Professional Documents
Culture Documents
Annex - A - Technical Specifications - RFSL PDF
Annex - A - Technical Specifications - RFSL PDF
TECHNICAL SPECIFICATION
Table of Contents
SCOPE OF WORK
1. INTRODUCTION
UNOPS wishes to engage the services of a contractor for implementation and completion of
various works of Refurbishment of Central Forensic Science Laboratory of Nepal Police at
Samakhushi, Kathmandu, Nepal.
There are internal work and external work under this scope of the work. The internal work covers
the works inside the buildings especially related to furnishing with lab working tables, chemical
storage cabinets, filing cabinets, office tables, chairs etc., partition works and the external work
covers the works related to compound fencing, internal fencing, compound gate, pavement works
and landscaping works.
All the work shall be in accordance with this scope of work, approved plans, specifications of
work, general conditions, and other related documents as indicated in the bidding documents,
unless otherwise stated.
The work in this contract shall include but not limited to the furnishing of all necessary tools,
materials, equipment, skilled manpower, transportation, machineries, accessories, site engineers
and supervisors to carry out all work as described below and as outlined in the Bill Of Quantity,
drawings and other accompanying documents unless otherwise stated.
Extend of Work:
The work to be carried out as part of SOW shall involve but not be limited to:
1. Mobilization and Demobilization.
2. Furniture fabrication and supply
3. On site lab working table fabrication and installation
4. Demolition activities
5. Floor tiling works
6. Aluminum partition works and aluminum doors
7. Chain link and barbed fencing works
8. Interlocking concrete pavement works and landscaping
9. Compound gate fabrication and installation
10. Surface drain and recharge well construction
All the work shall be carried as per the terms and condition of the contract in accordance to the
specification and drawing provided.
GR-0 10-1
G E N E R A L R E Q U I R E ME N T S E MP L O Y E R S U P P L I E D D AT A A N D I N F O R M AT I O N
1. GENERAL
This Section covers the directions for use of project-related data and information, such
as drawings and specifications, provided by the Employer to the Contractor at various
stages of the project.
1. The drawings enclosed with the Tender Documents show the general arrangement
and main dimensions of the project structures. During the progress of the work,
additional construction drawings will be issued by the Engineer, as necessary, to set
forth details shown on the drawings issued to the Contractor at award of the
Contract. Such additional drawings shall become part of the Contract.
2. The Contractor shall be governed by figured dimensions given on the drawings.
When required dimensions are not shown on the construction drawings, the
Contractor shall obtain such dimensions from the Engineer before proceeding with
the construction of the portion of the work to which they refer. In every case,
construction drawings shall take precedence over tender drawings.
3. Drawings and specifications are intended to complement each other so that, if
anything is shown on the drawings but not mentioned in the specifications, or vice
versa, it is to be followed and built as though specifically set forth in both.
4. If drawings conflict with specifications in any particular way, the specifications shall
govern.
5. The Engineer may, from time to time, issue additional detailed drawings,
specifications and instructions for the performance of the work and, upon issue,
such shall be deemed incorporated in the Contract. The Contractor shall
immediately review such drawings and promptly inform the Engineer of any errors,
discrepancies or conflict with other parts of the Contract before proceeding with the
work.
6. The Contractor shall, at all times, keep at least one copy of the drawings and
specifications in proper binding and filing for format at each project site. Such
drawings must be the latest revised issue and must bear the Engineer’s “Issued for
Construction” label.
7. All drawings and specifications and copies thereof, furnished by the Engineer, shall
remain the Employer’s property and are not to be copied/Xeroxed and used on other
works.
3. PATENTED MATERIALS
GR - 0 20 - 2
G E N E R AL R E Q U I R E M E N T S E M P L O Y E R S U P P L I E D D A T A AN D I N F O R MA T I O N
5. COSTS
The Contractor will receive, free of charge, one print of each construction drawing, one
copy of each revised drawing and one copy of the specifications. However, the
Contractor shall be responsible for furnishing, at no additional cost to the Employer,
additional copies of drawings and specifications, or necessary portions thereof, to its
own personnel, sub-contractors and material suppliers, as required.
GR-0 20-3
S EC T I ON GR - 0 30
1. ACCESS
The project sites under this package are located at various locations of the district to
which the package relates. These sites are accessible from the all-weather or graveled
link roads that takeoff from various points of the East-West Highway.
2. TRANSPORTATION OF MATERIALS
1. The Contractor shall be responsible for the transportation of all materials from the
point of manufacture or supply to storage areas or directly to the Site.
2. The Contractor shall investigate and respect the size and weight limitations along
the transportation routes. He shall allow for all costs of transportation in his Contract
Price.
3. The Contractor shall use every reasonable means to prevent any of the roads or
bridges on the routes to the Site from being damaged or injured by any traffic of the
Contractor or any of his sub-contractor.
4. If any damage occurs to any bridge or road arising from the transport of materials or
Plant, the Contractor shall notify the Engineer with a copy to the Employer, as soon
as he becomes aware of such damage or as soon as he receives any claim from
such authority entitled to make such claim.
5. The Contractor shall indemnify the road authority against damage. The Employer
shall not be liable for any costs, charges or expenses in respect thereof or in relation
thereto.
6. The Contractor shall bear the risk of loss or damage to all materials, equipment,
plant etc. prior to acceptance by the Employer.
7. The Contractor shall wrap, pack and crate all materials and Plant included in the
Works or part thereof, suitable for shipment according to the site climatic conditions,
and in a manner which facilitates handling and protects the material or Plant from
damage in rail, truck, ocean or air shipment as applicable, and within the size and
weight limitations imposed by the carrier. An approved drying agent, such as silica
gel, shall be packed in containers or packages holding materials and Plant that may
be adversely affected by moisture or excessive humidity. The Contractor shall check
right of way clearances and weight limitations and make all shipping arrangements.
Plant and material shall be shipped in proper sequence for efficient installation.
8. All Plant parts shall be marked to facilitate erection. All packing crates shall be
clearly and indelibly marked before shipping to indicate the Contract number and
shipping address, volume, weight, name, number and unit number of the contents,
slinging and weight bearing points.
9. Each packing crate shall contain a packing list in a waterproof envelope. Three
copies of the packing list shall be forwarded to the Engineer prior to dispatch. Parts
shall be described and also identified by their numbered markings in the packing
lists. All shipping documents shall be prepared in English and all dimensions,
weights and other measurement shall be given in metric units.
GR - 0 30 - 4
G E N E R AL R E Q U I R E M E N T S A C C E S S T R AN S P O R T AT I O N A N D S T O R A G E
10. Each package shall be marked with the Employer’s identification mark, details of
which will be provided by the Employer after order to commence the works.
1. The Contractor shall ensure that all material and Plant shall be protected during site
handling and storage against loss, corrosion, weather damage, deformation or
distortion and contamination by dirt.
2. Part on which the final alignment and running clearances of the equipment depend
shall be adequately blocked and protected to prevent distortion during storage,
handling and erection.
3. If the equipment is received at the Site before it is to be erected, the Contractor shall
store the equipment as packed, in a clean and well-protected place.
4. Installed plant shall be covered with clean tarpaulins and tied shot to prevent ingress
of dust and dirt during construction, as required by the Engineer.
5. For the duration of the Works on Site, the Contractor shall provide covered storage
facilities, weatherproof shelters, loading and unloading facilities as required for the
material and Plant.
6. All deliveries of materials and Plant shall be checked and discrepancies noted and
reported in writing to the Engineer. Lost items shall be replaced. Damaged items
shall be replaced (or repaired if permitted by the Engineer) to conform to the
Specifications.
GR-0 30-5
S EC T I ON GR - 0 40
SITE FACILITIES
During the performance of the Work, the Contractor shall provide and maintain suitable
site office and lunchroom facilities for the use of the Contractor and its sub-contractors.
He shall arrange accommodation for its and its sub-contractor’s staff outside of the
project premises. The locations of such facilities shall be subject to acceptance by the
Engineer.
2. PARKING FACILITIES
A parking area for the vehicles of the Contractor, sub-contractors and their employees
shall be provided by the Contractor outside the project work area as authorized by the
Engineer. No private vehicles will be allowed on site.
3. CONSTRUCTION POWER
The Contractor shall make his own arrangements for construction power supply. He
shall be required to provide a construction power distribution system, including all step-
down transformers, poles, cables and other accessories, needed for supply of power to
the construction sites, offices and camps.
Electric power may be available at the site, but the Contractor shall have available at the
site an emergency power supply (diesel generators) to ensure non-interrupted
construction power and to ensure the safety of the Works. The locations for installing
generators shall be approved by the Engineer.
The Engineer shall have the right, at all times, to inspect the Contractor’s electrical
installations. Those installations that are unsatisfactory shall be modified immediately by
the Contractor to the Engineer’s satisfaction at no additional cost to the Employer.
4. STORAGE FACILITIES
The Contractor shall maintain adequate storage facilities at the site for material, plant
and equipment to be employed in the works. The facilities shall conform to specific
storage requirements mentioned for different materials mentioned in the technical
specifications and in the Sections GR-090(Health and Safety) and GR-
100(Environmental Control). The Contractor’s storage facilities shall be subject to the
Engineer’s approval.
5. TOILET FACILITIES
The Contractor shall provide toilet facilities at the site for the use of its employees and
its sub-contractor’s employees. These facilities should include sewage collection,
treatment and disposal facilities. The construction site shall be kept clean and
serviceable at all times during the contract period.
The Contractor shall provide adequate first aid facilities on-site acceptable to the
Engineer. Failure of the Contractor to ensure the availability of first aid facilities on-site
GR - 0 40 - 6
G E N E R AL R E Q U I R E M E N T S S U B MI T T AL S
will result in an immediate ‘stop work’ order being issued. All costs and time delays
resulting from any such ‘stop work’ order shall entirely be the Contractor’s responsibility.
7. SECURITY
The Contractor shall assume full responsibility for security at the site for the purpose of
protecting its stores, equipment, material, persons and property and for enforcing
regulations normal to an operation of this type and size. He shall cooperate fully with the
Engineer to ensure the overall security and safety of the Works. However, security of
the Works will be the sole responsibility of the Contractor until such work is completed
and turned over to and accepted by the Employer.
Duties of the Contractor shall include but not be limited to:
1. Provisions and maintenance of all necessary fencing.
2. Property security.
3. Lighting.
4. Guards, etc.
5. Safety of contractor’s employees at work etc.
And all other measures for the protection of the whole of the Works, all material
delivered to site and all persons employed in connection with the Works continuously,
including nights and holidays for the duration of the Contract.
8. GARBAGE DISPOSAL
The Contractor shall maintain a safe, healthy and tidy worksite at all times. He shall be
responsible for the collection and disposal of all garbage and refuse for itself and its
subcontractors. Proper and sufficient receptacles for refuse shall be provided. Collection
of refuse and garbage shall be made at least once per week, and disposal shall be
acceptable to the Engineer as per the local authority rules, regulations and in an
environmentally friendly way. The contractor shall be fully responsible for garbage
management at his own cost.
The dumping of refuse or any contaminant into the any stream or other watercourse
shall not be permitted. No trees, part of a tree, refuse, debris substance, other material
or contaminant shall be permitted to be thrown, deposited or dumped into any lake, river
or upon the bed, shores or banks thereof.
No measurement or separate payment shall be made for work under this section. The
costs for all the above requirements shall be deemed to be covered under appropriate
unit prices tendered by the Contractor in the Bill of Quantities.
GR-0 50-7
G E N E R A L R E Q U I R E ME N T S S U B MI T T A L S
SUBMITTALS
1. GENERAL
This Section covers the preparation and submission of the Contractor’s drawings,
design calculations, samples, manufacturer’s literature and brochures, photographs,
installation instructions, operation and maintenance manuals, schedules and reports as
specified herein and in the various other sections of the Specifications.
All submittals shall be in the English language. All dimensions and drawings shall be in
metric units, with the exception of manufactured components not readily available in
metric units.
2. SHOP DRAWINGS
1. The Contractor shall provide, where necessary, shop drawings of the various
structures of the project. Such details shall be to the extent necessary for review,
checking and approval by the Engineer, fabrication, assembly, delivery, site erection
and safe operation under the conditions described in the Specifications, including
working drawings and specifications prepared by other manufacturers. All drawings
for load-bearing and water-retaining structures shall be signed and stamped by a
Professional Engineer experienced in this kind of work. The drawings shall be in
sufficient detail to show:
i. The general arrangement and dimensions of all parts and size of each and every
part of the work to be supplied under the Contract.
ii. The nature of the material from which the various parts are to be made.
iii. All connections.
The Contractor shall submit the shop drawings in duplicate to the Engineer for
review and comment. All drawings submitted to the Engineer for review and
approval shall be signed, checked and approved by the Contractor prior to
submission. The Engineer, unless otherwise specifically stated, shall be allowed 15
days to examine, review and comment upon such drawings or prints.
2. Work described by the shop drawings shall not commence without authorization
having been granted, in writing by the Engineer, and Employer will not accept or pay
for this work unless such authorization shall have first been granted.
3. All drawings shall bear the following title:
United Nations Office for Project Services
Modernization and Improvement of Policing Project (MIPP) in Nepal
4. All shop drawings on which changes are made shall have the revisions clearly
marked.
5. No change shall be made to any shop drawing accepted by the Engineer without
permission of the Engineer. Subsequent changes shall be requested by sending
another set of two copies of each reviewed drawing to the Engineer for review and
comment.
6. Review and comment of the Contractor’s drawings and design by the Engineer shall
not relieve the Contractor of the responsibility for correctness thereof, or for results
arising from errors or omissions, or for faults or defects, or for failure in the matter of
guarantees, which may become evident during construction or subsequent
operation.
7. After review and approval of the drawings by the Engineer, the Contractor shall
deliver to the Engineer, free of charge, two copies of all final drawings.
GR - 0 50 - 8
G E N E R AL R E Q U I R E M E N T S S U B MI T T AL S
The Contractor shall submit copies of his design notes and calculations for those
structures for whose design he is responsible (shoring, formwork, scaffolding etc.).
These calculations shall be carried out under the supervision of an engineer
experienced in similar types of work. The cover page of the calculations should bear the
stamp and signature of this engineer verifying the completeness and correctness of the
design(s). If requested by the Engineer, the Contractor shall provide information on his
designer's education and experience.
At the time of tender, these notes and design calculations should be in sufficient detail
to enable the Engineer to evaluate the overall adequacy of the design. To meet these
requirements, the design calculations should be sufficient to demonstrate how loads on
the major structural elements were determined. Later, before the Contractor orders
materials or commences manufacturing, detailed design calculations and notes shall be
submitted for the Engineer’s review. The Engineer will require two weeks for these
reviews; therefore, the Contractor shall plan his work accordingly.
1. Unless specified elsewhere in the Contract, materials incorporated into the work
shall be new, of an acceptable quality, and of the most suitable grades of their
respective kinds for their intended use, and the decision of the Engineer as to the
quality and suitability of material shall be final and binding.
2. Ownership of all material incorporated into the work or upon arrival at site,
whichever occurs first, shall be with the Employer. Any plant delivered by the
Contractor to the site may not be removed during the period of this Contract without
the approval of the Engineer.
3. During the progress of the work, the Contractor may offer material with equal or
better qualities and performance in substitution for those specified, which it
considers, will be in the Employer’s interest to accept. Any such offer shall be made
in writing to the Engineer for its consideration sufficiently in advance of the time at
which the Contractor wished to order the said material for use in the work, so that no
delay in the construction schedule occurs. The Contractor shall include, in duplicate
with its offer and at its own expense, complete data and samples that, together with
any other data the Engineer may require, will enable the Engineer to assess the
acceptability of the said material. The use of any material so offered will be
permitted only after written acceptance by the Engineer. Such acceptance by the
Engineer shall not relieve the Contractor from full responsibility for efficiency,
sufficiency, quality and performance of the substitute material.
4. When the equivalent material necessities changes to or coordination with any other
portion of the work, the data submitted shall include drawings and details showing all
such changes, and the Contractor shall perform these changes, at its own expense,
as part of any acceptance of substitute material.
5. If the accepted equivalent material is of less value to the Employer or involves less
cost to the Contractor than the materials specified, an adjustment shall be made in
favor of the Employer on the basis of prices stated in the written acceptance from
the Engineer. In no case shall payment in excess of the prices entered in the Bill of
Quantities be made because of substitution of any material in place of another under
the provisions of this clause.
5. SAMPLES
The Contractor shall furnish two samples of the various materials intended to be used
on or in the Work, together with the technical specifications whenever requested by the
Engineer. Samples shall be sent to the Engineer with the carriage prepaid.
GR-0 50-9
G E N E R A L R E Q U I R E ME N T S S U B MI T T A L S
After the Engineer has performed his review and analysis of samples, he will return one
sample to the Contractor, along with the Engineer’s comments.
Samples not approved shall be resubmitted until approved as satisfactory by the
Engineer. Approval of a sample shall not be taken in itself to change or modify any
Contract requirements.
Each sample shall be identified completely as to product, manufacture trade name,
style, model, location of use as well as names of the Contractor, Supplier and Project.
Field samples shall be prepared at the Site by the Contractor in the manner and number
requested by the Engineer.
6.1 General
The Contractor shall submit four copies of all detailed programs and procedures for
testing and/or commissioning of all materials and plant supplied under this Contract to
the Engineer for approval, not later than one month prior to the scheduled
commencement of these activities. Such programs and procedures shall include all the
tests specified in this Specification. The details should include the tests proposed to be
carried out, recommended test procedures, proposed sequence of testing with
anticipated duration of each test and a sample copy of the test result reports proposed
to be used. Programs of all these tests shall be incorporated into construction,
manufacturing and erection schedules.
GR-0 50-10
G E N E R AL R E Q U I R E M E N T S S U B MI T T AL S
1. Within ten calendar days from Notice of Award of Contract, the Contractor shall
submit to the Engineer, for revision and comment and acceptance by the Engineer,
a detailed construction program which shall include:
A network diagram construction schedule completely detailing the Contractor’s
proposed operation and schedule for construction of the work. The critical path
method network chart shall indicate the early and late start and completion date
for the various activities.
A narrative report which shall describe, in detail, the Contractor’s proposed
methods of carrying out each phase or portion of the work, the number of men
and the number, type and size of major pieces of plant required for the work.
2. The network diagram construction schedule shall show all activities represented by
the items listed in the Bill of Quantities and all related operations such as delivery
and erection of plant, construction of temporary roads, preparation of borrow areas,
etc.
3. In addition to construction activities, the network diagram construction schedule shall
show required dates of any material supplied by the Employer.
4. The Contractor’s network diagram construction schedule shall show and take into
account the key dates listed in Section GR-010 (Project Description).
5. The Contractor shall update and resubmit the network diagram construction
schedule to the Engineer on a monthly and on ad hoc basis. From time to time
during the period of the Contract, the Engineer will furnish the Contractor with
information on activities and events, whereupon the Contractor shall amend and
revise its network to include such information.
6. The construction program, as outlined above, when accepted by the Engineer, shall
form part of the Contract, and all work will be monitored by the Engineer and shall
be carried out by the Contractor in accordance with the program. In the event that
individual activities are not started by the late start date indicated on the accepted
schedule or when activities are not completed by the late completion date indicated
on the accepted schedule or, if the Contractor fails to maintain the scheduled
progress as indicated on the accepted schedule, the Contractor shall be required to
work extra shifts, Saturdays and holidays or take other necessary emergency action,
acceptable to the Engineer, to ensure that the Contractor returns to the accepted
construction program within a period of not more than five (5) calendar days or the
Engineer’s written notice to the Contractor. All such work to complete late activities
will be performed by the Contractor at no additional cost to the Employer.
The Contractor shall provide an instruction manual for guidance during installation and
testing of each item of equipment supplied by the Contractor and for subsequent
incorporation into the Employer’s operating and maintenance manual. The manual shall
describe and illustrate in detail the construction and recommended procedures for
GR- 050-1 1
G E N E R A L R E Q U I R E ME N T S S U B MI T T A L S
The Contractor shall submit three draft copies of the manual to the Engineer for review.
The Engineer will review and return the manual within 21 days of receipt. Following final
review, the Contractor shall forward two final copies of the complete manual to the
Employer. If revision of the manual becomes necessary as a result of information gained
during installation, testing, or initial operation, the Contractor shall immediately make the
appropriate revision and submit two copies of the revised pages and/or drawings,
suitably dated.
9. PHOTOGRAPHS
During manufacture and delivery, the Contractor shall provide photographs of every
major component of the work. Subsequently, during the construction and installation
stage, the Contractor shall provide progress photographs of the works on a monthly and
on ad hoc basis. All the photographs must be adequately identified with brief
descriptions of the works, dates and locations.
No measurement or separate payment shall be made for work under this section. The
costs for all the above requirements shall be deemed to be covered under appropriate
unit prices tendered by the Contractor in the Bill of Quantities.
GR-0 50-12
S E CT I ON G R- 0 6 0
PRE-CONSTRUCTION WORKS
1. GENERAL
This Section covers the works to be performed by the Contractor prior to commencing
the construction activities at the Site.
2. CONDITION-IN SURVEY
The Engineer and the Contractor shall carry out a joint condition-in survey using video
or digital photographs to record the condition of the Site upon handover to the
Contractor. This survey shall determine the state of the Site that the Contractor must
hand back upon completion of the Works (refer Section GR-100).
3. SITE FAMILIARIZATION
Prior to mobilization, the Contractor shall acquaint himself with the existing physical and
working conditions at the Site, in particular the following:
a. Existing structures, facilities and amenities at the Site, including occupied areas of
the Site or buildings.
b. Any limitations and restrictions on access on to and within the Site, use of the Site
for temporary works and construction plant, including working and storage areas,
location of offices, workshops, sheds, roads and parking.
c. Any limitations and restrictions on working times.
Based on this study, the Contractor shall prepare a site plan showing his proposed
locations and alignments of construction facilities and submit it to the Engineer for his
review and approval.
For the parts of Site designated as occupied areas, the Contractor shall, in consultation
with the Engineer, make the following provisions to allow occupants to continue using
the area during the entire construction period or part thereof, as required:
a. Make available safe access for occupants.
b. Arrange work to minimize nuisance to occupants and ensure their safety.
c. Protect occupants against weather, dust, dirt, water or other nuisance by such
means as temporary screens.
The Contractor shall plan and implement the following protection measures for persons
and property on and adjacent to the Site in order to minimize the number and duration
of interruptions:
a. Provide and maintain required barricades, guards, fencing, shoring, temporary
roadways, footpaths, signs, lighting and traffic flagging.
b. Protect and maintain access ways (roadways and footpaths) and existing services
(drains, watercourses etc.) that are in use on or adjacent to the Site. On-site
services that are to be continued shall be repaired, diverted or relocated as required
GR- 060-1 3
G E N E R A L R E Q U I R E ME N T S P RE - CO NS T RU CT I ON WO RK S
while those to be abandoned shall be cut and sealed or disconnected and made
safe.
c. Protect property that is to remain on or adjacent to the Site, including adjoining
property encroaching onto the Site.
The Contractor shall submit proposals to the Engineer for action on existing services
before starting this work.
7. DOCUMENT SUBMISSION
Prior to mobilization to the Site, the Contractor shall submit the following documents to
the Engineer for his review and approval:
Results of Condition-in Survey.
Site Survey [refer Section GR-070 (Layout of Work and Survey)].
Result of condition survey of adjoining property.
Work Method Statement.
Construction Program [refer Section GR-050 (Contractor’s Submittals)].
Contractor’s Quality Assurance/ Quality Control (QA/QC) Plan, as per the minimum
requirements set out in Section GR-080(Quality Control).
Contractor’s Health and Safety Plan (HSP), as per the minimum requirements set
out in Section GR-090 (Health and Safety).
Contractor’s Environmental Protection Plan, as per the minimum requirements set
out in Section GR-100 (Environmental Control).
Schedule of Materials and Installed Equipment.
A pre-construction meeting will be held between the Engineer and the Contractor to
review the above documentation. If the documentation is incomplete, the Contractor will
have three calendar days to revise and resubmit the documentation for approval.
No measurement or separate payment shall be made for work under this section. The
costs for all the above requirements shall be deemed to be covered under appropriate
unit prices tendered by the Contractor in the Bill of Quantities.
GR-0 60-14
S E CT I ON G R- 0 7 0
1. GENERAL
This section of the Specifications covers the requirements and procedures for layout of
work, quantity survey, quality control and verifying dimensions of existing structures.
The survey shall include, but may not be limited to, the following main activities:
1. Establishing the location, layout and setting dimensions of the new project
structures.
2. Surveying, measuring and recording the actual layout, dimensions and conditions of
existing structures and their components, where modification to or extension of them
are planned.
3. Monitoring the behavior of existing structures during the excavation and construction
of the adjacent new structures.
4. Measurements and dimensional checks during construction of concrete structures
and erection of structural steel for quality control.
2. BENCHMARKS
Prior to start of construction, the Engineer shall provide benchmarks to the Contractor in
the vicinity of project structures.
Utilizing the benchmark and existing structural features, the Contractor shall fix
necessary survey lines, points and elevations for each structure as the construction
work proceeds and shall verify all dimensions needed for his design or for control of
construction.
Survey point markers shall be durable, fixed firmly to rock or concrete and be
adequately protected. Each survey points shall be designated by a clearly legible and
durable inscription, which shall be provided and preserved by the Contractor. The
Contractor shall take all measures required, at his own cost, for the adequate protection
and preservation of the basic survey points.
The Contractor’s instruments and other survey equipment shall be accurate, suitable for
the surveys required in accordance with recognized professional standards and in
proper condition and adjustment at all time.
Surveys shall be performed only by qualified, properly trained and experienced
personnel. The Contractor shall be fully responsible for the correctness of his survey
work and for the actions of personnel engaged in it.
The Contractor shall record the surveys in proper field notebooks. A copy of such
records, measurement and calculations, properly indexed, shall be furnished to the
Engineer when completed.
GR- 070-1 5
G E N E R A L R E Q U I R E ME N T S L A Y O UT OF WO RK AND SU RV E Y
The Engineer may, at any time, use line and grade points markers established by the
Contractor. The Contractor’s surveys are a part of the Work and may be checked by the
Engineer or the representative of the Engineer at any time. The Contractor shall be
responsible for any lines, grades or measurements which do not comply with specified
or proper tolerances, or which are otherwise defective, and for any resultant defects in
the Work. The Contractor will be required to conduct re-surveys or check surveys to
correct errors indicated by review of the field notebooks.
