Activity Guide
Student Practices
Fundamentals Supplemental
R12.x Oracle Project Costing
Disclaimer
This document contains proprietary information and is protected by copyright and other intellectual property laws. You may copy and
print this document solely for your own use in an Oracle training course. The document may not be modified or altered in any way.
Except where your use constitutes "fair use" under copyright law, you may not use, share, download, upload, copy, print, display,
perform, reproduce, publish, license, post, transmit, or distribute this document in whole or in part without the express authorization
of Oracle.
The information contained in this document is subject to change without notice. If you find any problems in the document, please
report them in writing to: Oracle University, 500 Oracle Parkway, Redwood Shores, California 94065 USA. This document is not
warranted to be error-free.
If this documentation is delivered to the United States Government or anyone using the documentation on behalf of the United
States Government, the following notice is applicable:
Trademark Notice
Oracle is a registered trademark of Oracle Corporation and/or its affiliates. Other names may be trademarks of their respective
owners.
Author
Debjit Nag
Table of Contents
R12.x Oracle Project Costing Fundamentals Supplemental Student Practices Table of Contents
i
THESE eKIT MATERIALS ARE FOR YOUR USE IN THIS CLASSROOM ONLY. COPYING eKIT MATERIALS FROM THIS COMPUTER IS STRICTLY PROHIBITED
R12.x Oracle Project Costing Fundamentals Supplemental Student Practices Table of Contents
ii
THESE eKIT MATERIALS ARE FOR YOUR USE IN THIS CLASSROOM ONLY. COPYING eKIT MATERIALS FROM THIS COMPUTER IS STRICTLY PROHIBITED
R12.x Oracle Project Costing Fundamentals Supplemental Student Practices Table of Contents
iii
THESE eKIT MATERIALS ARE FOR YOUR USE IN THIS CLASSROOM ONLY. COPYING eKIT MATERIALS FROM THIS COMPUTER IS STRICTLY PROHIBITED
Preface
Profile
Before You Begin This Course
Prerequisites
This is an instructor-led course featuring lecture and hands-on exercises. Online demonstrations
and written practice sessions reinforce the concepts and skills introduced.
R12.x Oracle Project Costing Fundamentals Supplemental Student Practices Table of Contents
v
THESE eKIT MATERIALS ARE FOR YOUR USE IN THIS CLASSROOM ONLY. COPYING eKIT MATERIALS FROM THIS COMPUTER IS STRICTLY PROHIBITED
Related Publications
Oracle Publications
Title Part Number
Oracle Project Costing User Guide E13438-03
Oracle Projects Implementation Guide E13582-03
Oracle Projects Fundamentals E13581-03
• Read-me files
• Oracle Magazine
R12.x Oracle Project Costing Fundamentals Supplemental Student Practices Table of Contents
vi
THESE eKIT MATERIALS ARE FOR YOUR USE IN THIS CLASSROOM ONLY. COPYING eKIT MATERIALS FROM THIS COMPUTER IS STRICTLY PROHIBITED
Typographic Conventions
Typographic Conventions in Text
Convention Element Example
Bold italic Glossary term (if The algorithm inserts the new key.
there is a glossary)
Caps and Buttons, Click the Executable button.
lowercase check boxes, Select the Can’t Delete Card check box.
R12.x Oracle Project Costing Fundamentals Supplemental Student Practices Table of Contents
vii
THESE eKIT MATERIALS ARE FOR YOUR USE IN THIS CLASSROOM ONLY. COPYING eKIT MATERIALS FROM THIS COMPUTER IS STRICTLY PROHIBITED
(N) Invoice > Entry > Invoice Batches Summary (M) Query > Find (B) Approve
1. (N) From the Navigator window, select Invoice then Entry then Invoice Batches
Summary.
Notations:
(N) = Navigator
(M) = Menu
(T) = Tab
(B) = Button
(I) = Icon
(H) = Hyperlink
R12.x Oracle Project Costing Fundamentals Supplemental Student Practices Table of Contents
viii
THESE eKIT MATERIALS ARE FOR YOUR USE IN THIS CLASSROOM ONLY. COPYING eKIT MATERIALS FROM THIS COMPUTER IS STRICTLY PROHIBITED
4. Review the Enter Journals topic that appears in the document frame of the help system
window.
R12.x Oracle Project Costing Fundamentals Supplemental Student Practices Table of Contents
ix
THESE eKIT MATERIALS ARE FOR YOUR USE IN THIS CLASSROOM ONLY. COPYING eKIT MATERIALS FROM THIS COMPUTER IS STRICTLY PROHIBITED
x
Copyright © Oracle 2010. All rights reserved.
R12.x Oracle Project Costing Fundamentals Supplemental Student Practices Table of Contents
Oracle University and Catalyst Business Solutions use only
Oracle University and Catalyst Business Solutio
THESE eKIT MATERIALS ARE FOR YOUR USE IN THIS CLASSROOM ONLY. COPYING eKIT MATERIALS FR
Chapter 1 - Page 2
Copyright © Oracle, 2010. All rights reserved.
Objectives
Chapter 1 - Page 4
Copyright © Oracle, 2010. All rights reserved.
Chapter 1 - Page 6
Copyright © Oracle, 2010. All rights reserved.
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Create a Project
Copy the Capital Services Template to create a new project with the values as specified in the
following table:
Field Value
Project Number XXCS
Project Name XX Capital Services
Project Manager Gray, Mr. Donald R.
Organization Services-East
Project Start Date Today's Date
Project Finish Date Two Years from Today
Your project is based in Paris. Change the project currency to EUR and select Corporate as the
rate type to convert to project functional currency and to project currency.
• (N) Projects
• (B) Find
5. Select the Capital Services Template on the Projects, Templates Summary window.
7. Complete the fields on the Project Quick Entry window as specified in the following table:
Field Value
Project Number XXCS
Project Name XX Capital Services
Project Manager Gray, Mr. Donald R.
Organization Services-East
Project Start Date Today's Date
Project Finish Date Two Years from Today
14. Complete the fields on the Currency window as specified in the following table:
Field Value
Project Currency EUR
Conversion Attributes to Project Corporate
Functional Currency - Rate Type
Conversion Attributes to Project Corporate
Currency - Rate Type
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Define Exclusive Transaction Controls at the Project Level
Define exclusive transaction controls for you XX Capital Services project to prohibit people
from charging meals and telephone expenses to your project. As an exception, permit Emily
Heather to charge telephone expenses. Let the task details determine whether her telephone
expenses are capitalizable or not. When you are done, approve the project.
• (N) Projects
• (B) Find
4. Select the XX Capital Services project on the Projects, Templates Summary window.
5. (B) Open
7. (B) Detail
Everything is chargeable, except for meals and telephone expenses. The exception is that Emily
Heather can charge her telephone expenses.
• Select Approved.
• (B) OK
• (I) Save
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Prerequisite
The instructor must open the Encumbrance year in the GL to the current year.
If the submitted budgets remain in In Process status, then the instructor must submit the
concurrent program Workflow Background Process for the class:
• Submit the concurrent program Workflow Background with the parameters as specified
in the following table
Field Value
Item Type PA Budget Integration Workflow
Minimum Threshold Leave Blank
Maximum Threshold Leave Blank
Process Deferred Yes
Process Timeout Yes
Process Stuck Yes
Tasks
Create a Project
Use the responsibility Projects, Vision Service (USA). Copy the Service Center Template to
create a new project with the values as specified in the following table:
Field Value
Project Number XXService
Use the information as specified in the following table to set up bottom-up budget integration for
Field Value
Budget Type Cost Budget - Needs Approval
Control Flag No
Balance Type Budget
Non-Project Budget BOTTOM-UP
Enter a Budget
Use the Cost Budget - Needs Approval budget type to enter a budget for your project. When
you create the budget, select Project by GL Period as the entry method and Expenditure
Category for the resource list. Enter budget lines as specified in the following table:
Your periods will depend on the dates of your project. For example, if your project started in
February 2007, then the first four periods listed would be FEB-07, MAR-07, APR-07, and
MAY-07.
Use the Tools menu to generate and view budget accounting for your budget. Review the
accounts by budget line and by account.
Submit the budget and create a baseline version. The budget status will become In Progress.
The budget is undergoing baseline processing. You can click the Find button on the Budgets
window to update the status information for the budget. Note that the budget did not require
approval because the project type of your project is not enabled to use Workflow for budget
status changes.
Use the Tools menu to monitor the budget processing and review funds check results.
• (N) Projects
• (B) Find
4. Select the Service Center Template on the Projects, Templates Summary window.
6. Complete the fields on the Project Quick Entry window as specified in the following table:
Field Value
Project Number XXService
Project Name XX Service Center
Project Manager Gray, Mr. Donald R.
Project Start Date Today's date
Project Completion Date Two years from today
7. (B) OK
9. (B) Open
12. Complete the fields on the Budget Integration window as specified in the following table:
Field Value
Budget Type Cost Budget - Needs Approval
Control Flag No
Balance Type Budget
Non-Project Budget BOTTOM-UP
The Levels and Time Phase regions do not apply to bottom-up integrated budgets.
Enter a Budget
• (N) Budgets
17. Enter the draft budget information as specified in the following table:
Field Value
Version Name Enter a name for the version
Change Reason Leave Blank
Description Leave Blank
Your periods will depend on the dates of your project. For example, if your project started in
February 2007, then the first four periods listed would be FEB-07, MAR-07, APR-07, and
MAY-07.20.
Chapter 1 - Page 24
Copyright © Oracle, 2010. All rights reserved.
The instructor will transfer the budget accounting to Oracle General Ledger for the entire class.
4. (B) OK
5. Select the program PRC: Transfer Journal Entries to GL from the list of values in the Name
field and Vision Services for the operating unit.
6. Define the parameters for the program as specified in the following table:
Field Value
Process Category Budget
End Date Five month's from today
Post in General Ledger Yes
General Ledger Batch Name BottomUp
7. (B) OK
8. (B) Submit
• (B) Find
• Use (B) Refresh Data to monitor the progress of the request processing.
12. When the program is complete, close the Requests window and return to the Navigator.
• (B) OK
• (B) Find
Chapter 1 - Page 30
Copyright © Oracle, 2010. All rights reserved.
Entering Expenditures
Chapter 1 - Page 31
Copyright © Oracle, 2010. All rights reserved.
Assumptions
• Replace XX with the number that your instructor has assigned.
Tasks
Enter the Batch Information
Enter a timecard expenditure batch for the current week. Enter the header information as
specified in the following table:
Field Value
Operating Unit Vision Services
Batch Name XXBATCH
Ending Date This Sunday's Date
Class Timecards
Description Timecards
All Negative Transactions Entered As Unmatched Leave Blank
Reverse Expenditures in a Future Period Option Not Available
Control Totals 40
Control Count 2
Note: For all expenditure items in this batch, use Unscheduled as the Assignment Name and
Internal - capital as the Work Type.
