Work Method of Statement Topographic Survey

You might also like

Download as pdf or txt
Download as pdf or txt
You are on page 1of 13

PROJECT REPLACEMENT OF 34 INCH

Project: WORK METHOD OF STATEMENT


PIPELINE SECTION X 11 KM TOPOGRAPHIC SURVEY

Contractor: Alshola Almudia & Solcomei Document Number :TP-210364 GT SRTPPL 11


PM PR 013 1

Contractor Job Number : ED050


S IRT E OIL
Contract Number : 98 208-530-410
COMPANY
Sheet 1/ 13
Project N° TP-210364 GT

WORK METHOD OF STATEMENT


TOPOGRAPHIC SURVEY

001 23/01/2019 Issue for Review and Approval A.B.Mohamed S.Karoui


000 17/01/2019 Issue for Review and Approval A.B.Mohamed S.Karoui
Rev. Date REVISION TITLE PREPARED CHECKED APPROVED

Contractor Document Number: SRTPPL-PPL-CV-WP-005 Rev 01


PROJECT REPLACEMENT OF 34 INCH
Project: WORK METHOD OF STATEMENT
PIPELINE SECTION X 11 KM TOPOGRAPHIC SURVEY

Contractor: Alshola Almudia & Solcomei Document Number :TP-210364 GT SRTPPL 11


PM PR 013 1

Contractor Job Number : ED050


S IRT E OIL
Contract Number : 98 208-530-410
COMPANY
Sheet 2/ 13
Project N° TP-210364 GT

INDEX:

1 INTRODUCTION AND SCOPE .......................................................................................... 3


1.1 GENERAL ................................................................................................................... 3
1.2 SCOPE OF THE DOCUMENT .................................................................................... 3
1.3 DEFINITIONS .............................................................................................................. 3
1.4 ACRONYMS AND ABBREVIATIONS .......................................................................... 4
1.5 REFERENCE DOCUMENTS ....................................................................................... 4
2 TOPOGRAPHICAL SURVEY REQUIREMENTS ................................................................ 4
2.1 GENERAL ................................................................................................................... 4
2.2 COORDINATE SYSTEM ............................................................................................. 5
2.3 SURVEY ACCURACY ................................................................................................. 5
2.4 PERMANENT BENCHMARKS .................................................................................... 5
2.5 SURVEY CONTROL POINTS ..................................................................................... 6
3 PIPELINE ROUTE SURVEY METHODOLOGY .................................................................. 7
3.1 GENERAL ................................................................................................................... 7
3.2 PIPELINE ROUTE CORRIDOR ................................................................................... 7
3.3 CROSSINGS ............................................................................................................... 7
3.4 PARALLELISM WITH BURIED OR OVERHEAD SERVICES ...................................... 9
4 PLANT AREAS SURVEY METHODOLOGY ....................................................................... 9
5 DATA PROCESSING AND RESTITUTION ....................................................................... 10
5.1 GENERAL ................................................................................................................. 10
5.2 ELECTRONIC DATA COLLECTOR .......................................................................... 10
5.3 DRAWINGS ............................................................................................................... 11
Route maps .......................................................................................................................... 12
Crossings ............................................................................................................................. 12
5.4 EXCEL FILES ............................................................................................................ 13
5.5 FINAL TOPOGRAPHIC REPORT ............................................................................. 13

Contractor Document Number: SRTPPL-PPL-CV-WP-005 Rev 01


PROJECT REPLACEMENT OF 34 INCH
Project: WORK METHOD OF STATEMENT
PIPELINE SECTION X 11 KM TOPOGRAPHIC SURVEY

Contractor: Alshola Almudia & Solcomei Document Number :TP-210364 GT SRTPPL 11


PM PR 013 1

Contractor Job Number : ED050


S IRT E OIL
Contract Number : 98 208-530-410
COMPANY
Sheet 3/ 13
Project N° TP-210364 GT

1 INTRODUCTION AND SCOPE

1.1 GENERAL
The objective of the Replacement of 11 kilometers of the Brega- Misurata 34” Gas Pipeline (Brega-
Sidra Section KM 5+100 to KM 16+595)
This document shall also act as a guide to construction personnel on how to carry out the works
safely and in accordance with environmental and contract requirements.
The scope of topographic survey work shall include the initial setting out of the pipeline route. This
shall be followed by Pre-construction survey, topographic survey report and setting out ROW limits
drawings. Information shall be passed to the Drawing Office to produce strip maps and special
crossing drawings. During construction top of pipe levels and co-ordinates shall be taken prior to
backfilling operations and the information processed to produce as-built drawings.