7. RESPONSIBILITY
Any check or control by the Engineer shall not relieve the Contractor of his responsibility
for the accuracy of structures or parts of them with regard to their positions and
dimensions, or for the accuracy of the erection work executed by the Contractor or its
sub-contractor.
No measurement or separate payment shall be made for the works under this section.
The unit rates and lump sum prices offered for civil works shall be deemed to cover all
the Contractor’s necessary layout and survey works.
GR-0 70-16
S E CT I ON G R- 0 8 0
QUALITY CONTROL
1. GENERAL
The intent of this Section is to enable the Contractor to establish a necessary level of
quality control that will:
a. Adequately provide for the production of acceptable quality materials.
b. Provide sufficient information to assure both the Contractor and the Engineer that
the specification requirements can be met.
c. Allow the Contractor as much latitude as possible to develop his or her own standard
of control.
Although guidelines are established and certain minimum requirements are specified
herein and elsewhere in the Technical Specifications, the Contractor shall assume full
responsibility for accomplishing the stated purpose. The quality control requirements
contained in this section and elsewhere in the technical specifications are in addition to
and separate from the acceptance testing requirements. Acceptance testing
requirements are the responsibility of the Engineer.
2. DESCRIPTION OF PROGRAM
GR- 080-1 7
G E N E R A L R E Q U I R E ME N T S Q U AL I T Y C O N T R O L
The Contractor is encouraged to add any additional elements to the QCP that he deems
necessary to adequately control all production and/or construction processes required
by this contract.
Program Administrator
The Program Administrator shall be a full-time employee of the Contractor or a
consultant engaged by the Contractor. He shall have a minimum of 5 years of
experience in building construction and shall have had prior quality control experience
on a project of comparable size and scope as the contract. Additional qualifications for
the Program Administrator shall include at least one of the following requirements:
a. Professional engineer with one year of building construction experience acceptable
to the Engineer.
b. Engineer with two years of building construction experience acceptable to the
Engineer.
c. An individual with three years of building construction experience acceptable to the
Engineer, with a Bachelor of Science Degree in Civil Engineering, Civil Engineering
Technology or Construction.
d. Certified Construction materials technician.
The Program Administrator shall have full authority to institute any and all actions
necessary for the successful implementation of the QCP to ensure compliance with the
contract plans and technical specifications. He shall report directly to a responsible
officer of the construction firm.
GR-0 80-18
G E N E R AL R E Q U I R E M E N T S Q U ALI T Y CO NT R OL
The quality control technicians shall report directly to the Program Administrator and
shall perform the following functions:
a. Inspection of all materials, construction plant and equipment for conformance to the
technical specifications.
b. Performance of all quality control tests as required by the technical specifications.
The Contractor shall provide sufficient qualified quality control personnel to monitor each
work activity at all times. Where material is being produced in a plant for incorporation
into the work, separate plant and field technicians shall be provided at each plant and
field placement location. The scheduling and coordinating of all inspection and testing
must match the type and pace of work activity. The QCP shall state where different
technicians will be required for different work elements.
4. SUBMITTALS SCHEDULE
The Contractor shall submit a detailed listing of all submittals related to quality control,
e.g. mix designs, material certifications, etc., required by the technical specifications.
The listing shall be developed in a spreadsheet format and shall include:
a. Specification item number.
b. Item description.
c. Description of submittal.
d. Specification paragraph requiring submittal; and
e. Scheduled date of submittal.
5. INSPECTION REQUIREMENTS
Quality control inspection functions shall be organized to provide inspection for all
definable features of work, as detailed below. Inspections shall be performed daily to
ensure continuing compliance with the contract requirements until completion of the
particular feature of work. These shall include the following minimum requirements:
a. During plant operation for material production, quality control test results and
periodic inspections shall be utilized to ensure the quality of aggregates and other
mix components and to adjust and control mix proportioning to meet the approved
mix design and other requirements of the technical specifications. All equipment
utilized in proportioning and mixing shall be inspected to ensure its proper operating
condition. The QCP shall detail how these and other quality control functions will be
accomplished and utilized.
b. During field operations, quality control test results and periodic inspections shall be
utilized to ensure the quality of all materials and workmanship. All equipment utilized
in placing, finishing and compacting shall be inspected to ensure its proper operating
condition and to ensure that all such operations are in conformance to the technical
specifications and are within the plan dimensions, lines, grades and tolerances
specified. The Program shall document how these and other quality control functions
will be accomplished and utilized.
As a part of the overall QCP, the Contractor shall implement a quality control testing
plan, as required by the technical specifications. The testing plan shall include the
minimum tests and test frequencies required by each technical specification item, as
well as any additional quality control tests that the Contractor deems necessary to
adequately control production and/or construction processes.
GR- 080-1 9
G E N E R A L R E Q U I R E ME N T S Q U AL I T Y C O N T R O L
The testing plan can be developed in a spreadsheet format and shall, as a minimum,
include the following:
a. Specification item number (e.g. CS-040).
b. Item description (e.g. cement concrete).
c. Test type (e.g. gradation, grade).
d. Test standard (e.g. IS or ASTM test number, as applicable).
e. Test frequency (e.g. as required by technical specifications or minimum frequency
when requirements are not stated).
f. Responsibility (e.g. plant technician).
g. Control requirements (e.g. target, permissible deviations).
The testing plan shall contain a statistically based procedure of random sampling for
acquiring test samples. The Engineer shall be pre-informed by the contractor to witness
quality control sampling and testing.
7. DOCUMENTATION
The Contractor shall maintain current quality control records of all inspections and tests
performed. These records shall include factual evidence that the required inspections or
tests have been performed, including type and number of inspections or tests involved
the following:
Results of inspections or tests.
Nature of defects, deviations, causes for rejection, etc.
Proposed remedial actions.
Corrective actions taken.
The records must cover both conforming and defective or deficient features and must
include a statement that all supplies and materials incorporated in the work are in full
compliance with the terms of the contract. Legible copies of these records shall be
furnished to the Engineer daily or as required by the Engineer. The records shall cover
all work placed subsequent to the previously furnished records and shall be verified and
signed by the Contractor’s Program Administrator.
Specific contractor quality control records required for the contract shall include, but are
not necessarily limited to, the following records:
Daily Inspection Reports
Each Contractor Quality Control Technician shall maintain a daily log of all inspections
performed for both Contractor and sub-contractor’s operations on a form acceptable to
the Engineer. These technician’s daily reports shall provide factual evidence that
continuous quality control inspections have been performed and shall, as a minimum,
include the following:
a. Technical specification item number and description.
b. Compliance with approved submittals.
c. Proper storage of materials and equipment.
d. Proper operation of all equipment.
e. Adherence to plans and technical specifications.
f. Review of quality control tests.
g. Safety inspection.
GR-0 80-20
G E N E R AL R E Q U I R E M E N T S Q U ALI T Y CO NT R OL
The daily inspection reports shall identify inspections conducted, results of inspections,
location and nature of defects found, causes for rejection and remedial or corrective
actions taken or proposed. They shall be signed by the responsible Quality Control
Technician and the Program Administrator. The Engineer shall be provided at least one
copy of each daily inspection report on the work day following the day of record.
Test Reports
The Contractor shall be responsible for establishing a system that will record all quality
control test results. The test reports shall document the following information:
a. Technical specification item number and description.
b. Test designation.
c. Location.
d. Date of test.
e. Control requirements.
f. Test results.
g. Causes for rejection.
h. Recommended remedial actions.
i. Retests.
Test results from each day’s work period shall be submitted to the Engineer prior to the
start of the next day’s work period. When required by the technical specifications, the
Contractor shall maintain statistical quality control charts. The daily test reports shall be
signed by the responsible quality control technician and the Program Administrator and
verified by the Engineer.
The QCP shall indicate the appropriate action to be taken when a process is deemed, or
believed, to be out of control (out of tolerance) and detail what action will be taken to
bring the process into control. The requirements for corrective action shall include both
general requirements for operation of the QCP as a whole and for individual items of
work contained in the technical specifications.
The QCP shall detail how the results of quality control inspections and tests will be used
for determining the need for corrective action and shall contain clear sets of rules to
gauge when a process is out of control and the type of correction to be taken to regain
process control.
When applicable or required by the technical specifications, the Contractor shall
establish and utilize statistical quality control charts for individual quality control tests.
The requirements for corrective action shall be linked to the control charts.
9. SURVEILLANCE BY ENGINEER
All items of material and equipment shall be subject to surveillance by the Engineer at
the point of production, manufacture or shipment to determine if the Contractor,
producer, manufacturer or shipper maintains an adequate quality control system in
conformance with the requirements detailed herein and the applicable technical
specifications and plans. In addition, all items of materials, equipment and work in place
shall be subject to surveillance by the Engineer at the site for the same purpose.
Surveillance by the Engineer shall not relieve the Contractor of performing quality
control inspections of either on-site or off-site works of the Contractor or his sub-
contractors.
GR- 080-2 1
G E N E R A L R E Q U I R E ME N T S Q U AL I T Y C O N T R O L
10. NONCOMPLIANCE
The Engineer will notify the Contractor of any noncompliance with any of the foregoing
requirements. The Contractor shall, after receipt of such notice, immediately take
corrective action. Any notice, when delivered by the Engineer or his authorized
representative to the Contractor or his authorized representative at the Site of the work,
shall be considered sufficient notice.
In cases where quality control activities do not comply with either the Contractor’s QCP
or the contract provisions, or where the Contractor fails to properly operate and maintain
an effective QCP, as determined by the Engineer, the Engineer may:
a. Order the Contractor to replace ineffective or unqualified quality control personnel.
b. Order the Contractor to stop operations until appropriate corrective actions are
taken.
No measurement or separate payment shall be made for the works under this section. It
is deemed that all the costs of all the above requirements are covered under appropriate
unit prices tendered by the Contractor in the Bill of Quantities.
GR-0 80-22
S E CT I ON GR - 9 0
1. GENERAL
1.2 Compliance with UNOPS Workplace Safety and Health Policy and Procedures
The Contractor shall comply with the UNOPS Workplace Safety and Health Policy and
Procedures (WSHPP), including but not limited to other rules and regulations, standards
and codes of practice related and relevant to the promotion of safe practices and
conduct at the worksite.
It shall be the duty of the Contractor to comply with all such requirements of the
WSHPP, as affect him or any person or persons employed by him, and as related to any
work, act or operation performed or about to be performed by him. The Contractor shall
not permit any person to do anything that is not in accordance with the generally
accepted principles of safe and sound practices.
The Contractor shall ensure a safe environment on the site at all times. All safety
provisions shall be properly maintained and shall not be removed. The Contractor shall
ensure that his workmen take necessary and sufficient precautions when safety
provisions are used. The Contractor shall not allow any of the safety provisions to be
used unless he has satisfied himself that the provisions are safe.
Where the UNOPS Project Manager appoints an engineer to carry out the following
temporary works regulated by UNOPS WSHPP:
Cantilevered platforms erected more than 3 m above ground
Formwork structure
Runway and ramp for use of motor trucks or heavy vehicles
Stability of structure adjacent to excavation
Shoring and bracing for trench excavation > 4m
The engineer shall comply with any duties imposed on him under WSHPP, including:
Design it to acceptable codes and standards and in accordance with good
engineering practices.
Ensure that it is constructed in accordance to his design.
When constructed, the engineer should check it for safety and issue a certificate
stating that it is safe for its intended use.
The engineer shall exercise due diligence when carrying out his duties.
The Contractor shall ensure that the requirements of WSHPP and the requirements
specified hereunder are strictly complied with at all times.
GR-9 0-23
G E N E R A L R E Q U I R E ME N T S S I T E MEE T I NG S
GR-1 10-24
G E N E R AL R E Q U I R E M E N T S S I T E ME E T I N G S
The Contractor shall provide, erect and maintain an overlying screening net to cover the
entire external face of the scaffold. The installation of the net shall follow the erection of
the scaffold closely. A 90 mm high colored toe board shall be provided at the base of
the net. After installation, there shall be no opening between separate sets of the net,
and any torn net shall be replaced or repaired immediately. The scaffold shall be
effectively tied to the building structure by means of tiebacks. All tiebacks shall be
painted with bright color for easy identification.
For buildings next to areas less than 30 m away from the site boundary, the Contractor
shall provide special mid-height work platform supporting metal access scaffold at the
building elevation directly facing public areas, walkways, children playgrounds, schools
and other locations with public traffic. This platform shall be installed from the floor level
at the mid height of the building and shall project 6 m from the edge of the floor. They
shall be supported at the floor level below by diagonal members. Tension tiebacks to
upper floors shall not be used. Around the edges of the 6 m platform, guardrails and toe
boards shall be provided. Guardrail shall have sufficient strength and rigidity to
withstand, without permanent deformation or failure, a 50 kg load applied in any
direction at right angles to the guardrail.
The work platform and its supports shall be designed by an Engineer to a uniformly
distributed live load of 1.5 kg/m² and the loading from the scaffold. Supports for platform
shall be spaced at not more than 1.8 m centers.
GR- 110-2 5
G E N E R A L R E Q U I R E ME N T S S I T E MEE T I NG S
2.5 Barricades to Lift Openings, Voids, Open Sides of Buildings and Excavations
The Contractor shall barricade all lift openings, internal voids, open sides of buildings
and excavations where a person is liable to fall. The barricade shall be at least 1.1 m
high and shall have sufficient strength and rigidity to withstand a lateral point load of 50
kg.
GR-1 10-26
G E N E R AL R E Q U I R E M E N T S S I T E ME E T I N G S
Sills under the supports shall be set on firm soil or other suitable material in a pattern
that assures adequate stability for all props. Care shall be taken not to disturb the soil
under the support. Adequate drainage shall be provided to drain away water coming
due to rain, washing of forms or during the curing of the concrete, to avoid softening of
the supporting soil strata.
All centering shall be regularly inspected to ensure that footings of sills under every post
of centering are sound, the centering panels are plumb in both directions and all cross
braces are securely in place. During pouring of concrete, the centering shall be
constantly inspected and strengthened if required, and wedges below the vertical
supports shall be tightened. Adequate protection of centering shall be ensured from
moving vehicles or swinging loads.
Forms shall not be removed earlier than the limit laid down in the specifications and not
until it is certain that the concrete has developed sufficient strength to support itself and
all loads that will be imposed on it. Only workmen actually engaged in removing the
formwork shall be allowed in the area during these operations. Those engaged in
removing the formwork shall wear helmets, gloves and heavy soled shoes, and
approved safety belt if adequate footing is not provided above 2 in level. While cutting
any, wires in tension, care shall be taken to prevent backlash that might hit the body.
Dismantling of supports shall be done under the supervision of a competent engineer
and the order of dismantling of individual supports laid down in the instruction sheets
shall be closely followed.
2.10 Ladders
The Contractor must ensure that ladders are in an acceptable sound condition and
submit a written inspection report to UNOPS. If the ladders are made of a material other
than steel, the Contractor must ensure that the ladder is in sound condition. If they are
GR- 110-2 7
G E N E R A L R E Q U I R E ME N T S S I T E MEE T I NG S
constructed of lumber/timber, the Contractor must ensure that the timber is free of loose
knots or knot holes, must not have a split and must be strong and sturdy.
The Contractor’s worker must ensure that:
The ladder is secured against movement and placed on a base that is stable.
The base of an inclined ladder is no further from the base of the wall or structure
than 1.4 times of the height to where the ladder contacts the wall or structure.
The Contractor shall ensure that such PPE comply with the requirements of UNOPS. He
shall also ensure that his workmen properly use all equipment during the course of their
work. He shall record the issuance of all equipment to his workmen in prescribed forms.
Such forms shall be kept in the site office and made available for inspection at all times.
GR-1 10-28
G E N E R AL R E Q U I R E M E N T S S I T E ME E T I N G S
on a white background in gloss finishing paint. Warning lights shall be placed at similar
positions at night to serve as warnings.
GR- 110-2 9
G E N E R A L R E Q U I R E ME N T S S I T E MEE T I NG S
integrity. Pipe connectors, particularly those installed at heights shall be secured against
dislodgement, thereby becoming a falling object.
Where the equipment has to slew around as part of the operation, such as a back-hoe,
and where there are other workers in its proximity, a signaler shall be present to direct
the operator.
2.18 Housekeeping
The Contractor shall maintain and ensure a safe working environment by keeping the
site neat and tidy and free from hazards and debris. Materials shall be stacked up
safely. All work areas and access thereto shall be kept free from hazards and debris.
Housekeeping shall be carried out in such a manner and at such times so as not to
cause any inconvenience to either the adjoining occupiers or the public. Debris shall be
wetted to minimize the risk of dust. Containers for debris and rubbish are to be provided
at the designated places.
GR-1 10-30
G E N E R AL R E Q U I R E M E N T S S I T E ME E T I N G S
All first-aid provisions shall comply with UNOPS Health & Safety (First-Aid) Regulations.
GR- 110-3 1
G E N E R A L R E Q U I R E ME N T S S I T E MEE T I NG S
2.26 Demolition
Uncontrolled collapse of walls or other structures under demolition shall be prevented.
Walls and structures liable to collapse on workers shall be broken up gradually from the
top downwards. Scaffolds shall be provided to allow for this procedure.
Throwing of materials over the sides of the structure shall not be permitted. The dust
levels due to demolition shall be controlled. Special procedures shall be followed at sites
where dangerous materials, such as asbestos, are present.
The following actions shall be carried out before demolition is started:
Disconnect all service lines e.g. gas, electricity and water.
Fence off the building under demolition, providing a safety zone between the
building and the fencing as much as possible. Where required, hoardings shall be
provided.
Remove glass pieces and sharp materials.
Support structures that might collapse dangerously.
Where asbestos materials are present, appropriate dust control and respiratory
protection approved by the local authority must be used.
2.27 Excavations
No person shall enter or be permitted to enter an excavation that does not comply with
this part.
Work shall not be performed in a trench unless another worker is working above ground
in close proximity to the trench or to the means of access to it.
The type of soil in which an excavation is made shall be determined by visual and
physical examination of the soil at the walls of the excavation and within a horizontal
distance from each wall equal to the depth of the excavation measured away from the
excavation.
Before an excavation is begun, gas, electrical and other services in and near the area to
be excavated shall be accurately located and marked. If a service may pose a hazard,
the service shall be shut off and disconnected.
An excavation in which a worker may work shall have a clear work space of at least 450
mm between the wall of the excavation and any formwork or masonry or similar wall.
GR-1 10-32
G E N E R AL R E Q U I R E M E N T S S I T E ME E T I N G S
The walls of an excavation shall be stripped of loose rock or other material that may
slide, roll or fall upon a worker.
A level area extending at least one meter from the upper edge of each wall of an
excavation shall be kept clear of equipment, excavated soil, rock and construction
material.
The stability of a wall of an excavation shall be maintained where it may be affected by
stockpiling excavated soil or rock or construction materials.
No person shall operate a vehicle or other machine and no vehicle or other machine
shall be located in such a way as to affect the stability of a wall of an excavation.
If a person could fall into an excavation that is more than 2.4 m deep, a barrier at least
1.1 m high shall be provided at the top of every wall of the excavation that is not sloped.
Where the excavation is a trench and the depth exceeds six m or the width exceeds 3.6
m, a support system consisting of either timber or of an engineered support system
designed for the specific location and project shall be installed.
2.29 Painting
Paints containing lead or lead products shall not be used. Facemasks shall be supplied
to workers when paint is applied in the form of spray or when a surface having lead
paint is dry rubbed and scrapped.
As most paint materials are highly combustible, every precaution shall be taken to
eliminate danger from fire. Packages containing paints, varnishes, lacquers or other
volatile painting materials shall be kept tightly closed when not in actual use and shall
be placed where they shall not be exposed to excessive heat, spark, flame or direct rays
of the sun.
GR- 110-3 3
G E N E R A L R E Q U I R E ME N T S S I T E MEE T I NG S
designate a worker to control traffic on the construction site and must ensure that the
designated traffic controller wears a reflective vest, safety footwear and hard hat.
The passage of vehicles across a footpath shall be supervised to remove danger to the
school children and the public.
The Contractor and his workers must be vigilant at all times and must ensure that
pedestrians and school children do not cross the safety barriers and enter the
construction site.
2.32 Occupational Health and Environmental Controls
Shelter from adverse weather conditions shall be provided. Toilet facilities shall be
provided and maintained in a clean condition. Washing facilities with running water shall
be provided. Potable drinking water shall be provided. Food supplies of adequate quality
shall be available or provided in canteens on site.
All rest areas, canteens toilets and washing facilities shall be adequate in number,
convenient to the work areas and kept clean, well lit and ventilated. Toilet facilities shall
be easily accessible, especially to those working on very tall buildings. Adequate
facilities shall be provided for the changing drying and storing of clothing. Waste
disposal bins shall be provided for the disposal of garbage.
All workers shall be checked by the foreman before being hired to make sure they are
physically capable of the work and are free from obvious signs of sickness. Workers
who have to work at heights shall be checked by the foreman before starting work each
day. Any worker showing signs of sickness shall not be allowed to work at heights.
2.33 Others
The Contractor shall provide and maintain guards, fences or barriers around the
construction site, excavations, lift pits or other similar potential places of danger to
prevent accidents. The guards, fences and barriers shall be of sound material, good
construction and possess adequate strength.
No measurement or separate payment shall be made for the works under this section.
It is deemed that all the cost for above requirements are covered under appropriate unit
prices tendered by the Contractor in the Bill of Quantities.
GR-1 10-34
G E N E R AL R E Q U I R E M E N T S S I T E ME E T I N G S
Appendix I
Project Manager
United Nations Office for Project Services
Copy: UNOPS Health & Safety Officer
Modernization and Improvement of Policing Project in Nepal
I, __________________________________ of
_______________________________________
(Name of Managing Director) (Name of Company)
I/C No: __________________ understand that as the Contractor of /for the above worksite /
work area or order, it is my duty and responsibility to ensure that the provisions of UNOPS
Health & Safety Policy & Procedures, and any amendments or re-enactments thereto are
complied with.
GR- 110-3 5
S EC T I ON GR - 1 00
ENVIRONMENTAL CONTROL
1. GENERAL
Some generic environmental impacts can be expected during the construction of the
project structures. These impacts can be mitigated by the measures contained in this
section so that the works are performed in conformity with national environmental
standards.
3. AIR QUALITY
Impacts
Impacts on local air quality due to the following factors:
a. Fugitive dust generation in and around the construction area from earthworks,
demolition, stockpiles, etc.
b. Generation of diesel exhaust from heavy equipment and generators.
Mitigation Measures
a. Remove spoil/muck from construction sites at the earliest practicable.
b. Cover loose materials (sand, aggregates, etc.) and muck/spoil at stockpiles and
during their transportation.
c. Regularly sprinkle water in construction area to minimize dust generation.
d. Keep surrounding environment free of debris.
e. Prohibit open burning of construction / waste material at the site.
f. Provide PPE (masks, etc.) to workers, engineers and supervisors at construction
sites.
g. Ensure that all construction equipment and vehicles are in good operating condition.
h. Ensure that all project vehicles comply with national emission standards.
i. Prohibit excessive idling of construction vehicles at site.
j. Ensure proper collection and disposal of sewerage and solid wastes in camps,
offices and work areas.
4. SURFACE WATER
Impacts
Construction activities can result in:
GR-1 00-36
G E N E R AL R E Q U I R E M E N T S S I T E ME E T I N G S
5. GROUND WATER
Impacts
a. Contamination of runoff due to leaking fuel or lubricants from construction equipment
and fuel stores.
b. Incremental decrease in groundwater percolation due to increase in hardscaping.
Mitigation Measures
a. Implement all measures under item 4 above.
b. Use of paving with pervious joints (e.g. concrete blocks) to allow surface water
percolation.
6. NOISE
Impacts
a. Noise pollution from the use of heavy construction equipment and machinery.
Mitigation Measures
a. Ensure that all processes, machines and equipment implement one or more of the
following measures:
Engineering noise control, e.g., modifying noisy processes, machines and
equipment, relocating noisy processes or isolating them within enclosures,
erecting sound barriers, reducing kinetic or potential energy and regularly
maintaining machines and equipment.
Using quiet machines and equipment (generators, compressors and concrete
breakers) when such machines and equipment are available in the market.
Provide hearing protectors for workers who are exposed to excessive noise and
ensure that they are worn at all times.
Install warning signs in areas with excessive noise to remind workers that
hearing protectors must be worn.
GR- 110-3 7
G E N E R A L R E Q U I R E ME N T S S I T E MEE T I NG S
9. UNEXPLODED ORDNANCE
Impacts
a. Loss of life or limb from disturbance to or handling of unexploded ordnance (UXO)
uncovered during construction.
Mitigation Measures
a. Immediately vacated and secured area where a potential UXO is identified and notify
qualified and authorized disposal organization to dispose it.
b. Conduct excavation below the depth or outside the area that has already been
cleared only after approval from relevant authorities.
c. Provide onsite UXO safety training to all workers on identifying potential UXO and
the appropriate response.
GR-1 10-38
G E N E R AL R E Q U I R E M E N T S S I T E ME E T I N G S
11. SOCIOECONOMICS
Impacts
a. Influx of large number of skilled and semi-skilled workers into the project area,
resulting in conflict of interest between locals and migrants, deterioration of law and
order, gambling, increased alcohol consumption, prostitution, etc.
b. Generation of employment and small business opportunities for local residents.
c. Skill and capability enhancement of local workmen and residents.
Mitigation Measures
a. Create awareness on need for good social habits amongst migrant works and strict
monitoring of their activities.
b. Good coordination with local security agencies, stakeholders and residents to
maintain security and social harmony.
c. Priority to local employment and local skill development.
12. CULTURAL
Impacts
a. Uncovering of buried cultural or archaeological resources during construction
activities.
Mitigation Measures
a. Immediately cease construction activities in the area where cultural or
archaeological resources are unearthed.
b. Contact appropriate government office for necessary action and authorization for
further construction.
GR- 110-3 9
G E N E R A L R E Q U I R E ME N T S S I T E MEE T I NG S
SITE MEETINGS
The Contractor’s senior site representative shall report weekly to the Engineer on the
status of each activity planned for the period under consideration and to review
construction progress and consider matters arising from or having a bearing on the
Contract.