Enter expenditure items for Amy Marlin as specified in the following table:
Enter expenditure items for Ann Hamilton as specified in the following table:
After you verify your control totals, submit and release the batch.
Field Value
Operating Unit Vision Services
Batch Name XXBATCH
Ending Date This Sunday's Date
Class Timecards
Description Timecards
All Negative Transactions Entered As Unmatched Leave Blank
Reverse Expenditures in a Future Period Option Not Available
Control Totals 40
Control Count 2
4. (I) Save
5. (B) Expenditures
8. (I) Save
9. Position your cursor in the row under where you entered Amy Marlin's name.
12. Enter the expenditure items for Anne Hamilton as specified in the following table:
14. Close the Expenditures window and return to the Expenditure Batches window.
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Review Expenditure Items for Your Project
Use Expenditure Inquiry (Project) to review the expenditure items that you charged to your XX
Capital Services project. Note that the expenditure items have no cost because you have not run
costing programs for your project.
Use Expenditure Inquiry (All) to perform a second query to review all straight time that Amy
Marlin has charged since the beginning of January of 2006. Perform the query for the Vision
Services operating unit. Determine the total burdened cost for Amy's time over this period of
time.
Note the total project functional burdened cost in the total field at the bottom of the window:
_______________
View the cost distribution lines, accounting, and T-accounts for one of the expenditure items.
• (B) Find
7. For the Vision Services operating unit, query all straight time labor that Amy Marlin
charged since January 2006.
• (T) Resource
• (B) Totals
• Note the total project functional burdened cost in the total field at the bottom of the
window: _______________
Note: Your total may differ from the amount in the screen capture.
9. Position your cursor on one of the queried items with an amount in the Project Func
Burdened Cost field.
12. (B) OK
14. Close the Cost Distribution Lines window and return to the Expenditure Items window.
15. View subledger accounting information for the same expenditure item.
• (B) T Accounts
This button opens the Options window. You can set your T-Accounts options here.
• (B) T Accounts
Field Value
Operating Unit Vision Services
Batch Name XXBATCH2
Ending Date This Sunday's Date
Class Miscellaneous Transaction
Description Accruals
All Negative Transactions Entered As Unmatched Leave Blank
Reverse Expenditures in a Future Period Select
Control Totals Leave Blank
Control Count Leave Blank
4. (I) Save
5. (B) Expenditures
7. Enter the expenditure items for Services-East as specified in the following table:
8. (I) Save
9. Close the Expenditures window and return to the Expenditure Batches window.
Oracle Project Costing creates the reversing expenditure items when you release the batch.
You see two new reversing expenditure items, one for each expenditure item that you
entered.
• (B) OK
• Compare the accrual dates for the original and the reversing expenditure items.
Implementing Expenditures
Chapter 1 - Page 49
Copyright © Oracle, 2010. All rights reserved.
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Define an Expenditure Type
Define an expenditure type to record motor pool truck usage charges. Use the information as
specified in the following table:
Enter a description and assign the expenditure type an expenditure type class of Usages.
These internal charges are eligible for billing on some time and materials projects in Oracle
Project Billing. Assign a tax classification code of Location for the Vision Services operating
unit.
Assign a cost rate of $250 USD a day for the Vision Services operating unit.
Note: In a future practice, you will create non-labor resources for this expenditure type and
assign rate overrides.
• (T) Classifications
• Enter the basic expenditure type information as specified in the following table:
• Enter the description and date information as specified in the following table:
• Assign an expenditure type class to the new expenditure type as specified in the
following table:
4. (I) Save
• (I) Save
Chapter 1 - Page 54
Copyright © Oracle, 2010. All rights reserved.
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Distribute Labor Costs
Submit the concurrent program PRC: Distribute Labor Costs for your XXBATCH expenditure
batch. Ensure that you select your expenditure batch and project as program parameters. Review
the output report.
After the program is complete, query the expenditure items for your project in Expenditure
Inquiry and review the cost distribution line information for one of the expenditure items. The
distribution program calculates the raw and burdened cost for the four expenditure items.
The status of the cost distribution line is Pending. When the instructor runs the program PRC:
Generate Cost Accounting Events, the program will derive the default credit account for the cost
distribution line.
Note: The instructor will run the programs PRC: Generate Cost Accounting Events and PRC:
Create Accounting for the entire class in the next guided demonstration.
4. (B) OK
5. Select the program PRC: Distribute Labor Costs from the list of values in the Name field
and Vision Services for the operating unit.
6. Define the parameters for the program as specified in the following table:
Field Value
Expenditure Batch XXBATCH
Project Number XXCS
7. (B) OK
8. (B) Submit
• (B) Find
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
15. Query all expenditure items for your XX Capital Services Project.
• (B) Find
• Position your cursor on one of the queried items with an amount in the Project Func
Burdened Cost field.
• (B) OK
The instructor will submit a streamline program to create accounting for the entire class.
4. (B) OK
5. Select the program PRC: Submit Interface Streamline Processes from the list of values in
the Name field and Vision Services for the operating unit.
6. Define the parameters for the program as specified in the following table:
Field Value
Streamline Option XL: Interface Labor Costs To GL
7. (B) OK
8. (B) Submit
• (B) Find
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
12. When the streamline program is complete, close the Requests window and return to the
Navigator.
• (B) Find
• (B) OK
The status of the cost distribution line is Accepted -- Final Accounted in Oracle Subledger
Accounting.
Chapter 1 - Page 63
Copyright © Oracle, 2010. All rights reserved.
Field Value
Name XXExpCat/Indirect Cost Account
Description Uses expenditure category to look up indirect cost account values.
Note: Lists of values are not available when you define lookup sets.
You can map multiple intermediate values to the same segment value. This option enables
you to capture more detail in Oracle Project Costing than you need in Oracle Subledger
Accounting or Oracle General Ledger.
5. (I) Save
Field Value
Rule Name XX Indirect Cost Account Rule
Description Derives the default debit account for the indirect cost
account based on expenditure category.
Intermediate Value: Source Parameter
Intermediate Value: Value Expenditure Category
Segment Value: Source Lookup Set
Segment Value: Lookup Set XXExpCat/Indirect Cost Account
• Optionally, use the Lookup Set button to review the lookup set values.
4. (I) Save
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Define an AutoAccounting Rule
Define a rule for AutoAccounting that uses the expenditure organization to determine the
account value. Name your rule XX Exp Org to Department Rule.
Your implementation team previously defined a lookup set that maps organizations to accounts.
Use the lookup set Organization to Department Value in your rule. Review the lookup set as you
define the rule.
Field Value
Name XX Exp Org to Department Rule
Description Enter a brief description
Intermediate Value: Source Parameter
Intermediate Value: Value Expenditure Organization
Segment Value: Source Lookup Set
Segment Value: Lookup Set Organization to Department Value
4. (I) Save
• (B) Find
4. In the Function Transactions region, scroll down and select the function transaction Indirect,
All.
IMPORTANT: For this demonstration, do not enable the function transaction. Oracle
Project Costing does not use disabled function transactions during processing. Caution
students not to modify AutoAccounting rule assignments during class. Modifying
AutoAccounting can affect the processing of future demonstrations and practices.
5. With Indirect, All selected, enter the Segment Rule Pairings as specified in the following
table:
6. (I) Save
7. Close the Assign AutoAccounting Rules window and return to the Navigator.
Chapter 1 - Page 70
Copyright © Oracle, 2010. All rights reserved.
Assumptions
• Replace XX with the number that your instructor has assigned.
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Enter a Non-Labor Resource for Small Trucks
Define a non-labor resource named XXSmall Truck to select when a department is charged for
use of a small truck from the motor pool. Associate it with the XXMotor Pool Trucks expenditure
type that you defined in a previous practice. Assign the non-labor resource to the Shared Services
organization (motor pool is part of this organization).
Small trucks cost less to operate and maintain, so the motor pool does not charge other
organizations as much to use them. For the organization Vision Services, enter a cost rate
override of $100 USD a day for the remainder of this year and $125 USD a day for next year.
Define a non-labor resource named XXLarge Truck to select e when a department is charged for
use of a large truck from the motor pool. Associate it with the XXMotor Pool Trucks expenditure
type that you defined in a previous practice. Assign the non-labor resource to the Shared
Services organization (motor pool is part of this organization).
Do not enter a cost rate override. Instead, Oracle Project Costing uses the cost rate of $250 USD
a day that you defined for the expenditure type.
Field Value
Name XXSmall Truck
Description Enter a brief description
Expenditure Type XXMotor Pool Trucks
Equipment Resource Class Leave Blank
Effective Date From Today's Date
Effective Date To Leave Blank
4. With your new non-labor resource selected, enter an owning organization as specified in the
following table:
5. (I) Save
• Enter cost rate override information for the remainder of this year as specified in the
following table:
Field Value
Operating Unit Vision Services
Currency USD (View Only)
Rate 100
UOM Day (View Only)
Effective Date From Today's Date
Effective Date To 31-DEC of the current year
• (I) Save
• (I) New
• Enter cost rate override information for next year as specified in the following table:
Field Value
Operating Unit Vision Services
Currency USD (View Only)
Rate 125
UOM Day (View Only)
Effective Date From 01-JAN of next year
Effective Date To 31-DEC of next year
7. Close the Cost Rate Overrides window and return to the Non-Labor Resources window.
8. Place your cursor in the empty row below where you defined the XXSmall Truck non-labor
resource.
Field Value
Name XXLarge Truck
Description Enter a brief description
Expenditure Type XXMotor Pool Trucks
Equipment Resource Class Leave Blank
Effective Date From Today's Date
Effective Date To Leave Blank
10. With your new non-labor resource selected, enter an owning organization as specified in the
following table:
12. Close the Non-Labor Resources window and return to the Navigator.
Your instructor can help you troubleshoot any issues that you encounter so that you can update
your setup and retest.
Assumptions
• Replace XX with the number that your instructor has assigned.
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Enter and Process a Test Expenditure Batch
To validate that your setup is correct, you need to test the non-labor resources that you created in
the previous practice. First, enter an expenditure batch for the current week and name it XXTEST.
Select the Usages class.
Enter two expenditures for Amy Marlin as specified in the following tables:
Next, submit and release the batch. Run the program PRC: Distribute Usage and Miscellaneous
Costs to distribute the expenditure items. Ensure that you specify your expenditure batch and
project in the program parameters. Review the output report. If the report contains exceptions,
then research the issues, fix them, and rerun the distribution process to test the fix. If you
encounter missing cost rates exception, then verify that the cost rate is set up properly on the
XXMotor Pool expenditure type.
