NSPCL COMMENTS RESPONSE SHEET

PROJECT BHILAI CPP-II(2X30+1X14 MW)


PACKAGE R& M WORK FOR COAL CONVEYING SYTEM
NSPCL NTPC-SAIL POWER COMPANY LTD
CONTRACTOR INDIANA CONVEYORS PVT LTD Date: 29.05.2019
NSPCL Correspondence No. e-mail dated 20.05.2019
NSPCL Doc No. 2120-153-PVM-B-005

Document / Drawing Number Document / Drawing Title Revision


2120-153-PVM-B-004/005 GA DRG OF CONV GA1 INCLUDING LOAD DATA 2
No. NSPCL Comment INDIANA Response NSPCLResolution
Drg no 2120-153-PVM-B-005
Modification of tail end of conveyor no G1 with
new junction house & Load data

Typical load data calculation to be furnished separate calculation is being sent as attachment

Opening size of discharge chute to be furnished in


Incorporated in the revised drawing - drg attached
floor

Gallery support details to be furnished


We are not supporting the gallery in the tower, as it is already
supported on trestles. Only bracing in the bottom chord is modified
near the tail pulley and it is adequately braced.

General comments

FFL andFGL to be indicated and corresponding RL


a Incorporated in the revised drawing - drg attached
value to be marked in the notes
All floor levels to be marked as TOEFL (not TOC)
b Incorporated in the revised drawing - drg attached
c Coordinate to be marked in all floor plans Incorporated in the revised drawing - drg attached
Loads on all the chute supports to be furnished
d Loads have been considered - Refer calculations attached.
under plugged condition
e Key plan to be furnished Incorporated in the revised drawing - drg attached
f Provide machinery pland and foundation plan Incorporated in the revised drawing - drg attached
g Hoist schedule to be furnished Incorporated in the revised drawing - drg attached
h Short post loads to be furnished Short post loads furnished under F3 in load data.
Drive chain equipment loads to be furnished Loads furnished under F2 in the load data. Chain drive is not being
i
used.

NSPCL COMMENTS RESPONSE SHEET


PROJECT BHILAI CPP-II(2X30+1X14 MW)
PACKAGE R& M WORK FOR COAL CONVEYING SYTEM
NSPCL NTPC-SAIL POWER COMPANY LTD
CONTRACTOR INDIANA CONVEYORS PVT LTD Date: 11.06.2019
NSPCL Correspondence No. e-mail dated 7.06.2019
NSPCL Doc No. 2120-153-PVM-B-005

Document / Drawing Number Document / Drawing Title Revision


2120-153-PVM-B-005 GA DRG OF CONV GA1 INCLUDING LOAD DATA 3
No. NSPCL Comment INDIANA Response NSPCLResolution
Drg no 2120-153-PVM-B-005
Modification of tail end of conveyor no G1 with
new junction house & Load data
North to be indicated in key plan and each main plan
1 Incorporated in the revised drawing - drg attached
Coordinate to be indicated in the Key plan and each
2 Incorporated in the revised drawing - drg attached
plan view with 2 corner coordinates.
Curb wall shall be provided around all openings
3 Incorporated in the revised drawing - drg attached
4 Civil requirements are indicative agreed
5 Inspections doors shall be leak proof confirmed
6 Legends shall be furnish Legends shown in revised drg.
7 Belt changing hook to be provided. Incorporated in the revised drawing - drg attached
8 Rain water down comer to be indicated Incorporated in the revised drawing - drg attached
9 Trash chute shall be indicated Incorporated in the revised drawing - drg attached
10 Fire fighting details will be furnished separately.

Staircase entry shall be provided on each floor


11 confirmed
including ground floor

Following Details shall be shown for retained portion


of existing conveyor G1
Support from TP Support from TP not considered.
Entry from TP Entry from TP incorprated in revised drg.
Handling of tail pulley Handling of tail pulley- monorail shown
skirt board skirt board detail will be submitted separately.
DFDS, SW, DW DFDS, SW, DW
Foundation, Support from ground Foundation, Support from floor
Load data Load data furnished.
Interlock and Switches Please refer electrical part.

Following floor openings shall be shown:


Cable tray entry
13 confirmed.

DFDS and other water pipes confirmed.


Motor cable entry confirmed.
Discharge Chute confirmed.

14 Opening is fouling with motor foundation Corrected.

Document / Drawing Number Document / Drawing Title Revision


2120-153-PVM-B-005 GA DRG OF CONV GA1 INCLUDING LOAD DATA 4
No. NSPCL Comment INDIANA Response NSPCLResolution
Drg no 2120-153-PVM-B-005 email dated 20/8/19 dated 23/8/19

Monorail operating and maintenance platforms to


1 OK noted and incorporated in revised drawing.
be shown
Details and dimensions of support of the support OK noted and incorporated in revised drawing.
2

Load data to be released due to support of existing OK noted and incorporated in revised drawing. Loads of gallery has
3 conveyor G1. Accordingly cat II approval of this. been considered in the Junction house JH-1 drawing. So please review
the JH-1 drawing.

Document / Drawing Number Document / Drawing Title Revision


2120-153-PVM-B-005 Modification of tail end of conv G1 with new junction & load data 5
Changes in line with MOM dated 5-6th NOv 2019
dated 12/11/19
1 shall be incorporated Revised as per mom dt 5th and 6th Nov 2019