3. ATTENDANCE
The Contractor’s senior site representative shall attend each meeting, together with
such other members of its staff as may be required. The Contractor shall also be
responsible for the attendance of representatives of its sub-contractors and suppliers.
4. COST
No separate payment shall be made to the Contractor for the works under this section. It
is deemed that the costs for these works are covered under appropriate unit prices
tendered by the Contractor in the Bill of Quantities.
GR-1 10-40
DEMOBILIZATION
1. GENERAL
This Section covers the works to be performed by the Contractor prior to demobilizing
from the Site. All of these works shall be performed to the Engineer’s satisfaction.
2. FINAL CLEANING
Before handing over the site to the Employer, the Contractor shall clean the entire
building, including its interior and exterior surfaces. He shall clear all construction
wastes debris from the site and dispose them at an approved location in an acceptable
manner. He shall also remove surplus materials from the Site.
3. REINSTATEMENT
The Contractor shall clean and repair any damage caused to the Site by the installation
or use of any temporary works by him. He shall restore existing facilities that were used
during construction to their original condition.
4. CONDITION-OUT SURVEY
5. ADJOINING PROPERTY
6. DOCUMENT SUBMISSION
The Contractor shall submit the following documents to the Engineer after completion of
the construction:
Material test certificates
As-built drawings
Warranty statements
List of suppliers with their contact information
Spare materials, where applicable.
GR- 110-4 1
S P E C I F I C AT I O N S F O R L A B O R A T O R Y LAB F ACI L I T I ES
Within ten working days of handover, the Contractor shall remove from the site
temporary works and construction plants no longer required at the Site. However, he
shall be allowed to retain at the Site those temporary works and construction plants that
may be required by him for the purpose of fulfilling his obligations during the Defects
Liability Period.
No separate payment shall be made to the Contractor for the works under this section. It
is deemed that the costs for these works are covered under appropriate unit prices
tendered by the Contractor in the Bill of Quantities.
GR-1 10- 42
B - SPECIFICATION FOR FURNITURE
WORKS
TECHNICAL SPECIFICATIONS FOR FURNITURES SECTION FS-100
Note:
1. Product with ISI stamp shall have to be provided where available (in case of non-availability of
such stamping for a particular product UNOPS decision as per list of material or otherwise shall
be final & binding)
2. The contractor shall prepare shop drawings based upon provided drawings and get prior approval
before final fabrication & commissioning for the furniture related works.
3. The materials shall be got approved by the UNOPS before making any procurement samples of
all approved materials shall be submitted to the UNOPS for reference. The material supplied shall
be of same quality of the approved sample and will be compared/checked at site before installation
and also during execution of work. The materials will be rejected in totality for any defect/deviation
in quality and the same shall be replaced by the Contractor at his cost as per satisfaction of the
UNOPS.
FS-100- 43
TECHNICAL SPECIFICATIONS FOR FURNITURES SECTION FS-100
Laminate sheets shall be 1 mm (as per design requirements or as specified in the respective items)
thick with +0.3 mm tolerance and obtained from any of the following approved manufacturers e.g.
Merino, Century and Greenlam & samples should have approval of the UNOPS. The laminates shall
be resistant to chemicals for the granite top lab tables, wall hung/overhead chemical cabinets,
chemical storage cabinet and shall conform to the quality and standards as of Merino or equivalent
as directed by the UNOPS Engineer.
1.6 Hardware Fittings:
All hardware fittings for doors shall be either brass or as specified in the schedule of quantities. These
hardware fittings shall be obtained from approved manufacturers and shall bear ISI mark wherever
available. The samples for the fittings shall be submitted to UNOPS for their approval. Hardware
fittings for door shutters shall be paid in door shutter item or separately as given in schedule of
quantities. No separate payment shall be made for hardware fittings if not mentioned otherwise in
the schedule of quantities. The rate for hardware fittings shall include for supplying, fitting and fixing
the fittings with necessary cadmium plated screws, washers bolts, nuts etc. as required. All locks
shall be provided with keys in duplicate/triplicate and rate shall include for the same. Approved
samples of hardware fittings shall be deposited with UNOPS for reference.
1.7 Workmanship:
a) The workmanship shall be first class and to the approval of UNOPS. Scantlings and board shall
be accurately sawn and shall be of required width and thickness. All carpenter's work shall be
wrought except where otherwise described. The workmanship and joinery shall be accurately set out
in strict conformity according to the drawings and shall be framed together and securely fixed in
approved manner and with properly made joints. All work is to be properly tanned shouldered,
wedged, pinned, braced etc. and properly glued with approved quality glue to the satisfaction of
UNOPS/Engineer.
b) Screws: Unless otherwise specified all screws to be used in woodwork and joinery shall be of
cadmium plated and of approved quality. The size (diameter and length) should conform to those
specified in hardware schedule.
c) Tolerance: l.5 mm (l/l6") will be allowed for each wrought face of sizes specified except where
described as finished in which case they shall hold to the full dimensions.
d) Protection: All edges of timber frames etc. shall be protected from being damaged during
construction by providing rough timber casing securely fixed and other adequate protective
measures.
e) Door/Windows frames shall have cut rebate. Planted rebates shall not be permitted.
f) Where door frames are fixed flush with plaster to wall, teak wood cover mould 40 x l2 mm as per
drawings shall be provided all round and shall be painted or polish finished to match with finished
shutters. This will be paid as a separate item as described in Schedule of Quantities.
1.8 Rates to Include Apart from other factors mentioned elsewhere in this contract the rate for item
of wood work and joinery shall include for the following :-
A. Items of Scantling i) All labour, materials and equipments for fixing frame work as per drawing
including the cost of holdfasts, Rawl plugs, or other fasteners etc.
FS-100- 44
TECHNICAL SPECIFICATIONS FOR FURNITURES SECTION FS-100
B. Items of Shutters i) All labour, materials, hardware fittings and equipments for carrying out the
work as per drawing. ii) Labour for fixing the shutters in position (including/excluding the cost of
fittings as specified in the BOQ) as per drawing.
1.9 Mode of Measurement:
All measurements shall be as per relevant section of I.S. l200 of latest edition.
i) Scantling shall be measured in cum. The sectional area shall be the area of the least square, or
rectangles from which the scantling may be cut. The length shall be actual length of timber required
for the purposes including the extra portion required for jointing.
ii) Shutter shall be measured in square metre for closed door shutters area i.e. rebate to rebate
without extra measurement for rebates and/or splayed meeting styles of door.
iii) Partitions, encasing shall be measured in square metre of the finished work. For full height
partition no payment shall be made for additional frame work extended upto ceiling for rigidity of the
same. 2.0
PARTITIONS
2.1 Frame Work Modular Partitions will have a thickness of minimum 70 mm and the width and
height will be as per drawing & specifications. The vertical members will be made from
C.R.C.A/Aluminum tubes and the horizontal members from C.R.C.A/Aluminum frames. Low height
partitions will be free standing and self-supporting. In full height partitions, the vertical members will
be jacked under tension to the main ceiling/beam bottom (as the case may be). Both, low height and
full height partitions will be provided with levelling systems to adjust the partitions to unevenness and
differences in floor and ceiling levels.
2.2 Skirting Low Height Partitions will be provided with a box type skirting raceways for wire
management, either along the base and/or at table height as per drawing. The skirting will have a
height of minimum 128 mm and will be fabricated out of 0.8 mm CRCA sheet. There will be an
openable cover on both side for easy access to carry out electrical installations and maintenance. In
full height partitions, the skirting cover will have a height of minimum 128 mm. The skirting will be
approachable from both sides and will have channels for adjustment for floors. Box type raceway
can be provided at table height.
2.3 Finishes Partitions and Doors are available within fill panels in the following finishes:
a) P.F bonded exterior grade Prelaminated board of minimum 9 mm thickness (on both sides)
b) Fabric cladded soft board of minimum 12 mm thickness (on both sides)
c) Glass of minimum 6 mm thick toughened float glass as specified.
d) Stainless steel/Brass screws of approved size & make. Various combinations of the above finishes
on either side can be provided as specified by the UNOPS/Engineer. All the in-fill panels in doors
and partitions are fitted by using aluminum profiles and PVC extrusions are used as trimmings.
Phenol formaldehyde bonded exterior grade. Prelaminated boards shall be of any shade as per
drawing and direction. All metal sections, fabricated M.S components and aluminum profiles are
FS-100- 45
TECHNICAL SPECIFICATIONS FOR FURNITURES SECTION FS-100
finished in epoxy powder coating of a thickness 50 microns. The standard shades are Grey, Black
and Brown or as specified by UNOPS Engineer.
Table for brief specification for furniture and furnishing related works
FS-100- 46
TECHNICAL SPECIFICATIONS FOR FURNITURES SECTION FS-100
FS-100- 47
TECHNICAL SPECIFICATIONS FOR FURNITURES SECTION FS-100
FS-100- 48
TECHNICAL SPECIFICATIONS FOR FURNITURES SECTION FS-100
FOR EXTERNAL USE : 1ST quality Ghana Teak/Steam beach Wood, as suggested in details
specifications brown in color without knots, joints & bend wood.
FOR INTERNAL USE : 1ST quality C.P.Teak Wood/Steam beach, as suggested in detail
specifications without knots, joints & bend wood.
FOR WOODEN MOLDING : 1st quality of either Ghana Teak Wood or C.P.Wood/Steam beach as
specified in detail specifications of each item.
(3) : LAMINATES : Merino, Greenlam, Century, -Color, finish suggested by the UNOPS.
1.5MM/1mm thickness (I.S.I.MARK)
C : HINGES FOR DOOR : S.S. with S.S. pin, Heavy Duty – on approval- Sizes:5”x1”x1”.
D : STOPPERS FOR DOORS : S.S. matt finish – on approval – 6” & 8” size as suggested.
E : HANDLES FOR DOORS : S.S. matt finish – 6” Size on design approval (Kich or Eq.)
(5) : POLISH : Asian Mealamine, N.C.clear Lacquer polish as specified in detailed specifications.
(7) : POWDER COATING : 55 Micron – shade & finish (7 tank process) as suggested by Architect.
FS-100- 49
TECHNICAL SPECIFICATIONS FOR FURNITURES SECTION FS-100
Photo: Visitor’s chair w/o hand rest – Photo: Revolving chair Model GA 559
model GV 606
FS-100- 50
C - SPECIFICATIONS FOR CIVIL WORKS
Table of Contents
1. GENERAL
1.1 Scope
This section of the Specification covers the clearing and grubbing of construction sites in
preparation for excavation and subsequent construction, as defined hereunder:
a. Areas to be cleared shall include the entire foundation areas for building(s),
pavements, access roads and other permanent structures.
b. Areas to be grubbed, in addition to being cleared, shall include the foundation areas
for building(s), pavements, access roads and other permanent structures.
1.2 Definitions
The various terms covered under this section are defined below:
Top soil Surface layer of undisturbed natural soil that is rich in organic nutrients and
supports the growth of vegetation. Generally, the surface layer of soil to a
depth of 500 mm shall be considered to be top soil.
2. EXECUTION
2.1 Clearing
Unless otherwise directed by the Engineer, clearing shall extend to a line 1.5 m
horizontal distance outside the limits of the respective structures. Other areas shall be
cleared to the limits directed by the Engineer.
The Contractor shall remove all shrubs, vegetation, grass, brushwood, trees and
saplings of girth up to 30 cm measured at a height of 1 m above ground, fences,
debris, floatable materials, litter and similar matters from the areas specified to be
cleared. Trees of girth above 30 cm measured at a height of 1 m above ground shall
be cut only after written permission of the Engineer. Special care shall be taken to
preserve all vegetation outside the cleared areas to the maximum practicable extent.
The Contractor shall dispose of the cleared materials at a distance of 50 m outside the
periphery of the area under clearance. The disposed materials shall not be pushed or
felled into areas not designated to be cleared.
2.2 Grubbing
Unless otherwise directed by the Engineer, grubbing shall extend to a line minimum of 1
m outside the foundation or excavation lines. It shall consist of removal and disposal of
all tree stumps, including the tap roots, and all lateral roots exceeding 38 mm diameter
to a depth of 60 cm below ground level or 30 cm below formation level or 15 cm
below subgrade level, whichever is lower, and filling up, ramming and leveling of holes
or hollows with earth. Grubbing shall also include removal of any buried logs, posts or
other organic materials. Vegetation other than grasses shall also be removed from
grubbed areas so that topsoil may be salvaged for reuse.
C S- 01 0 - 5 1
S P E C I F I C AT I O N S F O R C I V I L W O R K S C L E AR I N G A N D G R U B B I N G
top soil shall be stockpiled in separate piles at locations determined by the Engineer for
later use in the Works. This activity shall be paid for as excavation. The stockpiles shall
be sloped to drain and located in areas where they will not be lost to erosion. Upon
completion of the Works, the stripped material shall be spread in locations as instructed
by the Engineer.
3.1 Measurement
Measurement for payment for clearing and grubbing shall be made of the area, in
square meters, of the area cleared and grubbed, as measured in the field and agreed
upon between the Engineer and the Contractor. Dimensions shall be measured nearest
to 10 mm, and individual quantities shall be calculated correct to two places of decimals
of a square meter.
3.2 Payment
Payment for clearing and grubbing shall be at the unit rate tendered in the Bill of
Quantities. The unit rate shall include the costs of labor, equipment, any materials,
stockpiling and disposal as specified in this section and BOQ description.
CS-01 0-52
S E CT I ON C S- 0 2 0
EARTHWORK IN SOIL
1. GENERAL
1.1 Scope
This section of the Specifications covers the earthwork in excavation for all types of
foundations, wet or dry. It covers earthwork in all types of soils, including sand, gravel,
loam, clay, mud, black cotton and other similar soft or loose material. It includes all
materials of earthy or sandy nature that can be easily ploughed, small shingles, gravels
and river shingles that can be easily removed and hard core macadam surface of any
description (water bound, grouted tarmac, etc.), lime concrete, mud concrete and their
mixtures which for excavation yields to application of picks, shovels, jumper, scarifier,
ripper and other manual digging implements. Removal of small boulders not exceeding
3,000 cc occurring in such strata shall be included in the rate of the excavation.
1.2 Definitions
The various types of excavations covered under this section are defined below:
Surface excavation Excavations exceeding 1.5 m in width and 10 sq. m on plan
but not exceeding 30 cm in depth
Rough excavation Excavation for earth from borrow pits, cutting hill side slopes,
etc.
Excavation over Excavation exceeding 1.5 m in width and 10 sq. m on plan
Area and exceeding 30 cm in depth.
Excavation for basements, water tanks, etc.
Excavation in trenches exceeding 1.5 m in width and 10 sq.
m on plan.
Trench excavation Excavation not exceeding 1.5 m in width or 10 sq. m on plan
for foundations and and to any depth in trenches (excluding trenches for pipes,
drains cables, conduits etc.)
Trench excavation Excavation not exceeding 1.5 m in width or 10 sq. m in plan and
for pipes, cables, to any depth trenches for pipes. Cables etc.
etc.
2. EXECUTION
C S- 02 0 - 5 3
S P E C I F I C AT I O N S F O R C I V I L W O R K S E ART H W OR K I N S OI L
2.2 Excavation
All excavation operations, whether conducted manually or by mechanical means,
shall include excavation and ‘getting out’ the excavated materials. In case of
excavation for trenches, basements, water tanks, etc., ‘getting out’ shall include
throwing the excavated materials at a distance of at least one m or half the depth of
excavation, whichever is more, clear off the edge of the excavation. In all other
cases, ‘getting out’ shall include depositing the excavated materials as specified. The
subsequent disposal of the excavated material shall be either stated as a separate
item or included with the items of excavation stating the lead.
During the excavation, the natural drainage of the area shall be maintained.
Excavation shall be done from top to bottom. Undermining or undercutting shall not be
done.
The excavation shall be done true to levels, slope, shape and pattern indicated on the
Drawings or as directed by the Engineer. Only the excavation shown on the Drawings
with additional allowances for centering and shuttering or as required by the Engineer
shall be measured and recorded for payment.
The elevations of the foundation bottom shown on the Drawings shall be considered as
approximate only, and changes in the dimensions and elevations of the foundation as
deemed necessary to secure satisfactory foundation shall be as per the instructions of
the Engineer.
The excavation shall be done manually or by mechanical means as directed by
Engineer considering feasibility, urgency of work, availability of labour /mechanical
equipment and other factors involved. The Contractor shall ensure every safety
measures for the workers. Neither any deduction nor any extra payment will be made
on this account.
2.2.1 Excavation over Area and in Trenches for Foundation and Drains
In firm soils, the sides of the trenches shall be kept vertical up to a depth of 2.5 m
from the bottom. For greater depths, the excavation profiles shall be widened by
allowing steps of 500 mm on either side after every 2.5 m from the bottom.
Alternatively, the excavation can be done so as to give a slope of 1:4 (1
horizontal: 4 vertical). Where the soil is soft, loose or slushy, the width of steps
shall be suitably increased or sides sloped or the soil shored up as directed by the
Engineer. It shall be the responsibility of the Contractor to take complete
CS-02 0-54
S P E CI FI C AT I O NS F OR CI VI L W OR K S E AR T H W O R K I N S O I L
instructions in writing from the Engineer regarding the stepping, sloping or shoring
to be done for excavation deeper than 2.5 m.
C S- 02 0 - 5 5
S P E C I F I C AT I O N S F O R C I V I L W O R K S E ART H W OR K I N S OI L
In case the excavation is done wider than that shown on the Drawings or as required
by the Engineer, additional filling, wherever required, shall be done by the Contractor
at his own cost.
After excavation is complete, the Contractor shall notify the Engineer that the excavation
is ready for inspection. No excavation shall be covered with concrete until it has been
inspected and approved by the Engineer in writing.
2.4 Shoring
Where necessary, the Contractor shall design the shoring in accordance with IS 3764:
1992 to ensure proper excavation. Shoring shall be of sufficient strength to resist side
pressures and ensure safety from slips, prevent damage to works and property and
injury to persons. It shall be removed as directed after all the items for which it is
required are completed.
Shoring shall generally be done when the depth of trench in soft/loose soil exceeds 2 m.
In case of loose and slushy soils, the depths at which shoring is to be done shall be
determined by the Engineer according to the nature of soil.
Shoring shall be ‘close’ or ‘open’ depending on the nature of soil and the depth of
trench.
2.5 Protection
Where directed by the Engineer, excavations shall be securely barricaded and
provided with proper caution signs, conspicuously displayed during the day and
properly illuminated with red lights and/or written using fluorescent reflective paint, as
directed by the Engineer, during the night to avoid accident. Night watchmen shall
patrol the excavations to avoid accidents. The Contractor shall be entirely responsible
CS-02 0-56
S P E CI FI C AT I O NS F OR CI VI L W OR K S E AR T H W O R K I N S O I L
for any injury to life and damage to property caused by his negligence or accidents due
to his operations.
The Contractor shall take adequate protective measures to see that the excavation
does not damage adjoining structures or dislocate existing services. Existing water
supply pipes, sluice valve chambers, sewer pipes, manholes, drainage pipes and
chambers, power supply cables, communication cables, etc. met within the course of
excavation shall be properly supported and adequately protected, so that these
services remain functional. All existing structures, foundations, pipes and cables that are
to be incorporated into the final work shall be adequately protected or replaced by the
Contractor.
The Contractor shall not store material or otherwise occupy any part of the site in a
manner likely to hinder the operations of such services. Any services damaged during
excavation shall be restored in reasonable time by the Contractor at his own cost.
Excavation shall not be carried out below the level of existing adjacent foundations. If it
is necessary for some reason to excavate below the adjacent foundations, these
foundations shall be underpinned and shored by the Contractor prior to proceeding with
the excavation. The Contractor shall get written permission from the Engineer for
shoring as required.
2.7 Antiquities
Any finds of archaeological interest, such as relics of antiquity, coins, fossils or other
articles of value, shall be delivered to the Engineer, who, in turn, shall hand it over to
the Employer for further processing with the concerned government agency.
2.8 Dewatering
The Contractor shall bail out or pump out of all water which may accumulate in the
excavation during the progress of the work, either from seepage, rain or any other
source and diverting surface flow, if any, by bunts or other means. The bunts shall be
removed after their purpose is served.
Pumping water from any foundation enclosure or trenches shall generally be done in
such a manner as to preclude the possibility of any damage to the foundation trenches,
concrete or masonry or any adjacent structures. The excavation shall be kept free from
water (a) during inspection and measurement, (b) when concrete and/or masonry works
are in progress and till they come above the natural water level and (c) till the Engineer
considers that the mortar is sufficiently set.
C S- 02 0 - 5 7
S P E C I F I C AT I O N S F O R C I V I L W O R K S E ART H W OR K I N S OI L
2.10 Backfilling
The excavation for open areas and trenches shall be backfilled as specified in Section
CS-030.
3.1 Measurement
The length and breadth of excavation shall be measured with a steel tape correct to the
nearest cm. The depth of cutting shall be measured, correct to 5 mm, by recording
levels before the start of the work and after its completion. For surface excavation, the
area of excavation shall be worked out to the nearest two places of decimal in square
meters. For all other types of excavation, the cubical contents shall be worked out to the
nearest two places of decimal in cubic meters.
For excavations over area and in trenches for foundations and drains up to a depth of
2.5 m, an all-around excavation of 150 mm beyond the outer dimension of footing shall
be measured for payment to make allowances for centering and shuttering. For
excavation depths greater than 2.5 m, an all-around excavation of 500 mm shall be
measured for this purpose. Any additional excavation beyond this limit shall be at the
risk and cost of the Contractor and shall not be measured for payment.
In case the ground is fairly uniform and where the site is not required to be leveled, the
Engineer may permit the measurements of depth of cutting with steel tape, correct to the
nearest cm. If the nature of excavation requires, diagonal ridges, cross ridges or dead-
men, fixed at positions decided by the Engineer, shall be left by the Contractor to permit
accurate measurements being taken with steel tape on the completion of the work.
Deduction of such ridges and dead-men shall be made from the measurements unless
the same are required to be removed later on and the earth so removed is utilized in the
work. In the latter case, nothing extra will be paid for their removal as subsequent
operation.
Driving of sounding bars or jumping small drill holes to explore the nature of the
substratum up to a total length of 1 m distributed in two or three places in each
foundation, if necessary, shall be considered incidental work and shall neither be
measured nor paid for separately.
Removal of slips and blows in the foundation trenches shall neither be measured nor
paid for.
Roads, embankments, etc. required for performing the excavation shall neither be
measured nor paid for.
If, in the opinion of the Engineer, it is necessary to carry the foundation below the levels
shown on the Drawings, the excavation for the first 1.5 m of additional depth shall be
included in the quantity for the particular classification at the unit rate quoted in item E1
of the Bill of Quantities. Excavation below this additional depth of 1.5 m shall be paid for
as extra work at a rate to be decided under the General Conditions of Contract, unless
the Contractor is willing to accept payment at the unit rates quoted in the Bill of
Quantities. For all depths less than the design depth plus 1.5 m, the excavation shall be
paid for at tendered rates.
3.2 Payment
Payment for excavation over area or in trenches for foundations, drains, cables, etc.
shall be made at the unit rate tendered in the Bill of Quantities. These rates shall include
the following:
CS-02 0-58
S P E CI FI C AT I O NS F OR CI VI L W OR K S E AR T H W O R K I N S O I L
a. Setting out works and making profiles, etc. according to the Drawings or as
instructed by the Engineer, and setting up benchmarks and other reference marks.
b. Excavation and removal of all materials of whatever nature, dry or wet, and
necessary for the construction of foundation, removal of blows and slips and use of
tools, plant and equipment necessary for satisfactory completion of the items and
preparing the bed for foundation.
c. Providing and subsequently removing shoring and strutting for cutting slopes.
d. Bailing and pumping out water, except when separately provided for in the Contract.
e. Forming (or leaving) dead-men and their removal after measurements.
f. Sorting of useful excavated material, conveying them up to the specified lead clear
beyond the structure stacking them neatly for backfilling or reuse and wasting
useless materials as directed by the Engineer.
g. Handing of antiquities and useful material.
h. Necessary protection including labour, materials and equipment to ensure safety
and protection against risk or accident.
i. Supply of facilities for inspection and measurement at any time by the Engineer.
j. Compensation for injury to humans and damage to property, if any, caused by the
Contractor’s operation connected with this item.
k. Small drill holes to explore the nature of substratum, if necessary.
No deduction shall be made from the rate, if in the opinion of the Engineer, any of the
operations specified in items c to k above are not required to be carried out on any
account whatsoever.
The lead of 3 0 m mentioned in the Bill of Quantities is the average lead for disposal
of excavated earth. The actual lead for this purpose may be more or less than the 30
m, for which no cost adjustment shall be made in the rates.
C S- 02 0 - 5 9
SE C T I O N CS - 0 30
FILL PLACEMENT
1. GENERAL
1.1 Scope
This section of the Specification covers the selection, placing and compaction of earth,
sand and gravel fill.
1.2 Definitions
Various types of backfills covered under this section are defined below:
Structural backfill Backfill where some measure of foundation support is required.
Random backfill Backfill where structural support is not a requirement.
2. MATERIALS
The Contractor shall produce backfill materials, including any necessary processing, to
meet the requirements for each class of backfill as specified below.
CS-03 0-60
S P E CI FI C AT I O NS F OR CI VI L W OR K S F I L L PL AC E MEN T
3. EXECUTION
C S- 03 0 - 6 1
S P E C I F I C AT I O N S F O R C I V I L W O R K S F I L L P L A C E ME N T
standing water, in the opinion of the Engineer, can be pumped out or diverted.
Permission may be granted to place rock fill by random dumping in areas where the
depth of water is greater than 500 mm, but the method and the quality of the fill material
shall be subject to approval, and, when the fill is 500 mm above the water surface, it
shall be compacted until there is no discernible settlement under the equipment used for
placing or compacting fill. Thereafter, normal backfilling and compaction shall be
resumed.
CS-03 0-62
S P E CI FI C AT I O NS F OR CI VI L W OR K S F I L L PL AC E MEN T
4.1 Measurement
For fills placed on sides of foundations, measurement of fills shall be made of the
volume, in cubic meters, bounded by the existing ground, excavated surface or surface
of structures and lines and grades of the fill as shown on the Drawings or as required by
the Engineer. For filling in plinths, under floors or as foundation base course, the depth
of filling shall be the compacted depth of filling. The dimensions of filling in this case
shall be the dimension measured prior to fill placement
Dimensions shall be measured with a steel tape correct to the nearest 10 mm, and
individual quantities shall be calculated correct to two places of decimals of a cubic
meter.
