Professional Documents
Culture Documents
RPRTNGFRM Eng
RPRTNGFRM Eng
and
INTEGRITY INSPECTION INFORMATION
REPORTING FORM
March 2013
Page 1 of 18
Introduction
The National Energy Board (NEB) requires certain NEB-regulated companies that own or operate pipelines
to annually report on pipeline performance measures and integrity inspection Information. These
companies comprise 96 percent of the length of operating pipelines that the NEB regulates. This report
form is for the 2015 calendar year. The information is on six key management system programs that
companies must maintain in accordance with the National Energy Board Onshore Pipeline Regulations.
Guidance
To enhance the accuracy and consistency of company reporting, guidance on definitions, descriptions of
terms, and interpretation is on the NEB website (www.neb-one.gc.ca).
2. A numerical value is required for all fields other than the comment fields. Where there is no data to be
entered (e.g. the field is not applicable) then the field is to be left blank. The comment field should be used
to explain more detail or identify any unusual events, trends or results.
3. Please submit only one workbook per pipeline system. There may be several workbooks for a given legal
company name depending on the number of pipeline systems. For any given system, only pipelines of 50
kilometres or more are to be entered in the form. A company can select their legal name on record with the
NEB from the dropdown on the "Main" tab and can fill out the pipeline system name. Data from each
pipeline in the pipeline system should be located on a separate Pipeline tab. You can add a tab using the
"Add Pipeline" button at the bottom of a pipeline page.
4. Where multiple companies utilize joint employees or other information, do not enter the same
information on each company report form. The aggregation of information results in duplicate entries. The
comment box can be used to identify where staff or activities are recorded on another company form.
5. For some of the Integrity Management Performance Measures (Section IV -1, 5 and 6) and the Integrity
Information (Section V) a separate worksheet (see the Pipeline tab at the bottom of the report form) is used
to capture data for each pipeline that makes up the pipeline system. The name of each pipeline must be
entered on a separate tab as well as in the pipeline specific form at Section IV-1.
This report form must be submitted on or before 1 April 2016, by email for each pipeline system to:
pipelinemeasures@neb-one.gc.ca
Further Information
If a company or person requires more information about the performance measures or the program for
managing the measures, please contact the NEB via mail, email, fax or telephone as follows:
Page 2 of 18
Email: pipelinemeasures@neb-one.gc.ca
TABLE OF CONTENTS
I. Safety Management
1. Facility Safety Inspections
2. Corrective and Preventative Actions
3. Near Misses
II. Security
1. Training and Competency
III. Emergency Management
1. Emergency Response Exercises
2. Communication
3. Training and Competency
4. Coordinating Operational Activities
IV. Integrity Management
1. Pipeline Condition
2. Equipment Inspection
3. Facility Piping Inspection
4. Facility Inspection Effectiveness
5. Assessment of Pipeline Hazards
6. Shutdowns for Hazard Control
V. Integrity Inspection Information
1. General
2. Kilometres of Integrity In-Line Inspections
3. Integrity Actions Taken Based on In-Line Inspections
4. Pipeline Condition Features Exceeding Integrity Criteria
VI. Environmental Protection
1. Program Training
2. Site-Specific Training
3. Restoration of Agricultural Land
4. Resolution of Environmental Issues
5. Environmental Inspections
VII. Damage Prevention
1. Public Awareness - Contractors
2. Public Awareness - Municipalities
3. Public Awareness - Landowners
4. Public Awareness - Others
Page 3 of 18
PIPELINE SYSTEM PERFORMANCE REPORTING
General Information
Pipeline Company Name:
Pipeline System Name:
Reporting Year: 2016
Contact Person:
Contact Email:
Contact Telephone:
I. Safety Management 1. Facility Safety Inspections
Data
c. Percentage 0.00%
B. Construction Corrective and Preventative Actions
c. Percentage 0.00%
Comments
I. Safety Management - 3. Near Misses
Data
A. Company Employee Near Misses
Page 4 of 18
a. The total number of company
employee near misses reviewed
by a competent person and
addressed
c. Percentage 0.00%
Comments
II. Security Measure - 1. Training and Competency
Data
c. Percentage 0.00%
Comments
III. Emergency Management - 1. Emergency Response Exercises
Data
A. Drills
a. The total number of drills
conducted
b. The total number of drills plan 1
c. Percentage 0.00%
B. Tabletop (i.e. Mock) Emergency Response Exercises
Page 5 of 18
d. The total number of
functional exercises conducted
Comments
III. Emergency Management - 2. Communication
Data
Consulting With All Agencies During the Updating of Emergency Procedures Manuals and Response
Plans
a. The number of liaison
activities conducted
b. The number of liaison
1
activities planned
c. Percentage 0.00%
Comments
III. Emergency Management - 3. Training and Competency
Data
c. Percentage 0.00%
Comments
