Section: RJN - DGG Dongargarh-Paniajob-Bortalao: Project: Rajnandgaon - Kalumna 3 Line Under CE C NGP
Section: RJN - DGG Dongargarh-Paniajob-Bortalao: Project: Rajnandgaon - Kalumna 3 Line Under CE C NGP
Section: RJN - DGG Dongargarh-Paniajob-Bortalao: Project: Rajnandgaon - Kalumna 3 Line Under CE C NGP
2020)
Section : Chhhattisgarh portion (ex BTL) i.e. approx. 47 Km with CE Con BSP
RJN – DGG firmly targeted for Feb 2021 (Rly Board)
Dongargarh-Paniajob-Bortalao 3rd line (16.70 km, in DGG ex BTL) (TDC Dec 2022)
1- Project sanction
EBR IF funded Work sanctioned in 2015-16 at the anticipated cost of Rs. 1272.65
crores. Single Estimate controlled by CE CON NGP, Accounting Unit at NAGPUR.
Last Revised Estimate Sanctioned for Rs. 2686.63 Crores in Feb 2019. Another
Revision under process at NGP Unit
Tech Details (nutshell)
2. Section Land - All in RJN district, SDM DGG area, DFO Khairagarh. Land for
the detour alignment (only required in detour & ROB) between PJB-BTL is to be
acquired. The details are as under:
Tree Cutting – 1200 in Rly Land, and in other portions, counting in progress.
Approx 10000-12000 expected (census is combined with process of
Acquisition/diversion). For Rly portion, 1200 trees, Collector permission
expected in one month.
o Major Bridge- Was Approved as Box Culvert ( shall undergo revision in view
of Rly Board Letter)
5. Tenders
Tenders for Earth Work, Bridges, Track & Ballast Supply and Building work
from DGG-PJB (7.9 Km) has been awarded along with RJN-DGG section and
work in progress (see table below)
7. Pertinent Issues:
Acquisition of Pvt and Govt Land 33 Approx hectare in between PJB-BTL in 4.5 Km
length out of 7 Km will depend on State Govt. Rajnandgaon District has been difficult,
as seen in RJN-DGG portion, where in Nagtarai and Accholi Village portion is still
litigated since physical possession has not been facilitated by District. Matter has to be
escalated at higher levels for timely intervention
Tunnel of 200 m length – all in Forest portion (PJB – BTL). Planned as Cut – Cover
Planning of invitation of tenders – For the Govt and Pvt Land Portion between PJB –
BTL, Land is expected by Feb 2021, and therefore Tenders can be planned now, so that
work can commence in Railway and Acquired portion in next working season. Forest
Portion tenders can be taken up after Online Application is completed, i.e. Sep 2020
(includes the tunnel portion)
Tree cutting permission for 13000 trees approx both in Railway area and to be
acquired– it is linked to forest land diversion – shall have to be chased up aggressively