1.2 SCOPE OF THE DOCUMENT


This document defines the requirement for the site survey of the pipelines route and associated
facilities for the Replacement of 11 kilometers of the Brega- Misurata 34” Gas Pipeline.

1.3 DEFINITIONS
The following definitions will be used in this document without the needs of any further explanation:

PROJECT Replacement of 11 kilometers of the Brega- Misurata 34” Gas Pipeline (Brega-
Sidra Section KM 5+100 to KM 16+595)
COMPANY SIRTE OIL COMPANY for Production, Manufacturing of Oil & Gas.
Consortium between ALSHOLA ALMUDIA & Solcomi Engineering &
CONTRACTOR
Technical Services. forming awarding entity of this CONTRACT

Should Is to be understood as strongly recommended

Is to be understood as giving freedom of choice


May be

Contractor Document Number: SRTPPL-PPL-CV-WP-005 Rev 01


PROJECT REPLACEMENT OF 34 INCH
Project: WORK METHOD OF STATEMENT
PIPELINE SECTION X 11 KM TOPOGRAPHIC SURVEY

Contractor: Alshola Almudia & Solcomei Document Number :TP-210364 GT SRTPPL 11


PM PR 013 1

Contractor Job Number : ED050


S IRT E OIL
Contract Number : 98 208-530-410
COMPANY
Sheet 4/ 13
Project N° TP-210364 GT

1.4 ACRONYMS AND ABBREVIATIONS

The following abbreviations will be used in this document:

DGPS Differential Global Positioning System


EPC Engineering, Procurement and Construction
FEED Front End Engineering Design
GPS Global Positioning System
IP’s Intersection Points KP Kilometre Post
LGL General Lybian Level
RTK Real Time Kinematic method
UTM Universal Transverse Mercator
WGS World Geodetic System

1.5 REFERENCE DOCUMENTS


Document No. Document title
C7-1737 A, B & C Legend Topography
1225-RS01-RS06-GD-L-2-AB

JS CS 1001 0 Surveying

2 TOPOGRAPHICAL SURVEY REQUIREMENTS

2.1 GENERAL
CONTRACTOR shall perform the topographical survey and mapping work required for the detail
design of the pipelines and associated facilities. As a minimum, CONTRACTOR shall carry out
the following activities:

 verify location of existing benchmarks and field survey control points;


 establish new permanent benchmarks along pipeline routes;

Contractor Document Number: SRTPPL-PPL-CV-WP-005 Rev 01


PROJECT REPLACEMENT OF 34 INCH
Project: WORK METHOD OF STATEMENT
PIPELINE SECTION X 11 KM TOPOGRAPHIC SURVEY

Contractor: Alshola Almudia & Solcomei Document Number :TP-210364 GT SRTPPL 11


PM PR 013 1

Contractor Job Number : ED050


S IRT E OIL
Contract Number : 98 208-530-410
COMPANY
Sheet 5/ 13
Project N° TP-210364 GT

 field survey pipeline using DGPS surveying techniques;


 identify, measure, define and survey any existing pipelines, and kind of road crossings
and other above/underground facilities and features within the surveyed area
 Detailed field survey map of every significant point (tie-in points, line valve stations,
crossings, etc.);
 Get location of existing overhead electrical power lines of various voltage close to pipeline
route;
 Processing survey data;
 Delivery of drawings, data and mapping as detailed in this specification;
 excel files of ground profile of the surveyed lines;
 Final survey report and final data back-up of all deliverables in Autocad.

