Saudi Aramco Test Report: Final Inspection/Re-Instatement Punch List

You might also like

Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 17

SAUDI ARAMCO ID/PIEU-15-July-2018-REV. 2018.05.00(Standards Cutoff - May 31,2018) Rev.2018.05.

00 31-May-18

SAUDI ARAMCO TEST REPORT SATR NUMBER DATE SUBMITTED DISCIPLINE

SATR-A-6133 Civil / Plumb


Final Inspection/Re-Instatement Punch List 24-Mar-16 Electrical
(Punch List by Contractor)
FEIL-Mech Mechanical
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR

MCC No.: Test Package No.:


System Description:
Originator/Agency: Approved By:

Covered Req'd for


Verified/
ITEMApproved By: By Scope Start-Up Completion
No. Description (Item entry date) Date Accepted Remarks
(scheduled) By:
Y/N Y/N

GENERAL
Provide proper ID for all equipment. ID numbers shall be legible
1.1 from 50 feet for process equipment
Remove all rust preventatives, oil, grease, etc. used to
preserve equipment during construction, and install proper
1.2 lubricants after review with Operations.

At time of turnover, all fire proofing and rough insulation shall


be complete. All equipment, piping, instruments, instruments
leads, etc. requiring insulation for heat conservation or proper
operation shall be covered so that startup operations will not be
1.3 delayed due to excessive heat loss. Insulation required for
personnel protection shall also be completed.

At time of turnover, painting shall be complete enough so that


an excessive amount of scaffolding is not left still standing in
1.4 the areas where the operators must work to start up the plant.

At the time of turnover, operating areas including platforms


shall be free of debris, tools and extraneous materials which
would impede operation or cause an unsafe condition. All
1.5 accessways shall be open for emergency vehicles

1.6 Check lighting intensities


Complete all necessary paving, fencing, and items of like
1.7 nature.
All testing of lifting equipment shall be witnessed by the
Inspection Department's Crane Inspection Representative
1.8 which can then be provided with a current inspection sticker or
the completion of the successful tests.

Perform Leak test of all piping and equipment handling process


fluids in accordance with SAES-L- 150 and repair all leaks.
Check all nuts and bolts to see that threads are fully engaged.
1.9 All torque procedures for bolting and bolt pre-loads should be
verified on (ANSI 600# and above) piping and equipment where
applicable

Verify all spare parts data packages have been submitted and
1.10 accepted by Material Supply Organization

All temporary fencing or barricades must be removed to allow


1.11 free access to the operating units.

Saudi Aramco: Company General Use


SAUDI ARAMCO TEST REPORT SATR NUMBER DATE SUBMITTED DISCIPLINE

SATR-A-6133 Civil / Plumb


Final Inspection/Re-Instatement Punch List 24-Mar-16 Electrical
(Punch List by Contractor)
FEIL-Mech Mechanical
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR

MCC No.: Test Package No.:


System Description:
All start up spare parts required by contract are available on
site.
1.12

1.13 CIVIL/STRUCTURAL
Inspect sewer lines and check all cleanouts manholes, and
service connections for proper installation and functioning.
1.14 Check manholes for leak tightness by filling and then observing
the water level for ten hours

Test buildings for leak tightness and maintenance of required


1.15 internal positive pressure. (Refer to SAES-J-801 and SAES-K-
002)

1.16 Access platforms, ladders, stairs, walkways and handrails.


Perform a "Flood Test" for verification of process area OWS
1.17 catch basins and a "Flow Test" of the floor drain for battery
rooms to the acid neutralization pits

Check access around equipment at grade and at elevated


areas to ensure it is proper for normal operation and
1.18 maintenance as well as for emergency escape. Refer to SAES-
B-054 for more details

Verify that all valves and instruments are provided with proper
access for normal operation and maintenance purposes as per
1.19 SAES-B-054.

ELECTRICAL
Perform dielectric strength tests on power transformer and
2.1 disconnect switch insulating oil and install when satisfactory.
Check condition of grease in grease lubricated motor and
2.2 generator bearings
Perform all necessary prestart-up non-operating tests and Hi
Pot checks on all power cables, generators, Switchgear, MCCs,
transformers and grounding resistors following manufacturers'
instructions and guidelines given in the applicable Saudi
2.3
Aramco Pre-Commissioning Forms Manual available from
Consulting Services Department

Measure and record the insulation resistance (Megger Testing)


of all power (480V or less), instrument wiring (including
2.4 thermocouple leads) and lighting circuits from conductor to
conductor and from each conductor to ground

Perform applicable checks, adjustments and field tests using, if


necessary in order to maintain schedule, temporary
2.5
construction power.

