EAMS

STANDARD INSPECTION AND TEST PLAN

ITP No: 573


INSTALLATION OF CELLULAR GLASS INSULATION
FOR TANK BASE (HOT SERVICE)

0 30/04/98 Issued for Implementation CMA SW MK


REV DATE REVISION BY CHKD APPR

p:\\itp\\mechan\\itp573.doc Standard Inspection and Test Plan ITP No. 573 Rev 0 Page 1 of 2
Standard Inspection and Test Plan
ITP No. 573

FORMS INDEX

LIST OF ATTACHED FORMS

No. Form No. Rev. Description


1. ITP-573 0 Installation of Cellular Glass Insulation for Tank Base (Hot
Service)

LIST OF REFERENCED FORMS

No. Form No. Doc. Ref. Description

Note: The referenced forms are included in and controlled by the referenced document.
Therefore, the latest revision of these forms, at the time of initiation of the forms, will be
utilised.
p:\\itp\\mechan\\itp573.doc Standard Inspection and Test Plan ITP No. 573 Rev 0 Page 2 of 2
STANDARD INSPECTION AND TEST PLAN ITP No. ITP-573

BECHTEL - EAMS INSTALLATION OF CELLULAR GLASS INSULATION Rev. No. 0


Hand. Class. Specific
FOR TANK BASE (HOT SERVICE)
Page 1 of 1
UNIT/ AREA EQUIPMENT NO./TANK NO. DESCRIPTION BARCODE

Activity Activity Inspection/Test Inspection and Acceptance Initials/Stamp and Date Report
No. Description Requirements Reference Document Sub-Contr. QC Contractor QC. Bechtel Rep. Client/TPI Rep. Reference No.:
573-1.0 Tank foundation complete ready for installation  Verify ITP-224 complete for tank ring, if ITP-221 H/R H/R
of cellular glass insulation. applicable. ITP-224
 Verify ITP-221 complete for earthworks. Spec. Rqs.
 Release for insulation.

573-2.0 Bitumen base applied to completed structural  Verify thickness of bitumen base as per spec. Spec. Rqmnts. W W
fill. rqmnts.

573-3.0 Insulation layers installed as per drawing/s with  Verify each layer installed as per drawing detail Detailed drawings W W
joints staggered and filled with specified filler. and joints adequately filled with specified filler. Spec. Rqmnts.

573-4.0 Top layer of insulation installed as per drawing  Verify top layer installed as per drawing/s Detailed drawings W W
with joints staggered and filled with specified detail and joints adequately filled with Spec. Rqmnts.
filler. specified filler.

573-5.0 Insulation laid over ring beam as per drawings.  Verify that insulation over ring beam is as per Detailed drawings W W
drawing and spec. requirement. Spec. Rqmnts.

573-6.0 Oil/sand mixture over top layer of insulation on  Verify thickness of oil/sand mixture is as per Spec. Rqmnts. W W
main base of tank. spec. rqmnts and with full coverage.

573-7.0 Oil/sand mixture over top layer of ring beam  Verify thickness of oil/sand mixture is as per Spec. Rqmnts. W W
insulation. spec. rqmnts and with full coverage.

573-8.0 Cellular insulation of tank base complete.  Verify all inspection/test requirements Spec. Rqmnts. H H W
complete and conformant.
 Insulation of tank base released.

Legend : S - Surveillance Inspection W - Witness Inspection Point H - Mandatory Hold Point For Inspection R - Record Review Note : * Generic Record not attached to ITP
Sub -contractor QC Date & Signature /Stamp No. Contractor QC Date & Signature /Stamp No. Bechtel Rep. Date & Signature /Stamp No. Client/TPI Rep. Date & Signature/ Stamp No. Computer. Ref. :