Name of the Project : Purvanchal Expressway (Package-ll)

Client : UPEIDA
Authority Engineer : Egis Date of Submission: 17-Jul-20
EPC Contractor : Gayatri Projects Limited Date of Inspection: 18-Jul-20
RFI Reference Activity Details Location Inspection Required Previous
Sl.No. Activity Length Side Layer Remarks
No. Date Work Layer From To Date Time
Type Details
Highway :
1 PE/GPL/P-2/HW/07/20/23314 17-07-20 L Kerb Laying of Kerb Casting (MCW) 41170 41290 120 RHS 18-07-20 10:30 AM

2 PE/GPL/P-2/HW/07/20/23315 17-07-20 L Kerb Laying of Kerb Casting (MCW) 41170 41250 80 LHS 18-07-20 2:30 PM

3 PE/GPL/P-2/HW/07/20/23316 17-07-20 Median Drain Shuttering checking & concreting for median drain wall Wall 41480 41520 40 18-07-20 12:30 PM

4 PE/GPL/P-2/HW/07/20/23317 17-07-20 Shoulder FDD of Earthen shoulder 2 42720 43290 570 LHS 18-07-20 10:00 AM

5 PE/GPL/P-2/HW/07/20/23318 17-07-20 Shoulder FDD of Earthen shoulder 1 42720 43290 570 RHS 18-07-20 11:30 AM

6 PE/GPL/P-2/HW/07/20/23319 17-07-20 EmB FDD of Embankment (MCW) 9 43750 43800 50 BHS 18-07-20 12:30 PM

7 PE/GPL/P-2/HW/07/20/23320 17-07-20 EmB FDD of Embankment (MCW) 22 43800 43900 100 RHS 18-07-20 4:30 PM

8 PE/GPL/P-2/HW/07/20/23321 17-07-20 EmB FDD of Embankment (MCW) 23 43900 44000 100 BHS 18-07-20 12:00 PM

9 PE/GPL/P-2/HW/07/20/23322 17-07-20 Median Median filling Top 44030 44220 190 18-07-20 3:30 PM

10 PE/GPL/P-2/HW/07/20/23323 17-07-20 Chute Drain Checking & Concreting of raft for Chute Drain Raft 44740 44840 100 RHS 18-07-20 11:00 AM

11 PE/GPL/P-2/HW/07/20/23324 17-07-20 Shoulder FDD of Earthen shoulder 1 45560 45740 180 LHS 18-07-20 12:00 PM

12 PE/GPL/P-2/HW/07/20/23325 17-07-20 Shoulder FDD of Earthen shoulder 1 45560 45740 180 RHS 18-07-20 12:30 PM

13 PE/GPL/P-2/HW/07/20/23326 17-07-20 SG FDD of Subgrade (MCW) Top-1 45800 45900 100 BHS 18-07-20 11:00 AM

14 PE/GPL/P-2/HW/07/20/23327 17-07-20 Chute Drain Checking & Concreting of raft for Chute Drain Raft 46600 46700 100 LHS 18-07-20 10:45 AM

15 PE/GPL/P-2/HW/07/20/23328 17-07-20 Shoulder FDD of Earthen shoulder 2 46620 46870 250 LHS 18-07-20 10:30 AM

16 PE/GPL/P-2/HW/07/20/23329 17-07-20 Shoulder FDD of Earthen shoulder 2 46620 46870 250 RHS 18-07-20 11:30 AM

17 PE/GPL/P-2/HW/07/20/23330 17-07-20 Side Slope Checking Of Side Slope (MCW) 46680 46780 100 LHS 18-07-20 1:00 PM

18 PE/GPL/P-2/HW/07/20/23331 17-07-20 Chute Drain Checking & Concreting of raft for Chute Drain Raft 46800 46870 70 RHS 18-07-20 10:30 AM

19 PE/GPL/P-2/HW/07/20/23332 17-07-20 Shoulder FDD of Earthen shoulder 1 46870 47060 190 RHS 18-07-20 11:30 AM

20 PE/GPL/P-2/HW/07/20/23333 17-07-20 EmB FDD of Embankment (MCW) 23 47400 47450 50 BHS 18-07-20 3:00 PM 23257/16-07-20

21 PE/GPL/P-2/HW/07/20/23334 17-07-20 EmB FDD of Embankment (MCW) 19 47450 47550 100 BHS 18-07-20 2:30 PM

22 PE/GPL/P-2/HW/07/20/23335 17-07-20 EmB FDD of Embankment (MCW) 14 47620 47700 80 BHS 18-07-20 2:30 PM

23 PE/GPL/P-2/HW/07/20/23336 17-07-20 Shoulder FDD of Earthen shoulder Top 49020 49210 190 LHS 18-07-20 10:00 AM

24 PE/GPL/P-2/HW/07/20/23337 17-07-20 Shoulder FDD of Earthen shoulder Top 49020 49210 190 RHS 18-07-20 11:00 AM

25 PE/GPL/P-2/HW/07/20/23338 17-07-20 Shoulder FDD of Earthen shoulder Top 49210 49580 370 LHS 18-07-20 3:00 PM

26 PE/GPL/P-2/HW/07/20/23339 17-07-20 Shoulder FDD of Earthen shoulder Top 49210 49580 370 RHS 18-07-20 2:00 PM

27 PE/GPL/P-2/HW/07/20/23340 17-07-20 Median Median filling Top 49210 49580 370 18-07-20 2:00 PM

28 PE/GPL/P-2/HW/07/20/23341 17-07-20 Chute Drain Checking & Concreting of raft for Chute Drain Raft 49400 49540 140 RHS 18-07-20 11:45 AM