Calibrate and set substation relays on all circuit breakers. Set


2.6 time delays. Set and test fault pressure relays and transformer
taps.
Energize substations and load centers by connection to
electrical distribution systems (Energized by authorized
2.7 electrical systems operator after obtaining approved
"Energization Authorization Certificate")

Saudi Aramco: Company General Use


SAUDI ARAMCO TEST REPORT SATR NUMBER DATE SUBMITTED DISCIPLINE

SATR-A-6133 Civil / Plumb


Final Inspection/Re-Instatement Punch List 24-Mar-16 Electrical
(Punch List by Contractor)
FEIL-Mech Mechanical
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR

MCC No.: Test Package No.:


System Description:
Check operability of emergency and instrument power systems
2.8 as well as emergency lighting system
Paint or tag all electrical apparatus (Push button boxes,
2.9 connection boxes, etc) according to Saudi Aramco's color code
or regulations
Perform a final functional checkout for all equipment and
2.10 systems.

PIPING
Flush, clean and hydro/pressure test, per SAEP-327, SAES-A-
004 and SAES-G-116, all piping and piping systems as
required by drawings, standards and specifications prior to
MCC. All orifice plates, strainers, control valves, thermowells,
and other items, which may be damaged during flushing and
3.1 testing, are to be removed from the system. With systems in
LPG service, and on completion of hydrotesting, system shall
be fully drained and dried.

Provide and install all strainers, both temporary and permanent,


3.2 spec. blinds, and temporary blinds, called for on drawings and
specifications

Check that all temporary blanks, plugs, caps, spectacle blinds


and temporary spools installed for the hydro/pressure test have
been removed and that all spectacle plates, blinds, etc. that are
3.3 to remain in the system are in their correct locations as per the
P&ID.

Provide and install other temporary blinds required for startup,


3.4 as specified by Proponent Operations.
Check packing and packing materials and lubrication of valves,
3.5 repack and lubricate as necessary
Supply supervised labor (Note 1) and necessary tools for post
hydro/pressure test, air blowing and/or water flushing
operations that may be required by Commissioning/Operations.
This will include opening flanges, dropping out control valves,
soft-seat valves, and spool pieces, installation of temporary
blinds and piping connections, removing all debris, blowing cut
lines, cleaning temporary strainers, replacing valves,
3.6 reassembling piping, repairing insulation and painting, etc., as
required for additional flushing of piping and equipment run-in
subsequent to MCC. Steam lines serving turbines shall be
cleaned by steam prior to placing into service

Schedule and direct additional Post MCC air blowing/steam


blowing and/or water flushing operations. Perform Leak test at
3.7 operational pressure of all piping and equipment handling
process fluids and repair all leaks.

Provide all replacement gaskets, spool pieces, temporary


connections, hoses, rigging and hoisting equipment, and blinds
3.8 required for additional post MCC Hydro/Pressure testing or
flushing operation

Supply and install line identification tags and signs. Stencil lines
3.9 for identification

Saudi Aramco: Company General Use


SAUDI ARAMCO TEST REPORT SATR NUMBER DATE SUBMITTED DISCIPLINE

SATR-A-6133 Civil / Plumb


Final Inspection/Re-Instatement Punch List 24-Mar-16 Electrical
(Punch List by Contractor)
FEIL-Mech Mechanical
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR

MCC No.: Test Package No.:


System Description:
Provide list and location of all blinds installed for start-up and
3.10 not detailed on P&ID's

Commission spring hangers and supports after hydro test,


3.11 check spring hangers and pipe anchors and guides in hot
position, provide cold and hot setting data

3.12 Check pipe anchors and guides.


3.13 Install corrosion probes
3.14 Remove temporary strainers (Normally after start-up
Confirm that bleeds and vents used during commissioning are
3.15 properly plugged.

