General Arrangement Drawing For Major Bridge at CH.: 273.075 (CA DESIGN CH.: 273.069) Drg. No. Date: March 2020

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 2

CLIENT: INDEPENDENT ENGINEER : CONCESSIONARE: EPC CONTRACTOR : DESIGN CONSULTANT : PROJECT : DRAWING TITLE :

4-laning of Amravati to Chickle Section of DRG. NO. CIPL/D1033/MJBR/GAD/DWG/101 (SH. 1 OF 2)


GENERAL ARRANGEMENT DRAWING
NH-6 from Km 166.000 to Km 360.000
(Package-I) in the state of Maharashtra FOR MAJOR BRIDGE @ CH.: 273.075 DATE : MARCH 2020 REV: R0
to be executed as BOT (Toll) project (CA DESIGN CH.: 273.069) CHECKED APPROVED
R0 MARCH 20 DESIGNED DRAWN
on DBFOT pattern under NHDP Phase III
REV DATE DESCRIPTION A B C D NS LS GS SK
SCALE : AS SHOWN PAPER SIZE : A3
A2
CLIENT: INDEPENDENT ENGINEER : CONCESSIONARE: EPC CONTRACTOR : DESIGN CONSULTANT : PROJECT : DRAWING TITLE :
4-laning of Amravati to Chickle Section of DRG. NO. CIPL/D1033/MJBR/GAD/DWG/101 (SH. 2 OF 2)
GENERAL ARRANGEMENT DRAWING
NH-6 from Km 166.000 to Km 360.000
(Package-I) in the state of Maharashtra FOR MAJOR BRIDGE @ CH.: 273.075 DATE : MARCH 2020 REV: R0
to be executed as BOT (Toll) project (CA DESIGN CH.: 273.069) CHECKED APPROVED
R0 MARCH 20 DESIGNED DRAWN
on DBFOT pattern under NHDP Phase III
REV DATE DESCRIPTION A B C D NS LS GS SK
SCALE : AS SHOWN PAPER SIZE : A3
A2