Query the expenditure items in Expenditure Inquiry and verify that they are cost distributed. Use
Field Value
Operating Unit Vision Services
Batch Name XXTEST
Ending Date This Sunday's Date
Class Usages
Description Usages
All Negative Transactions Entered As Unmatched Leave Blank
Reverse Expenditures in a Future Period Option Not Available
Control Totals Leave Blank
Control Count Leave Blank
4. (I) Save
5. (B) Expenditures
7. Enter the expenditure items for Amy Marlin as specified in the following tables:
8. (I) Save
9. Close the Expenditures window and return to the Expenditure Batches window.
15. (B) OK
16. Select the program PRC: Distribute Usage and Miscellaneous Costs from the list of values
in the Name field and Vision Services for the operating unit.
17. Define the parameters for the program as specified in the following table:
Field Value
Expenditure Batch XXTEST
Project Number XXCS
• (B) Find
22. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
If the report contains exceptions, then research the issues, fix them, and rerun the
distribution process to test the fix. If you encounter missing cost rates exception, then verify
that the cost rate is set up properly on the XXMotor Pool expenditure type.
27. Query the expenditure items from the XXTEST expenditure batch for task 3.0 on your
project.
• (T) Expenditure
• (B) Find
• (B) OK
• (B) OK
30. Drag the Non-Labor Resource column to the position next to the Project Functional Raw
Cost column.
Chapter 1 - Page 84
Copyright © Oracle, 2010. All rights reserved.
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Define a Cost Rate Schedule by Job
Define a job-based cost rate schedule. Enter the header information as specified in the following
table:
Field Value
Operating Unit Vision Services
Organization Services-East
Schedule XXCost Rate by Job
Description Enter a brief description
Currency USD
Share Across Operating Units Leave check box disabled
After you define the header information, select the Job tab and enter the job cost rate
information. Select the Vision Corporation job group and then enter jobs and rates as specified in
the following table:
Field Value
Operating Unit Vision Services
Organization Services-East
Schedule XXCost Rate by Job
Description Enter a brief description
Currency USD
Share Across Operating Units Leave check box disabled
4. (T) Job
• (I) Save
3. Enter the organization labor costing rules for Services-East as specified in the following
table:
Field Value
Operating Unit Vision Services
Organization Services-East
Labor Costing Rule Compensation
Cost Rate Schedule XXCost Rate by Job (select one of
the student's schedules from a
previous practice)
Default Job Schedule Bill Rate by Job
Effective Date From One year from today
Effective Date To Leave Blank
Note: Enter an effective start date of one year from today. This organization labor costing
rule is for demonstrations purposes only.
4. (I) Save
5. Close the Organization Labor Costing Rules window and return to the navigator.
• (N) Setup > Costing > Labor > Labor Costing Overrides
• (B) Find
Field Value
Costing Rule Exempt
Override Type Rate
Costing Schedule Leave Blank
Rate 122.45
Currency CAD
Rate Type Corporate
Rate Date Expenditure Item Date
Exchange Rate Leave Blank
Effective Date From Today's Date
Effective Date To Leave Blank
• (I) Save
5. Close the Labor Costing Overrides window and return to the Navigator.
Chapter 1 - Page 90
Copyright © Oracle, 2010. All rights reserved.
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Define the Burden Structure Header Information
Your company applies fringe, overhead, and general and administrative burden to various types
of costs. The finance department always uses an additive approach to calculate the burden.
Define the header information for a new additive burden structure and name it XXLabor and
Expenses. Note that your company does not want users to use this structure for overrides.
The finance department wants to apply fringe to labor costs to account for benefits and overhead
to account for human capital management administrative support. Define a labor cost base that
applies both types of burden costs to the following expenditure types:
− Administrative
− Clerical
− Design
− Professional
− Supervision
The finance department also wants to apply general and administrative burden to expense report
costs to account for the cost of using an outside travel agency and overhead to account for
managing the expense reports. Define an expenses cost base that applies both types of burden
costs to the following expenditure types:
− Airfare
− Car Rental
− Hotel
− Meals
− Mileage
− Telephone
Field Value
Structure XXLabor and Expenses
Effective From Today's Date
Effective To Leave Blank
Description Enter a brief description
Structure Type Additive
Structure Usage in Schedule Overrides - Allowed No
Structure Usage in Schedule Overrides - Default No
4. (I) Save
5. Select Labor from the list of values in the Cost Base field.
6. Enter the cost code for this cost base as specified in the following table:
8. (I) Save
9. Position your cursor in the empty row below Labor in the Cost Base Assignment region.
10. Select Expenses from the list of values in the Cost Base field.
11. Enter the cost codes for this cost base as specified in the following table:
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Define the Burden Schedule Header Information
You need to define a burden schedule to specify the burden multipliers for the cost codes on your
XXLabor and Expenses burden structure. The finance department does not have the final
multipliers at this time, so you must create a provisional burden schedule that will enable you to
specify the actual multipliers when they are available.
Define the header information for the provisional burden schedule and name it XXInternal
Costing. Use the organization hierarchy information as specified in the following table:
Field Value
Hierarchy Global
Version 1
Start Org Vision Corporation
Create the initial version of the schedule. Name the first version and identify the first day of next
month as the start date. You do not have an end date for this version at this time.
Enter the multipliers for each burden cost code. First enter the multipliers for Vision
Corporation, the start organization that you specified for the hierarchy. Costs for operating your
Services-East organization are higher than in other organizations, so the finance department has
provided you with a separate set of provisional multipliers for Services-East. Enter the
multipliers as specified in the following table:
Field Value
Name XXInternal Costing
Description Enter a brief description
Structure XXLabor and Expenses
Effective From Today's Date
Effective To Leave Blank
Type Provisional
Hierarchy Global
Version 1
Start Org Vision Corporation
5. Position your cursor in the Name field in the Versions region (above the label Name) and
enter version information as specified in the following table:
Field Value
Name Enter a version name
Start Date First day of next month
End Date Leave Blank
Structure (view only) XXLabor and Expenses
6. (I) Save
7. Enter the multipliers in the Multipliers region as specified in the following table:
8. (I) Save
When you select the Compile button, Oracle Project Costing submits the concurrent
program Compile Burden Schedule Revision.
10. Close the Burden Schedules window and return to the Navigator.
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Distribute Total Burdened Costs
Submit the concurrent program PRC: Total Burdened Cost for your XX Capital Services project.
Ensure that you select your project as a program parameter. Review the output report.
After the program is complete, query the expenditure items for your project in Expenditure
Inquiry and review the cost distribution line information for one of the expenditure items. The
distribution program determines the default total burdened cost accounting for the expenditure
items.
Select one of the expenditure items on your XX Capital Services and research how Oracle
Project Costing calculated the total burdened costs. Use the View Burdened Costs window to
assist your research. Answer the following questions:
1) What is the name of the burden schedule that Oracle Project Costing used to
calculate the burden amount?
2) Describe how Oracle Project Costing calculated the total burdened cost for the
expenditure item (cost codes, multipliers, calculations)?
4. (B) OK
5. Select the program PRC: Distribute Total Burdened Cost from the list of values in the Name
field and Vision Services for the operating unit.
6. Define the parameters for the program as specified in the following table:
Field Value
Project Number XXCS
7. (B) OK
8. (B) Submit
• (B) Find
11. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
15. Query all expenditure items for your XX Capital Services Project.
• (B) Find
• (B) OK
• Review the cost distribution line information for the burdened debit and the burdened
credit.
18. Close the Cost Distribution Lines window and return to the Project Expenditure Items
window.
• Enter information for your expenditure item (or use the data from the screen shot and
change the date to today’s date).
• (B) Burden
1) What is the name of the burden schedule that Oracle Project Costing used to
2) Describe how Oracle Project Costing calculated the total burdened cost for the
expenditure item (cost codes, multipliers, calculations)?
23. Close the View Burdened Costs window and return to the Navigator.
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Perform a Split and a Transfer
Amy Marlin has informed you that she incorrectly charged 10 hours of clerical work for the
week to task 1.1. Amy should have charged 6 hours of the clerical work to task 2.1 and 4 hours
to task 1.1. Adjust the expenditure items on your XX Capital Services project accordingly.
First, change the comment for the expenditure item to indicate that the Amy's supervisor, Donald
Gray, has approved the transfer. Next, split the expenditure item for 10 hours of Amy's clerical
work on task 1.1 into expenditure items of 6 and 4 hours. When you split the expenditure items,
both should remain capitalizable. Finally, transfer 6 hours to task 2.1.
Submit the concurrent program PRC: Distribute Labor Costs for your project to distribute the
adjusted expenditure items. Review the output report.
Donald Gray has requested an audit of all adjustment activity on the XX Capital Services project.
Run the AUD: Project Expenditure Adjustment Activity report to review all adjustment activity.
• (T) Resource
• (B) Find
You see the expenditure item for 10 hours of clerical labor from the batch you entered in a
previous practice.
• After the existing comment, enter a comment such as: Transfer of 6 hours to task 2.1
• (B) OK
• (B) OK
8. Review the results. You will see three new expenditure items:
− A reversing item of -10 hours
− A new item of 6 hours
− A new item of 4 hours
Field Value
Project Number XXCS
Name XX Capital Services
Task Number 2.1
Name Framing
11. Review the results. You will see one new expenditure item for task 1.1:
− A reversing item of -6 hours for task 1.1
In addition, the transfer created a new item of 6 hours for task 2.1. Because the original
query was for task 1.1, you do not see the new item for task 2.1. Optionally, you can revise
the query criteria to see all expenditure items for your project.
14. (B) OK
15. Select the program PRC: Distribute Labor Costs from the list of values in the Name field
and Vision Services for the operating unit.
Field Value
Project Number XXCS
17. (B) OK
• (B) Find
21. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
26. (B) OK
27. Select the program AUD: Project Expenditure Adjustment Activity from the list of values in
the Name field and Vision Services for the operating unit.
28. Define the parameters for the program as specified in the following table:
Field Value
Project Number XXCS
29. (B) OK
• (B) Find
33. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
After reviewing her timecards, Anne Hamilton realizes that she incorrectly charged 10 hours of
her time to your XX Capital Services project as Supervision. Anne has asked you to change the
expenditure type for the timecard with the earliest date for the week from Supervision to Sales.
Enter a timecard batch for the current week so that you can reverse the incorrect expenditure
item and enter a new corrected expenditure item. Name the batch XXCORRECTION.
Enter an expenditure for Anne Hamilton and then select the Reverse Original... button to find
and reverse the incorrect expenditure item. Reverse the Supervision expenditure item with the
earliest date for the current week that Ann charged to your project.