MECHANICAL EQUIPMENT
4.1 AIR FIN COOLERS
Perform all hydro/pressure tests as required per SAES-A-004.
4.2

Check levels and dimensions of substructure, machinery


4.3 mount, fan ring, Furnish record of measurements

Perform decoupled motor running test, (Min. 4 hours), check


4.4 vibration and perform necessary corrective work

4.5 Set and align fan assembly, fan shaft, sheave and driver

Demonstrate satisfactory operation of louvers; adjust as


4.6 necessary
Clean inside of the hood and remove all extraneous articles
4.7 around the air fin cooler

4.8 Set and adjust V-Belts


4.9 Check and verify fan tip clearances

BOILERS, DUCTWORK AND STACK


Perform hydrostatic tests per SAES-A-004. Empty water
5.1 completely after test and dry. Alternatively, can be laid up with
inhibitor added to test water.

5.2 Perform air leak test on completed casing


Check to see if provision has been made for thermal expansion
5.3 of all boiler parts and attached piping

Clean out stack and duct, open manholes and other opening for
inspection. Check operation of dampers. Close stack and duct
5.4 after inspection.

5.5 Check mechanical operation of soot blowers


Prepare boiler dry-out procedure including manufacturer's
recommendations and review with proponent 90 days in
5.6
advance of turnover

5.7 Re-couple fans to drivers after successful run-in of driver


Inspect internal surfaces of drums, remove all debris and
5.8 provide supervised labor to open, clear and close boilers after
boil out and/or acid cleaning.

Verify proper relief valve rating, certification, and installation


5.9

Saudi Aramco: Company General Use


SAUDI ARAMCO TEST REPORT SATR NUMBER DATE SUBMITTED DISCIPLINE

SATR-A-6133 Civil / Plumb


Final Inspection/Re-Instatement Punch List 24-Mar-16 Electrical
(Punch List by Contractor)
FEIL-Mech Mechanical
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR

MCC No.: Test Package No.:


System Description:
5.10 Repair damage to liners if it occurs during cureout

COMPRESSORS

Install compressor piping and make piping corrections as


required by manufacturer's tolerances. Set and cold align
6.1 compressor and driver. Furnish record of alignment to
Operations

Clean suction piping of gas compressors, mechanically and/or


6.2 chemically
Ensure that compressor suction piping, suction and interstage
drums, lube and seal oil piping, are in clean condition, free of
mill scale, weld spatter and all loose and foreign material.
6.3 Disassemble piping for cleanliness inspection as required.

Run-in the uncoupled compressor drive motor (minimum 4


6.4 hours).
Recouple compressor to driver after successful run-in of driver.
6.5 Complete cold alignment of train.

COOLING TOWERS
Clean inside and outside the tower. Remove all extraneous
7.1 articles around the tower.

Clean the cold water basin, water distribution deck and ensure
7.2 all spray nozzles are installed.

Couple fans to drivers. After the motor has been checked for
7.3 rotation, run-in 4 hours uncoupled, and check bearings.

FURNACES AND FIXED HEATERS


8.1 Perform hydrostatic test per SAES-A-004
Empty water from coil and air blow if necessary. Add corrosion
8.2 inhibitor to water in non-drainable coils.

Provide furnace dryout procedure based on manufacturer's


8.3 recommendations.

8.4 Check mechanical operation of soot blowers and dampers

Pre-Commission instruments on furnace and ensure all skin


8.5 thermocouples are properly installed and functional

8.6 Verify proper relief valve rating certification and installation

Check operation of stack dampers and verify correct position of


damper to correspond with instrumentation and external
8.7 pointer(s).

WEIGHING SCALES/PRODUCT METERS


Calibrate all solids weighing & measuring devices in their field-
installed operating positions. Furnish record of all calibration
data. Show that equipment meets the specified tolerance for
accuracy over full range of operating conditions Note:
9.1 Operations will arrange for independent calibration of weigh
scales and product meters for custody transfer where required
by government regulations

Saudi Aramco: Company General Use


SAUDI ARAMCO TEST REPORT SATR NUMBER DATE SUBMITTED DISCIPLINE

SATR-A-6133 Civil / Plumb


Final Inspection/Re-Instatement Punch List 24-Mar-16 Electrical
(Punch List by Contractor)
FEIL-Mech Mechanical
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR

MCC No.: Test Package No.:


System Description:
PUMPS

10.1 Set and cold align pump inlet and outlet piping and driver. Furni
Check the motor for rotation, run-in four hours uncoupled, and
10.2 check bearings.

