Download as pdf or txt
Download as pdf or txt
You are on page 1of 3

TRANSMISSION

Methods of maintenance on high


voltage fluid filled cables
by Mike Engelbrecht, CBi electric: African Cables

During April 2007, Bedfordview experienced a 67 hour blackout caused primarily by leaks on two 132 kV fluid filled cables which subsequently
led to breakdown of the cable insulation.

Fluid filled cables have been installed in Item Description Circuit length (km) Cable length (km) Quantity of
South Africa since the late 1960s, early accessories
1970s with a wide variety of types (BICC, 1 132 kV fluid-filled cable 222 355 710
Pirelli, Sumitomo, Dainichi-Nippon). Oval 2 88 kV fluid-filled cable 85 130 260
conductors, round conductors, hollow core, 3 66 kV fluid-filled cable 269 341 682
copper and aluminium and various sizes in
4 44 kV fluid-filled cable 48 48 96
both three and single core options currently
5 33 kV fluid-filled cable 373 373 748
convey power country wide with voltages
Total fluid-filled cable 997 1 247 2 496
ranging from 33 kV up to and including
132 kV [1, 2]. Table 1: Fluid filled cable in operation in South African Utilities.

The cable construction constitutes paper


l A significant decrease in maintenance type cable systems due to inadequate
insulation augmented by cable oil, under
on fluid filled systems due to pressure on maintenance. The first step therefore,
pressure, in order to improve electrical operating budgets towards returning the fluid filled cable asset
properties and avoid partial discharge
l A decreasing pool from which to source back to full design capability is to obtain a
activity. Oil pressure is maintained by either spares snapshot of how the cable system currently
a corrugated aluminium or lead sheath/
The above aspects have resulted in a operates. To this end, it is necessary to assess
metallic tape combination. All local major
dismal outlook for the future of fluid filled the cable circuit’s current working status. Any
utilities have these cables in their system
cables locally. However, as shown in historical operational information is helpful in
and they are all of the low pressure oil filled
Table 1 [2], there are still many of these this regard including the number of failures,
type, typically designed to operate at 3 - 4
circuits in operation. Local utilities cannot number of fluid leaks, number of fault
bar pressure.
merely replace all these circuits, due current exposures etc. Invariably the most
Over time these cables begin to leak to cost and time constraints, and the basic elements such as design profiles and
cable fluid and subsequently the cable challenge therefore remains to improve operating manuals are however enough to
pressure drops causing the cable insulation the working condition and reliability of the get started.
to eventually fail. Causes of leaks can be existing fluid filled circuits, thereby averting
Measurements including oil analysis,
categorized as follows: further outages. Systematic replacement,
pressure checks, serving tests, earthing
l Degradation of lead wipes on accessories. as budget spend becomes available, can
checks and general operating conditions
This is especially valid if these wipes have then be adopted.
are all determined during the cable
not been reinforced during assembly (a
How then to address the various problems assessment. Also of interest is the inspection
typical practice)
associated with ailing fluid filled cable and stock take of the types of accessories
l Lead fatigue if the system is over
circuits within local utility networks? available in order to effect a repair on the
pressurized
cable should a breakdown occur. Upon
l Third party damage leading to rupture of The answer is three fold:
completion of the circuit assessment a
the metallic sheath (the most common
l First, it is necessary to assess the current report is produced detailing the findings
cause)
relative condition of the fluid filled and necessary recommendations can be
In addition to the leaking circuits, further circuit. made as to the maintenance path ahead
reduced reliability has been associated with l Second, a decision needs to be taken as illustrated in Fig. 1.
fluid filled cables within South Africa, due to as to the future of the cable circuit i.e. is
the following aspects: it beyond repair or can it be re-instated Category one would be interpreted as the
to original design parameters? cable circuit being:
l Normal design life of the order of 30 years,
with many of the fluid filled cable circuits l Thirdly, leaks on fluid filled cables remain l In good working order: No immediate
in operation in excess of this duration the single biggest clue to an impending work is required other than routine annual
l A significant reduction in the skills electrical fault. Repair these and the
maintenance.
associated with repair, with many reliability of the circuit immediately
personnel skilled in such tasks having increases. l In fair working order: No Refurbishment
either left South Africa, to return to their of the joints / ancillary work and routine
Cable assessments
homelands, or even retired annual maintenance will ensure that
l An absence of training, with OEM jointing Information from condition based monitoring the cable returns to designed working
schools having closed down is rarely, if ever, available on fluid filled order.

energize - October 2008 - Page 31


TRANSMISSION

Fig. 1: Assessment and subsequent maintenance type required.

