Shriram Epc LTD.: Daily Progress Report
Shriram Epc LTD.: Daily Progress Report
1st half of staging height including 1st Brace beam 1st Brace beam
8 Job steel binding in steel binding in
room roof slab progress progress
SHRIRAM EPC LTD.
5. Compound Wall
SL No. Description Units BOQ Quantity Previous Today Cumulative Remarks
1 Excavation m3 352.64 226.6 0.0 226.6
2 Removal of Unserviceable Soil m3 222.72 203.9 0.0 203.9
3 PCC-M 15 m3 68.05 4.9 0.0 4.9
4 RCC- M 20 work in foundation m3 163.95 42.6 0.0 42.6
5 Steel Consumption MT 16.39 4.80 0.0 4.80
6 Brick Work m3 197.97 87.0 0.0 87.0
7 Plaster m² 1741.55 490.0 0.0 490.0
6. House Service Connections
SL No. Description No of Quantity Previous Today Cumulative Remarks
2 Way to Lilori Sthal,Opposite Lilori Park 900 980 140.28 130 110 110 4.5 4 5.00 15 8.00 10.00 7.00 4 8.00 4
3 Near Sarsawati Shisu Mandir, 1050 1030 80 79 135 134 1.92 0.6 2.49 1.98 2.24 1.56 3.24 3.074 3.91 1.6
Tetulmari(Baba Chowk)
3 Tetulmari- Boundry Wall 500 490 40 38 50 50 1.5 1.6 0.5 0.3 2.2 2.5 0.2 0.15 0 0