10.3 Recouple pump to driver. Furnish record to Operations


10.4 Install temporary packing if permanent packing or mechanical
seal is notmechanical
Reinstall suitable forseals
flushing. (If pump used
or permanent for flushing.)
packing prior to
10.5 startup

Make final check of cold alignment after pipe flushing. Correct if


10.6 necessary.

Check and run-in pump. All temporary strainers should be in


10.7 place

Make final hot alignment check and do any required doweling


10.8 of the pump and driver

If fire water or other permanent plant pumps are to be used for


supply of water during construction period they are to be
10.9
operated by Operations.

Maintenance of pumps covered by "h" above will be by


Contractor. At end of construction, pumps are to be put in first
10.10 class condition by Contractor.

TANKAGE

11.1 Hydrotest tank and internal piping, and clean inside tank

11.2 Close manways

Strap tank and issue record. (As an exception, Oper. will


11.3 arrange for independent calibration of product tanks for custody
transfer where required by government regulations.

11.4 Install and test appurtenances


11.5 Paint floating roof and inside of tank if required
Water flood floating roof rainwater sumps and test for leaks on
11.6 swivel joints subsequent to floating roof.

Verify proper operation of floating roof and ensure all pressure


release systems and vacuum breakers are clear and functional.
11.7

Test the manifolded foam fire protection system for storage


11.8 tanks if provided in accordance with SAES-B-017

TURBINE DRIVERS
Set and cold align turbine and associated piping. Check
12.1 parallel flange alignment. Furnish record of alignment to
operations
12.2 Chemically clean lube, seal, and hydraulic control lines
Install all permanent packing and accessories after flushing and
12.3 immediately prior to startup.

Check and run-in turbine, make vibration tests, check governor


12.4 and trips.

Saudi Aramco: Company General Use


SAUDI ARAMCO TEST REPORT SATR NUMBER DATE SUBMITTED DISCIPLINE

SATR-A-6133 Civil / Plumb


Final Inspection/Re-Instatement Punch List 24-Mar-16 Electrical
(Punch List by Contractor)
FEIL-Mech Mechanical
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR

MCC No.: Test Package No.:


System Description:
Recouple turbine driver to equipment. Make final hot alignment
12.5 check and dowel as necessary

VESSELS - TOWERS, REACTORS AND DRUMS


13.1 Hydrotest all vessels per SAES-A-004
Provide supervised labor to open, clean and close vessels
13.2 during and after flushing, if required

Cure and dry out castable linings. Contractor will provide


procedure, including time/temperature to be used, during drying
13.3 period source of heat must first be accepted by MCC.

Install all tower, reactor and drum internals and perform tray
13.4 leakage tests and leveling adjustments as required.

Clean out all vessels and open manholes and other openings
13.5 for inspection

Perform a detailed inspection of the vessel internals to include


holiday detection of internal coating as well as installation of
13.6
mechanical internals

Release Construction Agency to issue to Contractor written


13.7 authority to close up each vessel.

Properly close up all vessel internal manways and openings per


the proper torquing procedures, after final inspection or after
13.8 charging of chemicals, catalysts, etc., is completed.

For vessels where Contractor has responsibility for loading


13.9 chemicals

HEAT EXCHANGERS

14.1 Check that slide plates have been properly installed.


Open exchangers to allow detailed inspection of the internals.
For shell and tube exchangers, provide a source of high
pressure air, appropriate lances, and other arrangements
14.2 required for safe air blowing and/or flushing of the tubes during
initial operation if required for PAC

14.3 Check for damage to tubes and tube sheets.

14.4 Perform all hydrotesting per SAES-A-004


At the conclusion of flushing and cleaning, inspection, hydro-
testing, and correction of all deficiencies, issue authorization
14.5 (closure certificate) to close the exchangers

Install new gaskets on all broken connections, and then close


14.6 all ports to the exchanger following the proper torquing
procedures.