Field Value
Operating Unit Vision Services
Batch Name XXCORRECTION
Ending Date This Sunday's Date
Class Timecards
Description Enter a brief description
All Negative Transactions Entered As Unmatched Leave Blank
Reverse Expenditures in a Future Period Option Not Available
Control Totals Leave Blank
Control Count Leave Blank
4. (I) Save
5. (B) Expenditures
• (B) Find
• Select the Supervision expenditure item with the earliest expenditure item date.
Note: Hold down the Ctrl key on your keyboard and left-click the expenditure item to select
it.
11. Place your cursor in the first empty row after the reversing expenditure item.
12. Enter a new corrected expenditure item as specified in the following tables:
14. Close the Expenditures window and return to the Expenditure Batches window.
Run the “PRC: Update Project Summary Amounts for a Single Project” program for the cost
reimbursable project.
• (B) Find
• (B) Commitments
This project has Supplier Invoice, Purchase Orders, and Requisition commitments.
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
• If the student is not using the SERVICES User ID, then the instructor must ensure that
each employee associated with a User ID is assigned a position in Oracle HRMS and
that the position has adequate signing authority in Oracle Purchasing.
Tasks
Enter and Submit a Requisition in Oracle iProcurement
Your project manager has asked you to order 10 coffee makers for the project offices. You can
charge the coffee makers to task 1.2 of the XX Capital Services project.
Enter and submit a non-catalog requisition in Oracle iProcurement. Use the responsibility
iProcurement, Vision Services (USA). Enter the request information as specified on the following
table:
Field Value
Item Type Goods billed by quantity
Item Description Coffee makers for project office
Category MISC.MISC
Quantity 10
Unit of Measure Each
Unit Price 35.99
Currency USD
RFQ Required No
Negotiated No
Contract Number Leave Blank
New Supplier No
Supplier Name Consolidated Supplies
Site HOUSTON
Contact Name Fuller, Ernie
Phone 713 678-4553
Supplier Item Leave Blank
Field Value
Be sure to enter a brief justification and a message to the buyer. Your requisition does not require
any approvals. Submit your requisition.
• (T) Shop
Field Value
Item Type Goods billed by quantity
Item Description Coffee makers for project office
Category MISC.MISC
Quantity 10
Unit of Measure Each
Unit Price 35.99
Currency USD
RFQ Required No
Negotiated No
Contract Number Leave Blank
New Supplier No
Supplier Name Consolidated Supplies
Site HOUSTON
Contact Name Fuller, Ernie
Phone 713 678-4553
Supplier Item Leave Blank
4. (B) Checkout
5. Revise the project information in the Billing region as specified in the following table:
Field Value
Project XXCS
Task 1.2
Expenditure Type Supplies
Expenditure Org Services-East
Expenditure Item Date Today's Date
8. (B) Next
• (H) Show
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
• If the student is not using the SERVICES User ID, then the instructor must ensure that
the employee associated with the student's User IDs is set up as a Buyer in Oracle
Purchasing and that the employee's position has adequate signing authority.
• IMPORTANT: The instructor must set the current reporting period for Vision Services
operating unit to the period for the current week before students update summary
amounts:
• (B) OK
• (I) Save
Tasks
AutoCreate a Purchase Order
The project manager of the XX Capital Services project has asked you to create a purchase order
for the coffee makers. In Oracle Purchasing, use your requisition from the previous practice to
AutoCreate a new purchase order. Use the responsibility Purchasing, Vision Services (USA).
After you AutoCreate the new purchase order, review the project charging instructions on the
Project tab of the Distributions window (accessed from the Shipments window). You entered
this project information on the requisition and Oracle Purchasing copied it to the purchase order.
When you are ready, approve the purchase order. Verify that the status of the purchase order is
Approved.
• (N) AutoCreate
• (B) Clear
• (B) Find
4. Enable the check box next to the line for your requisition.
6. Review the information on the New Document window. Accept the default values.
7. (B) Create
• (B) Shipments
• (B) Distributions
• (T) Project
15. Verify that the status of the purchase order is now Approved.
16. Close the AutoCreate for Purchase Orders window and return to the Navigator.
• (B) OK
20. (B) OK
21. Select the program PRC: Update Project Summary Amounts for a Single Project from the
list of values in the Name field and Vision Services for the operating unit.
22. Define the parameters for the program as specified in the following table:
Field Value
Project Number XXCS
Through Date Leave Blank
Summarize Cost Yes
Expenditure Type Class Leave Blank
Summarize Revenue Yes
Summarize Budgets Yes
Budget Type Leave Blank
Summarize Commitments Yes
• (B) Find
27. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
• (B) Find
• (B) Commitments
• (B) Find
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
• IMPORTANT: The instructor must verify that the current AP period is open:
You received the invoice for the coffee makers that you ordered. In Oracle Payables, create an
invoice. Use the responsibility Payables, Vision Services (USA). Enter or verify the invoice
header information as specified in the following table:
Field Value
Operating Unit Vision Services
Type Standard
Trading Partner Consolidated Supplies (view only)
Supplier Num 1014 (view only)
Supplier Site HOUSTON
Invoice Date Today's Date
Invoice Number XX-INV
Invoice Curr USD
Invoice Amount 359.90
Match Action Purchase Order
GL Date Today's Date
Terms 4/10, 3/20, 2/30 Net 60
Match the invoice to the purchase order that you created in the previous practice. After you find
You must validate the invoice and create final subledger accounting before you can interface the
supplier costs to Oracle Project Costing as actual costs. First, validate the invoice. After the
invoice is validated, create final subledger accounting for it. Select the Final Post option when
you create accounting. Verify that the invoice status is Validated and that Accounted is Yes.
Field Value
Operating Unit Vision Services
Type Standard
Trading Partner Consolidated Supplies (view only)
Supplier Num 1014 (view only)
Supplier Site HOUSTON
Invoice Date Today's Date
Invoice Number XX-INV
Invoice Curr USD
Invoice Amount 359.90
Match Action Purchase Order
GL Date Today's Date
Terms 4/10, 3/20, 2/30 Net 60
Payment Method Check
Pay Group Standard
Payment Curr USD
Payment Rate Date Today's Date
Terms Date Today's Date
Taxation Country United States
• (B) Find
6. Select the Match check box next to the line for your purchase order.
• (T) Lines
• (B) Distributions
• (T) General
• (B) OK
• (B) Actions... 1
11. Verify that the invoice status is Validated and that Accounted is Yes.
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Interface Supplier Costs
In the previous practice, you validated and created final subledger accounting for your supplier
invoice. You can now interface the supplier costs to Oracle Project Costing as actual costs. Use
the responsibility Projects, Vision Services (USA). Run the program PRC: Interface Supplier
Costs. Ensure that you select your project as a program parameter. The program PRC: Interface
Supplier Costs automatically submits the program AUD: Supplier Costs Interface Audit. Review
the output report for AUD: Supplier Costs Interface Audit.
Use expenditure inquiry to query the expenditure item from the supplier invoice. Drill down to
view the invoice overview information and invoice workbench for the supplier cost expenditure
item.
4. (B) OK
5. Select the program PRC: Interface Supplier Costs from the list of values in the Name field
and Vision Services for the operating unit.
6. Define the parameters for the program as specified in the following table:
Field Value
Project Number XXCS
Batch Name Leave Blank
Through GL Date Leave Blank
Through Transaction Date Leave Blank
Interface Supplier Invoices Yes
Interface Receipt Accruals No
Interface AP Discounts No
7. (B) OK
8. (B) Submit
11. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing.
Note: Wait for the program with your Request ID to complete. The program PRC:
Interface Supplier Costs automatically submits the program AUD: Supplier Costs
Interface Audit. Look for the AUD: Supplier Costs Interface Audit program request with
your Request ID in the parameters.
12. Review the output report for AUD: Supplier Costs Interface Audit.
15. Query the expenditure items from the invoice XX-INV on your project.
• (T) Supplier
• (B) Find
• Select AP Invoice.
• (B) OK
6. (I) Save
• Transfer the supplier cost expenditure item from the previous practice to a different
task.
• Interface supplier costs from the canceled invoice to Oracle Project Costing.
• Analyze the expenditure items that result from the multiple adjustments.
Assumptions
• Replace XX with the number that your instructor has assigned.
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
• The instructor must complete the activities in previous guided demonstration to allow
adjustments for the Oracle Payables Supplier Invoices transaction source.
Tasks
Transfer an Expenditure Item in Oracle Projects
The project manager of the XX Capital Services project notifies you that you need to charge the
coffee makers to task 3.0 and not task 1.2. In Oracle Project Costing, transfer the expenditure
item to task 3.0 and then run the program PRC: Distribute Supplier Cost Adjustments to
distribute the adjustment. Ensure that you select your project as a program parameter. Review the
output report.
You discover that you have not yet received the coffee makers. After contacting the supplier, you
learn that the coffee makers are discontinued and will not be shipped. In Oracle Payables, find
and cancel the unpaid supplier invoice that you previously entered and validated. Use the
responsibility Payables, Vision Services (USA). After you cancel the invoice, create final
subledger accounting for the invoice. Select the Final Post option when you create accounting.
Verify that the invoice status is Cancelled and that Accounted is Yes.
Interface the canceled invoice costs to Oracle Project Costing. Use the responsibility Projects,
Vision Services (USA). Run the program PRC: Interface Supplier Costs. Ensure that you select
your project as a program parameter. Review the output report for the program AUD: Supplier
Costs Interface Audit.
Query all of the expenditure items from your XX-INV supplier invoice in Expenditure Inquiry.
Limit the find criteria to query only the expenditure items related to your supplier invoice.
Provide a brief analysis of when each expenditure item was created and the purpose of each
expenditure item:
2. Query the expenditure items from the invoice XX-INV on your project.
• (T) Supplier
• (B) Find
Field Value
Project Number XXCS
Name XX Capital Services
Task Number 3.0
Name Project Management
5. Review the results. You will see two new expenditure items:
− A new expenditure item for task 3.0
− A reversing expenditure item of for task 1.2
9. (B) OK
10. Select the program PRC: Distribute Supplier Cost Adjustments from the list of values in the
Name field and Vision Services for the operating unit.
11. Define the parameters for the program as specified in the following table:
Field Value
Project Number XXCS
• (B) Find
16. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
• (B) OK
• (B) Find
• (B) Actions... 1
• (B) Actions... 1
24. Verify that the invoice status is Cancelled and that Accounted is Yes.
• (B) OK
29. (B) OK
30. Select the program PRC: Interface Supplier Costs from the list of values in the Name field
and Vision Services for the operating unit.
31. Define the parameters for the program as specified in the following table:
Field Value
Project Number XXCS
Batch Name Leave Blank
Through GL Date Leave Blank
Through Transaction Date Leave Blank
Interface Supplier Invoices Yes
Interface Receipt Accruals No
Interface AP Discounts No
• (B) Find
36. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing.