2.2 COORDINATE SYSTEM


The coordinate system that shall be used for mapping the Pipeline shall be WGS84 Datum .

2.3 SURVEY ACCURACY


The accuracy of the survey works for the project shall be as follows:

 for the permanent benchmarks and control points the accuracy of measurements shall not
exceed ± 2,5 cm in plan and ± 5 cm in elevation;
 for the pipeline corridor the accuracy of measurements shall be ± 5cm in plan and ± 10cm
in elevation including any earth works and any other objects above ground.

2.4 PERMANENT BENCHMARKS


CONTRACTOR shall verify the existing benchmarks already established during a previous
topographical survey and reported in ref. [1].
If necessary, new permanent benchmarks shall be established along pipeline routes at intervals
of approximately 50 to 100 m , in protected locations outside the construction area for their
preservation, and they will be referenced to pipeline stationing by station and offset.
The location of these new benchmarks shall be inspected by Company and set up as drawings.
A triangulation system will be laid out for the control of future on-site construction surveys with

Contractor Document Number: SRTPPL-PPL-CV-WP-005 Rev 01


PROJECT REPLACEMENT OF 34 INCH
Project: WORK METHOD OF STATEMENT
PIPELINE SECTION X 11 KM TOPOGRAPHIC SURVEY

Contractor: Alshola Almudia & Solcomei Document Number :TP-210364 GT SRTPPL 11


PM PR 013 1

Contractor Job Number : ED050


S IRT E OIL
Contract Number : 98 208-530-410
COMPANY
Sheet 6/ 13
Project N° TP-210364 GT

all points strategically placed, permanently installed and accurately positioned relative to the
coordinate system adopted for the project.

CONTRACTOR shall submit for all benchmarks that will be used for setting out surveys a data
sheet detailing the following:

 Benchmark design;
 Individual benchmark reference number;
 The surveyed coordinates and elevation;
 Reference to the project coordinate system (par. 2.2);
 Sketches of benchmark location in relation to local landmarks and monuments.

CONTRACTOR shall perform all work associated with the construction of benchmarks, including
but not limited to the following:

 Earthworks (excavation and backfilling);


 Concrete requirements;
 Disposal of excess material;
 Cleaning and reinstatement of the site;
 Method of preserving benchmarks

2.5 SURVEY CONTROL POINTS


CONTRACTOR shall verify the existing field survey control points (primary and secondary)
already established during a previous topographical survey and reported in ref. [1]. CONTRACTOR
shall establish new survey control points if necessary to ensure the required accuracy of
the survey along the pipeline routes.

CONTRACTOR shall verify the plan and height coordinates for internal consistency prior to
their use on this project.
COMPANY will be responsible for obtaining the necessary authorization to establish
survey control points from the relevant authorities.

Contractor Document Number: SRTPPL-PPL-CV-WP-005 Rev 01


PROJECT REPLACEMENT OF 34 INCH
Project: WORK METHOD OF STATEMENT
PIPELINE SECTION X 11 KM TOPOGRAPHIC SURVEY

Contractor: Alshola Almudia & Solcomei Document Number :TP-210364 GT SRTPPL 11


PM PR 013 1

Contractor Job Number : ED050


S IRT E OIL
Contract Number : 98 208-530-410
COMPANY
Sheet 7/ 13
Project N° TP-210364 GT

3 PIPELINE ROUTE SURVEY METHODOLOGY

3.1 GENERAL
CONTRACTOR shall carry out surveys using Global Positioning System (GPS) satellite receiver
equipment. CONTRACTOR shall operate on RTK (Real-Time Kinematic) mode that consists
in a process where signal corrections are transmitted in real time from a reference receiver at a
known location to one or more remote receivers. The reference receiver shall be positioned on
permanent benchmarks or control points installed along pipeline routes as described in section 2.4
and section 2.5.