Category Two is interpreted as the cable that it ensures that the utility keeps its Once the point of breakdown has been
circuit being in an unacceptably poor working fluid filled cable circuits in good working located and exposed, and the necessary
condition, i.e. breakdown maintenance order. Furthermore, test results over time accessories and/or cables are available
could be utilised to patch but the circuit begin to give an excellent indication of for repair, it is still time consuming to repair
would, ultimately, need to be replaced. the natural ageing of the various cable the cable due to the complexity associated
c o m p o n e n t s. P l a n n e d r e p l a c e m e n t with a fluid filled, pressurised system. Also,
Refurbishment maintenance
forecasting becomes easier and technical once the cable is repaired, the cable
One local utility has already instituted a motivation based on reliable long term fluid required to replenish that which was
refurbishment programme on its aging tests is a reality. lost or removed during the fault must be
gas and fluid-filled cables. This type of de-gassed and circulated. Only once the
Break down maintenance
maintenance involves exposing, inspecting necessar y dielectric strength has been
and servicing cable joints. Work is done in This is the catastrophic scenario. The obtained may the circuit be returned to
off-peak periods with no power outages to lights are out and immediate repair of operation.
customers, the down side being that it is the circuit needs to be effected.The most
Utility responsibility
extremely tim e consuming with typically important aspect relating to breakdown
only one accessory completed over a week maintenance is having the necessar y Specialised equipment and highly skilled and
end. Although this type of maintenance spare parts in order to perform the repair. qualified personnel are required to conduct
also only concentrates on potential leak Lead times on fluid filled accessories are all types of maintenance on fluid filled
areas and is therefore limited, it does typically in excess of 16 weeks, and these cable circuits. These are locally available
however prevent leaks from occurring at are exclusively imported and extremely and there is therefore no reason that utilities
one of the most common leak areas on costly. In addition to these constraints, should not be utilising these resources in
the cable circuit. due to the wide variety of cables and order to maintain their fluid filled cable
manufacturers that developed these circuits. The Bedfordview disaster has also
Planned preventative maintenance systems (many of whom do not exist set a strong precedent for local electrical
The planned preventative maintenance anymore), the supplier needs to be utilities, sending a clear warning sign of what
scheme encompasses a similar scope furnished with exact cable details at time happens when things go wrong on a major
to that of cable assessment as detailed of order placement and the accessory is fluid filled cable circuit. Furthermore, in these
above. Planned preventative maintenance is then custom made, from scratch, to fit that times of load shedding, utilities can ill afford
effectively a condition monitoring programme specific cable. The consequence here is to have additional outages due to a poorly
and is conducted on an annual basis with that spares are not easily interchangeable maintained fluid filled cable network.
any defects highlighted by the various tests and many different spares need to be
Innovative leak location on fluid filled
repaired immediately. The single biggest catered for due to the variety of cable
cable systems
advantage associated with a planned constructions and types that exist in the
preventative maintenance scheme is South African electrical network. One of the most common problems

energize - October 2008 - Page 32


TRANSMISSION

Fig. 2: Schematic of principle of PFT operation.

associated with fluid filled cable circuits dielectric fluid and injected into the cable utilities and has been shown to be most
is the leaking of cable dielectric fluid into system. At a leak location, the PFT leaks into effective, having located over 30 leaks alone,
the surrounding environment. Many of the soil and vapourises (Fig. 2). The vapour in the past year, on a prominent London
these cable circuits cannot be taken out is then detected by means of a mobile based utility’s low pressure oil filled cable
of service due to their strategic nature and detection unit, housed in a test vehicle. network. Work is planned to commence
cable pressure is therefore maintained by in the latter half of 2008 on South African
Atmospheric concentrations of PFT are
regularly pumping up the cable system. This cables and once it is shown to be successful
extremely low and any measurement of
invariably results in over-pressurising of the locally it is envisaged that other South African
concentrations of PFT in the atmosphere
cable and could exacerbate existing leak utilities will follow suit in order to procure the
at concentrations higher than atmospheric
sites leading to further leaks. technology.
volumes then points to a leak from a
Traditionally, fluid leak location has been cable circuit, previously tagged with PFT. Acknowledgement
conducted via cr yogenically freezing Leak rates of 100 l/week have been shown The author acknowledges the valued input
the cable fluid and then monitoring the to be detectable and sensitivities in the from Mr Rhett Kelly, chief engineer, industry
cable pressure either side of the freeze. 200 ppm range are reliably measurable association resource centre (IARC), Eskom.
The leaking section is progressively halved with the detection unit.
until the leak is located to within 10-20 m. This article as originally presented at the 2008
Advantages with the technology include Electricity Distribution Maintenance Summit:
The effected length of the cable is then
the following: Midrand Gauteng, and is republished with
exposed and the leak visually located.
permission.
Limitations with this method include the l The cable need not be removed from
following: service during tagging or leak location. References

l The cable circuit needs to be out of l The measurement is extremely sensitive [1] A E Dickson: “Alternative Technologies for the
service in order to perform the freeze. and an accuracy of 2 m or better is Effective Operation of Ageing High Voltage
Cable”, Proceedings of the Africa Power
feasible, thereby minimising the amount
l Freezing pits need to be excavated along Conference, 1999.
the route in order to access the cable. of excavation.
[2] CA van Dyk: “Methods of Extending the
l Many simultaneous leaks can be Operational Life Expectancy of Ageing High
l It is difficult to locate more than a single
detected on a cable section. Voltage Networks”, Proceedings of the 57th
leak on the same cable section.
AMEU Convention, City of Tshwane, October
Per Fluorocarbon Trace (PFT) l The technology is relatively inexpensive 2001.
in that it costs roughly 138% of the cost [3] R Ghafurian, R N Dietz, T Rodenbaugh,
During 1998 Brookhaven Laboratories (USA associated with locating a leak via J Dominguez and N Tai: “Leak Location in
based research laboratory), Con Edison cryogenic freezing. Fluid Filled Cables Using the PFT Method”,
(New York based utility) and EPRI (USA based IEEE Transactions on Power Delivery, October
South Africa and PFT 1998.
research organisation) reported on leak
location in fluid filled cable circuits utilising The biggest South African utility is currently Contact Mike Engelbrecht,
the per fluorocarbon trace (PFT) method [3]. in the process of adjudicating tenders CBI electric : African Cables,
This method of leak detection uses small associated with PFT. The technology has been Tel 016 430-6270,
traces of PFT liquid, dissolved into cable proven in both American and British electrical mike.engelbrecht@africancables.com v

energize - October 2008 - Page 34

You might also like