Professional Documents
Culture Documents
MCQ On Planning and Management
MCQ On Planning and Management
MCQ On Planning and Management
4,7
5,9
5,7
7,9
3) Using the network given below, estimate the number of weeks by which the start of activity D can
be delayed without affecting project completion period?
It cannot be delayed
1 week
2 weeks
3 weeks
4) Please read the following statements
1. Critical path has no float and it determines the Project completion period.
2. Critical path is the largest path which actually is shortest duration in which the project can
be completed
1 only
2 only
Both 1 and 2
Neither 1 nor 2
5) Activities A,B and C are immediate predecessors for activity X, if the earliest finish times for the
three activities(A, B, C) are 12,15 and 10 respectively, then the earliest start time for activity X will
be
10
15
12
Cannot be determined