4.2 Payment
Payment for structural and random backfills shall be made at the unit prices tendered in
the Bill of Quantities. These unit rates shall include costs of excavating, loading, hauling,
dumping, spreading and compacting fills.
C S- 03 0 - 6 3
SE C T I O N CS - 0 40
1. GENERAL
1.1 Scope
This section of the Specification covers construction of cast-in-place concrete, including
furnishing all materials, labour, skill and equipment and performing all operations for
manufacturing, testing, transporting, forming, placing, finishing and curing concrete
required for completion of the Works.
All structures shall be built in a workmanlike manner and to the lines, grades, and
dimensions shown on the Drawings or prescribed by the Engineer. All metal or other
accessories necessary for concrete work completion shall be installed, and all openings
and concrete blackouts shall be formed as shown on the Drawings or as directed by the
Engineer.
The dimensions of each structure shown on the Drawings shall be subject to such
changes as may be found necessary by the Engineer to adapt the structures to the
conditions disclosed by the excavation. The locations of typical construction joints shall
be shown on the Drawings, but the Drawings may not show all construction joints that
may be required. The location of all construction joints shall be subject to the approval
by the Engineer. Concrete shall be placed in lifts as shown on the Drawings or as
approved by the Engineer.
1.2 Definitions
Various terms included in this section are defined below:
Ordinary concrete Concrete produced by adopting nominal concrete mix
Controlled concrete Concrete produced by designing the concrete mix
Fine aggregate Aggregate most of which passes through 4.75 mm IS sieve
and contains only as much fine material as is permitted in IS
383 for various sizes and grading
Coarse aggregate Aggregate most of which is retained on 4.75 mm I.S. sieve
CS-04 0-64
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
i. IS 1322: 1993 – Specification for Bitumen Felt for Water Proofing and Damp
Proofing
j. IS 1791: 1985 – General Requirements for Batch-type Concrete Mixers
k. IS 2386 (Part I): 1963 – Method of Test for Aggregates for Concrete: Particle Size
and Shape
l. IS 2386 (Part II): 1963 – Method of Test for Aggregates for Concrete: Estimation of
Deleterious Materials and Organic Impurities
m. IS 2386 (Part III): 1963 – Method of Test for Aggregates for Concrete: Specific
Gravity, Density, Voids Absorption and Bulking
n. IS 2386 (Part IV): 1963 – Method of Test for Aggregates for Concrete: Mechanical
Properties
o. IS 2386 (Part V): 1963 – Method of Test for Aggregates for Concrete: Soundness
p. IS 2505: 1992 – General Requirements for Concrete Vibrators - Immersion Type
q. IS 2506: 1985 – General Requirements for Concrete Vibrators - Screed Board
Concrete Vibrators
r. IS 2645: 2003 – Specification for Integral Waterproofing Compounds For Cement
Mortar and Concrete
s. IS 3068: 1986 – Specification for Broken Brick (Burnt Clay) Coarse Aggregate for
Use in Concrete.
t. IS 3812: 2003 – Specification for Fly Ash For Use as Pozzolana and Admixture in
Cement Mortar and Concrete
u. IS 4656 – Specification for Form Vibrators for Concrete
v. IS 7861 (Part I): 1981 – Code of Practice for Extreme Weather Concreting,
Recommended Practice for Hot Weather Concreting
w. IS 7861 (Part II): 1981 – Code of Practice for Extreme Weather Concreting,
Recommended Practice for Cold Weather Concreting
x. IS 9103: 1999 – Specification for Concrete Admixtures
1.4 Submittals
C S- 04 0 - 6 5
S P E C I F I C AT I O N S F O R C I V I L W O R K S C EMEN T CONC R ET E WOR K S
1.4.3 Procedures
The Contractor shall submit to the Engineer procedures covering concrete batching,
mixing, transporting, forming, placing, curing and protecting the concrete.
2. MATERIALS
2.1 Water
Water for construction work shall not be salty or blackish and shall be clean drinking
water, reasonably clear and free from objectionable quantities of silt and traces of oils,
acid and injurious alkali, salts, sugar, organic matter, vegetation growth and other
material that may be deleterious to bricks, stone, concrete or steel. Water shall be
obtained from the sources approved by the Engineer. Sources of water shall be
maintained at such a depth and water shall be withdrawn in such a manner as to
exclude silt, mud, grass or other foreign materials. Containers for transport, storage and
handling of water shall be clean.
The pH value of water shall not be less than 6. The following concentrations represent
the maximum permissible values of deleterious materials in water:
a. Limit on Acidity: Neutralization of 100 ml sample of water, using phenolphthalein as
an indicator, shall not require more than 5 ml of 0.02 normal NaOH, tested as per IS
3025 (Part 22): 1986.
b. Limit on Alkalinity: Neutralization of 100 ml sample of water, using mixed indicator,
shall not require more than 25 ml of 0.02 normal H2SO4, tested as per IS 3025 (Part
23): 1986.
CS-04 0-66
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
Water found satisfactory for mixing shall be considered suitable for curing. However,
water used for curing shall not produce any objectionable stain or unsightly deposit on
the surface.
Water from each source shall be tested before the commencement of Works and
thereafter once in every three months till the completion of the Works. In case of
groundwater, testing shall also be done for different points of drawdown. Water from
each source shall be tested during the dry season before monsoon and again after
monsoon.
2.2 Cement
2.2.1 Types
The cement used in concrete shall be any of the following grades:
a. 43 grade ordinary Portland cement conforming to IS 8112: 1989
b. 53 grade ordinary Portland cement conforming to IS 12269:1987
c. Rapid hardening Portland cement conforming to IS 8041: 1990
d. Portland slag cement conforming to IS 455: 1989
e. Portland Pozzolana cement (flyash based) conforming to IS 1489 (Part 1): 1991
f. Portland Pozzolona cement (calcined clay based) conforming to IS 1489 (Part 2):
1991
g. Hydrophobic cement conforming to IS 8043: 1991
h. Low heat Portland cement conforming to IS 12600: 1989
i. Sulphate resisting Portland cement conforming to IS 12330: 1988
j. White cement conforming to IS 8042: 1989
The type of cement selected should be appropriate for the intended use as per
instruction of the Engineer. Different types of cement shall not be mixed together. In
case more than one type of cement is used in any work, a record shall be kept showing
the location and the types of cement used.
Higher grade cement, specially grade 53, shall be used only where such use is
warranted for making higher strength concrete and also where good quality assurance
measures are in place, by which proper precaution are taken to relieve the higher heat
of hydration through chilling of aggregates or by proper curing of concrete.
High alumina, low heat Portland, super sulphate, rapid hardening and blended cements
shall be used only with the prior approval of the Engineer. Necessary precautions with
regard to their setting and hardening times, time required for de-shuttering, curing, etc.,
shall also be taken after carefully complying with specific literature for these cement
types. Other combinations of Portland cement with mineral admixtures of quality
conforming to relevant Indian Standards may also be used in the manufacture of
C S- 04 0 - 6 7
S P E C I F I C AT I O N S F O R C I V I L W O R K S C EMEN T CONC R ET E WOR K S
concrete, provided that there are satisfactory data on their suitability, such as
performance tests on concrete containing them, and only in such case wherein
specifically called for in the contract.
Where the cement type is not specified, ordinary Portland cement shall be used. The
measurement of proportion of cement should normally be on the basis of weight and
whole bags each undisturbed and sealed 50 kg. When part bag is required, cement
shall be taken to see that each bag contain full quantity of cement.
The Contractor should ensure that the cement is of sound and of required quality before
using it. Cement required for use shall be as fresh as possible. Any cement that has
deteriorated, cracked or has been damaged shall not be used. Cement with doubtful
quality shall not be used pending testing and satisfactory results. Cement that is
condemned shall be immediately removed from the work site.
2.2.4 Supply
The cement shall be packed in jute sacking bags conforming to IS 2580 or double
hessian bituminized (CRI type) or woven HDPE conforming to IS 11652. Woven
polypropylene conforming to IS 11653, jute synthetic union conforming to IS 12174 or
any other approved composite bags may be used. The bags shall bear the
manufacturer’s name and/or his registered trademark, the grade, batch number and
type of cement and the date of manufacturing of batch of cement with NS mark printed.
Every delivery of cement shall be accompanied by a manufacturer’s certificate
confirming that the supplied cement conforms to relevant specifications. These
certificates shall be endorsed to the Engineer for his record.
Every consignment of cement must have identification marks on packages indicating the
date of manufacturing, grade and type of cement, batch number, etc. Cement brought to
works shall not be more than 6 weeks old from the date of manufacture.
Effective precautionary measures shall be taken to eliminate dust nuisance during
loading or transferring cement.
CS-04 0-68
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
the cement bags shall be kept close together so as to reduce air circulation. Stacking
shall not be more than 10 bags high to avoid lumping under pressure. In stacks more
than 8 bags high, the cement bags shall be arranged in header and stretcher fashion i.e.
alternately lengthwise and crosswise, so as to tie the stacks together and minimize the
danger of toppling over.
Different kinds or brands of cement or cement of the same brand from different factory
(mills) shall be stacked and stored in separate groups and shall not be mixed during use
except when directed in writing by the Engineer. Cement shall be kept in a store under
double locking arrangement so that it can be taken out or fresh stock admitted with the
knowledge of supervising staff of the Works.
Cement bags shall be stacked in a manner to facilitate their removal and use in the
order in which they are received. A board indicating stock and daily transactions of
cement shall be kept in each room of the cement store. The cement shall not be stored
unduly long periods. It shall not be handled in such a way as to impair its strength or
useful characteristics.
When temporarily stored in the open for use within 48 hours, cement shall be kept on a
platform of planks about 150 to 200 mm above the ground and covered with a tarpaulin.
For extra safety during monsoon, or when cement is expected to be stored for an
unusually long period, each stack shall be completely enclosed by a water proofing
membrane, such as polyethylene, which shall cover the top of the stack. Care shall be
taken to see that the water proofing membrane is not damaged at any time during use.
Storage of cement at the work site shall be at the Contractor’s expense and risk. Any
damage occurring to cement due to faulty storage in the Contractor’s shed or on
account of negligence on his part shall be the liability of the Contractor.
Ordinary cement stored for more than two months from the date of receipt from the
factory shall be subjected to test and used only if found satisfactory. The cost of test
shall be borne by the contractor responsible for the storage after two months from
receipt.
C S- 04 0 - 6 9
S P E C I F I C AT I O N S F O R C I V I L W O R K S C EMEN T CONC R ET E WOR K S
2.3.4 Gradation
Unless otherwise directed or approved, the grading of sand shall lie within the limits
indicated hereunder: (Refer Code IS 383 1970)
IS Sieve Percentage passing for
Grading Grading Zone Grading Zone Grading Zone
Zone I II III IV
10 mm 100 100 100 100
4.75 mm 90-100 90-100 90-100 95-100
2.36 mm 60-95 75-100 85-100 95-100
1.18 mm 30-70 55-90 75-100 90-100
600 microns 15-34 35-59 60-79 80-100
300 microns 5-20 8-30 12-40 15-50
150 microns 0-10 0-10 0-10 0-15
Where the grading falls outside the limits of any particular grading zone of sieves, other
than the 600 microns IS sieve, by not more than 5%, it shall be regarded as falling within
that grading zone. This tolerance shall not be applied to percentage passing the 600
micron IS sieve or to percentage passing any other sieve size on the coarser limit of
grading zone I or the finer limit of grading zone IV. Fine aggregates conforming to
Grading Zone IV shall not be used for reinforced cement concrete works unless mix
designs and preliminary tests have shown its suitability for producing concrete of the
specified strength and workability.
CS-04 0-70
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
bricks, or a thin layer of lean concrete shall be made so as to prevent contamination with
clay, dust, vegetable and other foreign matter.
Stacks of fine aggregates shall be kept in stockpiles sufficiently removed from those of
coarse aggregates to prevent the material at the edges of the piles from getting
intermixed. If required, divide walls shall be provided to separate the aggregates. Fine
aggregates shall be stacked in a place where loss due to the effect of wind is minimum.
Unless specified otherwise or necessitated by site conditions, stacking of the fine
aggregates should be carried out in regular stacks. The suggested sizes for fine
aggregate stacks are as follows:
SN Length (m) Breadth (m) Height (m)
1 2.0 2.0 0.50
2 5.0 5.0 1.00
3 5.0 1.0 0.50
2.3.8 Measurements
As the fine aggregate bulks to a substantial extent when partially wet, measurements
shall be taken when the stacks are dry or appropriate allowance made for bulking. In
case the fine aggregate is damp at the time of proportioning the ingredients for concrete,
its quantity shall be increased suitably to allow for bulkage. The relation between
moisture content and percentage of bulking is given below for guidance only.
Moisture content (%) Bulking % (by volume)
2 15
3 20
4 25
5 30
C S- 04 0 - 7 1
S P E C I F I C AT I O N S F O R C I V I L W O R K S C EMEN T CONC R ET E WOR K S
a. Normal cement concrete of 100 mm and above thickness: graded 20 mm and below.
b. Cement concrete topping thickness 40 mm and above: graded from 12 mm and
below.
c. Mass cement concrete of 500 mm and above: graded 38 mm and below.
b. Nominal sizes of single-sized stone aggregate or gravel shall be 63, 40, 20, 16, 12.5
or 10 mm, as specified. For any one of the nominal size, the proportion of other
sizes shall be as listed below:
IS Sieve Percentage passing (by weight) for nominal size of
63 mm 40 mm 20 mm 16 mm 12.5 mm 10 mm
80 mm 100 - - - - -
63 mm 85-100 100 - - - -
40 mm 0-30 85-100 100 - - -
20 mm 0- 5 0-20 85-100 100 - -
16 mm - - - 85-100 100 -
12.5 mm - - - - 85-100 100
10 mm 0-5 0-5 0-20 0-30 0-45 85-100
4.75 mm - - 0-5 0-5 0-10 0-20
2.36 mm - - - - - 0-5
c. When stone aggregate or gravel brought to site is single sized (ungraded), it shall be
mixed with single-sized aggregate of different sizes in the proportion to be
determined by field tests to obtain graded aggregate of specified nominal size. For
CS-04 0-72
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
the required nominal size, the proportion of other sizes in mixed aggregate shall be
in accordance with those specified under a above. The recommended proportions
by volume for mixing of different sizes of single size (ungraded) aggregate to obtain
the required nominal size of graded aggregate shall be as follows:
Cement Nominal size of Parts of single size aggregate of size
concrete graded aggregate 50 mm 40 mm 20 mm 12.5 10 mm
required mm
1:6:12 63 9 - 3 - -
1:6:12 40 - 9 3 - -
1:5:10 63 7.5 - 2.5 - -
1:5:10 40 - 7.5 2.5 - -
1:4:8 63 6 - 2 - -
1:4:8 40 - 6 2 - -
1:3:6 63 4.5 - 1.5 - -
1:3:6 40 - 4.5 1.5 - -
1:3:6 20 - - 4.5 - 1.5
1:2:4 40 - 2.5 1 - 1.5
1:2:4 20 - - 3 - 1
1:2:4 12.5 - - - 3 1
1:1.5:3 20 0 0 2 - 1
The proportions indicated above are by volume. If necessary, these proportions may
be varied marginally by the Engineer after sieve analysis of aggregate brought to
site for obtaining the required graded aggregate. No adjustments in the rate shall
be made for any variation in the proportions so ordered by the Engineer. If single-
size coarse aggregates are not premixed at site to obtain the graded coarse
aggregate required for the mix, the volume of single size aggregates required for
the mix shall be suitably increased to account for reduction in the total volume at
the site of mixing.
Grading tests shall be taken in the beginning and at change of source or material.
Where required by the Engineer, tests indicated in IS 383 and IS 456 shall be carried
out in an approved laboratory at the Contractor’s cost to show the acceptability of the
material.
Coarse aggregates of a porous nature, where absorption of water after 24 hours
immersion in water, is more than 5% by weight shall not be used.
Sample of coarse aggregates required for the work shall be approved by the Engineer
both for quality and grading and shall be kept in the site office. The coarse aggregates
to be used shall conform to these samples.
For controlled concrete, the aggregate shall be supplied in separate batches, consisting
at least of coarse, medium and fine grading. These shall be combined in proportions
given by standard grading curves specified in relevant IS codes.
2.4.3 Stacking
Coarse aggregate shall be stacked on a hard, dry and level patch of ground. When
stack piling, the aggregate shall not form pyramids resulting in segregation of different
sized materials. It shall be stacked separately according to nominal size of coarse
aggregates and handled in such a manner as to prevent intermixing of different sizes of
aggregate required separately for grading purposes. No foreign matters shall be allowed
to be mixed with the aggregates. If covered with dust, etc., the aggregates shall be
washed clean before use.
C S- 04 0 - 7 3
S P E C I F I C AT I O N S F O R C I V I L W O R K S C EMEN T CONC R ET E WOR K S
2.4.4 Testing
Coarse aggregate shall be tested for the followings (as per IS 2386).
a. Determination of particle size and shape.
b. Estimation of organic impurities (as per IS 2386 Part II).
c. Surface moisture.
d. Determination of 10% fine value.
2.4.5 Measurements
The aggregates shall be measured in stacks and paid for after making a deduction of
7.5% of the gross measurements of stacks in respect of aggregates of nominal size
40 mm and above. No deduction from the gross measurements of the stacks is to be
made in respect of aggregate of nominal size below 40 mm.
2.5 Admixtures
Admixtures for promoting workability, improving strength, accelerating or retarding
setting, entraining air or for any other purpose may be used in concrete as specified or
only with the prior approval of the Engineer. The admixtures shall conform to IS 9103.
No admixtures shall be accepted for use in concrete unless these are tested in
accordance with IS 9103 and the test results are approved by the Engineer.
The proprietary name and the net quantity of content shall be clearly indicated in each
package or container of admixtures. The admixtures shall be uniform within each batch
and uniform between all batches.
The dosage of admixtures may vary according to manufacturer’s specifications. These
specifications shall be carefully followed so as to ensure complete solution of the
product or to prepare a standard solution of uniform strength for easy use.
If two or more admixtures from the same manufacturers are used simultaneously, the
manufacturer shall certify their compatibility. Admixtures produced by different
manufacturers shall be tested to establish their compatibility before their use in
concrete. All such test reports shall be furnished to the Engineer for his approval before
their use in concrete.
Some admixture may be in the form of powder, particle or high concentration liquids that
may require mixing with water prior to dosing. Under these conditions, water in solution
shall be considered as part of the total water content in the batch in order to maintain
the water-cement ratio.
Certain admixtures may contain significant amounts of finely divided insoluble materials
or active ingredients that may or may not be readily soluble. It is essential for such
admixtures that precautions be taken to ensure that these constituents be kept in a state
of uniform suspension before actual batching. When relatively small amounts of
powered admixtures are to be used directly, these shall be pre-blended with cement.
CS-04 0-74
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
3. GRADES OF CONCRETE
The grades of concrete to be used in the Works shall be indicated in the Drawings or in
the Bill of Quantities by M (mix) and a number denoting the required characteristic
compressive strength of 150 mm cube at 28 days, expressed in N/mm2. The
characteristic strength of concrete shall be defined as the strength of material below
which not more that 5% of the test results are expected to fall.
Generally, the following grades of concrete shall be used for the works:
Group Grade designation Specified characteristic
compressive strength
(N/mm2)
Ordinary M10 10
concrete M15 15
M20 20
Standard M25 25
concrete M30 30
M35 35
M40 40
M45 45
M50 50
M55 55
M60 60
High M65 65
strength M70 70
concrete M75 75
M80 80
Grades M10 and M15 concrete may be used for lean concrete, foundations of masonry
walls or temporary construction. Grades lower than M20 shall not be used in reinforced
concrete. The minimum grade of concrete for plain and reinforced concrete shall be as
follows:
Exposure Plain Concrete Reinforced Concrete
Minimum Maximu Minimum Minimum Maximu Minimum
cement m free grade of cement m free grade of
content water concrete content water concrete
(kg/m3) cement (kg/m3) cement
ratio ratio
Mild 220 0.60 - 300 0.55 M20
Moderate 240 0.60 M15 300 0.50 M25
Severe 250 0.50 M20 320 0.45 M30
Very severe 260 0.45 M20 340 0.45 M35
Extreme 280 0.40 M25 360 0.40 M40
The cement content prescribed in the above table is irrespective of the grade of
cement. Additions such as fly ash or ground granulated blast furnace slag may be
taken into account in the concrete composition with respect to the cement content and
water-cement ratio, if the suitability is established and as long as the maximum
amounts taken into account do not exceed the limit of pozzolana and slag specified in
IS 1489 (Part 1) and IS 455, respectively.
C S- 04 0 - 7 5
S P E C I F I C AT I O N S F O R C I V I L W O R K S C EMEN T CONC R ET E WOR K S
The above minimum cement contents and maximum water cement ratios apply to 20
mm nominal maximum size aggregate only. For other sizes of aggregates, these
should be changed as per Table 6 of IS 456.
4. WORKABILITY
The concrete mix proportion shall be such that the concrete has adequate workability for
its placing conditions and can properly be compacted with the means available.
Suggested ranges of workability of concrete measured in accordance with IS 1199 are
given below:
Placing conditions Workability Slump (mm)
Blinding concrete: shallow Very low Determine compacting factor (see IS
sections: Pavements using 1199), suggested value of
pavers compacting factor 0.75 to 0.80
Mass concrete: Lightly Low 25-75
reinforced sections in slabs,
beams, wall, columns, floors
Hand placed pavements: Medium 50-100
canal lining; Strip footing
Heavily reinforced sections in
slabs, beams, walls, columns:
Slip form work: Pumped Medium 75-100
concrete
Trench fill High 100-150
Tremie concrete Very High Determine flow (see IS 9103)
For most placing conditions, internal vibrators (needle vibrators) are suitable. The
diameter of the needle shall be determined based on the density and spacing of
reinforcement bars and thickness of sections. For tremie concrete, vibrators shall not be
used.
The concrete mix proportions shall be selected to ensure that the workability of the fresh
concrete is suitable for the conditions of handling and placing, so that after compaction,
it surrounds all reinforcements and completely fills the formwork. When concrete is
hardened, it shall have the required strength, durability and surface finish.
The determination of the proportions of cement, aggregates and water to attain the
required strengths shall be made as follows:
a. By adopting nominal concrete mix; such concrete shall be called “Ordinary
Concrete”.
b. By designing the concrete mix; such concrete shall be called “Controlled Concrete”.
CS-04 0-76
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
1
To be taken as the sum of the individual masses of fine and coarse aggregates
C S- 04 0 - 7 7
S P E C I F I C AT I O N S F O R C I V I L W O R K S C EMEN T CONC R ET E WOR K S
The mix shall be designed to produce the grade of concrete having the required
workability and characteristic strength not less than appropriate values given in the table
above.
Where‘s’ is the deviation of the individual test strength from the average strength of a
sample and n is the number of sample test results.
When significant changes are made in the production of concrete (for example changes
in the materials used, mix design, equipment’s or technical control), the standard
deviation value shall be separately calculated for such batches of concrete.
Assumed Standard Deviation
Where sufficient test results for a particular grade of concrete are not available, the
value of standard deviation given in table below may be assumed for design of mix in
the first instance. As soon as the results of samples are available, actual calculated
standard deviation shall be used and the mix designed properly. However, when
adequate past records for a similar grade exist and justify to the designer a value of
CS-04 0-78
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
standard deviation different from that shown in table below, it shall be permissible to use
that value.
Grade of Assumed Standard Deviation (N/mm2)
concrete
M 10 3.5
M 15
M 20 4.0
M25
M30 5.0
M35
M40
M45
M50
The above values correspond to the site control having proper storage of cement: weigh
batching of all materials, controlled addition of water, regular checking of all materials,
aggregate grading and moisture contents and periodical checking of workability: and
strength. Where there is deviation from the above, the values given in the above table
shall be increased by 1 N/mm2.
C S- 04 0 - 7 9
S P E C I F I C AT I O N S F O R C I V I L W O R K S C EMEN T CONC R ET E WOR K S
6. EXECUTION
6.1 Batching
In batching concrete, the quantity of various constituents shall be determined as follows
(see also IS 4925):
a. Cement and aggregate by mass.
b. Admixtures, if solid, by mass; however, liquid admixture may be measured in volume
or mass.
c. Water weighed or measured by volume in a calibrated tank.
Except where it can be shown to the satisfaction of the Engineer that supply of properly
graded aggregate of uniform quality can be maintained over the period of work, the
grading of aggregate shall be controlled by obtaining coarse aggregate in different sizes
and blending them in the right proportions when required, the aggregates of different
sizes being stocked in separate stockpiles. The material shall be stockpiled for several
hours, preferably a day, before use. The grading of coarse and fine aggregates shall be
checked as frequently as possible, the frequency for a given job being determined by
the Engineer to ensure that the specified grading is maintained.
The accuracy of the measuring equipment for grading shall be within ±2% of the
quantity of cement being measured and within ±3% of the quantity of aggregate,
admixtures and water being measured.
The proportion/type and grading of aggregates shall be made by trial in such a way so
as to obtain the densest possible concrete. All ingredients of the concrete shall be used
by mass only.
Volume batching may be allowed only where weigh-batching is not practicable and
provided that accuracy used in concrete have earlier been established. Allowance for
bulking shall be made in accordance with IS 2386 (Part 3). The mass volume
relationship shall be checked as frequently as necessary, the frequency for the given job
being determined by Engineer to ensure that the specified grading is maintained.
In order to maintain the water cement ratio at its correct value, determination of moisture
contents in both fine and coarse aggregates shall be made as frequently as possible,
this frequency for being determined by the Engineer according to weather conditions.