Low Pressure (SAES-A-004) leak test exchangers

MIXERS
15.1 Rotate mixers by hand to ascertain that they turn freely
Disassemble bearings and other components to allow
15.2 inspection, then reassemble.

Saudi Aramco: Company General Use


SAUDI ARAMCO TEST REPORT SATR NUMBER DATE SUBMITTED DISCIPLINE

SATR-A-6133 Civil / Plumb


Final Inspection/Re-Instatement Punch List 24-Mar-16 Electrical
(Punch List by Contractor)
FEIL-Mech Mechanical
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR

MCC No.: Test Package No.:


System Description:
Check alignment & set blades at proper height per vendor
15.3 requirements

15.4 Confirm rotation is correct for blade installation.


15.5 Conduct four (4) hour uncoupled running test of motor

AIR CONDITIONING AND AIR HANDLING EQUIPMENT


Air conditioning and air handling units, individual components
appurtenances, piping and wiring connected to the units, and
16.1 instrumentation controlling the units shall be precommissioned
per vendor instructions

Provide all freon or other cooling medium and charge or


16.2 recharge the units as required

All ductwork shall be inspected prior to closing, to verify that all


fittings and air volume control devices, and duct heaters have
been properly fabricated, installed and operate properly. All
dampers shall be thoroughly cleaned to insure proper
operation. Ducts plenums and casings shall be cleaned of all
debris and blown free of particles fiberglass, dust and rubbish
16.3 before installation of registers and grills. Equipment shall be
properly lubricated. Filters and strainers used during
construction shall be cleaned or replaced

Conduct capacity tests of air conditioning and air handling units.


16.4

16.5 Conduct building fire damper "closure" test

PRESSURE RELIEF AND DISPOSAL SYSTEM (FLARES &


BURN PIT)
Check pressure relief valves (PZV), pressure relief and
blowdown piping, relief knockout drums, flares and burn pits for
17.1 completeness and proper line up prior to placing the facility in
service

Check all PZVs tags to ensure that the PZVs are not overdue
17.2 for T&I and the set pressure is correct as per the P&ID.

Verify that all block valves upstream and downstream pressure


relief valves (PZV) are car-sealed in their proper position. The
inlet block valve to the PZV that is in service shall be open. The
inlet block valve to the standby PZV shall be closed and all PZV
17.3 outlet block valves shall be car-sealed open. All inlet and outlet
block valves for PZVs shall be painted orange

Check bellow-type PZVs to ensure their bonnets are painted


17.4 green

Verify that the outlets and vents of all PZVs are pointed to a
safe location away from equipment, piping, walkways and
17.5
working platforms

Check the flare/burn pit ignition system for completeness and


17.6 proper labeling

Saudi Aramco: Company General Use


SAUDI ARAMCO TEST REPORT SATR NUMBER DATE SUBMITTED DISCIPLINE

SATR-A-6133 Civil / Plumb


Final Inspection/Re-Instatement Punch List 24-Mar-16 Electrical
(Punch List by Contractor)
FEIL-Mech Mechanical
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR

MCC No.: Test Package No.:


System Description:
Ensure that flare and burn pit areas have proper warning signs
17.7 for toxic gas and heat radiation

MISCELLANEOUS MECHANICAL EQUIPMENT


All equipment and components not otherwise addressed by this
list shall where applicable, be installed, adjusted, lubricated,
18.1 tested, confirmed for proper functioning

FIRE AND SAFETY SYSTEMS


Conduct Capacity and Flush Tests of the Fire Water System
19.1

Schedule relief valve testing with Aramco's agreement,


sufficiently in advance of startup to permit orderly installation.
All relief valves are to be tested within 90 days prior to turnover
19.2 date. Remove as necessary and transport all relief valves to
and from the approved Aramco facility.

Test, set, and tag relief valves prior to final installation. Install
all relief valves after Aramco or approved Agency, sets and test
19.3 them

19.4 Install all road signs, safety shields, warning signs, barriers
Paint and/or tag all relief valves, car sealed valves and safety
equipment per Aramco Standards. Verify valve position per
19.5 P&ID and then install car seals on block valves where required
in accordance with SAES J 600

Install and pre-commission Fire and Safety systems: Portable


fire extinguishers Stretchers Emergency air packs and
containers Deluge systems, sprinkler systems Safety showers
and eyebaths Tag all fire extinguishers and all fixed fire
protection equipment Fire protection equipment layout map for
19.6 facility Gas detection systems Fire detection and alarm
systems New or revised plant evacuation, stop-work, etc. alarm
systems

COMMUNICATIONS
OSP: cables, manholes, conduits, protection and termination.
Tower: Structure and foundation, wave guide bridge, grounding,
20.1 etc. Buildings and Support utilities; grounding, etc. Power: DC
Plant, Standby, etc.