29 PE/GPL/P-2/HW/07/20/23342 17-07-20 Tack Coat Application of Tack Coat Over Prime Coat (MCW) 54230 54530 300 LHS 18-07-20 12:00 PM

30 PE/GPL/P-2/HW/07/20/23343 17-07-20 DBM Laying & Level Cheking of DBM ( MCW) Top 54230 54530 300 LHS 18-07-20 12:30 PM

31 PE/GPL/P-2/HW/07/20/23344 17-07-20 Tack Coat Application of Tack Coat Over Prime Coat (MCW) 54280 54380 100 RHS 18-07-20 9:30 AM

32 PE/GPL/P-2/HW/07/20/23345 17-07-20 DBM Laying & Level Cheking of DBM ( MCW) Top 54280 54380 100 RHS 18-07-20 10:00 AM
Page 1 of 2
RFI Reference Activity Details Location Inspection Required Previous
Sl.No. Activity Length Side Layer Remarks
No. Date Work Layer From To Date Time
Type Details

33 PE/GPL/P-2/HW/07/20/23346 17-07-20 Re-FDD GSB FDD On GSB Top Layer (MCW) Top 55600 55910 310 RHS 18-07-20 10:00 AM

34 PE/GPL/P-2/HW/07/20/23347 17-07-20 WMM Laying & Fdd testing of WMM (MCW) Top-1 55790 55910 120 LHS 18-07-20 11:00 AM

35 PE/GPL/P-2/HW/07/20/23348 17-07-20 WMM Laying & Fdd testing of WMM (MCW) Top-1 55800 55910 110 RHS 18-07-20 11:30 AM

36 PE/GPL/P-2/HW/07/20/23349 17-07-20 Tack Coat Application of Tack Coat Over Prime Coat (MCW) 57020 57220 200 RHS 18-07-20 11:00 AM

37 PE/GPL/P-2/HW/07/20/23350 17-07-20 DBM Laying & Level Cheking of DBM ( MCW) Top 57020 57220 200 RHS 18-07-20 11:45 AM

38 PE/GPL/P-2/HW/07/20/23351 17-07-20 L Kerb Laying of Kerb Casting (MCW) 63630 63740 110 LHS 18-07-20 11:00 AM

39 PE/GPL/P-2/HW/07/20/23352 17-07-20 L Kerb Laying of Kerb Casting (MCW) 63630 63740 110 RHS 18-07-20 3:30 PM

40 PE/GPL/P-2/HW/07/20/23353 17-07-20 Mountable Kerb Laying of Mountable Kerb (MCW) 63800 63870 70 RHS 18-07-20 4:30 PM

41 PE/GPL/P-2/HW/07/20/23354 17-07-20 EmB FDD of Embankment (MCW) 9 66900 67000 100 LHS 18-07-20 4:30 PM

42 PE/GPL/P-2/HW/07/20/23355 17-07-20 DBM Surface irregularities of DBM Top 68370 68770 400 LHS 18-07-20 11:45 AM

43 PE/GPL/P-2/HW/07/20/23356 17-07-20 DBM Surface irregularities of DBM Top 68550 68770 220 RHS 18-07-20 10:00 AM

44 PE/GPL/P-2/HW/07/20/23357 17-07-20 GSB FDD & Level Checking On GSB Top Layer (MCW) Top 71000 71100 100 LHS 18-07-20 4:00 PM

45 PE/GPL/P-2/HW/07/20/23358 17-07-20 EmB FDD of Embankment (MCW) 18 71100 71220 120 LHS 18-07-20 4:00 PM

46 PE/GPL/P-2/HW/07/20/23359 17-07-20 EmB FDD of Embankment (MCW) 18 71100 71220 120 RHS 18-07-20 12:00 AM

47 PE/GPL/P-2/HW/07/20/23360 17-07-20 EmB FDD of Embankment (MCW) 3 75680 75720 40 BHS 18-07-20 11:00 AM

48 PE/GPL/P-2/HW/07/20/23361 17-07-20 EmB FDD of Embankment (MCW) 6 77760 77780 20 BHS 18-07-20 3:30 PM

Service Road :
1 PE/GPL/P-2/SR/07/20/1745 17-07-20 EmB FDD of Embankment (SR) 10 76900 77000 100 LHS 18-07-20 5:00 PM 1714/02-07-20

Lab :
1 PE/GPL/P-2/Lab/07/20/842 17-07-20 Core Test Core cutting of DBM (MCW) 68550 68770 220 RHS 18-07-20 10:00 AM

2 PE/GPL/P-2/Lab/07/20/843 17-07-20 BA Sampling Sampling of Borrow Area-315 76300 LHS 18-07-20 11:00 AM

Structures :

1 PE/GPL/P-2/STR/07/20/6007 17-07-20 PUP Raft Reinforcement , shuttring checking & concreting for PUP (MCW) 45770 RHS 18-07-20 10:00 AM

Raft Reinforcement , shuttring checking & concreting for MNB


2 PE/GPL/P-2/STR/07/20/6008 17-07-20 MNB 50916 LHS 18-07-20 11:00 AM
(MCW)

Wall final lift ,haunch , bracket & slab reinforcement , shuttring


3 PE/GPL/P-2/STR/07/20/6009 17-07-20 VUP 68323 RHS 18-07-20 2:00 PM
checking & concreting VUP (MCW)

4 PE/GPL/P-2/STR/07/20/6010 17-07-20 MNB A2 side Initial Load test checking for Vertical Load for MNB (MCW) 77963 LHS 18-07-20 10:00 AM

Page 2 of 2