Note: Wait for the program with your Request ID to complete. The program PRC:
Interface Supplier Costs automatically submits the program AUD: Supplier Costs
Interface Audit. Look for the AUD: Supplier Costs Interface Audit program request with
your Request ID in the parameters.
37. Review the output report for AUD: Supplier Costs Interface Audit.
40. Query the expenditure items from the invoice XX-INV on your project.
• (T) Supplier
• (B) Find
First, you interfaced supplier costs to Oracle Project Costing, which created the new
supplier cost expenditure item for task 1.2.
Second, you transferred the cost to task 3.0. The transfer created a new expenditure item
for task 3.0 and a reversal for the original expenditure item for task 1.2.
Third, you cancelled the invoice in Oracle Payables and interfaced supplier costs to
Oracle Project Costing. The program PRC: Interface Supplier Costs created an
expenditure item to reverse the transferred expenditure item on task 3.0. Oracle
Payables did not know about the adjustment activity in Oracle Project Costing, so the
cancellation created an expenditure item to reverse the original expenditure item for
task 1.2. Because the transfer previously reversed the original expenditure item in
Oracle Project Costing, the interface program created an expenditure item to reverse the
cancellation reversal (appears as a positive expenditure item for task 1.2). The net
outcome is that the total cost is now zero.
41. Close the open windows and return to the Navigator when finished.
4. (B) Find
5. (T) Expnd/Costing
7. (I) Save
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Enter an Expense Report
You traveled to Montreal to meet with clients regarding the XX Capital Services project. Enter
an expense report for your travel expenses. In Oracle Internet Expenses, create a new expense
report. Use the responsibility iExpenses, Vision Services (USA). Enter the general expense report
information as specified in the following table:
Field Value
Name Marlin, Ms. Amy (34)
Services Department 422
Reimbursement Currency USD - US dollar
Expense Template Travel
Purpose Meeting in Montreal
Approver Brown, Ms. Casey
You are now in the role of Casey Brown, the expense report approver. Log in as CBROWN with
the password of WELCOME and select the iExpenses responsibility. Find the notification for
your expense report (look for your expense report number) and approve it.
Log in as DGRAY with the password of WELCOME and select the Internet Expenses Auditor,
Vision Services responsibility to audit the expense report. Use the advanced search option on the
Expenses Audit tab to find your expense report. Enter today's date as the Receipt Package
Received Date. Verify that you received the two receipts and then complete the audit.
4. Enter the general expense report information as specified in the following table:
Field Value
Name Marlin, Ms. Amy (34)
Services Department 422
Reimbursement Currency USD - US dollar
Expense Template Travel
Purpose Meeting in Montreal
Approver Brown, Ms. Casey
5. (B) Next
• (B) Save
• (B) Save
• (B) Next
• (B) Next
• (B) Return
Field Value
User Name CBROWN
Password WELCOME
• (B) Approve
• (H) Home
Field Value
User Name DGRAY
Password WELCOME
• Enter the expense report number in the Search by Expense Report Number field.
• (B) Go
• Select the Receipt Verified check box for the two receipts.
• Select Complete Audit from the list in the Expense Report Action field.
• (B) Apply
1. Log out
Field Value
6. (B) Next
8. (B) Next
11. Accept the default values on the Schedule Request: Notifications page.
13. Accept the default values on the Schedule Request: Printing page.
17. (B) OK
18. Select the Refresh button to update the status until the program is complete.
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Validate and Create Accounting for the Expense Report Invoice
As a result of the instructor running Expense Report Import in the previous guided
demonstration, your expense report is now an expense report invoice in Oracle Payables. Log in
as SERVICES with the password of WELCOME and select the Oracle Payables, Vision Services
(USA) responsibility.
First, find the invoice on the Invoice Workbench in Oracle Payables. Next, validate the invoice.
After the invoice is validated, create final subledger accounting for the invoice. Select the Final
Post option when you create accounting. Verify that the invoice status is Validated and that
Accounted is Yes.
Switch your responsibility to Projects, Vision Services (USA) and Run the program PRC:
Interface Expense Reports from Payables. Ensure that you select your project as a program
parameter. The program PRC: Interface Expense Reports from Payables automatically submits
the program AUD: Supplier Costs Interface Audit. Review the output report for AUD: Supplier
Costs Interface Audit.
After the program is complete, query the expense report expenditure items for your XX Capital
Services project in Expenditure Inquiry. Review the expenditure items.
1. Log in as SERVICES:
Field Value
User Name SERVICES
• (I) Find
• (B) Find
• (B) Actions... 1
• (B) Actions... 1
7. Verify that the invoice status is Validated and that Accounted is Yes.
• (B) OK
12. (B) OK
13. Select the program PRC: Interface Expense Reports from Payables from the list of values in
the Name field and Vision Services for the operating unit.
14. Define the parameters for the program as specified in the following table:
Field Value
Project Number XXCS
Batch Name Leave Blank
End GL Date Leave Blank
End Expenditure Item Date Leave Blank
15. (B) OK
• (B) Find
• Use (B) Refresh Data to monitor the progress of the request processing.
Note: Wait for the program with your Request ID to complete. The program PRCPRC:
Interface Expense Reports from Payables automatically submits the program AUD:
Supplier Costs Interface Audit. Look for the AUD: Supplier Costs Interface Audit
program request with your Request ID in the parameters.
20. Review the output report for AUD: Supplier Costs Interface Audit.
21. Close the output page and the Requests window and return to the Navigator.
23. Query the expenditure items from the expense report on your project.
• (B) Find
In this guided demonstration, the instructor will set the Proj Override timecard approval style to
Approve Timecards
• (N) Preferences
• (T) Preferences
Field Value
Approval Style Project Manager
Override Approval Style Project Manager
• (I) Save
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Prerequisite
IMPORTANT: Each student will submit a timecard as Amy Marlin. Because a person can have
only one timecard for a period, the instructor must assign each student a period for which to
create and submit a timecard for Amy Marlin. Starting with the period for next week, the
instructor will assign each student a unique period to use for this practice.
Tasks
Enter a Timecard
Submit your timecard in Oracle Time & Labor to account for your work for the week. Use the
responsibility OTL, Vision Services (USA).
Field Value
Period IMPORTANT: Select the unique period
that the instructor assigns to you.
Overriding Approver Leave Blank
Comments Enter brief comments
Template Leave blank
Overwrite No
You worked 6 hours a day, Monday through Friday, performing professional duties on your XX
Capital Services project. Charge this time to task 3.0. You also worked 2 hours a day performing
clerical duties for the Feasibility Study project. Charge this time to task 1.1.1. After you enter the
timecard lines, review and submit the timecard.
In the previous demonstration, the instructor changed the timecard approval style to route
timecards to project managers for approval. As a result, Oracle Time & Labor will route the
approval notification for the XXCS project to Donald Gray for approval and the approval
notification for the Feasibility Study project to Bob Cochran for approval.
Log in as the user DGRAY with the password of WELCOME. Navigate to Donald Gray's
worklist. Select the hyperlink for the notification for the timecard that you submitted for Amy
Marlin, review the notification, and approve the timecard. The 30 hours represents the amount
Important: Select the hyperlink that has the dates for the timecard period that your instructor
assigned to you.
Approve the Timecard for the Feasibility Study Project as Bob Cochran
Log in as the user BCOCHRAN with the password of WELCOME. Navigate to Bob Cochran's
worklist. Select the hyperlink for the notification for the timecard that you submitted for Amy
Marlin, review the notification, and approve the timecard. The 10 hours represents the amount
charged to the Feasibility Study project where Bob Cochran is the project manager.
Important: Select the hyperlink that has the dates for the timecard period that your instructor
assigned to you.
Field Value
Period IMPORTANT: Select the unique period
that the instructor assigns to you.
Overriding Approver Leave Blank
Comments Enter brief comments
Template Leave blank
Overwrite No
5. Enter the project information in the first timecard line as specified in the following table:
Field Value
Project XXCS
Task 3.0
Type Professional - (Straight Time)
6. Enter 6 hours of time for each day, Monday-Friday for the first line.
7. Enter the project information in the second timecard line as specified in the following table:
Field Value
Project Feasibility Study
Task 1.1.1
Type Clerical - (Straight Time)
8. Enter 2 hours of time for each day, Monday-Friday for the second line.
9. (B) Save
In the previous demonstration, the instructor changed the timecard approval style to route
timecards for the appropriate project managers for approval. As a result, Oracle Time &
Labor will route the time for the XXCS project to Donald Gray for approval and the time for
the Feasibility Study project to Bob Cochran for approval.
Field Value
User Name DGRAY
Password WELCOME
• Select the hyperlink for the notification for the timecard that you submitted for Amy
Marlin.
Important: Select the hyperlink that has the dates for the timecard period that your
instructor assigned to you.
Approve the Timecard for the Feasibility Study Project as Bob Cochran
Field Value
User Name BCOCHRAN
Password WELCOME
• Select the hyperlink for the notification for the timecard that you submitted for Amy
Marlin.
Important: Select the hyperlink that has the dates for the timecard period that your
instructor assigned to you.
Field Value
User Name SERVICES
4. Define the parameters for the program PRC: Transaction Import as specified in the
following table:
Field Value
Transaction Source Oracle Time and Labor
Batch Name Leave Blank
5. (B) OK
6. (B) Submit
• (B) Find
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
12. Close the report page and open windows and return to the Navigator when finished.
• (T) Expenditure
• (B) Find
16. Close the open windows and return to the Navigator when finished.
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Define the General Allocation Rule Information
The finance department has asked you to define an allocation rule to allocate a fixed amount of
shared costs each month to the tasks in your XX Capital Services project. The costs must be
allocated in full once each GL period. The rule should prorate the costs based on the total
burdened cost for each chargeable task.
Name your rule XXService Allocation. Enter the allocation rule information as specified in the
following table:
Field Value
Operating Unit Vision Services
Name XXService Allocation
Description Enter a brief description
Effective Date From Today's Date
Effective Date To Leave Blank
Basis Method Prorate
Allocation Method Full
Allocation Period Type GL
Targets Selection Operating Unit
Expnd Org Services-East
Expnd Type Class Miscellaneous Transaction
Expnd Type Support Svcs Allocation
Auto Release No
Allow Duplicate Targets No
The finance department has calculated that they need to allocate a fixed shared cost amount of
100,000.00 USD each month. Use this information to define the source for the allocation rule.
Allocate the costs to your XX Capital Services project. Your project manager has obtained an
exception that exempts task 3.0 of your XX Capital Services project from the allocation. Define
the targets for the allocation rule accordingly.
The finance department wants you to create a transaction on task 8.0 of the Service Center
project to offset the allocation transactions. Use the same expenditure organization, expenditure
type class, and expenditure type for the offset transaction that you use for the allocation
transactions.
