Download as xlsx, pdf, or txt
Download as xlsx, pdf, or txt
You are on page 1of 4

SHRIRAM EPC LTD.

DAILY PROGRESS REPORT Date 20-06-20


i Project Start Date:- 04.12.2018 CLIENT :- JUIDCO Ltd.
ii Project End Date:- 03.09.2021 CONSULTANT:- NJS Engineers India Pvt. Ltd.
iii Project Name :- Dhanbad Water Supply Scheme Phase-I REPORT DATE: 22-06-20
iv Weather Report :- Cold & Sunny HOLIDAY -
MANPOWER - MACHINE - MATERIAL DESCRIPTION
Manpower Strength Machine Description Material Details
Opening
Working Location Skilled Unskilled Machine Description Qty Working Material Received Issued Balance
Balance
i Zone-01 (Rahul Chowk) JCB 4 0 Cement (Bag) 15 2750 2735 15
ii Zone-02 (Tilatand) Excavator 1 0 Sand (m³) 13 276 263 13
iii Zone-03 (Chhatabad) Hydra 3 0 Aggregate (m³) 2 308 307 2
iv Zone-34 (Kustour) Tractor 4 0 Steel (MT) 0.267 50.701 50.434 0.267
v ESR-02 ( Leloristhan) 4 4 Truck 1 0
vi ESR-03 ( Tetulmari) 2 4 Tractor/Hand Breaker 7 0
vii ESR-06 ( Godhar) 8 14 Mixer Machine 1 0
Total Labours 36 Total 21 0
1.Rising & Gravity Mains.
Supply Details Laying Details
Sl No Description of Works Pipe Size BOQ Qty. Remarks
Previous Today Cumulative Previous Today Cumulative
100 mm Dia 0 - - - - - -
150 mm Dia 0 - - - - - -
200 mm Dia 0 - - - - - -
250 mm Dia 580 - - - - - -
Supply, Laying,Testing and Commissioning 300 mm Dia 5618 - - - - - -
1 of Clear Water Rising and Gravity Main
Pipelines(DI-K9) 350 mm Dia 1587 - - - - - -
400 mm Dia 8417 - - - - - -
450 mm Dia 1839 - - - - - -
500 mm Dia 3347 - - - - - -
600 mm Dia 4,426 - - - - - -
Total Length 25,814 0 0 0 0 0 0
2. Distribution Pipelines(19 Zones)
Supply Details Laying Details
Sl No Description of Works Pipe Size BOQ Qty. (Mtr) Remarks
Previous Today Cumulative Previous Today Cumulative
100 mm Dia 284712 150291.5 0 150291.5 85237.90 0.00 85237.90
150 mm Dia 42521 - - - - - -
200 mm Dia 19597 - - - - - -
250 mm Dia 9897 - - - - - -
300 mm Dia 9443 - - - - - -
Supply, Laying,Testing and No work due to rain.
1 Commissioning of Distribution 350 mm Dia 4523 - - - - - -
Pipelines(DI-K7) Total Nos. of Zone- 19 400 mm Dia 4469 - - - - - -
450 mm Dia 1513 - - - - - -
500 mm Dia 2854 - - - - - -
600 mm Dia 295 - - - - - -
Total Length 379824 150291.5 0 150291.5 85237.90 0.00 85237.90

2 Fittings & Specials 429000.4 (Kg) 38436 0 38436 9258 0 9258.00


SHRIRAM EPC LTD.
Earthwork in excavation (As perofI.S
Description 3114 /1965 for laying
Works BOQ Qty. Previous Today Cumulative
of different types and sizes of pipes so as to give one
meter average cover over the socket of pipe with disposal
3 220849.04 53699.877 0 53699.877
of excavated earth within initial lead and lift as per
specification
Earthwork in and
Extra for earthwork direction
in allof
excavation of
kindsEngineer-in-Charge
of soil for
foundation of(b) As
each additional
trenches
4 per
lift classification
of
toewall,1mspillway, of soilregulator
or part thereof
head item
over-Btheintake
initial well
lift ofand
1.5m as per
outlet 191.38
specification
etc.as per design and direction
section inofordinary
Engineer-in-Charge.
or soft rock (vide
5 classification of soil item-C) and disposal of soil (beyond 24538.78
50 M away from the edge of the trenches) with initial
lead of 150 M and initial lift of 1.5 m as per
Supplying
specification tools anddirection
and cutting road as well
of E/I restoring
(where theissame
blasting not as per
6
specification
required). and direction of E/I.
Pucca Road (Except black top only taken out material to
7 11245.47
be used) for cutting road as per requirement.
Water bound macadam road (taken out material will
8 be used) for cutting road as per requirement and 17492.96
Dismantling
making goodplain cement or lime concrete work
the same.
including stacking serviceable materials in countable
9 stacks within
Providing 15 meter
coarse lead and
clean sand disposal
in filling of un-
in foundation 1936.72 1530 0 1530
serviceable
trenches or materials with all leads
in plinth including all complete
ramming and wateringas perin
direction of E/I
layers not exceeding 150mm thick with all leads and lifts
10 1811.77
including cost of all materials, labour, royalty and taxes all
Providing
complete designation
as per building 75Aspecification
one brick flat andsoling joint filled
direction of E/I
with local
Providing
(mode sand
PCC including cost
M-150 incompacted
of measurement of watering,
nominal mix of taxes,
volume) (1:2:4)royalty,
in
11 24156.94
all
foundation with approved quality of stones chips 20of
complete as per building specification and direction
E/I. to 6 mm size graded and clean coarse sand of
mm
12 FM 2.5 to 3.0 including screening, shuttering, mixing 3623.54
Earthwork in back in
cement concrete filling
mixer theand
trenches
placingafter laying
in position,
different
vibrating,types andcuring,
striking, sizes oftaxes
pipesandwith earthall
royalty removed
complete
13 during excavation
Providing coarse
as per building within
clean initial
sand
specification in
and lead
filling and liftofasE/I
in foundation
direction per 225339.07 52948.06 0.00 52948.06
specification
trenches or inand design
plinth of Engineer
including ramming -in- and
charge (for in
watering
classification
layers of soil item
not exceeding 150mmA & Bthick
) with all leads and lifts
14 31335.48
including cost of all materials, labour, royalty and taxes all
complete as per building specification and direction of E/I
3. Consumer Surveycompacted volume)
(mode of measurement
SL No. Description Units BOQ Quantity Previous Today Cumulative Remarks

