Professional Documents
Culture Documents
JSA LNG Tank Wall Construction
JSA LNG Tank Wall Construction
JSA LNG Tank Wall Construction
1 Erection of Formwork
Collision of the 2 Tower Cranes 1 1 1 TSKJN, CB&I and JBN Before being used: by TSKJN, CB&I,
Inspection of cranes, JBN,
Daily Checklists by Operators,
Units
Trip Hazard/Fall 2 1 2 Storage on Main (Middle) JSA/START/ToolBox Talk to be done
Platform only before work starts,
ScaffTag System to be
used per quadrant
2b Housekeeping
Trip Hazard/Fall 2 1 2 Clean up as required and Before moving any unit, housekeeping to
at the end of each shift be done
3 Concreting
Spillages, Unsafe Driving, 1 1 1 TSKJN, CB&I and JBN Before being used: by TSKJN, CB&I,
Unsafe Operation, Inspection of equipment, JBN,
Daily Checklists by Operators,
4 Access
6a Normal operations
6b Concreting
Notes:
1 If Emergency alarm sounds at any time any held or suspended load must be made safe with the minimum amount of staff and electrical equipment turned off before final
evacuation to the Muster Point.
2 Stop work where conditions change that affect the safety of the operation.
3 S.T.A.R.T. and Toolbox talk will be carried out by Supervisor before work starts.
Prepared by
Approved by