The amount of the added water shall be adjusted to compensate for any observed
variations in moisture contents. For the determination of moisture content in the
aggregates, IS 2386 (Part 3) may be referred to. To allow for the variation in mass for
aggregate due to variations in their moisture content, suitable adjustments in the
masses of aggregates shall be made. In the absence of exact data and only in the case
of nominal mixes, the amount of surface water may be estimated from the values given
below:
Aggregate Approximate quantity of surface water
Percent by mass l/m3
Very wet sand 7.5 120
Moderately wet sand 5.0 80
Moist sand 2.5 40
Moist gravel or crushed 1.25-2.5 20-40
rock
CS-04 0-80
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
6.2 Mixing
Concrete shall be mixed in a mechanical mixer. However, in exceptional circumstances,
such as mechanical breakdown of mixer, work in remote areas or power breakdown and
when the quantity of concrete work is very small, hand mixing may be done with the
specific prior permission of the Engineer.
c. The design of the loader shall be such that it allows the loading hopper to be
elevated to such a height that the centerline of the chute plate of the hopper, when
in discharge position, is at an angle of not less than 50º to the horizontal. A
mechanical device to aid discharge of the contents as quickly as possible from the
hopper to the drum may also be provided. Even when a mechanical device is
provided, it is recommended that the angle of centerline of the chute plate of the
hopper, when in discharge position, should be as larger as practicable, preferably
not less than 40º to horizontal.
d. When the means of raising and lowering the loading hopper includes flexible wire
ropes winding on to a drum or drums, the method of fastening the wire to rope to the
drums shall be such as to avoid, as far as possible, any tendency to cut the strands
of the ropes and the fastening should preferably be positioned clear of the barrel of
the drum for example, outside the drums flange. When the loading hopper is
lowered to its normal loading position, these should be at least one and a half drums
of rope on the drum.
e. Clutch brake and hydraulic control lever shall be designed so as to prevent
displacement by liberation or by accidental contact with any person.
f. The clutch and brake control arrangements shall also be so designed that the
operator can control the falling speed of the loader.
2
Tilting, non-tilting or reverse type
C S- 04 0 - 8 1
S P E C I F I C AT I O N S F O R C I V I L W O R K S C EMEN T CONC R ET E WOR K S
g. Safety device shall be provided to secure the hopper in raised position when not in
use.
Mixing Efficiency
The mixer shall be tested under normal working conditions in accordance with the
method specified in IS 4643 with a view to check its ability to mix the ingredients to
obtain concrete having uniformity within the prescribed limits. The uniformity of mixed
concrete shall be evaluated by finding the percentage variation in quantity (mass in
water) of cement, fine aggregate and coarse aggregate in a freshly mixed batch of
concrete. The percentage variation between the quantities of cement, fine aggregate
and coarse aggregates (as found by weighing in water) in the two halves of a batch and
average of the two halves of the batch shall not be more than the following limits:
cement 8%, fine aggregate 6% and coarse aggregate 5%.
Mixing
Prior to mixing, the mixer drum shall be flushed clean with water. A measured quantity
of coarse aggregate shall be placed first in the hopper. This shall be followed with a
measured quantity of fine aggregate and then cement. In case the fine aggregate is
damp, half of the required quantity of coarse aggregate shall be placed in the hopper,
followed by fine aggregate and cement. Finally, the balance quantity of coarse
aggregate shall be fed in the hopper, and the dry materials shall be slipped into the
drum by raising the hopper. The dry materials shall be mixed for at least four turns of the
drum. While the drum is rotating, water shall be added gradually to achieve the water
cement ratio as specified or as required by the Engineer. Thereafter, the mixing shall be
continued until concrete of uniform colour with uniformly distributed material and
consistency is obtained. Mixing shall be done for at least two minutes after adding water
and at least forty revolutions after all the materials and water are in the drum. When
absorbent aggregates are used or when the mix is very dry, the mixing time shall be
extended as may be directed by the Engineer. Mixer shall not be loaded above their
rated capacity as this prevents thorough mixing. If there is segregation after unloading
from the mixer, the concrete should be remixed.
The entire contents of the drum shall be discharged before the ingredients for the next
batch are fed into the drum. No partly set or remixed or excessively wet concrete shall
be used and it shall be immediately removed from site.
When the mixer is closed down for the day or at any time exceeding 20 minutes, the
mixer shall be thoroughly cleaned. When the next mixing commences, the first mix shall
have 10% additional cement at no extra cost to the Employer to allow for loss in the
drum.
CS-04 0-82
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
consistency is obtained. The mixing platform shall be washed and cleaned at the end of
the day.
Before mixing, stone aggregate or gravel shall be washed with water to remove, dirt,
dust and other foreign materials. For guidance, the mixing time may be 1.5 to 2 minutes;
however, it may be taken as 2.5 to 3 minutes for hydrophobic cement.
6.3 Consistency
Concrete which can flow sluggishly into forms and around reinforcement without any
segregation of coarse aggregate from the mortar shall be used. The consistency shall
depend on whether the concrete is vibrated on or hand tamped. It shall be determined
by slump test as prescribed for workability.
C S- 04 0 - 8 3
S P E C I F I C AT I O N S F O R C I V I L W O R K S C EMEN T CONC R ET E WOR K S
6.7 Compaction
Concrete shall be thoroughly compacted and fully worked around embedded fixtures
and into corners of the formwork. Compaction shall be completed before the initial
setting starts. Compaction shall be done by mechanical vibrator of appropriate type till a
dense concrete is obtained. The mechanical vibrators shall conform to IS 2505, IS 2506,
IS 2514 and IS 4656. For the items where mechanical vibrators are not to be used, the
Contractor shall take permission of the Engineer in writing before the start of the work.
To prevent segregation, over vibration shall be avoided.
The concrete that is to be compacted by vibration should appear anything from earth dry
to slightly glistening, and the mix should have the appearance of lacking in fines. While
placing, segregation is likely to take place when the concrete is tipped into the formwork
and this should be avoided. The concrete mix should not contain surplus water and
sand that will develop segregation under influence of vibratory compaction.
The distribution of new concrete should be uniform for the whole section and the surface
kept horizontal the whole time, thus ensuring the movement of concrete downward only.
Vibrators shall not be used as a spreading or distribution agent.
Vibration shall continue during the whole period occupied by placing the concrete, the
vibration being adjusted so that the center of vibration approximates to the center of the
mass being compacted at the time of placing. The concrete should not be over vibrated,
and the period of insertion of internal vibrator should be about 15 seconds at any point.
The compactness of concrete shall be judged when the mortar fills the spaces between
the coarse aggregate so as to form a glistening and even surface except for slight
irregularities where the coarse aggregate breaks this smooth surface. When this
condition has been attained, the vibrator shall be withdrawn slowly. The vibrator must
not be placed against the steel or the formwork, the minimum distance between the two
being 75 mm. The compressor must be placed in such a position that formwork,
reinforcement and recently laid concrete are subjected to the minimum amount of
vibration.
CS-04 0-84
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
member. All vertical construction joints shall be made with step boards, which are rigidly
fixed and slotted to allow for the passage of the reinforcing steel. If desired by the
Engineer keys and/or dowel bars shall be provided at the construction joints. In the case
of water retaining structures, water stops of approved material shall be provided if so
specified in the drawings or desired by the Engineer. Construction joints shall be
provided in positions as described, the joints shall be in accordance with the followings:
Construction joints shall be made horizontally at the top of the foundations and
horizontally 75 mm below the lowest beam coffin at the head of columns. Concrete in
the ribs and slabs of tee and ell beams shall be placed in one operation, but, for large
beams, concrete in the rib up to a level 25 mm below the slab coffin shall be placed first.
Concrete in haunches or splays on the beams or braces and concrete in the head of
adjoining portion of the columns shall be placed at the same time as that in the beams
or braces. Concrete in splays at the junction of walls and slabs shall be placed at the
same time as that in the slab. Construction joints in the length of a beam shall be
avoided where practicable, but where joints are unavoidable, they shall be made as
previously approved by the Engineer. Construction joints in slabs shall be made parallel
to the main reinforcement, and where required at right angles to the main reinforcement,
they shall be made at a place previously approved by the Engineer.
Before fresh concrete is placed, the cement skin of the partially hardened concrete shall
be thoroughly removed and surface made rough by hacking, sand blasting, water
jetting, air jetting or any other method as directed by the Engineer. The rough surface
shall be thoroughly wetted for about two hours and shall be dried and coated with 1:1
freshly mixed cement sand slurry before placing the new concrete. The new concrete
shall be worked against the prepared surface before the slurry sets. Special care must
always be taken to see that the first layer of concrete placed after a construction joint is
cold. Joints during pour shall be treated with 1:1 freshly made cement sand slurry only
after removing all loose materials.
Moist curing shall be performed by keeping the concrete surface wet by ponding, by
continuous spraying or by covering the surface with an approved water-saturated
covering such as 25 mm sand or sawdust, or wet gunny jute bags. The exposed
concrete surfaces shall be saturated with water for at least seven days from the date of
placing concrete in case of ordinary Portland cement and at least 10 days where mineral
admixtures or blended cements are used. The period of curing shall not be less than 10
days for concrete exposed to dry and hot weather conditions. In the case of concrete
where mineral admixtures or blended cements are used, the above minimum period
may be extended to 14 days. Where forms remain in places during the curing period,
they shall be kept sufficiently wetted with clean water to reduce cracks and to prevent
joints from opening in the forms.
Impermeable membrane such as polythene sheet covering the concrete surface may
also be used to provide effective barrier against the evaporation. Surfaces from which
forms have been removed before the curing period has elapsed shall be protected as
specified for surfaces not covered by forms.
C S- 04 0 - 8 5
S P E C I F I C AT I O N S F O R C I V I L W O R K S C EMEN T CONC R ET E WOR K S
6.10 Finishes
Immediately after stripping the formwork, minor defects and honeycombed areas shall
be patched and holes filled before the concrete is thoroughly dry. Patch areas shall be
chipped away to 25 mm depth with regular edges perpendicular to the surface. The
areas to be patched shall be thoroughly wetted, including the areas at least 150 mm
wide entirely surrounding them, just prior to placing the patching mortar. Mortar shall be
of the same material and proportions as used for the concrete without coarse
aggregate. A sufficient quantity of white cement shall be substituted for part of the
ordinary cement so that the patching mortar, when dry, will be more or less of the same
colour for exposed concrete finish and will match the surrounding concrete. Water in the
mix shall be kept to a minimum and mortar shall be re-tempered without adding water
and shall be allowed to stand for one hour prior to use. Mortar shall be thoroughly
compacted into place, screeded so as to leave the patch slightly higher than
surrounding surfaces, left undisturbed for one to two hours to permit initial shrinkage
and finished to match the adjoining work.
Where patches exceed 25 mm depth, they shall be trimmed and wetted as specified,
after which the opening shall be filled to within 25 mm of the surface. After sufficient
shrinkage time has elapsed, the patching shall proceed as described above. Patches
shall be kept wet for 7 days.
Tie holes left by the withdrawal of rods, or holes left by removal of ends of ties, shall be
filled solidly with mortar. For holes passing entirely through the wall, plunger-type grease
gun or other device to force mortar through the wall, starting at the back face, shall be
used. When a hole is completely filled, excess mortar shall be struck off with a cloth
flush with the surface holes not passing entirely through walls shall be filled solidly with
mortar. Any excess mortar shall be struck off with a cloth flush with the surface. Holes
not passing entirely through walls shall be filled solidly with mortar. The surface of non-
shuttered faces of concrete work other than slabs shall be smoothed with a wooden
float (or, if approved, with a steel trowel) to give a finish equal to that of the rubbed down
shuttered faces. Concealed concrete faces shall be left as is except that honeycombed
surfaces shall be made good.
The top faces of slabs not intended to be surfaced shall be leveled and floated to a
smooth finish at the levels or falls shown on the drawings or elsewhere. The floating
shall not be executed to the extent of bringing excess fine material to the surface.
Ribbed surfaces of slabs shall, where instructed, be formed by approved implements
giving the depth and patterns instructed. The top faces of slabs intended to be covered
CS-04 0-86
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
with creed, granolithic or similar surfacing shall be left with a spade finish. The soffits of
slabs and faces of wall intended to be rendered shall be roughened by approved means
to form a key.
Concrete surfaces to take finishes other than those specifically referred to herein shall
be prepared in an approved manner to suit the finish as instructed.
8.1 Sampling
Samples from fresh concrete shall be taken as per IS 1199 and cubes shall be made,
cured and tested at 28 days in accordance with IS 516.
In order to get a relatively quicker idea of the quality of concrete, option tests on beams
for modulus of rupture at 72 (±) 2 hours or at 7 days or compressive strength tests at 7
days may be carried out in addition to 28 days compressive strength tests. For this
purpose, the values given in table below may be taken for general guidance in the case
of concrete made with ordinary cement. In all cases, the 28 days compressive strength
specified shall alone be the criterion for acceptance or rejection of the concrete. If,
however, from test carried out in particular job over a reasonably long period, it has
been established to the satisfaction of the Engineer that a suitable ratio between 28
days compressive strength and modulus of rupture at 72 (±) 2 hours or 7 days or
compressive strength at 7 days may be accepted, the Engineer may suitably relax the
frequency of 28 days compressive strength, provided the expected strength values at
the specified early age are consistently met.
Grade of Compressive strength on Modulus of rupture by beam test
concrete 15 cm cubes min. at 7 days (min.)
At 72 (±) 2 hours, At 7 days, N/mm2
2
N/mm
M 10 7.0 1.2 1.7
M 15 10.0 1.5 2.1
M 20 13.5 1.7 2.4
M 25 17.0 1.9 2.7
M 30 20.0 2.1 3.0
M 35 23.5 2.3 3.2
C S- 04 0 - 8 7
S P E C I F I C AT I O N S F O R C I V I L W O R K S C EMEN T CONC R ET E WOR K S
8.3 Frequency
The minimum frequency of sampling of concrete of each grade shall be as follows:
Quantity of concrete in Number of samples
the work (in cu m.)
1-5 1
6-15 2
16-30 3
31-50 4
51 and above 4 plus one additional for each
additional 50 cum. or part there of
At least one sample shall be taken from each shift. Where concrete is continuous
production unit, such as ready-mix concrete plant, frequency of sampling may be as
directed by the engineer.
8.5 Testing
The samples of concrete shall be tested in an approved laboratory in the presence of
the Engineer, and the test results shall be submitted in triplicate to the Engineer. The
Contractor shall carry out the sampling and testing according to the provisions of this
Specification at his own cost. No payment shall be made for the concrete used in
specimens.
8.7 Consistency
To control the consistency of concrete from every mixing plant, slump test shall be
carried out as often as demanded by the Engineer and invariably from the same batch
of concrete from which the test cubes are made. Slump tests shall be done immediately
after sampling
CS-04 0-88
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
is found not suitable for the intended use, the cost of these special tests shall be borne
by the Contractor.
9. ACCEPTANCE CRITERIA
In the absence of established value of standard deviation, the values given in Table may
be assumed, and attempt should be made to obtain results of 30 samples as early as
possible to establish the value of standard deviation.
C S- 04 0 - 8 9
S P E C I F I C AT I O N S F O R C I V I L W O R K S C EMEN T CONC R ET E WOR K S
a. The mean strength determined from any group of four consecutive test results
. least 0.3 N/mm2.
exceeds the specified characteristic strength by at
b. The strength determined from any test result is not less than the specified
characteristic strength by 0.3 N/mm2.
CS-04 0-90
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
chamfered faces, shall be true right angles. The rises shall be clean and sharp except
those specified or shown to be rounded. The wearing surface shall be true to the lines.
On being fractured, the interior of the units should present a clean homogenous
appearance.
The longitudinal reinforcement shall have a minimum cover of 12 mm or twice the
diameter of the main bar, whichever is more, unless otherwise directed in respect of all
items, except fencing posts or electric posts where the minimum cover shall be 25 mm.
10.2 Curing
After having been cast in the mould or form, the concrete shall be adequately protected
during setting in the first stages of hardening from shocks and from harmful effects of
frost, sunshine, drying winds and cold.
All precast work shall be protected from the direct rays of the sun for at least 7 days
after casting. During this period, each unit shall be kept constantly watered or preferably
be completely immersed in water if the size of unit so permits. Otherwise, curing
practices as given in clauses stated earlier shall be followed.
The precast articles shall be matured for 28 days before erection or being built in so that
the concrete shall have sufficient strength to prevent damage to units when first
handled. Side shutters shall not be struck in less than 24 hours after depositing
concrete, and no precast unit shall be lifted until the concrete reaches strength of at
least twice the stress to which the concrete may be subjected at the time of lifting.
10.3 Marking
Precast units shall be clearly marked to indicate the top of member and its location and
orientation in the structure.
The Engineer shall instruct that a loading test be made on the works or any part thereof
if, in his opinion, such a test be deemed necessary for one or more of the following
reasons.
a. The site made concrete test cubes failing to attain the specified strength is not
acceptable as per “Acceptance Criteria” of IS: 456 - (latest revision).
b. Over loading during construction of the works or part thereof.
c. Concrete improperly cured.
d. Any other circumstances attributable to alleged negligence on the part of the
Contractor that, in the opinion of the Engineer, may result in the works or part
thereof having less than the expected strength.
e. Any reason other than the foregoing.
If the loading test be instructed to be made solely or in part for the reason above, the
test shall be made at the Contractor’s own cost.
C S- 04 0 - 9 1
S P E C I F I C AT I O N S F O R C I V I L W O R K S C EMEN T CONC R ET E WOR K S
For the purpose of a loading test on floors, roofs and similar structures and their
supports, the member under consideration shall be subjected to a superimposed load
equal to one and a quarter (1.25) times the specified superimposed load used for
design, and this load shall be maintained for a period of 24 hours before removal. The
deflection due to the imposed load only shall be recorded. If, within 24 hours of removal
of the imposed load, the structure does not recover at least 75% of the deflection under
superimposed load, the test may be repeated after a lapse of 72 hours. If the recovery is
less than 80 percent, the structure shall be deemed to be unacceptable. If the maximum
deflection in mm shown during the 24 hours under load is less than 40 l 2/D, where l is
the effective length in m and D the overall depth of the section in mm, it is not necessary
for the recovery to be measured, and the above mentioned recovery provisions shall not
apply.
Other non-destructive test methods may by adopted, in which case the acceptance
criteria shall be agreed upon between the Engineer and the Contractor, and the test
shall be done under expert guidance.
If the member shows evident failure, such changes as are necessary to make the
structure adequately strong shall be made free of cost. If on the other hand, the failure
becomes evident, the Engineer under special circumstances (with the approval of the
designer), can retain the portion of the structure under test, provided suitable
modification for strengthening and/or dispersion of design load is feasible. Cost of such
modification of dispersion of load shall be borne by the Contractor.
If the result of the loading test is not satisfactory, the Engineer shall instruct that part of
the works concerned shall be taken down or removed and reconstructed to comply with
this specification, or that such other remedial measures shall be taken to make the
works secure. If the test be instructed to be made for one or more of the reasons (a) to
(e) inclusive as herein before specified, the Contractor shall take down or remove and
reconstruct the defective works or shall take the remedial measures instructed at his
own cost.
If in the course of dismantling, any damage is done to the embedded items and or other
adjacent structures, the same shall be made good free of charge by the Contractor to
the satisfaction of Engineer.
The Contractor shall leave all openings, grooves, chases, etc. in concrete work as
shown on the Drawings or as specified by the Engineer. He shall build into the concrete
work all the materials noted below and shall embed and secure the same as and when
required. The materials are required to be supplied by the Contractor, shall be of best
quality available of approved manufacture and shall be up to the satisfaction of the
Engineer.
The following materials may be embedded:
a. Inserts, hangers, anchors, opening frames, manholes, covers, floor clips, sleeves
and conduits.
b. Anchor bolts and plates for machinery, equipment and for structural steel work.
c. Dowels bars, etc. for concrete work falling under scope of future works.
d. Lugs or plugs for door and window frames occurring in concrete work.
e. Flashing and jointing in concrete work.
f. Any other built-in-fixtures as may be required.
Correct location, exact alignment, etc. of all these shall be entirely the responsibility of
the Contractor.
CS-04 0-92
S P E CI FI C AT I O NS F OR CI VI L W OR K S C E ME N T C O N C R E T E W O R K S
13.1 Measurement
Measurement of concrete for payment will be made only to the neat lines of the
structures, excluding finishes, as shown in the Drawings or as established by the
Engineer. Dimensions of length, breadth and thickness shall be measured correct to
nearest 10 mm except for the thickness of slab and partition which shall be measured to
nearest 5 mm. Areas shall be worked out to nearest 0.01 sq. m, and the cubic contents
of consolidated concrete shall be worked out to nearest 0.01 cu m. Any work done in
excess over the specified dimension or sections shown in the Drawing shall be ignored.
In measuring concrete for payment, the areas/ volume of all cavities, depressions,
openings, embedded pipes, woodwork and metal work, except reinforcement bars and
anchor bolts and bars, will be deducted.
13.2 Payment
Payment for concreting works shall be made at the unit rates per cubic meter quoted in
the Bill of Quantities. The unit rates shall include the cost of all labours, materials and
equipment required in the construction at all levels, including furnishing and hauling
cement, its storage, protection, etc. all complete, but excluding the costs of furnishing
and placing reinforcement bars, which shall be paid separately.
C S- 04 0 - 9 3
SE C T I O N CS - 0 50
1. GENERAL
1.1 Scope
This specification covers providing and fixing steel reinforcement of various sizes in all
types of RCC works, including necessary supports, spacers, tie wire and accessories.
1.2 Standards
The work specified in this section shall be in accordance with the following standards, or
approved equal, except as they are modified and supplemented herein:
a. IS 456 – 2000: Code of Practice for Plain and Reinforced Concrete
b. IS 432 (Part 1) – 1982: Specification for Mild Steel and Medium Tensile Steel Bars
and Hard-drawn Steel Wire Concrete Reinforcement
c. IS 1139 – 2008: Specifications for High Strength Deformed Steel Bars and Wires for
Concrete Reinforcement
d. IS 1786 – 2008: Specifications for High Strength Deformed Steel Bars and Wires for
Concrete Reinforcement
e. IS 2502 – 1963: Code of Practice for Bending and Fixing of Bars for Concrete
Reinforcement
1.3 Submittals
CS-05 0-94
S P E CI FI C AT I O NS F OR CI VI L W OR K S S T EE L RE I N FO R C E ME N T F O R C ON CR ET E
tests shall be carried out by the contractor on behalf of the Engineer for the purpose of
obtaining the information and conform to relevant IS code at his own cost.
2. PRODUCTS
2.1 Reinforcement
Bar reinforcement described as “mild steel” shall be plain, round hot rolled steel bars of
grade Fe 250, where the figure following Fe indicated the specified minimum 0.2% proof
stress or yield stress in N/mm2. Bar reinforcement described as “Tor steel” shall be hot
rolled, deformed bars or cold twisted steel bars of grade Fe 415. Likewise, bars
described as “TMT” shall be thermo-mechanically treated deformed steel bars of grade
Fe 500. With respect to manufacture, quality, physical properties and related
requirements, reinforcement of the foregoing description shall comply with appropriate
parts of the latest versions of IS: 432 for mild steel and IS: 1786 for tor steel and TMT.
Reinforcement shall be free from pitting due to corrosion, loose rust, mill scale, paint, oil,
grease, adhering earth, ice or other materials that may impair the bond between the
concrete and the reinforcement or that may, in the opinion the of the Engineer, cause
corrosion of the reinforcement or disintegration of the concrete. Adhering lime wash or
cement grout shall be permitted.
Each reinforcing bars shall be tested, and any bar showing cracks or flows or scales
shall not be used. The size of a reinforcement bar described on the working drawings or
elsewhere shall be the minimum, and the rolling margin and other tolerances shall be
wholly above this size.
3. EXECUTION
3.1 Bending
Unless otherwise specified, reinforcing steel shall be bent in accordance with procedure
specified in the latest revision of IS 2502 or as approved by the Engineer.
Reinforcement bars shall be bent by machine or other approved means producing a
gradual and even motion. All the bars shall be cold bent unless otherwise approved.
Bends and shapes shall comply strictly with the dimensions in the approved bar bending
schedule. Bars correctly bent shall only be used. No reinforcement shall be bent when in
position in the work without the approval of the Engineer, whether or not the
reinforcement is partially embedded in concrete. Bars shall not be straightened in a
manner that will injure the materials. Re-bending can be done only if approved by the
Engineer.
C S- 05 0 - 9 5
S P E C I F I C AT I O N S F O R C I V I L W O R K S S T E E L R E I N F O R C E ME N T F O R C O N C R E T E
cured for at least seven days. The sizes and locations of concrete blocks shall be as
approved by the Engineer.
Laps and anchorage lengths of reinforcing bars shall be in accordance with latest
revision of IS: 456 unless otherwise specified. If the bars in a lap are of different
diameter, the smaller diameter shall guide the lap length. The laps shall be staggered as
far as practicable and as directed by the Engineer. Where required or indicated in
Drawings, mechanical couplers shall be used for lapping bars.
Except in the case of TMT bars, welding by gas or electricity may be permitted by the
Engineer under suitable conditions and with suitable safe guards in accordance with the
relevant I.S. However, welding between ends of a bar in line whereby stress is
transferred across the section may be allowed for mild steel bars only.
3.5 Cleaning
Before placing concrete, the reinforcement shall be cleaned of loose rust, oil, grease,
paint or other harmful matters that could impair bond with concrete. Rust shall be
removed by wire brushing, by rubbing with burlap or by equivalent means.
3.6 Inspection
Concrete shall not be placed until the Engineer has inspected the reinforcing steel and
given his permission to place concrete. Concrete placed in violation of this requirement
will be subject to removal and rejection, at the Contractor’s expense.
4.1 Measurement
Reinforcement shall be measured in kg or metric tons computed based on drawings and
the approved bar bending schedule using the theoretical unit weights of reinforcement.
No allowance in weight shall be allowed for cutting to waste, rolling margin, extra length
or other tolerance. Standard hooks and laps, as approved, shall be measured for
payment. However, chairs, spacer bars, etc. shall not be measured.
4.2 Payment
Payment for reinforcement shall be made at the unit rate tendered in the Bill of
Quantities. The unit rate shall include supply and delivery, unloading, hauling, storing,
sorting, cutting, bending, cleaning, placing and securing and maintaining in position all
reinforcement bars, as shown in the Drawings or as directed by the Engineer, including
material and labour for the complete works. Nothing extra shall be paid for preparation
of the bar bending schedule and testing.
CS-05 0-96
S E CT I ON C S- 0 6 0
1. GENERAL
1.1 Scope
This specification covers centering and shuttering works for RCC works of any size,
shape etc., at any level, including strutting, propping and removal thereof.
1.2 Standards
The work specified in this section shall be in accordance with the following standards (or
approved equal) except as they are modified and supplemented herein:
a. IS: 456 – 2000: Code of Practice for Plain and Reinforced Concrete
b. IS: 2750 – 1964: Specification for Steel Scaffoldings.