3.2 PIPELINE ROUTE CORRIDOR


CONTRACTOR shall survey a strip along the pipeline corridors for a minimum distance of 100m
on either side of the pipeline centerline. The route survey shall be conducted in the direction of
flow.
The frequency or density of the survey shall be determined by the ground profile and surrounding
topography to enable contours to be drawn at 0,5 m intervals; survey points will not be at a spacing
of greater than 50m and at any significant change in elevation.
All pipeline route Intersection Points (IP’s) along the route shall be surveyed.
Additionally any defined point for existing installations and infrastructure shall be surveyed. Each
survey point will consist of the northing, easting and elevation.
During the survey CONTRACTOR shall identify, measure, define and survey all key features
within the pipeline corridor.

3.3 CROSSINGS
CONTRACTOR shall perform a detailed topographical survey at all main crossing to enable
additional surface/subsurface features to be mapped and included in detailed engineering design.
The survey shall be carried out on a grid not exceeding 5m spacing or as appropriate
for the local site conditions and at any specific points (changes in slope,etc) to enable contours
to be drawn at 0.25 m intervals in elevation.The following minimum data/information shall be
recorded for all crossings of the proposed pipelines:

Contractor Document Number: SRTPPL-PPL-CV-WP-005 Rev 01


PROJECT REPLACEMENT OF 34 INCH
Project: WORK METHOD OF STATEMENT
PIPELINE SECTION X 11 KM TOPOGRAPHIC SURVEY

Contractor: Alshola Almudia & Solcomei Document Number :TP-210364 GT SRTPPL 11


PM PR 013 1

Contractor Job Number : ED050


S IRT E OIL
Contract Number : 98 208-530-410
COMPANY
Sheet 8/ 13
Project N° TP-210364 GT

Major Road/Permanent track (service roads)


 survey points sufficient to create a ground profile showing the road centerline, curbs, road
edges, bar
 ditch, contour breaks, right-of-way limits, fences, pole lines, cables, utilities (including type of
utility, size, owner, use, depth/height/clearances) for minimum distance of 100m on either
side of the road right-of-way and 100m on either side of the proposed pipeline centerline;
 Surfacing and right angle of crossing;
 KP of the road referred to the centerline of crossing (for National and County road);
 limits of the total road width;
 safety area limits;
 protection area limits;
 artificial works (retaining walls, consolidation works);

Oueds/Watercourse

 Survey points sufficient to define crossing topography for a minimum distance of 100 m on
either side of the pipeline centerline and 100m on either side of the oueds/watercourse banks;
 Top of bank, toe of bank, width (high bank to high bank), depth (high bank to bottom),
centreline of oueds/watercourse, top of water elevation (where present) and related date of
survey, water depth profile along the oueds/stream surveyed at a maximum interval of 25 m
or adequately less in line with oued’s size and features (and related date of survey) where
present, water flow direction.
 Ground profile of the crossing along the centerline of the proposed pipeline
 Composition of the bed (e.g. rock, sand, gravel, concrete lined, etc.).

Existing services/utilities (pipelines, cable, power lines, etc.)

 survey points sufficient to define crossing topography of an area with a minimum distance
on either side of the crossed service and on either side of the proposed pipeline centerline;
 survey points at all centerline intersections between proposed pipeline and existing utilities;

Contractor Document Number: SRTPPL-PPL-CV-WP-005 Rev 01


PROJECT REPLACEMENT OF 34 INCH
Project: WORK METHOD OF STATEMENT
PIPELINE SECTION X 11 KM TOPOGRAPHIC SURVEY

Contractor: Alshola Almudia & Solcomei Document Number :TP-210364 GT SRTPPL 11


PM PR 013 1

Contractor Job Number : ED050


S IRT E OIL
Contract Number : 98 208-530-410
COMPANY
Sheet 9/ 13
Project N° TP-210364 GT

 coordinates and angle of crossing;


 depth/distance from the ground of the services (where applicable);
 owner of the service;
 physical characteristics (material, diameter, thickness, pressure, voltage);
 distance between pylons;
 Support positions and types for aboveground pipelines.

As a part of the survey documentation, each crossing shall be accompanied with at least two
photos made from specific view points, reflecting the terrain status and general features before
construction works.