Ensure Communications equipment, transmission switches,


muxes data equipment alarms and miscellaneous equipment
20.2 etc. is correctly installed

Ensure equipment correctly installed and pre-commissioned

INSTRUMENTATION AND CONTROL


SYSTEMS
Perform required tightness tests on instrument take-off piping
21.1 and air piping and tubing

Saudi Aramco: Company General Use


SAUDI ARAMCO TEST REPORT SATR NUMBER DATE SUBMITTED DISCIPLINE

SATR-A-6133 Civil / Plumb


Final Inspection/Re-Instatement Punch List 24-Mar-16 Electrical
(Punch List by Contractor)
FEIL-Mech Mechanical
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR

MCC No.: Test Package No.:


System Description:
Check continuity and identification of transmission and control
systems loops for each instrument to insure proper hook-up.
This applies to both pneumatic and electrical systems (analog
and digital). Identification refers to the proper tagging of cable
and / or each control loop conductor where it is terminated at
21.2 multiple connection points (instrument, junction box, termination
panel, marshalling cabinet, etc.)

Remove rotameters, orifice places, flow nozzles, venturi and


other in-line primary flow elements, strainers, and other
21.3 equipment as necessary before hydrostatic testing, flushing or
chemical cleaning prior to MC

Reinstall above equipment. Check for direction of flow and


21.4 proper operation, e.g. travel, action with air failure, etc.

Check and tag orifice plates and flow nozzles, calibrate all
instruments and transmitters and receiver readings for each
21.5 instrument loop

Install pressure and temperature gauges after line flushing, and


21.6 check air supply for required pressure.

21.7 Provide and install sealing fluids where required


Perform final loop check which is a full functional demonstration
21.8 of I/O, DCS & ESD systems.

Continuity check alarms, computer inputs, digital inputs and


21.9 other wiring

21.10 Install analyzers and check continuity


21.11 Micrometer and inspect all meter runs
Provide calibration gas and test analyzers. Synchronize
21.12 transmitter and receiver, bring onstream and fine tune

Complete Control System/Site Acceptance Test W p Complete


ESD Fire & Gas Site Acceptance Tests W q. Complete
21.13 Metering Systems Site Acceptance Tests

Complete all Auxiliary Systems Site Acceptance Tests (Burner


21.14 Systems, Compressor Controls etc­)

CATALYST, CHEMICALS AND


DESICCANTS
Inspect all towers and drums for cleanliness before loading
22.1 catalysts, etc

Install first loading of any chemical purchased as a package


22.2 with the equipment.

Supply supervised labor to load all other chemicals and


catalyst, catalyst baskets, tower packings. (Operations
22.3
schedule and direct).

22.4 Air blow if required

22.5 Inspect after final loading. Obtain samples of all

Saudi Aramco: Company General Use


SAUDI ARAMCO TEST REPORT SATR NUMBER DATE SUBMITTED DISCIPLINE

SATR-A-6133 Civil / Plumb


Final Inspection/Re-Instatement Punch List 24-Mar-16 Electrical
(Punch List by Contractor)
FEIL-Mech Mechanical
PROJECT TITLE WBS/BI/JO NUMBER CONTRACTOR/SUBCONTRACTOR

MCC No.: Test Package No.:


System Description:

END OF CHECKLIST

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU-15-July-2018-REV. 2018.05.00(Standards Cutoff - May 31,2018)

Saudi Aramco: Company General Use


Rev.2018.05.00

15-Jul-18

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use


SAUDI ARAMCO ID/PIEU-15-July-2018-REV. 2018.05.00(Standards Cutoff - May 31,2018)

Saudi Aramco: Company General Use


Rev.2018.05.00

15-Jul-18

Saudi Aramco: Company General Use


###

Saudi Aramco: Company General Use

You might also like