1.3 Tolerances
The formwork shall be so made as to produce finished concrete that is true to shape,
lines, levels, plumb and dimensions as shown on the Drawings, subject to the following
tolerance unless otherwise specified elsewhere in this Specification or Drawings or
directed by the Engineer:
a. Sectional dimension: 5 mm
b. Plumb: 1 in 1000 of height
c. Levels: 3 mm before any deflection has taken place
1.4 Submittals
All formwork shall be designed and detailed by the Contractor and submitted to the
Engineer for approval. The formwork shall safely support the static and live loads that
could be applied to it during construction, maintenance and removal. The deformations
of the formwork shall be less than the specified tolerances.
2. PRODUCTS
C S- 06 0 - 9 7
S P E C I F I C AT I O N S F O R C I V I L W O R K S F O R MW O R K F O R R C C
3. EXECUTION
3.1 Construction
The centering for the formwork shall be true and rigid and thoroughly braced horizontally
and diagonally. The forms shall be sufficiently strong to carry, without undue
deformation, the dead weight of the concrete as a liquid and working load. Where the
concrete is vibrated, the formwork shall be strong enough to withstand the effects of
vibration without appreciable deflection, bulging or distortion and shall be sufficiently
tight to prevent any leakage of mortar. The formwork shall be such as to ensure the
concrete a smooth uniform surface free from honeycombs, air bubbles, fines and other
blemishes.
Any blemishes or defect found on the surface of the concrete must be brought to the
notice of the Engineer and immediately rectified free of charge as directed or approved
by the Engineer. Where there are chances of fixtures being embedded, only mild steel
or concrete of adequate strength shall be used.
Block outs and sleeves shall be provided for mechanical and electrical work wherever
necessary, as shown on the Drawings, or as directed by the Engineer.
Embedded items shall be secured prior to concrete placement. Templates shall be used
to set equipment anchor bolts and other items where final alignment is critical.
For exposed interior and exterior concrete surface of beams, columns and walls,
plywood or other approved forms, thoroughly cleaned and tied together with approved
corrosion-resident divides shall be used. Rigid care shall be exercised in ensuring that
all columns are plumb and true and thoroughly cross-braced to keep them so. All floor
and beam centering shall be crowned not less than 8 mm in all directions for every 5 m
span. Unless described in the Drawing or elsewhere to the contrary, beveled strips 25
mm x 25 mm shall be provided, without any extra charge, to form angles and in corners
of column and beam boxes for chamfering of corners.
Temporary openings for cleaning, inspection and for pouring concrete shall be provided
at the base of vertical forms and at other places, where they are necessary and are
directed by the Engineer. The temporary openings shall be so formed that they can be
conveniently concreted.
CS-06 0-98
S P E CI FI C AT I O NS F OR CI VI L W OR K S FO R MW OR K F OR R CC
The forms shall not be removed until site cured test cubes develop 50% of the 28-day
strength. Before removing any formwork, the Contractor must notify the Engineer well in
advance to enable him to inspect the concrete if he so desires.
4.1 Measurement
Measurement of payment for formwork shall be made of the area, in square meters, of
the concrete surface formed to the neat lines as shown on the Drawings or as required
by the Engineer.
4.2 Payment
Payment for formwork shall be made at the unit rate tendered in the Bill of Quantities.
The unit rate shall include for all necessary materials and labours required to design,
supply, fabricate, erect and remove the formwork, stage scaffoldings and the cost of all
other necessary works connected therewith.
No separate payment shall be made for formwork required for construction and
contraction joint or required for construction over break. The cost of such formwork is
deemed to be included in the appropriate unit costs of other works.
C S- 06 0 - 9 9
SE C T I O N CS - 0 70
1. GENERAL
1.1 Scope
This specification covers the construction of brickwork in general and the erection of half
brick, full brick and thicker walls in superstructure in particular. It covers brickwork with
normal machine-made and chimney bricks and in tradition decorative bricks (dachi apa).
1.2 Standards
Bricks shall conform to the requirement of I.S. 1077: 1992 – Specification for Common
Burnt Clay Building Bricks.
1.3 Submittal
Representative samples of bricks to be used shall be submitted to the Engineer and his
approval taken before bulk purchase. The samples shall be kept with the Engineer for
future reference and comparison. All bricks supplied shall conform to these approved
samples in all respects.
All bricks shall have to be approved by the Engineer. Any bricks not up to the
specification must be removed from the site immediately at Contractor’s own cost.
2. PRODUCTS
2.1 Bricks
2.1.2 Quality
Machine-made and chimney bricks shall be of first class quality. They shall be uniform
deep red in color, thoroughly burnt, regular in shape and size and shall have sharp and
square edges and parallel faces to ensure uniformity in the thickness of the courses of
brickwork. They shall be sound, hard, homogeneous texture and emit a clear ringing
sound on being struck. Their water absorption shall be minimum.
Dachi apa bricks shall meet all of the requirements of machine-made and chimney
bricks. However, they shall conform to the shape, size, thickness and design specified
from the manufacturer’s catalogue.
Bricks shall be free from cracks, chips, flaws, stones or lumps of any kind. They shall be
free from salt that affect the mortar of the masonry. They shall not show any sign of
efflorescence, either dry or subsequent to soaking in water.
C S- 0 7 0 - 1 00
S P E CI FI C AT I O NS F OR CI VI L W OR K S B R I C K MA S O N R Y W O R K S
2.1.3 Storage
Bricks shall not be dumped at site. They shall be stacked in regular layers even as they
are unloaded. Bricks selected for different types of work shall be stacked separately.
The supply of bricks shall be arranged such that at least two weeks’ requirement of
bricks is available at site at any time.
2.2 Cement
Cement used for masonry shall conform to IS: 8112-1989. It shall be stored above
ground level on perfectly dry platform in a watertight shed. It shall be stacked not more
than ten bags high. The bags shall be stocked in a manner to facilitate removal and use
in the order in which they are received. Partly set cement shall not be used.
2.3 Water
Water shall be clean drinking water, free from deleterious matters and shall be stored in
temporary reservoirs or tanks constructed of brickwork with cement plaster finish.
3. EXECUTION
3.2 Scaffolding
Double scaffolding having two sets of vertical supports shall be provided as directed by
the Engineer. The supports shall be sound and strong and of steel tubular construction
unless otherwise approved. The vertical posts shall be tied together with horizontal
pieces over which the scaffolding planks shall be fixed. The three sides of the
scaffolding shall be covered with l m wide ply boards to protect the materials from
dropping off while working.
CS-070-1 01
S P E C I F I C AT I O N S F O R C I V I L W O R K S B RI C K MAS ON R Y WO RK S
3.4 Bond
Unless otherwise specified in the Drawings, English Bond shall be used in the
construction of full brick and thicker walls. For half brick thick walls and decorative
bricks, stretcher bond shall be used throughout.
Quoin bricks shall be laid header and stretcher in alternative courses, bond being
obtained by placing a closer next to the quoin header. The arrangements of quoin in a
course shall generally be symmetrical. Holes of required size shall be left in the
brickwork during laying for fixing pipes, service lines, passage of water etc. After the
pipes, service lines, etc. are fixed, the leftover space in the holes shall be filled with 1:3
cement mortar or 1:3:6 cement concrete, and the face neatly made up with bricks in
cement mortar. When iron fixtures etc. are to be laid in, the brickwork shall be entirely
covered with not less than 10 mm of 1:3 cement-sand mortar.
C S- 0 7 0 - 1 02
S P E CI FI C AT I O NS F OR CI VI L W OR K S B R I C K MA S O N R Y W O R K S
thus form a composite wall. This strip shall cover the full width of the half brick wall and
part width of the decorative brick wall so that the outer appearance of the latter is not
affected.
3.9 Rise
During construction, no part of a half-brick thick wall shall rise more than 1 m above the
general construction level to avoid unequal settlement and improper jointing. Where the
masonry of one part has to be delayed, the work shall be racked back suitably at an
angle not exceeding 45 degrees according to bond and not toothed.
4.1 Measurement
Measurement for payments shall be done either in running meter, square meter or cubic
meter as indicated in the Bill of Quantities. Deductions of all openings and any concrete
works in the brickwork shall be done to arrive at the net quantity. However, nothing extra
shall be paid for making such openings, etc. No deductions shall be done for holdfasts.
Unless specified otherwise, nothing extra shall be admissible for cutting of bricks to suit
the RCC structure, walls in any shape other than straight or any cutting necessary for
shaping the walls to the structural design requirements. Extra payment shall, however,
be permissible for providing quarter brick thick brickwork, brick on edge, brick in soldier
course, springs, etc. for exposed brickwork and for brickwork in arches. Cutting in
brickwork shall be admissible only for civil works.
4.2 Payment
Payment for full brick masonry shall be made at the unit rate tendered in the Bill of
Quantities. These unit rates shall include necessary materials, labours and tools for
proper execution of the work, all auxiliary works, double scaffolding, (special)
conveyance of materials, curing, etc. The rates shall be applicable for works at all level
and of all shapes.
CS-070-1 03
SE C T I O N CS - 0 80
1. GENERAL
1.1 Scope
This specification covers preparation of subgrade for interlocking pavement and
interlocking pavement.
1.2 Standards
The work specified in this section shall be in accordance with the following
standards, or approved equal, except as they are modified and supplemented
herein:
Concrete paving block M30: IS: 15658 (2006).
1.3 Submittals
1.3.2 Procedures
The Contractor shall submit to the Engineer procedures covering base preparation,
laying and finishing of works.
C S- 0 8 0 - 1 04
S P E CI FI C AT I O NS F OR CI VI L W OR K S I NT E R L O C K I N G P A V I N G B L O C K S
2. MATERIALS
3. EXECUTION
4.1 Measurement
Measurement of interlocking paving blocks for payment will be made only to the neat
finishing lines, as shown in the Drawings or as established by the Engineer. The size
shall be measured correct up to 10 mm, and the content worked out in square meter
as required.
4.2 Payment
Payment for interlocking paving blocks shall be made at the unit rates per square
meter quoted in the Bill of Quantities. The unit rates shall include the cost of all
labours, materials and equipment required in the construction at all levels, including
survey works, levelling cross sections and profiles for proper drainage to
surface/runoff drains, procurement, laying of concrete paving block, filling with stone
dust and leveling including its storage, protection, etc. all complete.
CS-080-1 05
A L U MI N U M P AR T I T I O N S A N D D O O R S
1. GENERAL
1.1 Scope
The work of this section covers the furnishing and installing of aluminum partitions,
doors, windows, ventilators and all related necessary items.
1.2 Standards
The work specified in this section shall be in accordance with the following standards, or
approved equal, except as they are modified and supplemented herein:
Subject BIS No.
Specification for aluminum partition, door IS 1948
Wrought aluminum and aluminum alloys bars, rod and sections IS 733
(For general engineering purposes)-Specification.
Dimension for screw threads for general purposes. IS 1362
Code of practice for fixing and glazing of metal doors, windows and IS 1081
ventilators.
1.3 Submittals
1.3.2 Procedures
The Contractor shall submit to the Engineer procedures covering the fabrication,
installation, finishing and glazing works.
1.3.3 Sample
Before starting the work, the contractor shall submit all the shop drawings and get prior
approval from the Engineer.
2. MATERIAL
2.1 Materials
C S- 0 9 0 - 1 06
AL U MI N U M P A R T I T I O N S AN D D O O R S
2.1.5 Screws
Screws threads of machine screws used in the fabrication of aluminum doors, windows
and ventilators shall conform to IS 1362.
3. EXECUTION
CS-090-1 07
A L U MI N U M P AR T I T I O N S A N D D O O R S
final fixing is done. Engineer in his sole discretion may allow the units to be assembled
in their final location if the situation so warrants.
Where aluminum comes into contact with stone masonry, brick work, concrete, plaster
or dissimilar metal, it shall be coated with an approved insulation lacquer, paint or plastic
tape to ensure that electrochemical corrosion is avoided. Insulation material shall be
trimmed off to a clean flush line on completion.
The contractor shall be responsible for the doors, windows etc. being set straight,
plumb, level and for their satisfactory operation after fixing is complete.
3.3 Fabrication
For fixing aluminum alloy hinges, slots shall be cut in the fixed frame and the hinges
inserted inside and may be riveted to the frame. The hinges shall normally be of the
projecting type 67 mm wide. The pins for hinges shall be of stainless steel of non-
magnetic type or aluminum alloy HR30. Irrespective of hinges being anodized or
not, the aluminum alloy pins shall be anodized to a minimum film thickness of
0.025 mm shall be sealed with oil, wax or lanolin.
The handle for shutters shall be of cast aluminum conforming to IS Designation A-5-M of
IS 617 and mounted on a handle plate welded or riveted to the opening frame in such a
way that it could be fixed before the shutter is glazed. The handle should have anodized
finish with minimum anodic film thickness of 0.015 mm.
The aluminum hinges for ventilators shall be either cast or fabricated out of extruded
sections and shall be riveted to the fixed rail after cutting a slot in it.
Cast of extruded aluminum alloy hinges for doors shall be of the same type as in the
windows but of larger size. The hinges shall normally be of the 50 mm projecting. A
suitable lock for the door operable either from inside or outside shall be provided.
3.5 Finish
Aluminum doors, windows and ventilators may be supplied in either matt, scratch-brush
or polished finish. They may, additionally, also be anodized, if so required by the
Engineer. If colour anodizing is to be done then only approved light-fast shades should
be used.
A thick layer of clear transparent lacquer based on methacrylates or cellulose butyrate,
shall be applied on aluminum doors, windows and ventilators by the supplier to protect
the surface from wet cement during installation. This lacquer coating shall be removed
after installation is completed.
3.6 Glazing
Glazing shall be provided on the outside of the frames. If required, glazing clips may be
provided as extra fittings. Four glazing clips may be provided per glass pane. In case of
doors, windows and ventilators without horizontal glazing bars the glazing clips shall be
spaced according to the slots in the vertical members, otherwise the spacing shall be 30
cm.
All glass shall be of the best quality, free from specks, bubbles, smokes, veins, air holes,
blister and other defects. The thickness of glass panes shall be uniform.
After installation is complete, the Contractor shall demonstrate to the Engineer that the
doors and windows operate properly in accordance with the intent and meaning of the
C S- 0 9 0 - 1 08
S P E CI FI C AT I O NS F OR CI VI LWO RK A L U MI N U M P AR T I T I O N S & D O O R S
4.1 Measurement
Measurement of aluminum doors and windows for payment will be made only as shown
in the Drawings or as established by the Engineer. The content shall be worked out in
square meter.
4.2 Payment
Payment for aluminum partitions and doors shall be made at the unit rates per square
meter in the Bill of Quantities. The unit rates shall include the cost of all labours,
materials and equipment required in the construction at all levels.
CS-090-1 09
CS-100
TILING WORKS
1. GENERAL
1.1 Scope
This specification covers providing and laying ceramic tiles glazed/non glazed, telia tiles,
clay tiles, monolithic tiles, and stone faced tiles in base mortar in floor as well as in walls
or sloped roof in general.
1.2 Standards
The work specified in this section shall be in accordance with the following standards, or
approved equal, except as they are modified and supplemented herein:
Subject IS No.
Specification for 43 grade ordinary portland Cement IS 8112-1989
Specification for portland slag cement IS 455
Method of measurement of Building and Civil Engineering work IS 1200-(Part XI )
(Part 11) paving, floor finishes, dado and skirting
Specification for cement concrete flooring tiles IS 1237- Edition
Specification for bitumen felts for water proofing and damp- IS 1322
proofing
Code of practice for laying and finishing of cement concrete IS 1443
flooring tiles
Specification for portland pozzolana cement (Part-I) fly ash based IS 1489 (Part-I)
Specification for Portland pozzolana cement (Part II) calcined IS 1489-(Part II)
clay based
Specification for sand stone (Slab & Tiles) IS 3622
Acid and/or alkali Resistant tiles. IS 4457
Specification for rapid hardening portland cement IS 8041
Specification for white portland cement IS 8042
Specification for hydrophobic portland cement IS 8043
Specification for sulphate resisting portland cement. IS 12330
Methods of Testing of ceramic tiles IS: 13630 (Part-
10 to 15)
Specification for ceramic tiles; definition, classification IS 13712
characteristic and marking
Specification for pressed ceramic tile IS 15622
1.3 Submittals
PA G E | 1 10
CS-100
1.3.2 Procedures
The Contractor shall submit to the Engineer procedures covering base preparation,
laying and finishing of works.
1.3.4 Sampling
In any consignment all the blocks/slabs/tiles of the same group, size and finish shall be
grouped together to constitute a lot. Sample shall be selected and tested separately for
each lot for determining its conformity or otherwise to the requirements of the
specification. The number of blocks/slabs/tiles to be selected for the samples shall
depend upon the size of the lot and shall be in accordance with the relevant IS code.
2. MATERIALS
Sample of roof tiling shall be produced before engineer for approval and the contractor
shall procure only those tiles that clearly and definitely confirm with the approved
sample. The roof tiles shall be laid in polymer modified, rigid, cementitious tile adhesive
(Sika Tilofix or equivalent). Joints shall be kept as thin as possible and shall not exceed
6mm and all the joints are pointed with waterproof tile grout.
Laying shall start from one side in the slope as indicated in drawing or instruction. Under
no circumstances shall the contractor insert small stone chips underneath the slab to
raise its level to desired level. After the clay tiles are laid, the mortar in the joints shall be
raked to a depth of 12.5mm to 20mm. Joints flush pointed with waterproof tile grout.
Special care shall be taken to protect the floor from walking over it before it is
completely dry or in any event not earlier than 3 days.
2.7 Mortar
Mortar shall be 1 part of cement and 3 parts of sand or as specified in the Bill of
Quantities. Materials and preparation of mortar shall conform to the plaster work.
PA G E | 1 12
C S - 10 0
3. EXECUTION
PAGE | 113
C S- 10 0
3.3 Finishing
The finally laid tile shall be given epoxy grout or a coat of white cement slurry as per the
instruction of the Engineer to fill up the joints, which shall wiped off from the tiles.
4.1 Measurement
The measurement for payment shall be done in square meter and running meter as
described in the item for respective thickness.
4.2 Payment
Payment for vitrified monolithic tile flooring shall be made at the unit rates per square
meter quoted in the Bill of Quantities. The unit rates shall include the cost of all labours,
materials and equipment required in the construction at all levels, including furnishing
and hauling cement, tiles their storage, protection, etc. all complete.
PA G E | 1 14
C S - 10 0
PLASTER WORK
1. GENERAL
1.1 Scope
This specification covers 12.5mm, 15mm or 20 mm plaster on different surfaces like
cement or masonry.
2. STANDARDS
The work specified in this section shall be in accordance with the following standards, or
approved equal, except as they are modified and supplemented herein:
Subject BIS No.
IS Code of practice for application of cement and cement- IS 1661 -1972
lime plaster finishes
Specifications for sand for plaster IS 1542
Specification for coarse and fine aggregates for natural sources for IS 383
concrete
Specification for 43 grade OPC IS 8112-1989
This specification covers cement plaster or lime plaster finishes to walls, columns
ceilings and similar surfaces on background normally wet with, such as brick, or
concrete (plain or reinforced).
3. MATERIALS
3.1 Cement
The cement shall be ordinary Portland cement of approved brand and manufacture and
shall comply in all respects with the I.S. 8112-1989 for ordinary Portland cement. It shall
be delivered on the site in packages with an unbroken seal fixed by the makers and
plainly marked with the name of brand and the manufacturer. It shall be stored in a dry
place in regular piles not exceeding ten bags high kept over wooden timber and planks
with sufficient walking space in such a manner that it will be efficiently protected from
moisture and contamination and that the consignments can be used up in the order in
which they are received. Set cement shall be immediately removed from the work and
replaced by the Contractor at his own expense.
If desired, tests shall be made by taking samples of cement from stores or elsewhere
from the works. The selection of samples and procedure for testing shall comply with the
appropriate Indian Standard.
PAGE | 115
C S- 10 0
3.2 Water
Water for construction work shall not be salty or blackish and shall be clean drinking
water, reasonably clear and free from objectionable quantities of silt and traces of oils,
acid and injurious alkali, salts, organic matter and other deleterious material which will
weaken the concrete. Water shall be obtained from the sources approved by the
Engineer. Sources of water shall be maintained at such a depth and the water shall be
withdrawn in such a manner as to exclude silt, mud, grass or other foreign materials.
Containers for transport, storage and handling of water shall be clean.
3.3 Sand
Sand shall consist of silicious material having hard, strong, durable, uncoated particles,
free from undesirable amounts of dust, lumbs, soft, or flaky particles or other deleterious
substances. The amount of different undesirable substances shall not exceed the
percentage limits by weight as specified in relevant I.S. Codes but in no case, the total
amount of all undesirable substances shall exceed five percent by weight. All fine
aggregate (sand) shall conform to I.S. 383-1970 and IS 1542-1992.
3.4 Lime
The lime shall comply with I.S. 712:1956. All impurities, ashes, or pieces improperly
burnt shall be screened or picked out before slaking. The lime shall be slaked with water
not less than one week or more than two weeks before use. The slaked lime shall be
screened through I.S. 240 sieve for first coat and I.S. 120 sieve for second and third
coat of plaster.
The slaked lime shall be stored in a weather proof and damp proof closed shed with
impervious storey and sides to protect it against rain, moisture, weather and extraneous
materials mixing with it. The lime shall be used when fresh, i.e. within 14 days of its
removal from kiln.
All lime that has been damaged by rain, moisture, dirt, air slaking or any other cause
shall be rejected and all rejected material shall be removed from the site forthwith.
Sample of lime shall be approved by the Engineer who shall keep it in his site office for
reference. Field test of lime shall be in accordance with IS 1624-1960.
3.6 Mortars
PA G E | 1 16
C S - 10 0
(mixes of lime putty and sand can be kept for a period of 72 hours, provided it is kept
damp and not allowed to dry).
The well mixed mortar shall be transported from the mixing platform to the site of work in
such a manner as to prevent formation of laitance or segregation.
3.8 Scaffolding
Double scaffolding having two sets of vertical supports shall be provided as directed by
the Engineer. The supports shall be sound and strong and of steel tubular, wooden
ballies, planks, trestles, G. I. Pipes, ply board and other scaffolding material. The vertical
posts shall be tied together with horizontal pieces over which the scaffolding planks be
fixed. The three sides of the scaffolding should be covered with l.0 m wide plyboards to
protect the materials from dropping off while working.
4. EXECUTION
4.3.1 Cleanliness
The loose layer of dust on masonry shall be brushed away before the plaster is applied.
A stiff bristle brush or wire brush may be used or, to be more effective, brushing may be
combined with blowing of compressed air. Laitance on a freshly cast concrete surface
shall be removed, The contaminated layer formed on concrete surface due to formation
of soap by the reaction of resins with calcium hydrate or due to moils oils shall be
removed by brush.
Special care shall be taken in repairing for re-rendering an old plaster coat. Old layers of
the plaster coats shall be completely removed and made good. Crumbled and frost-
damaged parts shall be cut out and patched. Any trace of algae or moss formation shall
be removed. If the background contains soluble salts, particularly sulphates, the
PAGE | 117
C S- 10 0
application of plaster shall be done only after the efflorescence of the salt is complete,
and efflorescence is thoroughly removed from the surface.
4.3.2 Roughness
The roughness of the background may generally improve the bond of the plaster. A
smooth surface may be roughened by wire brushing if it is not hard, or by hacking or
bush-hammering if it is hard. Alternatively, to obtain a rough surface, a mortar may be
forcibly dashed on to the surface (spatter dash treatment) by suitable means on to a
hard surface like concrete. On a soft smooth surface, a thin coat of cement slurry 1:1
(cement and sand) may be applied for the purpose. After roughening the surface, care
shall be taken to moisten the surface sufficiently before plastering, as otherwise the
freshly exposed surface may tend to absorb considerable amount of water from the
plaster. In addition to general roughness in the masonry, the joints shall also be raked to
a depth of about 3 mm for providing key to plaster.
4.3.4 Evenness
The background shall be even in order to avoid variations in the thickness of plaster.
Any unevenness must be levelled before the plaster is applied. Local projections in
brickwork shall be removed. For coat thick plaster work, the local projection shall not
exceed 12 mm of the general surface as determined by the periphery of the surface
concerned, and local depression shall not exceed 19 mm. For two coats of plaster, a
local projection shall not exceed 12 mm and local depression 12 mm.
PA G E | 1 18
C S - 10 0
When the surface has begun to harden, it shall be leveled off with a straight grained
wood float. At a later period during drying out, when the face is quite stiff and there is no
moisture on the surface, the float shall be worked with a circular movement bringing the
sand in the plaster to the face and producing a uniform texture.
Alternatively, the facing shall be tapped gently with a wood float after the setting has
commenced but before the plaster is dry, and care shall be taken that the tapping is
even, uniform and is not overdone. As a final operation, to remove any float marks
which may be left on the surface, a damp rubber sponge shall be applied with a circular
motion on the face.
4.7 Moulding
All moulding shall be worked true to template and drawn neat, clean and level. All
exposed angles and junctions with door frames etc. shall be carefully finished.
5.1 Measurement
Measurement of plaster and putty punning for payment will be made only to the neat
lines as shown in the Drawings or as established by the Engineer. The size shall be
measured correct up to 10 mm, and the content worked out in square meter as required.
5.2 Payment
Payment for ordinary plaster shall be made at the unit rates per square meter quoted for
item in the Bill of Quantities. The unit rates shall include the cost of all labours, materials
and equipment required in the construction at all levels, including furnishing and hauling
material, its storage, protection, etc. all complete
PAGE | 119
LANDSCAPING
1. GENERAL
1.1 Scope
This section covers the land development and landscaping internally and externally
which includes supply of soil, cutting, refilling depressions and hollows, cutting of trees,
removal of roots, plantation of trees, laying of turfs, civil works as per drawing or
instruction of Engineer.
1.2 Standards
The work specified in this section shall be in accordance with the following standards, or
approved equal, except as they are modified and supplemented herein:
Subject BIS No.
Stacking and storage of Construction Materials and Components IS 4082
at site-Recommendations.
Specification for coarse and fine aggregate from natural sources IS 383
for concrete.