III. Emergency Management - 4. Coordinating Operational Activities
Data
Page 6 of 18
a. The total number of company
employees and contractors who
have participated in emergency
response exercises and drills
c. Percentage 0.00%
Comments
IV. Integrity Management
Go to Individual Pipeline Section
IV. Integrity Management - 2. Equipment Inspection
Data
A. Tank Inspections
a. The total number of tanks 1
c. Percentage 0.00%
Comments
d. The total number of
scheduled routine staff tank 1
inspections
e. Percentage 0.00%
Comments
g. Percentage 0.00%
Comments
i. Percentage 0.00%
Comments
B. Mainline Valve Inspections
a. The total number of mainline
1
valves
Page 7 of 18
b. The total number of routine
staff mainline valve inspections
c. Percentage 0.00%
Comments
d. The total number of
scheduled routine staff mainline 1
valve inspections
e. Percentage 0.00%
Comments
f. The total number of certified
maintenance mainline valve
inspections
g. Percentage 0.00%
Comments
h. The total number of
scheduled certified
1
maintenance mainline valve
inspections
i. Percentage 0.00%
Comments
IV. Integrity Management - 3. Facility Piping Inspection
Data
A. Liquid Pump Stations
a. The total number of pump
stations
Page 8 of 18
Comments
B. Gas Compressor Stations
a. The total number of
compressor stations
g. Percentage 0.00%
Comments
IV. Integrity Management - 4. Inspection Effectiveness
Data
A. Liquid Facility Incidents
a. The total number of
reportable incidents at liquid
facilities
b. The total number of liquid
1
facilities
c. Ratio 0.00
Comments
B. Gas Facility Incidents
a. The total number of
reportable incidents at gas
facilities
b. The total number of gas
1
facilities
c. Ratio 0.00
Comments
V. Integrity Inspection Information
Go to Individual Pipeline Section
Page 9 of 18
Go to Individual Pipeline Section
VI. Environmental Protection - 1. Environmental Protection Program Training
Data
c. Percentage 0.00%
Comments
VI. Environmental Protection - 2. Site-Specific Environmental Protection Plan Training
Data
a. Kilometres of NEB-regulated
right-of-way on agricultural land
that is restored to a condition
similar to the surrounding
environment and consistent
with the current land use with
an in-service date within the last
5 years (including the current
reporting year).
Page 10 of 18
b. The total kilometres of NEB-
regulated right-of-way that is 1
disturbed agricultural land
within the last 5 years (including
the current reporting year).
c. Percentage 0.00%
Comments
B. Operational Excavations within the last 5 years
a. Number of operational
excavations on agricultural land
that are restored to a condition
similar to the surrounding
environment and consistent
with the current land use for
excavations within the last 5
years (including the current
reporting year).
c. Percentage 0.00%
Comments
VI. Environmental Protection - 4. Resolution of Environmental Issues
Data
Page 11 of 18
b. The total number of
operational environmental
issues identified in the
Environmental Protection
Program or Environmental
1
Protection Plan over a five-year
period (five year period began
with issues identified at the
start of 2013 and carries
forward)
c. Percentage 0.00%
Comments
VI. Environmental Protection – 5. Environmental Inspections
Data
Page 12 of 18
VII. Damage Prevention - 3. Pipeline Awareness - Landowners
Data
a. The total number of
unauthorized activities by 1
landowners
c. Ratio 0.00
Comments
Report Validation Information
Pipeline Company Name:
Pipeline System for This Report:
Page 13 of 18
Pipeline Specific Reporting
Return to Main Form
IV. Integrity Management - 1. Pipeline Condition
Data
Pipeline Name:
a. The total number of features
identified by ILI for field investigation,
1
according to IMP dig criteria, for metal
loss
c. Percentage 0.00%
Comments
f. Percentage 0.00%
Comments
Page 14 of 18
Return to Main Form to Fill Out Part IV - 2, 3, & 4
IV. Integrity Management - 5. Assessment of Pipeline Hazards
Data
i. Percentage 0.00%
j. The kilometres of pipeline where
material, manufacturing or
construction hazard assessment was
received in this calendar year
l. Percentage 0.00%
m. The kilometres of pipeline where
geotechnical and weather-related
hazard assessment was received in
this calendar year
Page 15 of 18
n. The kilometres of pipeline that are
susceptible to geotechnical and 1
weather-related hazards prior to any
form of mitigation
o. Percentage 0.00%
Comments
IV. Integrity Management - 6. Pipeline Integrity Shutdowns for Hazard Control
Data
Comments
Page 16 of 18
c. Reinspection frequency in years for pipeline specific criteria based on hazardous conditions for:
i. Corrosion or metal loss tool
ii. Dent or deformation tool
iii. crack or long seam feature
detection tool
Comments
V. Integrity Inspection Information - 2. Kilometres of Integrity In-Line Inspections
Data
a. Kilometres inspected in the calendar
year using corrosion or metal loss in-
line inspection tools
Comments
V. Integrity Inspection Information - 4. Pipeline Condition Features Exceeding Integrity Criteria
Data
Features Excavated
Page 17 of 18
Based on excavation data, the total
number of features exceeding CSA
Z662 criteria, for dents.
Comments
Return to Main Form
Page 18 of 18