A project manager is drafting a charter for a software development project. In support of this process, the project
manager has scheduled a brainstorming meeting to gather relevant information.
Which of the following activities is the project manager least likely to conduct?
Hint:
Which answer choice represents an activity that can only occur later in the project?
Correct Answer: D
Explanation:
The question states that the project charter is being developed, which occurs during project initiation. Brainstorming is a
data gathering technique which may be useful in the development of the project charter. Brainstorming is a specialized
meeting led by a facilitator which can be used to gather data and solutions or ideas from stakeholders, subject matter
experts, and team members when developing the project charter. Note, the question is asking for the activity which is
'least' likely to be conducted during the development of the project charter. The communications management plan is not
created until later in the project during the Plan Communications Management process. Therefore, the project manager
would not be able to follow the communications management plan in determining the meeting attendees, making this the
'least' likely activity to be conducted in this scenario.
Reference:
A Guide to the Project Management Body of Knowledge, (PMBOK® Guide) – Sixth Edition, Project Management Institute
Inc., 2017, Page(s) 80
https://www.project-management-prepcast.com/6-pmp-exam-simulator/task,stu_result/stu_id,1061810/id,6/quiz_id,127?task=stu_result&tmpl=quiz&id=6 2/2