Code of practice for preparation and use of Masonry mortar. IS 2250
Code of practice for brick work. IS 2212
Recommendations for dressing of natural building stones. IS 1129
Polished Building Stones (Part-1) Granite IS 14223 (Part 1)
1.3 Submittals
1.3.2 Procedures
The Contractor shall submit to the Engineer procedures covering dressing, trenching,
uprooting weeds, supply, staking and spreading of sludge, turfing, plantation, and care
of works.
1.3.4 Sample
Before starting the work, the contractor shall get samples of turfs and soil approved
by the Engineer.
2. MATERIAL
2.1 Materials
Turf, top soil, water, cement, bricks, aggregate and other civil work materials.
2.1.1 Turfs
Turfs shall be interpreted as grass that is seasonally dormant during the cold or dry
seasons and is capable of renewing growth after the dormant period. The turfs shall be
brought by the Contractor from areas where the topsoil is reasonably fertile and contains
PA G E | 1 20
a high percentage of loamy topsoil. Turfs shall be cut or stripped from living, thickly
matted turf relatively free of weeds or other undesirable foreign plants, large stones,
roots or other materials which might be detrimental to the development of the turf or to
future maintenance. Turf including the soil containing the roots shall be planted in a neat
and systematic way. The strips of the turf shall be in uniform widths not less than 225
mm and length not more than 450 mm, but such lengths should be readily lifted without
breaking, tearing or loss of soil.
3. EXECUTION
PAGE | 121
3.4 Care of Works
The Contractor shall provide general care for the turfed area, protect against traffic and
shall continue until final inspection and acceptance of the work. If the surface becomes
gullied or otherwise damaged during the period, the affected area shall be repaved to
reestablish the grade and condition as directed.
4.1 Measurement
Measurement of landscaping for payment will be made only to the works, as shown in
the Drawings or as established by the Engineer. The size shall be measured correct up
to 10 mm, and the content worked out in square meter on the ground surface covered
by landscaping work.
4.2 Payment
Payment for landscaping shall be made at the unit rates square metre quoted in the Bill
of Quantities. The unit rates shall include the cost of all labours, materials and
equipments all complete as per drawing and instruction of the Engineer.
PA G E | 1 22
BARBED WIRE FENCE WORK
1. GENERAL
1.1 Scope
This section covers the internal boundary demarcation fencing works of barbed wire
supported of MS angle post as per drawing or instruction of Engineer.
1.2 Standards
The work specified in this section shall be in accordance with the following standards, or
approved equal, except as they are modified and supplemented herein:
Subject BIS No.
Code of practice for use of steel tubes in general building IS 806
construction.
Code of practice for use of metal arc welding for general IS 816
construction in mild steel.
Code of procedures for inspection of welds. IS 822
Manual for metal arc welding in mild steel. IS 823
Methods for sampling of steel pipes, tube and fittings. IS 4711
Dimensions for clearance holes for bolts and screws. IS 1821
1.3 Submittals
1.4 Materials
MS angle, barberd wire, water, cement, sand, aggregate and other civil work materials.
PAGE | 123
2. EXECUTION
2.1 The MS angle posts are erected over the foundation of concrete bed as per the
drawing. The barbed wire is tightened to the post in the hooks. A tension not
exceeding 400kg/m2 is applied while erecting the wires in layers as per the design.
At the end diagonal bracing shall be made.
3.1 Measurement
The above work shall be measured in Sq. m. in the vertical plan above the foundation
completed as specified.
3.2 Payment
Payment for this work shall be made at the unit rates in square metre quoted in the
Bill of Quantities. The unit rates shall include the cost of all labours, materials and
equipments all complete as per drawing and instruction of the Engineer.
PA G E | 1 24
CHAIN LINK FENCE WORK
4. GENERAL
4.1 Scope
This section covers the boundary fencing works of chain link fence supported of MS
tubular posts as per drawing or instruction of Engineer.
4.2 Standards
The work specified in this section shall be in accordance with the following standards,
or approved equal, except as they are modified and supplemented herein:
Subject BIS No.
Code of practice for use of steel tubes in general building IS 806
construction.
Code of practice for use of metal arc welding for general IS 816
construction in mild steel.
Code of procedures for inspection of welds. IS 822
Manual for metal arc welding in mild steel. IS 823
Methods for sampling of steel pipes, tube and fittings. IS 4711
Dimensions for clearance holes for bolts and screws. IS 1821
4.3 Submittals
4.4 Materials
MS angle, barberd wire, water, cement, sand, aggregate and other civil work
materials.
PA G E | 1 25
5. EXECUTION
5.1 The MS tubular posts are erected over the foundation of concrete bed as per the
drawing. The MS angle frames as of the sections specified shall be welded to the
vertical posts as per the drawings and instruction by the UNOPS Engineer.
All the MS members shall be painted with minimum of one coat of re-oxide primer
and two coats of enamel paint of approved color as per the instruction of the UNOPS
Engineer.
6.1 Measurement
The above work of fencing shall be measured in Sq. m. in the vertical plan above the
foundation completed as specified.
6.2 Payment
Payment for this work shall be made at the unit rates in square metre quoted in the
Bill of Quantities. The unit rates shall include the cost of all labours, materials and
equipments all complete as per drawing and instruction of the Engineer.
PA G E | 1 26
GYPSUM BOARD FALSE CEILING
1. GENERAL
1.1 Scope
This section covers the false ceiling works of gypsum board for the
meeting/auditorium room of the main building as per the instruction of UNOPS
Engineer.
1.2 Materials
9.5 mm-12mm thick (or as specified) Gypsum board tiles of 610 x 610 mm size ( or as
per design) conforming to IS 2095: 1982 & 2542-1981. The tiles shall be plain,
textured or designed with design patterns as per drawings or approved by the
UNOPS Engineer.
The suspenders are galvanized mild steel straps of 28G and horizontal and
transverse members are galvanized mild steel channel of 16 G.
1.3 Execution
PA G E | 1 27
the suspended grid comprising properly galvanized 0.5mm thick 80mm x 26mm
ceiling section to be placed at maximum distance 457mm c/c, 0.5mm thick 20mm x
45mm x 30mm channel along the wall, 0.9mm thick 15mm x 45mm intermediate
channel to be placed at maximum distance of 122mm c/c, 0.5mm thick 25mm x
25mm ceiling angle to be placed at maximum distance connecting clip and 22mm x
37mm softie cleat to be fixed at RCC ceiling by using standard screw and proper
metal grip, as per drawing, manufacturers' specification, and instruction of Engineer,
all complete.
1.4 Finish
The ceiling boards free of damages are fixed to the framing in perfect line and level.
The joints are sealed with plaster of Paris and non-woven paper tapes without
forming any bubble the joints shall be finished flush to make the ceiling in one piece.
The finished surface shall be smooth and true to plane and curved as required.
Once laying of ceiling is completed the dust and floors are cleaned for the painting
works.
1.5.1 Measurement
It shall be measured flat in square meter of the actual area covered.
1.5.2 Payment
Payment for work will be made on the basis of contract unit price indicated in the
BOQ. The payment will be full and final compensation for all material, labours, and
equipment to complete the works as specified.
PA G E | 1 28
D - SPECIFICATIONS FOR SANITARY
WORKS & ELECTRICAL WORKS
Table of Contents
Section SS-040: Soil, Waste, Vent and Rain Water Piping----------------------------------Page 141-143
GENERAL
1. SCOPE OF WORK
The Contractor shall furnish all materials, labor and related items necessary to
complete the work indicated on the drawings and specified herein.
2. GENERAL
Unless specifically mentioned otherwise, all the applicable codes and standards
published by the International / National / Indian Standards and its subsequent
revision and all other standards, which may be published by them before construction
work starts, shall govern in respect of design, workmanship, quality and properties or
materials and method of testing. (All materials shall confirm and bear stamps of the
required Standard, specification or equivalent.)
Some of these available standards are listed below:
IS: 778 Specifications for Gun Metal Gate, Globe & Check Valves and for Water,
Steam and Oil only.
IS: 779 Specifications for Flow Meter for Water only.
IS: 781 Specifications for Cast Copper Alloy Screw Down Bib Taps and Stop Valves
for Water Services.
IS: 781E Specification for Sand Cast Brass Screw Down Bib Taps and Stop
Taps for Water Services.
IS: 1172 Basic Requirements of Water Supply, Drainage and Sanitation.
IS: 1239 / NS: 199 Specifications for Galvanized Mild Steel Tubes, Tubular and
Other Galvanized Wrought Steel Fittings.
IS: 1879 Specification for GI Pipe Fittings.
IS: 544 Specification for threads of GI Pipe Fittings (parallel female and taper male
threads).
IS: 1703 Specification for Ball Valve (horizontal plunger type) including float for
water supply purpose.
IS: 1726 Specification for Cast Iron Manhole Covers & Frames.
IS: 1742 Code of Practice for Building Drainage.
IS: 2064 Code of Practice for Selection, Installation and Maintenance of
Sanitary Appliances.
IS: 2056 Code of Practice for Water Supply in Building.
IS: 5329 Code of Practice for Sanitary Pipe Work Above Ground for Building.
IS: 2556 Specification for Vitreous Sanitary Appliances (Vitreous China).
NS: 40 Specifications for High Density Polyethylene (HDPE) Pipe.
NS: 68 / IS: 4985 Specifications for Rigid Poly Vinyl Chloride (uPVC) Pipe.
IS: 5382 Specifications for Rubber Rings of Rigid Poly Vinyl Chloride (uPVC)
Pipe.
PA G E | 1 29
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S GEN E R AL
BS: 4514 / DIN: 1953 Specifications for Rigid Poly Vinyl Chloride (uPVC) Pipe
Fittings.
DIN: 8078 General Quality Requirements and Testing of Poly Propylene Random
Copolymer (PP-R) Pipes.
DIN: 8077 Dimensions of Poly Propylene Random Copolymer (PP-R) Pipes.
DIN: 6962 Pipe Joints and Components for Poly Propylene Random Copolymer
(PP-R) Pressure Pipes.
DIN: 16928 Connections and Components Layout for Poly Propylene Random
Copolymer Pipe.
ASTM: D 1784 Specification for PVC Materials for PVC Schedule 40 Pipe and
Pipe Fittings
ASTM: D 1785 Specification for Dimensions for PVC Schedule 40 Plain End
Pipe
ASTM: D 2466 Specification for Dimensions for PVC Schedule 40 Pipe
Fittings
ASTM: D 2564 Specification for Solvent Cement for PVC Schedule 40 Pipe
and Pipe Fittings
ASTM: D 2846 Specification for Dimensions for C-PVC Schedule 40 Pipe and
Pipe Fittings
ASTM: 493 Specification for Solvent Cement for C-PVC Schedule 40 Pipe
and Pipe Fittings
The Contractor will submit all samples to the Engineer for approval, together with
Manufacturer's literature and installation instructions and obtain his full approval
before placing any material orders or commencing the works.
In cases where materials are not available in Imperial Measurements (as referred to)
the nearest size metric units or vice versa shall be provided, with prior approval of the
Engineer, at no extra cost to the contract.
All materials provided for the contract will be in strict accordance with the latest
version of the applicable Indian Standards. All manufacturer's data, specifications
and relative information together with samples will be submitted to the Engineer for
approval prior to being purchased, otherwise at the contractor's own risk.
Tenders shall be based upon complete installations. Products required which are not
shown or mentioned, or not specified herein as to manufacturer; quality, etc. shall be
furnished of the highest quality.
Materials shall be new and free from all defects.
All materials, apparatus or equipment called for on the plans or in the specifications
by trade names, or the name of a particular manufacturer, or by catalogue reference
are the materials, apparatus, or equipment which should be allowed for in the
Tender, or qualification submitted at the time of Tender submission.
PA G E | 1 30
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S GEN E R AL
5. REGULATIONS
The work shall be carried out in accordance with all rules, regulations, by-laws and
requirements of all authorities having jurisdiction. All changes and alterations
required by an authorized inspector of any authority having jurisdiction should be
carried out at no cost to the Owner.
7. SHOP DRAWINGS
The contractor shall submit to the Engineer all shop and setting out drawings or
diagrams necessary in order to make clear the work intended or to show its relation
to adjacent work of other trades.
The contractor shall make any changes in such drawings or diagrams, which the
Engineer may require, consistent with the contract.
Details of shop drawings submitted for approval shall show clearly the relations of the
various parts to the main members and lines of the structure, and where correct
fabrication of the work depends upon field measurements, such measurements shall
be made by the contractor and noted on the drawings before being submitted for
approval.
8. AS BUILT RECORD
The contractor shall request a complete set of mechanical drawings (white) from the
Engineer and use these for "As Built" records.
"As Built" records shall be retained in the site office and kept up to date daily in
regard to changes in actual installation from the plans and specifications. Alterations
to duct work, piping services, etc. shall be noted and the revised arrangement drawn
in accurately, complete with dimensions from column lines. Every precaution shall be
taken to protect the drawings from damage and loss.
PA G E | 1 31
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S GEN E R AL
The "As Built" records shall be made available to the Engineer upon request and
made available at each site meeting. After no further alteration can be expected and
the contract is nearing completion, the records shall be submitted for final approval.
The contractor shall include on "As Built" records the dimensions location of all
buried piping and valves, and during construction plainly mark location of exterior
services and valves to prevent damage to these until the project is completed.
10. PAINTING
All equipment supplied under this specification shall be delivered to the site with a
factory applied prime coat of paint unless noted otherwise. All supports and hangers
shall receive a prime coat of paint.
Painting where required for pipe, duct services, equipment identification, including
stenciling shall be carried out by a paint tradesman under this division in accordance
with the workmanship and material specification.
All factory prime-coated or finish coated equipment shall be touched up or repainted
if equipment is marred during shipment or installation.
Unless shown otherwise, the contractor shall be responsible for measures to control
the thermal movement of piping and apparatus. Piping shall be erected in such
manners that strain and weight do not come directly upon connections, joints or
apparatus.
Where possible, the effect shall be obtained by providing changes in direction and
loops in pipe runs, supplemented by the necessary guides, anchors and limit stops.
An adequate number of sleeves (pipe inserts) of mild steel shall be provided where
pipes pass through concrete, masonry and similar work. The pipe inserts shall have a
flange welded in the center around its circumference, in order to provide water tight
and secure fixing into the structure. The sizes of the pipe sleeves (pipe inserts) shall
be as per the drawings supplied and / or as given below.
a. Sleeves through Exterior Walls below Grade:
i. Sleeves in exterior foundation walls below grade shall project 25 mm beyond
the outside surface of the wall and be flush with the inside surface.
ii. The annular space between the sleeve and the pipe shall be caulked with un-
tarred oakum and sealed with approved caulking compound. The sealing
PA G E | 1 32
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S GEN E R AL
shall be 25 mm deep from each side. The pipe and sleeve surfaces shall be
cleaned to enable good bonding. Allow 24 hours for setting of the compound.
The contractor shall adhere strictly to the manufacturer's recommendation.
b. Sleeves through Interior Wall, Floor and Ceilings:
i. Sleeves through interior masonry walls and partitions shall be set flush with
finished wall surfaces.
ii. Sleeves through floors in finished areas shall terminate 25 mm above the
finished floor.
iii. Sleeves through floors in service area (e.g., mechanical rooms) shall
terminate 50 mm above the finished floor.
iv. The annular space between sleeves and pipes shall be packed with Silicon
Rubber. In Machine Room, the packing shall be finished at both ends of the
sleeve with 6 mm deep caulking compound. In other areas the finishing may
be on the room side only.
v. Pipe insulation shall be carried full thickness through pipe sleeves.
Sleeves Size:
Out Side (OD) Diameter of Pipe Sleeve Size
(If Insulated, OD of Insulation) (Nominal Bore of the Pipe for Sleeve)
OD 20 mm to OD 32 mm NB 2" (50 mm)
OD 33 mm to OD 50 mm NB 2½" (65 mm)
OD 51 mm to OD 75 mm NB 4" (100 mm)
OD 76 mm to OD 110 mm NB 5" (125 mm)
OD 111 mm to OD 125 mm NB 6" (150 mm)
OD 126 mm to 160 mm NB 8" (200 mm)
OD 161 mm to OD 200 mm NB 10" (250 mm)
13. CLEAN UP
The contractor shall clean all exposed metal surfaces from grease, dirt or other
foreign materials. Chrome plated and polished work shall be left bright and clean. All
openings in pipes and fixtures shall be properly capped and plugged during
construction.
Fixtures and equipment shall be properly protected from damage during the
construction period and shall be cleaned in accordance with the manufacturer's
instructions.
General:
i. These clauses shall apply to all piping systems including water supply and
drainage systems, which shall also be governed by the applicable
requirements of the IS specifications.
ii. The contractor shall notify the Engineer / Site In-Charge at least 24 hours in
advance of all tests.
iii. Tests of piping system or protection thereof shall include all apparatus
forming part of the complete systems, except where such apparatus is factory
tested prior to installation in the systems.
iv. All tests shall be performed before the application of pipe covering or before
being concealed.
PA G E | 1 33
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S GEN E R AL
v. For Drainage System, except where otherwise noted, all Soil, Waste, Rain
Water, Vent and Fittings shall be tested by Smoke Test and left in working
order after completion. The smoke test shall be carried out as stated below:
vi. Smoke shall be pumped into the Drainpipes at the lowest level from a smoke
machine, which consists of a blower and a burner.
vii. The materials usually burnt are greasy cotton waste, which form clear
pungent smoke that is easily detected by sight as well as by smell, if leaking
at any point of the drain. During testing if any joints are found leaking the
same shall be rectified by the contractor at no extra cost and to the
satisfaction of the Site–in-Charge.
viii. For Water Supply Line, except where otherwise noted, shall be tested by
Hydraulic Test and the test pressure shall be two times the maximum working
pressure of the systems, or 10 kgf per cm², whichever is greater. Test fluid
shall be water, unless otherwise indicated.
ix. Piping systems may be tested in whole or in part. Each system to be tested
shall be suitably isolated from existing or new systems using temporary
blanks between flanges (thickness of blanks shall be approved by the
Engineer), or caps. Where necessary for testing purposes, a pair of flanges
shall be installed in the piping system for the installation of blanks. Tests shall
not be performed against a closed valve.
x. All drains valves, safety or relief valves and other pressure sensitive devices
shall be removed prior to testing, and the openings capped or plugged. It is
not permissible to plug or seal safety or relief valves. Air shall be removed
from the highest points to the satisfaction of the Engineer before flushing vent
openings.
xi. Temporary blanks or caps shall be removed when testing has been
satisfactorily completed and drains, vents, safety or relief valves etc.
replaced.
xii. At least four hours shall elapse after erection before any welded or brazed
line is subjected to test pressure.
xiii. When test pressure is attained, the test pump or compressor shall be
disconnected and the connection capped. The test pressure gauge shall be
left in the system.
xiv. At least four hours shall elapse after test pressure is applied before the
system is inspected for leaks. All joints, glands, connections etc. shall be
carefully inspected for leaks and tightened as necessary.
xv. Test pressure shall be maintained without appreciable drop in pressure for a
minimum period of 24 hours.
xvi. Joints or connections, which continue to leak after tightening shall be
completely dismantled, checked, cleaned (replace if necessary), re-assemble
and retested. Opening, caulking or hemp shall not be used for leaking joints.
xvii. All water shall be drained from system following testing to prevent damage.
xviii. During testing, precautions shall be taken to prevent injury to persons or
property as a result of sudden rupture of a piping system.
PA G E | 1 34
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S SE C T I O N SS - 0 20
EXCAVATION WORK
The drainage, water supply and sewer lines are to be laid to alignment and gradients
shown on the drawings but subject to such modifications as shall be ordered by the
Engineer from time to time to meet the requirements of the works. No deviations from
the lines, depths of cuttings or gradients of sewers shown on the drawings shall be
permitted except by the express direction in writing of the Engineer.
2. EXCAVATION IN TUNNELS:
The excavation shall be open cutting unless the permission of the Engineer for the
ground to be tunneled is obtained in writing. Where Sewer lines have to be
constructed along narrow passages, the Engineer may order the excavation to be
made partly in tunnel and in such cases the excavated soil shall be brought back
later on for refilling the trenches or tunnels.
In excavating the trenches, etc. the soil, road metal, pavement, kerbing, etc. and turf
is to be placed on one side and preserved for reinstatement when the trench or other
excavation shall be filled up. The surface of all trenches and holes shall be restored
and maintained the satisfaction of the Engineer and of the owners of the roads or
other property traversed and the contractor shall not cut or break down any live fence
or trees in the line of the proposed works but shall seek tunnel under them unless the
Engineer shall order to the contrary.
The contractor shall grub up and clear the surface over the trenches and other
excavations of all trees, stumps, roots and all other in cumbrances affecting
execution of the work & shall remove them from the site to the approval of the
Engineer.
4. OBSTRUCTION OF ROADS:
The contractor shall not occupy or obstruct by his operation more than one half of the
width of any road or street, and if sufficient space shall then be left for public &
private transit, he shall remove the materials excavated and bring them back again
when trench is required to be refilled. The contractor shall obtain the consent of the
Engineer in writing before closing any road to vehicular traffic, and the foot-walks
must be kept clear at all times.
5. REMOVAL OF SEWAGE:
All night soil, sewage or any other offensive matter met with during the excavation of
the works, immediately after it is taken out of any trench, sewer or cesspool, shall not
be deposited upon the surface or where it is likely to be a nuisance or passed into
any sewer or drain but shall, at once be put into carts and removed to a suitable
place to be provided by the contractor.
P A G E 1 35
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S EX C A V AT I ON W OR K
PA G E | 1 36
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S EX C A V AT I ON W OR K
PA G E | 1 37
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S SE C T I O N SS - 0 30
1. GULLY TRAPS:
The work covered under this section comprises of the supply and installation of the
following:
a. Night Soil and Waste Water drainage system complete
b. Strom Water drainage system complete
Pipes for these works shall be as follows:
a. Pipes up to OD 110 mm size should be of High Density Polyethylene (HDPE) Pipe
having working pressure of 4.0 kgf per sq cm in accordance with Nepal Standard
NS: 40 and carried out as described herein.
b. Pipes over OD 110 mm and up to OD 250 mm should be of High Density
Polyethylene (HDPE) Pipe having working pressure of 2.5 kgf per sq cm
(minimum) in accordance with Nepal Standard NS: 40 and carried out as described
herein.
c. Pipes over 250 mm diameter, should be of Reinforced Cement Concrete Pipes
(RCC) Pipes (Hume Pipe) as per schedule NP-2 or NP-3 in accordance with Indian
Standard IS: 458 and carried out as described herein.
a. High Density Polyethylene (HDPE) Pipe: All High Density Polyethylene (HDPE)
Pipe in accordance with NS: 40 for Sewer Drainage lines passing under buildings,
floors, roads or paths with heavy traffic or in exposed positions above ground shall
be in but welded joints. The position of such pipes shall generally be shown on the
drawings or details.
b. Laying and Jointing of HDPE Pipes: HDPE Pipes shall be in thermal fusion but
welded joints. The jointing of pipes and fittings shall not be made with different
kinds of pipes and proprietary systems, but only by but welded joints.
Trenches, beds, surrounds and backfilling will be carried out as described herein
this specification, and as detailed in the Drawings or as directed by Site-in-Charge
to suit the site conditions as necessary.
a. Reinforced Cement Concrete (RCC) Pipes: Hume RCC (Hume) Pipes called for
on the drawings shall be Centrifugally Spun Reinforced Cement Concrete Pipes.
PA G E | 1 38
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S S AN I T AR Y A N D S E W E R P I P E S
Pipes shall be true perfectly round; free from cracks, cylinder, straight with a
uniform bore of specified internal diameter, throughout. Cracked or wrapped Pipes
with uneven texture
b. shall not be used. Pipe shall be of Class (Non Pressure Type) NP-1 or NP-3 as
specified and should confirm the Indian Standard (IS): 485. Adequate number of
collars as required shall also be supplied and installed along with the pipes.
c. Laying and Jointing of RCC (Hume) Pipes: RCC (Hume) Pipes shall be laid and
jointed as per the code of practice of cement concert pipes of Indian Standard (IS):
783. After setting out the pipe to correct grade / alignment, the collars shall be
centred over the joints and filled in with the tarred spun yarn, till the sufficient
space is left around the collar to receive the cement mortar. The space shall then
be filled with cement mortar in ratio of 1:1 (1 cement; 1 washed coarse sand) and
chalked by means of proper tools. All joints shall be finished at an angle of 45º to
the longitudinal axis of the pipe around the collars. The joints shall be cured for at
least 4 days. The joints shall be t4ested to a head of 2.5 metre of water column.
The majority of Sub Soil Drainage and Surface Water Drainage are routed in to
nearby drainage system running along the boundary wall and / or in to the water
stream near the area. The Contractor will allow for all work outside the site boundary,
including public protection, for the whole period of work while making the final
connection. The existing pavement, if broken up, will reinstate to the entire
satisfaction of the Engineer and necessary Authority.
When sufficient approved material has been placed around and over the pipe, a
further bed of coarse aggregate (average 40 mm in size) will be placed of a depth of
150 mm, prior to back filling the trench with excavated materials. "Loose
Compaction" only shall be carried out in 300 mm layers up to the required level.
All manholes shall be provided with cement concrete benching in 1:2:4 mix. The
benching shall have a slope of 100 mm towards the channel. The depth of the
PA G E | 1 39
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S S AN I T AR Y A N D S E W E R P I P E S
channel shall be the full diameter of the pipe. Benching shall be finished with a
floating coat of neat cement.
The manhole chamber covers and frames shall comply with the following
ratings:
Manhole Cover Out Side Size of Inside Size of Frame Weight in Kg
Frame
Light 27" x 27" 24 " x 24" or Ø 500 78.5 kg
mm
Heavy 27" x 27" 24 " x 24" or Ø 600 216 kg
mm
All manholes shall be plastered with 12 mm thick cement mortar 1:3 (1 cement & 3
coarse sand) and finished inside with a floating coat of neat cement. Manholes shall
be plastered outside as above cut with rough plaster.
All manholes shall be provided with cast iron covers and frames and embedded in
reinforced cement concrete slab weight of cover and frame thickness of slab shall be
as specified in the Bill of Quantities or given above.
6. MAKING CONNECTIONS:
Contractor shall connect the new sewer line to the existing manhole by cutting the
walls, benching and restoring them to the original condition. A new channel shall be
cut in the benching of the existing manhole for the new connections; contractor shall
remove all sewage and water if encountered in making the connection without
additional cost.