3.4 PARALLELISM WITH BURIED OR OVERHEAD SERVICES


The following information shall be recorded when the proposed pipeline run in parallel with a
buried pipeline within a (+-) 7.5 m corridor width on either side of the centerline of the pipeline:

 locate by survey points and tie the utility at intervals at all proposed pipeline centerline
Intersection Points (IP’s);
 locate by survey points all above ground facilities associated with the buried parallel utility;
 Type of utility, size, owner, use and depth.

The following information shall be recorded when the proposed pipeline run in parallel with an
overhead utility within a corridor width on either side of the centerline of the pipeline:

 locate by survey points all poles or structures, record the pole or structure number;
 Number and type of utility, size, owner, number and height of wires/cables.

4 PLANT AREAS SURVEY METHODOLOGY


Ground elevations shall be measured on a 5 m grid minimum or as appropriate for the local site
conditions and at any specific points (changes in slope, etc).
The survey shall be carried out on a grid not exceeding 5m spacing or as appropriate for the
local site conditions and at any specific points (changes in slope, etc) to enable contours
to be drawn at 0.1 m intervals in elevation.

Contractor Document Number: SRTPPL-PPL-CV-WP-005 Rev 01


PROJECT REPLACEMENT OF 34 INCH
Project: WORK METHOD OF STATEMENT
PIPELINE SECTION X 11 KM TOPOGRAPHIC SURVEY

Contractor: Alshola Almudia & Solcomei Document Number :TP-210364 GT SRTPPL 11


PM PR 013 1

Contractor Job Number : ED050


S IRT E OIL
Contract Number : 98 208-530-410
COMPANY
Sheet 10/ 13
Project N° TP-210364 GT

CONTRACTOR shall survey all existing features within the interested plant area. CONTRACTOR
shall map the following features during the facility site survey:

 roads, culverts and tracks;


 structures, wells, concrete foundations, etc. ;
 fences, berms, pits or walls;
 overhead power lines, poles or pylons;
 oueds ;
 sudden elevation changes or geological features;
 buried pipelines, cables and other foreign services and features;
 above ground pipelines (including supports), foreign services and other features; Areas of
vegetation.

5 DATA PROCESSING AND RESTITUTION

5.1 GENERAL

CONTRACTOR shall provide CONTRACTOR with the following information and services:

 Field data (field notes, conventional survey field book, electronic data collector);
 Drawings (route maps, crossings, plant areas);
 Excel files with pipeline axis data;
 Final topographic report.
All text, dimensions, test data, results and all other information relating to the work will be
expressed in the English language and referenced to the Metric system.

5.2 ELECTRONIC DATA COLLECTOR


The CONTRACTOR shall provide data from electronic data collectors supplemented with
conventional survey field books to the extent necessary to produce accurate and complete field
notes.
Each electronic field data record shall, at a minimum, includes:

Contractor Document Number: SRTPPL-PPL-CV-WP-005 Rev 01


PROJECT REPLACEMENT OF 34 INCH
Project: WORK METHOD OF STATEMENT
PIPELINE SECTION X 11 KM TOPOGRAPHIC SURVEY

Contractor: Alshola Almudia & Solcomei Document Number :TP-210364 GT SRTPPL 11


PM PR 013 1

Contractor Job Number : ED050


S IRT E OIL
Contract Number : 98 208-530-410
COMPANY
Sheet 11/ 13
Project N° TP-210364 GT

 survey point number – unique numeric identifier;


 standard feature code - unique alphanumeric identifier;
 easting coordinate;
 northing coordinate;
 elevation;
 “Field Note Description” of the feature

All electronic field data collected during the survey shall contain sufficient information to
accurately define the characteristics of the corresponding feature.

Electronic field data collected during the survey shall at a minimum be backed up at the
midpoint and end of the workday to avoid losing an entire day's work. Whenever possible, all
electronic measurements and recordings will be marked with a time tag as well as a tag showing
whether the data were input automatically or from the keyboard.
The survey crew chief shall ensure that survey crew data collectors are downloaded and data files
delivered to Survey Technician on a daily basis. The Survey Technician will review, process
and QA/QC data files.

