Download as pdf or txt
Download as pdf or txt
You are on page 1of 12

Project Name : High Rise Residential Development (Abdali Views)

Employer Representative Design & Supervision Consultant Contract Administrator Contractor

DAILY REPORT
Date: Thursday, May 07, 2020 Ref #: DPR 472
II. Manpower
Indirect Project Staff  Working Hours 7 (Ramadan)
Description QTY. Description QTY.
Project Manager 1 Office Boy 2
Planning Manager 1 Storekeeper 1
Construction Manager 1 Storekeeper assistant 1
Finishing Manager   Lab technician 1
Technical Manager 1 Guard 4
Electrical Manager 1 Nurse 1
Mechanical Manager 1 Electrical Foreman 2
QA/QC Manager 1 Quantity surveyor 1
Safety Manager 1 Mechanical technical Engineer 2
Electrical Engineer 3
Mechanical Engineer 2
Technical Engineer 1
Safety Officer 1
Planning / Cost Engineer 2
Document Control 1
Electrical Drafts man 1
Mechanical Drafts man 2
Civil Site Engineer 3
Civil Drafts man 1
Civil Foreman 6
Mechanical Foreman 3
Accountant 2
Surveyor 1
Surveyor assistant 1
Office Boy 6 Working online 
Total Indirect stuff 59
Works are going partially at the site because of the manpower has been reduced due to the authorities' regulations to insulate areas.
Direct Stuff Working Hours  : 7 hours (Ramadan)
Description QTY. Description QTY.
Carpenter 7 Isolation team
Carpenter Assistant 8 Stone installer 15
Labor 10 Gypsum board team
Steel Fixers Tiling team 23
Rigger 2 Welder
Operators & Drivers 8 Aluminium installaton team
Tower Crain Installation Team Plumber 8
Concrete service team Plumber Assistant 4
Block Builder 0 Duct man 7
Block Builder Assistant 0 Duct man Assistant 2
Plasterer Insulator 3
Plasterer Assistant Insulator  Assistant 2
Painter Electrician  18
Concrete repair team 11 Electrician Assistant 6
Scaffolder
Total Direct stuff 134
Works are going partially at the site because of the manpower has been reduced due to the authorities' regulations to insulate areas.
Working Machinery
Description QTY. Description QTY.
Excavator 0 Tower light 1
Truck  1 Electrical Generator 1
Loader 0 Shoring Machine 0
LB 3 Coring Machine 0
JCB 2 Air Compressor 3
Bobcat 1 Bus (22 passengers) 1
Flat bed with crane (8 Ton) 1 Bus (50 passengers) 3
Mobile Crane 30 Ton 1 Pickups 3
Mobile Crane 45 Ton 0 Steel Cutting Machine 3
Roller 3 ton 1 Steel bending Machine 4
Mini Roller 1 Forklift 2
Container 12 ft 2 Tower Crain 2
Container 20 ft 4 Concrete vibratos 12
Concrete Pumps 0 Concrete Mixer 6
Mini LB 1 Man hoist 2
Water Tank 1 1 of 3
Project Name : High Rise Residential Development (Abdali Views)

Employer Representative: Design & supervision Consultant: Contract Administrator Contractor:

DAILY REPORT
Date: Thursday, May 07, 2020 Ref #: DPR 472
I. Major Works Status
A) Civil Works Zone / Area Approx. Executed QTY.
Work Done
1 Water Proofing at Wet Areas 5th

2 Tiling 3rd,5th

4 Water Proofing  3rd‐5th

Planned Work for Next Working Day
1 Water Proofing at Wet Areas 5th

2 Tiling 3rd‐5th

3 Stone installation 16th

4 Water Proofing  3rd‐5th

B) Mechanical Works Zone / Area
Work Done
1 Drainage installation 1st,8th,18th

2 Ducting works 2nd

3 Insulation pipe & duct 5th‐8th

4 Installation FCU 14th

Planned Work for Next Working Day
1 Drainage installation 1st,8th,18th

2 Ducting works 2nd

3 Insulation pipe & duct 5th‐8th

4 Installation FCU 14th

C) Electrical Works Zone / Area
Work Done
1 1st fix PVC conduits installation under tiles for power system 13th 

2  1st fix PVC conduits and Back boxes  installa on in the walls for electrical systems 22nd

5 Installation copper tape for lightning protection system External walls

Planned Work for Next Working Day
1  1st fix PVC conduits  installa on under  les for power system 12th,13th

2  1st fix PVC conduits and Back boxes  installa on in the walls for electrical systems 22nd

3 2nd fix wires pulling for lighting system at corridor area 21th

4 installation back boxes of FDB'S for all apartments 21th

5 Installation copper tape for lightning protection system External walls

2 of 3
Project Name : High Rise Residential Development (Abdali Views)

Employer Representative Design & Supervision Consultant Contract Administrator Contractor:

DAILY REPORT
Date: Thursday, May 07, 2020 Ref #: DPR 472
III. MATERIALS DELIVERD TO SITE
Material Description Quantity Unit

Weather: Cloudy

Weather :  Average Temperature: 20/12°C

Average wind speed : 25 km/h

IV. Meetings & Site visits:

V. Notes:
1 Works are going partially at the site because of the manpower has been reduced due to the authorities' regulations to insulate areas.

VI. Accident:

Submission Date:
Contract: Mohammed Hamaideh Signature:
10‐May‐2020

 Receipt Date:
Contract Administrator: Isam Hamdan Signature:
‐May‐2020

3 of 3
 
Abdali Views Pr oject  
COV
VID‐19 Health
h & Safety preevention meaasures 

7th May 20220 

 Complying with local au
uthorities’ reccommendatio on by loadingg 50% of actu
ual seats to keep safe 
between worrkers with fulll compliancee of wearing m
distance b mask and glo oves and usinng hand 
sterilizzing. 

      

   

 
 
Abdali Views Pr oject  
 

• Workers screening at entry o
of project gate
e (flu‐like sym
mptoms such h as fever, tireedness, coughing, or 
congestio
on or high bo
ody temperatture) with full implementaation of wearring disposab ble mask and gloves and 
respecting safe social distance. 

     

   

   
 
Abdali Views Pr oject  
   

   

   

   

   

    
 
Abdali Views Pr oject  
    

 Stterilizing worrkers busses &
& staff vehiclles.  
 

   

   
 

   
 
 
Abdali Views Pr oject  
 

       
 
 

       
 
 
 
 
 
 
 
 
 
 
Abdali Views Pr oject  
 

 Conducting COVID‐19 prrevention me
easures awareeness to all ssite workers tthrough smalll groups. 
 
 

     
 

     
 
 
 
 
 
 
 
 
 
Abdali Views Pr oject  
 

 Respecting soccial distance during workss and projectt hoists use.

     

   

 
 
Abdali Views Pr oject  
 

 Esstablishing Hand Sterilizin
ng stations att project engiineers, Admin
n & safety sitte offices.  
 

 
 

       
   
 
Abdali Views Pr oject  
   

 Stterilizing projject offices, kkitchens, toile
ets, hoists, seecurity kioskss etc. 

   

     

     

     

     

   

  

You might also like