carriage of C.I. fittings Tonne 0.44 94.80 41.71
(c) Labour for laying valve (Rate as per Item No.
18.24 of SH : Water supply (DSR-2013) Qtl 4.430 221.27 980.23
(d) Providing glanged joints to sluice valves with
bolts, nuts and rubber insertion etc. (Rate as
per Item No. 18.30.2 of SH: Water supply)
Each 20.000 181.38 3627.60
TOTAL 132199.54
Add 1 % for water charges except Item No. C & @ 1% of Rs. ### 1275.92
TOTAL 133475.46
Add 10% for contractor’s profit Except Item No. @ 10% of Rs. ### 12886.76
C & Dof 10.00 Nos.
Cost TOTAL 146362.22
Cost of 1.0 No. SAY RS. 14635.00
#REF!
#REF!
DETAILES OF MEASUREMENT
5 M. S. work in R.C.C.
qty same as item no (3) 1 1.580 0.785 1.000 1.24
qty same as item no (4) 1 7.540 0.785 3.500 20.72
TOTAL 21.96 QTL
6 Water proof painting
C1 2 3.000 6.000 36.00
TOTAL 36.00 SQM
7 M.S. work
GATE 1 12.000 2.100 85.000 2142.00
TOTAL 2142.00 KG
PRAVACHAN HALL
1 COST OF CONSTRUCTION
GROUND FLOOR 316.84 SQM. 9840.00 31.18
TOTAL 316.84 SQM. TOTAL 31.18
TOTAL 53.66