The amount that the rule allocates to each chargeable task is based on the actual total burdened
cost for the fiscal year to date. Define the basis method and specify a relative period of 0 (current
period) to determine the actual total burdened cost for each task.
Field Value
Operating Unit Vision Services
Name XXService Allocation
Description Enter a brief description
Effective Date From Today's Date
Effective Date To Leave Blank
Basis Method Prorate
Allocation Method Full
Allocation Period Type GL
Targets Selection Operating Unit
Expnd Org Services-East
Expnd Type Class Miscellaneous Transaction
Expnd Type Support Svcs Allocation
Auto Release No
Allow Duplicate Targets No
4. (I) Save
5. (B) Sources
Field Value
Allocation Pool % 100
Fixed Source Amount 100,000.00
7. (I) Save
9. (B) Targets
15. Specify the project and task as specified in the following table:
Field Value
Project Service Center
Task 8.0
16. Specify the Offset Transaction Attributes as specified in the following table:
Field Value
Expenditure Organization Services-East
Expenditure Type Class Miscellaneous Transaction
Expenditure Type Support Svcs Allocation
Field Value
Basis Category Actuals
Amount Type Total Burdened Cost
GL Amount Class FYTD
Relative Period 0
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Prerequisite
If not done previously, the instructor must set the current reporting period for Vision Services
operating unit to the period for the current week:
• (B) OK
• (I) Save
Run the program PRC: Update Project Summary Amounts for a Single Project for your XX
Capital Services project to summarize the costs. The allocation rule in this practice uses a prorate
basis method. This basis method uses summary amounts during allocation generation processing
to determine the basis percentage for each chargeable target task.
You are ready to generate allocation transactions for the current GL period. Submit the program
PRC: Generate Allocation Transactions for the Vision Services operating unit. Specify your rule
name, the current GL period, and today's date as the expenditure item date in the program
parameters.
Review the output report. You may see exceptions on the report. For example, the exception
code PA_AL_ZERO_TXN_BASIS_AMT means that no actual total burdened costs are
associated with the target task. As a result, the program did not allocate costs to the task.
Use the Review Allocation Runs window to review the status, basis details, source details, and
transaction totals for the allocation run. Release the allocation run. When you release the
Monitor the progress of the request and review the output report.
Use the Review Allocation Runs window to verify that the run is in Release Success status.
Record the information in the Allocation Expnd Batch field: ________________
Use Expenditure Inquiry (All) to review the released expenditure items. Enter the expenditure
batch number for your allocation run in the Find Expenditure Items window to limit your query.
4. (B) OK
5. Select the program PRC: Update Project Summary Amounts for a Single Project from the
list of values in the Name field and Vision Services for the operating unit.
6. Define the parameters for the program as specified in the following table:
Field Value
Project Number XXCS
Through Date Leave Blank
Summarize Cost Yes
Expenditure Type Class Leave Blank
Summarize Revenue Yes
Summarize Budgets Yes
Budget Type Leave Blank
Summarize Commitments Yes
7. (B) OK
8. (B) Submit
• (B) Find
11. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
16. (B) OK
17. Select the program PRC: Generate Allocation Transactions from the list of values in the
Name field and Vision Services for the operating unit.
18. Define the parameters for the program as specified in the following table:
Field Value
19. (B) OK
• (B) Find
23. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing.
25. Close the output page and the Requests window and return to the Navigator.
• (B) Find
• (B) Transactions
• (B) Totals
• (B) Release...
When you release the allocation run, Oracle Project Costing submits the concurrent
program PRC: Release Allocation Runs.
35. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing.
37. Close the output page and the Requests window and return to the Navigator.
• (B) Find
40. Record the information in the Allocation Expnd Batch field: ________________
• (T) Expenditure
• (B) Find
Note: Individual student’s results may not match the results displayed in the book, because each
students will a use unique time period.
Oracle Project Costing opens the Define Recurring Journal Formula window.
• (B) Lines
• Close the Journal Entry Line and Define Recurring Journal Formula windows.
• (B) Sources
Note that the source for this allocation rule is account 01-840-7420-000 in Oracle
General Ledger. The GL Allocation Batch in step one posts an amount to this account.
The Project Allocation Rule then allocates the amount in this account to the target
projects.
Asset Capitalization
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Set the Cost Allocation Method for Your Project
After consulting with your project manager, you have decided that when the generate asset lines
program cannot automatically associate an asset line with a single asset, the program should
spread the asset costs evenly across the assets. Set the cost allocation method on your XX Capital
Services project to Spread Evenly.
In addition, you want to collect common costs on your project and allocate these costs to assets
at a later point in time. Set the grouping level for task 3.0 to Common Costs.
The asset manager sent you information regarding two assets that you are building on your XX
Capital Services project.
Define the first asset on your project as specified in the following table:
Field Value
Capitalization Details Tab
Asset Name XXLab Building
Project Asset Type Estimated
Asset Details Tab
Book SVCS CORP
Asset Category BUILDING-OFFICE
Field Value
Capitalization Details Tab
Asset Name XXLab Computer
Project Asset Type Estimated
Asset Details Tab
Book SVCS CORP
Asset Category COMPUTER-SERVER
Asset Number XX2
Actual Units 1
Location, Employee Tab
Location USA-CA-SAN FRANCISCO-NONE
Depreciation Tab
Depreciate Yes
Depreciation Expense Account 01-510-7360-000
Amortize Adjustments Yes
Description Tab
Description (enter freeform) XXLAB COMPUTER
In preparation for capitalizing asset costs, you must run cost distribution programs for your
project. First, submit the program PRC: Submit Project Streamline Processes and run the
streamline option LU: Labor/Usage Cost for your project.
After the program completes, submit the program PRC: Distribute Total Burdened Cost for your
XX Capital Services project. Ensure that you select your project as a program parameter. Review
the output report.
• (N) Projects
• (B) Find
4. Select the XX Capital Services project on the Projects, Templates Summary window.
5. (B) Open
8. Select Spread Evenly from the list in the Asset Cost Allocation Method field.
10. Close the Capital Information window and return to the Projects, Templates window.
• (B) Find
21. Select the Capital Project Assets option button at the top of the window.
Field Value
Capitalization Details Tab
Asset Name XXLab Building
Project Asset Type Estimated
Asset Details Tab
Book SVCS CORP
Asset Category BUILDING-OFFICE
Asset Number XX1
Actual Units 1
Location, Employee Tab
Location USA-CA-SAN FRANCISCO-NONE
Depreciation Tab
Depreciate Yes
Depreciation Expense Account 01-510-7320-000
Amortize Adjustments Yes
Description Tab
Description (enter freeform) XXLAB BUILDING
Field Value
To Project No
To Task Yes
Top Task
1.0
Field Value
Capitalization Details Tab
Asset Name XXLab Computer
Project Asset Type Estimated
Asset Details Tab
Book SVCS CORP
Asset Category COMPUTER-SERVER
Asset Number XX2
Actual Units 1
Location, Employee Tab
Location USA-CA-SAN FRANCISCO-NONE
Depreciation Tab
Depreciate Yes
Depreciation Expense Account 01-510-7360-000
Amortize Adjustments Yes
Description Tab
Description (enter freeform) XXLAB COMPUTER
Field Value
To Project No
To Task Yes
Top Task
2.0
37. (B) OK
38. Select the program PRC: Submit Project Streamline Processes from the list of values in the
Name field and Vision Services for the operating unit.
39. Define the parameters for the program as specified in the following table:
Field Value
Streamline Option LU: Labor/Usage Cost
Project Number XXCS
• (B) Find
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
47. (B) OK
48. Select the program PRC: Distribute Total Burdened Cost from the list of values in the Name
field and Vision Services for the operating unit.
49. Define the parameters for the program as specified in the following table:
Field Value
Project Number XXCS
• (B) Find
54. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
The instructor will generate cost accounting events and create final subledger accounting for
the entire class in the next demonstration.
Note: Individual student’s results may not match the results displayed in the book, because each
students will a use unique time period to enter a timecard.
4. (B) OK
5. Select the program PRC: Generate Cost Accounting Events from the list of values in the
Name field and Vision Services for the operating unit.
6. Leave all the parameters blank. The program will generate cost accounting events for all
process categories.
7. (B) OK
8. (B) Submit
• (B) Find
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
Create Accounting
15. (B) OK
16. Select the program PRC: Create Accounting from the list of values in the Name field and
Vision Services for the operating unit.
Field Value
Process Category Leave Blank (program will
process accounting events for all
process categories)
End Date Friday of the current week
Mode Final
Errors Only No
Report Summary
Transfer to General Ledger Yes
Post in General Ledger Yes
General Ledger Batch Name Leave Blank
Include User Transaction Identifiers No
18. (B) OK
• (B) Find
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
23. Close the output report page and the open windows and return to the Navigator.
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Update Project Summary Amounts
Run the program PRC: Update Project Summary Amounts for a Single Project for your XX
Capital Services project to summarize the costs.
Your project manager has certified that the XXLab Building and XXLab Computer assets are
finished and ready for capitalization. Change the asset type for both assets to As-Built and record
an actual in service date of 31-DEC-2006.
Note: You are entering 31-DEC-2006 in order to demonstrate the interface to Oracle Assets. If
you enter today's date, you will not be able to interface the asset to Oracle Assets because the
asset period is not open.
The costs on your project are final accounted in Oracle Subledger Accounting and the two assets
have in service dates, so you are now ready to generate asset lines for your XX Capital Services
project. To generate asset lines, use today's date as the Asset Date Through and this Sunday's
date as the PA Through Date. You are also ready to include the costs from common cost task 3.0
when you generate asset lines.
Review the output report for the program PRC: Generate Asset Lines for a Single Project.
Review the asset lines for your XX Capital Services project and answer the following questions:
1. Why are all asset lines for task 1.0 assigned to XXLab Building?
2. Why are all asset lines for task 2.0 assigned to XXLab Computer?
3. Why are all asset lines for task 3.0 split between the two assets?
4. Why are the asset lines grouped by expenditure types such as Clerical, Hotel, XXMotor
After completing the asset line analysis, you decide to move some costs on task 3.0 from XXLab
Computer to XXLab Building. Split an asset line assigned to XXLab Computer for task 3.0 and
assign 85% of the cost to XX Lab Building and the remainder to XXLab Computer.
When you are satisfied with the asset lines, you are ready to interface the assets to Oracle Assets.
Submit the program PRC: Interface Assets to Oracle Assets. Ensure that you enter your XXCS
project number in both the From Project Number and To Project Number program parameter
fields.