5.3 DRAWINGS
CONTRACTOR shall produce drawings in AutoCAD format (.dwg) and pdf format in accordance
to the following requirements:

 drawing sheet size shall be A2 as required


 all drawing information shall be on individual layers according to topographical legend
used during the previous topographical survey
 all common symbols should be created into cells and the cell library to be part of the
deliverables;
 the north arrow shall be positioned in the top right hand corner of the plan aperture;
 match lines shall state the previous and subsequent drawing numbers as
appropriate;
 all reference files and all libraries etc. used in the production of the drawings shall be provided

Contractor Document Number: SRTPPL-PPL-CV-WP-005 Rev 01


PROJECT REPLACEMENT OF 34 INCH
Project: WORK METHOD OF STATEMENT
PIPELINE SECTION X 11 KM TOPOGRAPHIC SURVEY

Contractor: Alshola Almudia & Solcomei Document Number :TP-210364 GT SRTPPL 11


PM PR 013 1

Contractor Job Number : ED050


S IRT E OIL
Contract Number : 98 208-530-410
COMPANY
Sheet 12/ 13
Project N° TP-210364 GT

in electronic format compatible with the electronic files for the drawings

Route maps
On the basis of the section 3.2, CONTRACTOR shall produce a plano-altimetric map of the
pipeline corridors including, as a minimum:

 Easting and Northing coordinates, coordinate grid and coordinate system reference, spheroid
and datum parameters;
 all survey points recorded;
 existing natural features;
 existing man made features, houses, vegetation, concrete pavement, electric lines, poles,
pipelines, roads etc.;
 benchmarks already installed;
 new benchmarks installed during survey;
 route line profile illustrating a true representation of the pipeline route gradient;

The coordinates of the new benchmarks shall be shown next to the symbol. The referenced
elevations will be rounded off and shown to the nearest 0.05 m.

A proper scale, not lower than 1:2000, shall be selected to ensure a good readability of the
documents.

Crossings
On the basis of section 3.3, CONTRACTOR shall produce crossings drawings including, as as
Minimum:

 Contour lines shown at 0.25 m vertical spacing;


 Easting and Northing coordinates, coordinate grid and coordinate system reference, spheroid
and datum parameters;
 all survey points recorded;
 existing natural features
 existing man made features, houses, vegetation, concrete pavement, electric lines, poles,

Contractor Document Number: SRTPPL-PPL-CV-WP-005 Rev 01


PROJECT REPLACEMENT OF 34 INCH
Project: WORK METHOD OF STATEMENT
PIPELINE SECTION X 11 KM TOPOGRAPHIC SURVEY

Contractor: Alshola Almudia & Solcomei Document Number :TP-210364 GT SRTPPL 11


PM PR 013 1

Contractor Job Number : ED050


S IRT E OIL
Contract Number : 98 208-530-410
COMPANY
Sheet 13/ 13
Project N° TP-210364 GT

pipelines, roads etc.;


 benchmarks already installed;
 New benchmarks installed during survey;
 Angle of intersection in degrees between the pipeline route and the crossed structures;
 KP of the pipeline route corresponding to the centerline of the crossing;

A proper scale, depending on the extension of the surveyed area, shall be selected to ensure a
good readability of the documents and will be indicated in the drawing.

5.4 EXCEL FILES


Route line profile coordinates, ground elevation, deviation and crossing information shall be
processed in a excel file, for the preparation of the pipeline alignment sheet.

5.5 FINAL TOPOGRAPHIC REPORT


CONTRACTOR shall include in the final report the description of survey methods, survey data
computation and presentation, list of personnel, equipment and the items listed below:

 general key map on report cover;


 instruments data specifications, type and certificate/calibration reports;
 station description, coordinates and source of all control points used for the survey;
 field observations, including the measurements files, analogical and digital;
 monograph of GPS Primary Control Point;
 calculations and adjustments;
 GPS data processing compute and diagrams of satellites observations and conversion
formulas;
 list of all pipeline route intersection points with relevant coordinates, elevation and
progressive kilometers (where requested).

Contractor Document Number: SRTPPL-PPL-CV-WP-005 Rev 01

You might also like