Consumer Survey Sample 55245 52110 0 52110

4. ELEVATED SERVICE RESERVOIR


ESR-3
ESR-1 ESR-2 (13 Lakh Litre) ESR-4 ESR-5 ESR-6 ESR-7 ESR-8
Sl No Description Units (18 Lakh Litre) (21 Lakh Litre) Liloro Tetulmari near (17 Lakh Litre) (24.5 Lakh Litre) (24 Lakh Litre) (18 Lakh Litre) (20.5 Lakh Litre)
Chatabad near Jamia Asthan sarswati sisu Jila Parishad Gadeyriya WTP JMADA JMADA JMADA
Masjid mandir Bhandardih Plant Officer Colony Officer Colony Officer Colony

1 soil analysis (SBC ) Job Completed Completed Completed

2 Excavation Job Completed Completed Completed

3 Anti-termite Spray Job Completed Completed Due to public Completed


objection for
Due to low SBC construction of Work stopped due Awaiting for Awaiting for
4 PCC Job land changed and Completed Completed ESR in to low SBC and Completed approval from approval from
alternate land Community hall alternate land JMADA for JMADA for
5 RCC work in foundation Job verified and letter Completed Completed work stopped verified and letter Steel Binding removing the removing the
submitted to DMC and alternate submitted to DMC in progress existing building existing building
for NOC . land verified and for NOC . and tree. and tree.
6 Pedestals Job Completed Completed letter submitted
to DMC for NOC .
7 Grade Beam Job Completed Completed

1st half of staging height including 1st Brace beam 1st Brace beam
8 Job steel binding in steel binding in
room roof slab progress progress
SHRIRAM EPC LTD.
5. Compound Wall
SL No. Description Units BOQ Quantity Previous Today Cumulative Remarks
1 Excavation m3 352.64 226.6 0.0 226.6
2 Removal of Unserviceable Soil m3 222.72 203.9 0.0 203.9
3 PCC-M 15 m3 68.05 4.9 0.0 4.9
4 RCC- M 20 work in foundation m3 163.95 42.6 0.0 42.6
5 Steel Consumption MT 16.39 4.80 0.0 4.80
6 Brick Work m3 197.97 87.0 0.0 87.0
7 Plaster m² 1741.55 490.0 0.0 490.0
6. House Service Connections
SL No. Description No of Quantity Previous Today Cumulative Remarks

1 House Service Connections 55245


MATERIALS DETAILS FOR JUIDCO
CEMENT SAND AGGREGATE 8 MM 10 MM 12 MM 16 MM 20 MM
ESR NO. SITE
PUR USED PUR USED PUR USED PUR USED PUR USED PUR USED PUR USED PUR USED
1 Near Talab,Chattabad Masjid Road

2 Way to Lilori Sthal,Opposite Lilori Park 900 980 140.28 130 110 110 4.5 4 5.00 15 8.00 10.00 7.00 4 8.00 4

3 Near Sarsawati Shisu Mandir, 1050 1030 80 79 135 134 1.92 0.6 2.49 1.98 2.24 1.56 3.24 3.074 3.91 1.6
Tetulmari(Baba Chowk)

4 Near Chetudih Malkera Road,Chhatabad

In & Around Gareriya Water Treatment


5 15 1 1
Plant

6 JMADA Officers Colony 300 220 16 15 13 12

7 JMADA Officers Colony

8 JMADA Officers Colony

3 Tetulmari- Boundry Wall 500 490 40 38 50 50 1.5 1.6 0.5 0.3 2.2 2.5 0.2 0.15 0 0

TOTAL 2750 2735 276 263 308 307 8 6 8 17 12 14 10 7 12 6

BALANCE 15 13 2 1.7 -9.3 -1.6 3 6

You might also like