You can now view your assets in Mass Additions in Oracle Assets. Use the responsibility Assets,
Vision Services (USA). Navigate to the Find Mass Additions window to query the assets for you
project. For the find criteria, also include SVCS CORP as the Book. Select one of the MERGED
lines, review the details, and view the project details.
4. (B) OK
5. Select the program PRC: Update Project Summary Amounts for a Single Project from the
list of values in the Name field and Vision Services for the operating unit.
6. Define the parameters for the program as specified in the following table:
Field Value
Project Number XXCS
Through Date Leave Blank
Summarize Cost Yes
Expenditure Type Class Leave Blank
Summarize Revenue Yes
Summarize Budgets Yes
Budget Type Leave Blank
Summarize Commitments Yes
8. (B) Submit
• (B) Find
11. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
• (B) Find
Note: You are entering 31-DEC-2006 in order to demonstrate the interface to Oracle
Assets. If you enter today's date, you will not be able to interface the asset to Oracle
Assets because the asset period is not open.
The Actual In-Service Date may not match the date in the book. You need to determine
the Open Period for SRVC CORP in the Assets module.
Field Value
Asset Date Through Today's Date
PA Date Through This Sunday's Date
Include Common Tasks Yes
This initiates the Program PRC: Generate Asset Lines for a Single Project. Note your
request ID:
You can see the ID at the bottom of the Oracle Applications window.
• (B) Find
25. Wait for the process to finish. When the process is complete, select the process.
• (B) Find
Answer: You assigned only XXLab Building to top task 1.0. As a result, the asset lines
generation program assigned all costs to this asset.
2. Why are all asset lines for task 2.0 assigned to XXLab Computer?
Answer: You assigned only XXLab Computer to top task 2.0. As a result, the asset lines
generation program assigned all costs to this asset.
3. Why are all asset lines for task 3.0 split between the two assets?
Answer: You set the grouping level for task 3.0 to Common Costs and assigned Spread
Evenly as the cost allocation method for your project. As a result, the asset lines
generation program divided the capitalizable costs for task 3.0 evenly between the two
eligible assets.
4. Why are the asset lines grouped by expenditure types such as Clerical, Hotel, XXMotor
Pool and Trucks?
Answer: The project type for your project is Construction. The grouping method
assigned to the project type is Expenditure Type. As a result, the asset lines generation
program grouped all costs by the expenditure type associated with the expenditure type
for each capitalizable expenditure item.
31. Select one of the asset lines for task 3.0 and split it between the two assets.
Asset %
XXLab Building 85.00
XXLab Computer 15.00
38. (B) OK
39. Select the program PRC: Interface Assets to Oracle Assets from the list of values in the
Name field and Vision Services for the operating unit.
Field Value
From Project Number XXCS
To Project Number XXCS
Date Placed in Service Through Leave Blank
Note: You must type your project number correctly. These fields are case and punctuation
sensitive.
41. (B) OK
• (B) Find
45. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
• (B) OK
• (B) Find
You will see that your two assets are in the POST queue. Each individual asset line is also
visible. They are MERGED.
• (B) Open
You can drill back to Oracle Projects from Oracle Assets to see the asset line detail
information.
Note: Individual student’s results may not match the results displayed in the book, because each
students will a use unique time period.
3. Enter the standard unit cost for an asset book and asset category combination as specified in
the following table:
Field Value
Asset Book SVCS CORP
Asset Category COMPUTER-PC
Book Currency USD
Cost Per Unit 2,500.00
4. (I) Save
5. Close the Project Asset Standard Unit Costs window and return to the Navigator.
Assumptions
• Replace XX with the number that your instructor has assigned.
Tasks
Define a Proceeds of Sale Expenditure Type
Your company records proceeds of sale amounts for retirement cost processing in Oracle Project
Costing. Define a unique expenditure type to classify and account for the amounts as specified in
the following table:
Field Value
Code XXPROCEEDS OF SALE
Meaning XX-Proceeds of Sale
Description XX-Proceeds of Sale expenditure type
Effective Date From Today’s Date
• (N) Setup > Capitalization > Assets > Retirement Cost Classification
4. (I) New
5. Define the proceeds of sale expenditure type as specified in the following table:
Field Value
Code XXPROCEEDS OF SALE
Meaning XXProceeds of Sale
Description XXProceeds of Sale expenditure type
Effective Date From Today’s Date
6. (I) Save
7. Close the Retirement Cost Classification Lookups window and return to the Navigator.
Cross Charge
Assumptions
• Replace XX with the number that your instructor has assigned.
Tasks
Set Cross Charge Attributes at the Project Level
Resources owned by another operating unit, Vision Services R&D, will perform work on your
XX Capital Services project. Enable your project to receive cross charges from other operating
units. Set up the project to use the Global TP Schedule to determine the transfer prices for both
labor and non-labor cross charges.
Allow resources from other operating units to charge only task 1.1. Set up task 1.1 to use the
Global TP Schedule to determine the transfer prices for both labor and non-labor cross charges.
• (N) Projects
• (B) Find
4. Select the XX Capital Services project on the Projects, Templates Summary window.
5. (B) Open
7. (B) Detail
8. Set the Cross Charge attributes for the project as specified in the following table:
Field Value
Allow Charges from other Operating Units Yes (enable check box)
Process Cross Charge For Labor Yes (enable check box)
Transfer Price Schedule: Labor Global TP Schedule
9. (I) Save
10. Close the Project Multinational Setup window and return to the Projects, Templates
window.
17. Set the Cross Charge attributes for the task 1.1 as specified in the following table:
Field Value
Allow Charges from other Operating Units Yes (enable check box)
Process Cross Charge For Labor Yes (enable check box)
Transfer Price Schedule: Labor Global TP Schedule
Fixed Date: Labor Leave Blank
Process Cross Charge For Non-Labor Yes (enable check box)
Transfer Price Schedule: Non-Labor Global TP Schedule
Fixed Date: Non-Labor Leave Blank
Assumptions
• Replace XX with the number that your instructor has assigned.
Tasks
Enter Cross Charges in an Expenditure Batch
You are now in the role of Austin Sanders, a resource from Vision Services R&D. Log in as
ASANDERS with the password of WELCOME and select the Projects, Vision Services R&D
(USA) responsibility.
Enter a usage expenditure batch for the current week. Enter the header information as specified
in the following table:
Field Value
Operating Unit Vision Services R&D
Batch Name XXCROSSCHARGE
Ending Date This Sunday's Date
Class Usages
Description Usages
All Negative Transactions Entered As Unmatched Leave Blank
Reverse Expenditures in a Future Period Option Not Available
Enter expenditure items for Austin Sanders as specified in the following tables:
Submit the concurrent program PRC: Distribute Usage and Miscellaneous Costs for your
XXCROSSCHARGE expenditure batch. Review the output report.
Submit the concurrent program PRC: Distribute Borrowed and Lent Amounts. Define the
parameters for the program as specified in the following table:
Field Value
Expenditure Group XXCROSSCHARGE
Through Date This Sunday's Date
Receiver Operating Unit Vision Services
From Project Number XXCS
To Project Number XXCS
Generate Report Yes
The program PRC: Distribute Borrowed and Lent Amounts automatically submits the program
PRC: Borrowed and Lent Amounts Distribution Report. Review the output report for PRC:
Borrowed and Lent Amounts Distribution Report.
1. Log out
Field Value
Field Value
Operating Unit Vision Services R&D
Batch Name XXCROSSCHARGE
Ending Date This Sunday's Date
Class Usages
Description Usages
All Negative Transactions Entered As Unmatched Leave Blank
Reverse Expenditures in a Future Period Option Not Available
7. (B) Expenditures
9. (I) Save
10. Enter an expenditure item for Austin Sanders as specified in the following tables:
15. Close the Expenditure Batches window and return to the Navigator.
18. (B) OK
19. Select the program PRC: Distribute Usage and Miscellaneous Costs from the list of values
in the Name field and Vision Services R&D for the operating unit.
20. Define the parameters for the program as specified in the following table:
Field Value
Expenditure Batch XXCROSSCHARGE
• (B) Find
25. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
30. (B) OK
31. Select the program PRC: Distribute Total Burdened Cost from the list of values in the Name
field and Vision Services R&D for the operating unit.
32. Define the parameters for the program as specified in the following table:
Field Value
Expenditure Batch XXCROSSCHARGE
33. (B) OK
• (B) Find
37. Wait for the program to finish. When the program is complete, select the program.
42. (B) OK
43. Select the program PRC: Distribute Borrowed and Lent Amounts from the list of values in
the Name field and Vision Services R&D for the operating unit.
44. Define the parameters for the program as specified in the following table:
Field Value
Expenditure Group XXCROSSCHARGE
Through Date This Sunday's Date
Receiver Operating Unit Vision Services
From Project Number XXCS
To Project Number XXCS
Generate Report Yes
• (B) Find
49. Wait for the program to finish. When the program is complete, select the program.
• Use (B) Refresh Data to monitor the progress of the request processing.
Note: Wait for the program with your Request ID to complete. The program PRC:
Distribute Borrowed and Lent Amounts automatically submits the program PRC:
Borrowed and Lent Amounts Distribution Report. Look for the PRC: Borrowed and
Lent Amounts Distribution Report program request with your Request ID in the
parameters.
50. Review the output report for PRC: Borrowed and Lent Amounts Distribution Report.
The instructor will complete the processing for your costs and cross charges in the next
demonstration.
Field Value
5. (B) OK
6. Select the program PRC: Generate Cost Accounting Events from the list of values in the
Name field and Vision Services R&D for the operating unit.
7. Leave all the parameters blank. The program will generate cost accounting events for all
process categories.
8. (B) OK
9. (B) Submit
• (B) Find
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
17. Select the program PRC: Generate Cross Charge Accounting Events from the list of values
in the Name field and Vision Services R&D for the operating unit.
18. Define the parameters for the program as specified in the following table:
Field Value
Process Category Borrowed and Lent
End GL Date Sunday of the current week
Generate Report Yes
19. (B) OK
• (B) Find
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
Create Accounting
27. (B) OK
28. Select the program PRC: Create Accounting from the list of values in the Name field and
Vision Services R&D for the operating unit.
29. Define the parameters for the program as specified in the following table:
Field Value
Process Category Leave Blank (program will process accounting
events for all process categories)
30. (B) OK
• (B) Find
• Use (B) Refresh Data to monitor the progress of the request processing.
35. Close open windows and return to the Navigator when finished.
Assumptions
• Replace XX with the number that your instructor has assigned.
Tasks
How did Oracle Projects calculate the borrowed and lent amount?
• (T) Expenditure
• (B) Find
• (B) OK
Answer: The program PRC: Distribute Borrowed and Lent Amounts used the Global
TP Schedule transfer price schedule that you assigned to task 1.1 for non-labor costs.
This transfer price schedule uses the Expenses - Cost+50% transfer price rule. This rule
marks up the burdened cost 150% to determine the transfer price amount for non-labor
costs.
Assumptions
• Replace XX with the number that your instructor has assigned.
Tasks
Define Transfer Price Rules
Log in as SERVICES with the password of WELCOME and select the Projects, Vision Services
(USA) responsibility.
You are implementing borrowed and lent cross charge at your company. Define two transfer
price rules to use in your transfer price schedule that meet the following requirements:
• For labor cost - transfer price equals 100% of the raw cost. Name the rule XXLabor at
Raw Cost.
• For non-labor cost - transfer price equals 100% of the burdened cost. Name the rule
XXNon-Labor at Burdened Cost.
1. Log out
2. Log in as SERVICES.
Field Value
• (N) Setup > Costing > Cross Charge > Transfer Price Rules
5. Enter a transfer labor transfer price rule as specified in the following table:
Field Value
Name XXLabor at Raw Cost
Type Labor
Effective Dates From Today's Date
Effective Dates To Leave Blank
Description Enter a brief description
Basis Raw Cost
Use Basis
Apply 100%
7. (I) New
Field Value
Name XXNon-Labor at Burdened Cost
Type Non-Labor
Effective Dates From Today's Date
Effective Dates To Leave Blank
Description Enter a brief description
Basis Burdened Cost
Use Basis
Apply 100%
10. Close the Transfer Price Rules window and return to the Navigator.
Assumptions
• Replace XX with the number that your instructor has assigned.
Tasks
Define a Transfer Price Schedule
You can use the transfer price rules that you defined in the previous practices to define a transfer
price schedule. Name the new transfer price schedule XXServices East/West Schedule.
The organizations Services-East and Services-West have agreed to share resources for certain
projects. They will transfer costs based on the XXLabor at Raw Cost and XXNon-Labor at
Burdened Cost transfer price rules that you defined.
Define two lines on the transfer price schedule and assign your transfer price rules. Use an apply
percentage of 100 percent (no discount or markup). For the first line, assign the rules for when
Services-East provides the resources and Services-West receives the benefit of the resources. For
the second line, reverse the relationship between the organizations.
• (N) Setup > Costing > Cross Charge > Transfer Price Schedules
Field Value
Name XXServices East/West Schedule
Effective Dates From Today's Date
Effective Dates To Leave Blank
Description Enter a brief description
6. Close the Transfer Price Schedules window and return to the Navigator.
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
Enter a Miscellaneous Transaction
Use the responsibility Inventory, Vision Services (USA) to enter a miscellaneous transaction for
your XX Capital Services project. When you access the Miscellaneous Transactions window for
the first time, select Vision Services as the organization.
Create a non-serial-triggered Receipt From miscellaneous transaction and enter the transaction
line information as specified in the following table:
Field Value
Item f75000
Subinventory Common
UOM Ea
Quantity 1
Account 01-000-1410-000
Source Project XXCS
Source Task 3.0
Expenditure Type Material
Expenditure Org Services-East
Save the miscellaneous transaction when you are finished entering the line. The instructor will
process your miscellaneous transaction in the next guided demonstration.
4. (B) OK
Field Value
Date Accept Default Value
Type Receipt From
Source Leave Blank
Account Leave Blank
Serial-Triggered No
Field Value
Item f75000
Subinventory Common
UOM Ea
Quantity 1
Account 01-000-1410-000
Source Project XXCS
Source Task 3.0
Expenditure Type Material
Expenditure Org Services-East
The instructor will process your miscellaneous transaction in the next guided demonstration.
1. Log in as SERVICES.
If you receive a message that the manager is already active, then click the OK button.
6. (B) Submit
7. (B) OK
10. Enter 0 in the Number of Days to Leave Costs Uncollected field in the Parameters window.
11. (B) OK
13. (B) No
• (B) Find
• (B) OK
Instructor Note: Workflow takes about an hour to process/move the data to the project
interface table.
17. Define the parameters for the program PRC: Transaction Import as specified in the
following table:
Field Value
Transaction Source Inventory Misc
Batch Name Select the batch name that is
available on the list of value.
If no batch name is available, then return to Oracle Inventory and perform the step to
transfer the cost to Oracle Project Costing again. The Cost Manager must complete
processing before you can run the program to transfer costs to Oracle Project Costing.
18. (B) OK
• (B) Find
• Use (B) Refresh Data to monitor the progress of the request processing. When the Phase
shows Completed, open the output report.
You will see an expenditure group listed under the transaction source Inventory Misc on the
second page of the report.
25. Close the report page and open windows and return to the Navigator.
Assumptions
• You must have access to an Oracle Application Vision database or comparable training
or test instance at your site on which to complete this practice.
Tasks
View Inventory Expenditure Items
Use Expenditure Inquiry (project) to view the expenditure item for the Receipt From
miscellaneous transaction on your XX Capital Services project. Specify the transaction source
Inventory Misc in your query criteria. Review the cost distribution lines for the expenditure item.
• (T) Expenditure
• (B) Find
• (B) OK
• (T) User
3. (I) New
Field Value
Name XXProject Issue
Description Issue to Project
Source Type Inventory
Action Issue from stores
Project Yes (enable check box)
Shortage Message Online No
Shortage Message Notification No
Status Control No
Location Required No
Inactive On Leave Blank
5. (I) Save
4. (I) New
Field Value
Code XXREDUCTION
Meaning XX-Budget Reduction
Description Reduction of Funding
Tag Leave Blank
Effective Date From Today’s Date
Effective Date To Leave Blank
5. (I) Save
Field Value
Budget Type XX-Capital Cost Budget
Description XX-Capital Cost Budget - Requires
Approval
Effective Date From Today's Date
Effective Date To Leave Blank
Amount Type Cost Budget
Upgrade No
Use Workflow for Yes
Budget Status Changes
The Use Workflow for Budget Status Changes check box is at the bottom of the window.
4. (I) Save
Field Value
Budget Entry Method XX-Project at Completion
Description XX-Project at Completion with no resources
Effective Date From Today's Date
Effective Date To Leave Blank
Entry Level Project
Categorized By Resources No
Time Phased By None
Cost Enterable Fields
Quantity Yes
Raw Cost Yes
Burdened Cost Yes
Revenue Enterable Fields
Quantity Yes
Revenue Yes
4. (I) Save
Assumptions
• Replace XX with the number that your instructor has assigned.
Tasks
Define the Basic Rate Name Information
Your company plans to calculate capitalized interest for costs incurred when you invest in long-
term capital projects. Define a capitalized interest rate name to represent the interest type that the
finance department plans to capitalize as specified in the following table:
Field Value
Rate Name XXDebt Costs-Local
Description Cost of Borrowings
Expenditure Type Interest
Define additional information for the capitalized interest rate name. For the operating unit Vision
Services, you want the expenditure organization source to be the project owning organization.
Each project must have an Open CIP amount of 10,000.00 and be at least 30 days from the start
date to meet the threshold for calculation of capitalized interest. Select Full as the current period
convention to specify the portion of the current period CIP amount to include in the interest
calculation. Choose to spread the amounts evenly across accounting periods. Finally, assign the
Simple interest method to this capitalized interest rate name.
For Vision Services, exclude the following expenditure types from interest rate calculation for the
capitalized interest rate name:
− F&A Costs
− Fringe
− Overhead
4. (I) New
Field Value
Rate Name XXDebt Costs-Local
Description Cost of Borrowings
Expenditure Type Interest
Effective Date From Today's Date
6. (I) Save
8. Define the capitalized interest rate information as specified in the following table:
Field Value
Operating Unit Vision Services
Exp Organization Source Project Owning Org
9. (I) Save
10. Close the window with the additional information and return to the first window
12. Define capitalized interest rate exclusions for the operating unit Vision Services as specified
in the following table:
Assumptions
• Replace XX with the number that your instructor has assigned.
Tasks
Define Capitalized Interest Rate Schedule Header Information
Define a capitalized interest rate schedule to specify the multipliers for the XXDebt Costs-Local
capitalized interest rate name that you defined in the previous practice. Define the information
for the provisional capitalized interest rate schedule and name it XXDebt Cost Schedule. Use the
organization hierarchy information as specified in the following table:
Field Value
Hierarchy Global
Version 1
Start Org Vision Corporation
Create the initial version of the schedule. Name the first version and identify the first day of
current month as the start date. You do not have an end date for this version at this time.
First, enter the multiplier for Vision Corporation, the start organization that you specified for the
hierarchy. Interest rates for operating your Services-East organization are higher than for other
organizations, so the finance department has provided you with a separate multiplier for
Services-East. Enter the multipliers as specified in the following table:
Field Value
Name XXDebt Cost Schedule
Description Enter a brief description
Effective Date From Today's Date
Effective Date To Leave Blank
Hierarchy Global
Version 1
Start Org Vision Corporation
4. (I) Save
5. Enter the name and dates for the version as specified in the following table:
Field Value
Name Version 1
Start Date First day of the current month
6. (I) Save
8. (I) Save
Selecting the Compile button submits a concurrent program - PRC: Compile Capitalized
Interest Rate Schedule.
10. Close the Capitalized Interest Rate Schedule window and return to the Navigator.
For the guided demonstration, you will specify the capitalized interest rate schedule for an
existing capital project type.
• Enter query mode: (M) View > Query By Example > Enter
• Run the query: (M) View > Query By Example > Run
Field Value
Default Schedule Select one of the student's XXDebt Cost Schedule
from the previous practice.
Allow Override Yes (enable check box)
6. (I) Save
Assumptions
• Replace XX with the number that your instructor has assigned.
Prerequisite
The instructor must perform the previous guided demonstration before you do this practice. The
Allow Override check box for capitalized interest must be enabled for the Construction project
type. Otherwise, you will be unable to update the capitalized interest rate schedule for your XX
Capital Services project.
Tasks
Assign a Capitalized Rate Schedule to the XX Capital Services Project
Your project manager has asked you to set up your XX Capital Services project for capitalized
interest calculation for a six month period. Assign the XXDebt Cost Schedule to the project,
allow capitalized interest calculation, and specify a capitalized interest stop date.
• (N) Projects
• (B) Find
4. Select the XX Capital Services project on the Projects, Templates Summary window.
5. (B) Open
Field Value
Capitalized Interest Schedule XXDebt Cost Schedule
Allow Capital Interest Yes (enable check box)
Capital Interest Stop Date Enter a date six months from today
For the guided demonstration, you will set the project status control for capitalized interest for an
existing project status.
• Enter query mode: (M) View > Query By Example > Enter
• Run the query: (M) View > Query By Example > Run
4. In the Status Controls region, scroll down until you find the Capitalized Interest action.
5. Enable the Allow check box for the Capitalized Interest action.
6. (I) Save