PA G E | 1 40
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S SE C T I O N SS - 0 40
PA G E | 1 41
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S S O I L , W A S T E , V E N T A N D R AI N W A T E R P I P I N G
PA G E | 1 42
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S S O I L , W A S T E , V E N T A N D R AI N W A T E R P I P I N G
walls using uPVC washers, Galvanized Screws and Plastic dowels. In case of pipes
laid horizontally, pipe shall be supported on M.S. Brackets / Hangers of approved
design clamped with uPVC Clips.
All pipes laid shall have its open ends securely closed with appropriate plugs during
progress of work. Pipes and fittings shall be fixed by using proper approved holder
bat clams and special hangers. The pipes shall be fixed perfectly vertical or in a line
as directed or as shown in the drawings. The pipes, lay vertically or horizontally shall
have the supporting clamps, hangers, Brackets, etc., as per the specification or as
directed by the site in charge. uPVC bat clamps holders shall be used to fix all
vertical uPVC pipes in truly vertical position. Branch pipes shall be connected to the
stack at the same angle as that of the fittings. Each stack shall be terminated at top
for vent. Horizontal pipes running below the ceiling shall be fixed on structural with
adjustable clamps. Horizontal pipes shall be laid to uniform slope as mentioned in the
drawings and the clamps adjusted to the proper levels so that the pipes fully rest on
them. As per the site condition, if required or directed by the site in charge, pre-
fabricated semicircular (half the diameter of the said pipe) made out of Plain GI Sheet
of proper thickness shall be provided below the horizontal running pips along with
above-mentioned adjustable clamps.
1.5 TESTING
All uPVC Soil, Waste, Vent, Rain Water (SWR) pipes and uPVC pipe fittings shall be
tested by smoke test and left in working order after completion. The smoke test shall
be carried out as stated below:
Smoke shall be pumped into the SWR pipes at the lowest level from a smoke
machine, which consists of a blower and a burner.
The materials usually brunt are greasy cotton waste which form clear pungent smoke
which is easily detectable by sight as well as by smell if leaking at any point of the
drain. During testing if any joint is found leaking the same shall be rectified by the
Contractor at no extra cost & to the satisfaction of the Engineer.
PA G E | 1 43
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S SE C T I O N SS - 0 50
Waste pipe from appliances e.g. wash-basins, shower, bath tub, sinks, drinking
fountain, urinals, water closets, etc. shall be of uPVC as given in the Schedule of
Quantities or drawings. "Galvanized or Black Wrought Iron Pipes or Pipe Fittings
should not be used for Soil Pipes, Waste Pipes, Rain Water Pipes, Anti-Siphon
Pipes, Vent Pipes or Drain Pipes from any appliances."
All pipes shall be fixed in gradient towards the out fall drain. Pipes inside a toilet room
shall be chased unless otherwise shown on the drawings. Where required pipes may
be run at ceiling level in suitable gradient as mentioned in the drawing or directed by
the site in charge and supported on structural clamps.
2. CLEAN OUTS
Clean-outs shall be full pipe size up to 110 mm and a minimum of 110 mm on larger
pipe. A clean out shall be installed at, or as close as possible to, the base of every
vertical waste, soil and drain stack. A clean out shall be installed at the up-slope of
each pipe at which a building drain or branch changes direction by more than 45°.
Clean-outs in horizontal drainage piping shall be at intervals not greater than:
- 15 m where the piping is of dia 100 mm and smaller.
- 30 m where the piping is of large than dia 100 mm.
- 6 m where waste pipes are horizontally connected to sinks.
Nickel Bronze or Stainless Steel Floor Plates with Frames shall be installed on
finished floors for access to clean-outs. Clean-outs on horizontal lines in finished
areas shall be as per IS specifications.
PA G E | 1 44
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S SE C T I O N SS - 0 60
WATER SUPPLY
1. PIPE LINE:
All Water Supply Pipe Line shall be as mentioned in the drawings and Bill of
quantities.
The Pipes may be:
Hot Deep Galvanized (GI) Electric Resisted Welded (ERW) Mild Steel Tubes / Pipes
conforming to IS: 1239 of class specified, when class is not specified they shall be
Class-B (Medium) of approved brand.
Pipe Fittings shall be Hot Deep Galvanized Malleable Cast Iron confirming to IS:
1879 of approved brand. The Pipe Fittings are Sockets / Couplings, Elbows, Bends,
Tees, Reducers, Unions, etc. Manufacturer's Trademark and ISI Mark should be
stamped on the GI Pipe Fittings.
GI Pipe and GI pipe Fittings shall have threaded joints as per the manufactures
specifications with TEFLON Tape. After cutting the threads in the pipe, care shall be
taken to remove burr from the end of the pipe with appropriate tools.
Chlorinated Polyvinyl Chloride (CPVC) Tubes / Pipes of Class 13.5 in Copper Tube
Size (CTS) dimensions conforming to ASTM: D 2846 of approved brand.
Pipe Fittings shall be of Chlorinated Polyvinyl Chloride (CPVC) of Class 11 in Copper
Tube Size (CTS) dimensions conforming to ASTM: D 2846 of approved brand. The
Pipe Fittings are Couplings, Elbows, Bends, Tees, Transition Coupling, Transition
Bushings, etc. Manufacturer's Trademark should be stamped on the CPVC Pipe
Fittings.
CPVC Pipe and CPVC Pipe Fittings shall have cold weld joints by CPVC Solvent
cement confirming to ASTM: 493. After cutting the pipe, care shall be taken to
remove burr from the end of the pipe with appropriate tools. Only with TEFLON tape,
threaded Fixtures shall be fitted with CPVC Threaded Adopters.
Lead Free Polyvinyl Chloride (PVC) Tubes / Pipes of Schedule: 40, dimensions
conforming to ASTM: D 1785 and Materials conforming to ASTM: D 1784 of
approved brand.
Pipe Fittings shall be of Lead Free Polyvinyl Chloride (PVC) of Schedule: 40,
dimensions conforming to ASTM: D 2466 of approved brand. The Pipe Fittings are
Couplings,
PA G E | 1 45
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S W AT ER S UP PL Y
Poly Propylene Random Copolymer (PP-R) Tubes / Pipes and Pipe Fittings
conforming to DIN: 8077 / 8078 of Class as specified (if not specified should be of PN
20 Series) of approved brand. The Pipe Fittings are Couplings, Elbows, Bends, Tees,
Transition Coupling, Transition Bushings, etc. Manufacturer's Trademark should be
stamped on the PP-R Pipes and Pipe Fittings.
PP-R Pipes and PP-R Pipe Fittings shall have hot fusion welding process at 260º C
as per the manufacturer’s specifications, instructions and guideline. Only with
TEFLON tape, threaded Fixtures shall be fitted with PP-R Threaded Adopters.
6. LAYING
All Pipes and fittings shall be of class specified in BOQ manufactured under
respective Standards.
All main supply pipes and other pipes to be laid under the ground shall be laid over a
minimum of 600 mm sand bedding or selected granular material compacted as
described herein this specification.
The water main shall be laid and maintained to the required lines and grades with
fittings, valves, and connections at the required locations and all valves and stems
plumb.
Proper implements, tools and facilities shall be provided and used by the Contractor
for the safe and convenient performance for the work.
All pipes, valves and fittings shall be carefully lowered into the trench piece by piece
by hand ropes or other suitable tools or equipment in such a manner as to prevent
damage to water main materials and protective coatings and linings.
Under no circumstances shall water main materials be dropped or dumped into the
trench.
Valves, valve covers, meters, tapping sleeves and other accessories shall be
installed as per the manufacturer's recommendations and in conjunctions and
compliance with the requirements of the Local Government or Public Service
Authority specifications.
It will be the responsibility of the Contractor to furnish and install all proper size pipe
bends for both horizontal and vertical deflections that are required to construct the
water main to the line and grade as shown and specified.
7. JOINTING
The jointing shall be made in accordance with the instructions of the pipe and fitting
manufactures. The pressure pipe shall be tested to a minimum of 10 kg / sq. cm.
pressure.
PA G E | 1 46
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S W AT ER S UP PL Y
The setting and arrangement of pipes shall be as per the working drawings. Pipes
are cut to size and ends are squared.
The pipes and fittings shall be inspected at the site before use. Where the pipes have
to be cut, the end shall be carefully plugged so that no obstruction to bore is affected.
The pipe shall be cleaned and cleared of all foreign matters before being laid. For
joining, the outside of pipe (thread for GI pipe line) and the inside of the socket shall
be cleaned. Care should be taken that all pipes and fittings are properly joined so as
to make the joints completely watertight.
After lying, the open ends of the pipe shall be temporarily plugged to prevent access
of water, soil or any other foreign materials.
Jointing of pipes shall be made according to the different kind of pipes by thread
screwing, cold welding, flanges, or flexible joints etc. Joints between dissimilar
materials, e.g. copper shall be by means of copper-alloy unions or union ferrules, etc.
Care shall be taken to ensure that all piping and fittings are clean internally and free
from particles of sand, soil, metal, plastic, filings and chips, etc.
8. CLAMPS
All pipes laid shall have its open ends securely closed with appropriate plugs during
progress of work. Pipes and pipe fittings shall be fixed by using proper approved
holder bat clams and special hangers. The pipes shall be fixed perfectly vertical or in
a line as directed or as shown in the drawings. The pipes laid vertically shall have
supporting, the clamps at 1.5 metres centre to centre and the pipes laid horizontally,
the clamps at every 1.2 metres centre to centre as shown in the Drawing or as
directed by the site in charge. MS bat clamps holders shall be used to fix all vertical
pipes in truly vertical position. Horizontal pipes running below the ceiling shall be
fixed on structural with adjustable clamps. Horizontal pipes shall be laid to uniform
slope as mentioned in the drawings and the clamps adjusted to the proper levels so
that the pipes fully rest on them. As per the site condition, if required or directed by
the site in charge, pre-fabricated semicircular (half the diameter of the said pipe)
made out of Plain GI Sheet of proper thickness shall be provided below the horizontal
running pips along with above-mentioned adjustable clamps. No Iron hooks shall
anchor pipes in wall chases.
The water service lines shall be hydrostatically tested. Test pressure shall be 10 kg /
sq. cm. and the pipes shall be tested for the specified pressure for 24 hours.
Defective pipes, pipe fittings and pipe joints shall be replaced or repaired immediately
and retested.
Dielectric unions shall be installed at every connection between iron / steel and
coppers / brass / bronze.
11. UNIONS
PA G E | 1 47
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S W AT ER S UP PL Y
13. VALVES
PA G E | 1 48
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S SE C T I O N SS - 0 70
1. PIPES
All pipes lay outside of the building and generally underground shall be considered
as External Water Supply. The types of Pipe and Pipe Fittings shall be as per
drawings and / or as mentioned in the Bill of Quantities. The installation of pipe line
shall be properly carried out and should be completely watertight. All fixtures and
fittings shall be properly installed and checked against leaks at designated pressure.
Necessary Pipe Sleeves in the wall, floor, etc should be provided as per the
specification.
2. EXCAVATION
Generally, external water mains pipe shall be laid a minimum of 600 mm below
ground level. Excavation for trenches shall be done as specified elsewhere, but the
depth of the trenches shall be as follow
3. BACKFILLING
Backfilling of trenches shall not commence until the pipes therein have been tested
and approved by the site in charge. Under non-paved areas selected excavated
materials free from large stones refuse, or organic material as approved by the
Engineer shall do the backfill.
PA G E | 1 49
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S SE C T I O N SS - 0 80
1. PIPES
All pipes inside the building from Over Head Tank to the Toilets and Kitchen and
where specified, shall be considered as Internal Water Supply Pipe Line. The types
of Pipe and Pipe Fittings shall be as per drawings and / or as mentioned in the Bill of
Quantities. The installation of pipe line shall be properly carried out and should be
completely watertight. All fixtures and fittings shall be properly installed and checked
against leaks at designated pressure. Expansion of hot water pipes shall be
compensated for by flexible piping layouts and / or by utilizing bends in pipe line.
Necessary Pipe Sleeves in the wall, floor, etc as well as pipe supports, clamps,
brackets, etc should be provided as per the specification and instruction of the site in
charge.
PA G E | 1 50
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S SE C T I O N SS - 0 90
The pipes and pipe fittings before being laid or fixed shall be examined to see that
there are no cracks or defects. The pipes and fittings shall be thoroughly cleaned of
all dust and dirt. After laying or fixing the pipes in position they shall be arranged in
such a way that centre line of pipes coincide with the centre line of the alignment.
Fittings, Valves, etc., shall also be laid in their position as stated above. CPVC or
PVC Pipes shall be fixed by push fit before any solvent cement is applied and when
cleared by the site in charge then only permanent joints to be made. All the horizontal
and vertical run pipes should be supported to walls with the help of PVC Pipe Clamps
that should be anchored by Galvanized Screws and Plastic dowels. In case of pipes
laid horizontally under ceiling, pipe shall be supported on M.S. Brackets / Hangers of
approved design.
PA G E | 1 51
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S P I P E S U P P O R T AN D H A N G E R
PA G E | 1 52
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S SE C T I O N SS - 1 00
MEASUREMENT
1. MEASUREMENT
GI, uPVC, CPVC, Lead Free PVC and PP-R Pipe Line above ground or underground
shall be measured per running meter and the rate shall be inclusive of all fittings
including unions, Hangers, Brackets, Clamps, Pipe Sleeves, cutting chases, etc on
wall, ceiling, floor and making good the same and testing of pipes and fittings,
making good.
GI pipes below ground shall be measured per running meter and the rate shall be
inclusive of all fittings including unions, except the excavation for trenches refilling
and disposal of surplus earth and testing of pipes and fittings, making good.
Other Fixtures such as Gunmetal valves, non-return valves, ball cocks, foot valves,
stop cocks, bib cocks, etc., shall be measured by number.
PA G E | 1 53
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S SE C T I O N SS - 1 10
PIPE INSULATION
1. PIPE INSULATION
All Hot Water Supply and Hot Water Return Pipe Lines shall be insulated (if required)
with extruded Synthetic Rubber Polymer Compound, pre-formed tubular sectioned
pipe insulation. The pipe insulation shall be fixed using proper adhesive and self-
adhesive tapes as per the manufacturer’s specifications. Specialist skilled workmen
trained in the trade shall apply all insulation strictly as per manufacturer
recommendations. Before applying insulation, all pipe work and fittings shall be
brushed clean, all dust, dirt and oil removed. Each length of piping to be insulated
shall be tested for its performance requirements. Only such pipe lengths, which are
free from defect, shall be insulated. After testing the pipe lengths shall be dried out.
All insulation on ducts and piping shall be continuous and full thickness and as
specified where passing through walls, floors, partitions and pipe sleeves.
2. PROTECTION OF INSULATION
PA G E | 1 54
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S SE C T I O N SS - 1 20
1. BATHROOM FIXTURES
All bathroom fixtures, Ceramic and CP fittings shall be supplied as per schedule 1
and install in position including transportation to site of work. No allowances shall be
made for theft, breakage and defective materials after taking delivery of the
materials.
2. INSTALLATION OF FIXTURES
The fixtures and fittings shall be provided with all such accessories as are required to
complete the item in satisfactory working conditions, whether specifically mentioned
or not in the Schedule of Quantities, Specifications and Drawings.
The Bathroom fixtures and fittings shall be installed at the correct assigned position
as shown on the drawings and as directed by the Engineer, and shall fully meet with
the esthetic and symmetrical requirements as demanded by the Engineer.
All fixtures and accessories shall be fixed in accordance with a set pattern matching
the tiles or interior finish as per Engineer requirements. Wherever necessary, the
fittings shall be centered to dimensions and pattern as called for.
Skilled workman shall install fixtures with appropriate tools according to the best
trade practice. Manufacturer's instructions shall be followed for the installation of
fixtures. Fixtures in all toilets shall be standard height, mounting as called for on the
drawings. Fixtures shall be mounted rigid, plumb and true to alignment.
The installation of the bathroom fixtures and fittings shall be as per the shop
drawings approved by the Engineer.
The contractor shall assemble on trial basis at least one set of each type of bathroom
fixture and fittings in order to determine precisely the required supply and disposal
connection. Relevant instructions from manufacturers shall be followed as applicable.
This trial assembly shall be developed to facilitate determining the location of
punctures, holes, holding devices etc. that will be required for final installation in
position of all bathroom fixtures and fittings. The above assembly shall be subject to
final approval by the Engineer.
The fixtures in the trial assembly can be reused for final installation without any
additional payments for fixing or dismantling of the fixtures.
The contractor at his own cost shall where required, provide all fixtures and fittings
securely in position. The fixing devices shall be rigidly anchored into the building
structure. The devices shall be rust resistant and shall be so fixed that they do not
present an unsightly look in the final assembly. These shall be installed complete
with appropriate washers and gaskets, jointing Materials and Screws etc. as per
manufacture manuals.
PA G E | 1 55
Specifications for Sanitary Works Bathroom Fixtures and Fittings
5. FINAL INSTALLATION
The contractor at his own cost shall install all bathroom fixtures and fittings in their
final position in accordance with approved trail assemblies and as shown on
drawings. The installation shall be complete with all supply and waste connections.
The connection between built-in piping system and the bathroom fixtures shall be
through proper couplings, unions and flanges to facilitate removal / replacement of
bathroom fixtures without disturbing the built in piping system. All couplings, unions
and flanges shall match in appearance with other exposed fittings.
Fixtures shall be mounted rigid, plumb and true to alignment. The outlets of water
closet bowls and similar appliances shall be examined to ensure that outlet ends are
butting on the receiving pipes before making the joints. It shall be ensured that the
receiving pipes are clear of obstruction. When fixtures are being mounted attention
shall be paid to the possibility of movement and settlement by other causes.
Overflows shall be arranged as to give visible warning and discharge. A check shall
be made to ensure that necessary anchoring devices have been provided for
supporting Water Closets, Wash Basins, Sinks and other appliances.
The contractor shall take every precaution to protect all bathroom fixtures and fittings
issued to them against damage, misuse, crazing, staining, breakage and pilferage by
providing proper wrapping and locking arrangement till the completion and handing
over of the installation. At the time of handing over, the contractor shall clean,
disinfect and polish all fixtures and fittings. Any fixtures and fittings found damaged,
cracked, chipped, stained or scratched shall be removed and new fixtures and fittings
free from defects shall be installed at his own cost to complete the work.
PA G E | 1 56
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S SE C T I O N SS - 1 30
TESTING
1. TESTING
All fixtures and fittings shall be tested for their proper performance by the Contractor
thoroughly to satisfy the Engineer that they are in order, before applying for virtual
completion.
PA G E | 1 57
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S SE C T I O N SS - 1 30
MISCELLANEOUS WORK
All piping systems shall be suitably painted or otherwise color identification of pipes
as per IS: 2065 (code of practice for water supply in buildings). The identification
colors and letter symbols for various services shall be as follows:
Service Identification Letter Symbol
Colour
1 Soil, Waste and Vent Piping and all Black or Brown S
drains (except for PVC and HDPE
pipe)
2. Water Supply Lines Green CWS
3. Hot Water Supply Red HWS
4. Hot Water Return Orange HWR
5. Gas Supply Pipe Line Golden Yellow GAS
6. Fire Hydrant Pipe Line Blue FH
The letter symbols shall either be legibly painted or affixed in an appropriate manner
to be read conveniently. Locations where painting cannot be done, fastening self-
adhesive PVC tapes of appropriate color in an approved manner shall identify the
piping system. The tapes varying in 15 mm to 50 mm wide strips depending on the
size of pipe on which the tapes are fastened shall be applied at regular intervals on
continuous runs and at all bends junctions and tees.
2. PAINTING
The Contractor shall supply all materials, labor tools and other equipment necessary
for carrying out painting work. Painting as described herein shall be applied to all
surfaces requiring painting. Paint materials used in the work shall be of approved
make of ready mixed variety supplied to site in manufactures original containers.
Thinning where necessary shall only be done as per manufactures instructions. All
surfaces to be painted shall be cleaned free of all dirt and dust before painting is
started. Painting shall only be started after the receiving surfaces are in a condition fit
to receive painting as certified by the Engineer. Properly qualified, skilled and
experienced painters shall be employed to painting work.
3. PREPARATION OF SURFACES
All steel and iron surfaces to be painted shall be washed with mineral spirits to
remove all dirt and grease. Where rust or scale is present, the surfaces shall be wire
PA G E | 1 58
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S
brushed to remove such rust. The cleaned surfaces shall be given one coat of approved
phosphate before priming coat is applied.
All galvanized metal to be painted shall be thoroughly cleaned with naphthalene and
treated with a solution of 20 litres of 36% acetic acid, 1.35 kg. of blue vitriol and 1.35 kg.
Of powered alum dissolved in 225 litres of water.
4. PAINTING FINISHES
The Painting Finishes shall consist of the operations briefly mentioned below:
All cast iron soil, waste vent pipes, manhole covers, gratings and frames shall be
painted with three coats of bituminous base paint.
All cast iron mains pipes shall be painted with one coat Zinc Chromate primer followed
by three coats of synthetic enamel paint.
All non-galvanized steel surfaces shall be painted with one coat of Zinc Chromate
primer followed by three coast of synthetic enamel paint.
All galvanized surfaces shall be coated with galvanized metal primer after washing with
galvanized metal cleaner. The surface shall then be painted with three coats of synthetic
enamel paint.
Pipe surface of the HDPE, uPVC, CPVC, Lead Free PVC, PP-R Pipes and Pipe Fittings
shall not be painted with Synthetic Paints unless otherwise instructed.
All painted finished surfaces shall be smooth throughout and retain a consistent uniform
shade all through. Where in the opinion of the Engineer, the painting is not consistent in
application or appearance; the contractor at his own cost shall redo the painting to his
satisfaction.
Before commissioning the water supply system the contractor shall arrange to disinfect
the entire system as described in the succeeding paragraph.
The water pipes shall first be filled with water and thoroughly flushed out. The storage
tanks shall then be filled with water again and disinfecting chemical containing chlorine
added gradually while tanks are being filled to ensure through mixing. Sufficient
chemical shall be used to give the water a dose of 50 parts of chlorine to one million
parts of water. If ordinary bleaching powder is used, the proportions will be 150 gms of
powder to 1'000 litres of water. The powder shall be mixed with water in the storage
tank. If a proprietary brand of chemical is used the proportions shall be as specified by
the makers. When the storage tank is full, the supply shall be stopped and all the taps
on the distributing pipes opened successively working progressively away from storage
tank. Each tap shall be closed when the water discharge begins to smell of chlorine.
The storage tank shall then be filled up with water from supply pipe and added with
more disinfecting chemical in the recommended proportions. The storage tank and pipe
shall then remain charged at least for three hours. Finally the tank and pipes shall be
thoroughly flushed out before any water is used for domestic purposes.
All inlets, outlets, valves piping and other incidental work connected with installation of
all Mechanical equipment supplied by other agencies shall be carried out by the
Contractor in accordance with the Drawings, requirements for proper performance of
equipment manufactures instruction and the directions of the Engineer.
The equipment’s to be supplied by the other agencies consist mainly of Water
Treatment Plant, Hydro-Pneumatic System and Boiler for Hot Water, Pumps, Kitchen
PAGE | 159
S P E C I F I C AT I O N S F O R S A N I T A R Y W O R K S MI S CE LL A NE OU S W O RK
Equipments and Laundry Equipments. The connections to the various equipments shall
be connected through proper unions / flanges and isolating valves. The work of
connections shall be executed in accordance with the requirement of equipment
suppliers, under the directions of the Consultant. The various aspects of connection
work shall be executed in a manner similar to the work of respective trades mentioned
elsewhere in the specification.
7. SAFETY CODE
PA G E | 1 60
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S S AN I T A R Y S C H E D U L E
1.02 Type: 'WC-2' (for Persons with Physical Limitations) consisting of:
1.02.a White Glazed Vitreous China Porcelain Wall - # CO209 + # "INDUS" - - 100 mm
Hung `P' trap Water Closet Basin and also E8308 Parryware, India
Double Flap, Solid Section, White Seat with
Cover, Hinges, etc
1.02.b Concealed Flushing Cistern 80 mm thick - # C821099 "LINEA-N" ½" - 40 mm
including WC Outlet Bend with WC Connector Parryware, India
Pipe, WC Fastening Bracket, threaded bolts,
Integrated Stop Valve with R½" water supply
Connector Pipe
1.02.c CP Twin Actuator Plate (with Squre Push - # C821499 "LINEA-N" - - -
Buttons - Satin Finish) for above Concealed Parryware, India
PA G E | 16 1
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S S AN I T A R Y S C H E D U L E
Cistern
1.02.d CP Health Faucet with 7 mm dia x 1 m long - # ALD-CHR- Jaquar, India ½" - -
Flexible Tube and Wall Bracket 585
1.02.e CP Regulating (Angle) Valve Long Thread with - # CQT-23059 Jaquar, India ½" - ½"
CP Wall Flange for Health Faucet
1.02.f CP Toilet Paper Holder with Flap - # ACN-1151N Jaquar, India - - -
1.02.g CP Twin Robe Hook - # ACN-1161N Jaquar, India - - -
2.00 Squatting (Asian) Pan Set:
2.01 Type: 'SP-1' consisting of:
2.01.a White Glazed Vitreous China Porcelain Floor 500 x 400 x # C0123 + 'P' Parryware, India 1¼" - 100 mm
Mounted Squatting (Asian) Pan with PVC 'P' 210 mm Trap (110 mm)
Trap
2.01.b White Glazed Plastic Duel Flushing Cistern with 3/6 lts # E8177 "SUPERIO" ½" - 1¼"
necessary fittings, Installation Kit, Flush Bend Parryware, India
Pipe, etc.
2.01.c CP Regulating (Angle) Valve Long Thread with - # G3453A1 "AMBER" ½" - ½"
CP Wall Flange for Health Faucet Parryware, India
2.01.d CP Flexible Connection Hose 450 mm long # T991299 Parryware, India ½" - ½"
2.01.e CP Bib Cock Long Body with CP Wall Flange - # G3406A1 "AMBER" ½" - -
Parryware, India
3.00 Wash Basin Set:
3.01 Type: 'WB-1' consisting of:
3.01.a White Glazed Vitreous China Porcelain Corner 450 x 330 X "Corner Basin" Parryware, India ½" - 1¼"
Basin Basin including fixing Bolts 145 mm # Co408
3.01.b CP Bottle Trap, 32 mm size with Wall 250 x 190 mm # T3201A1 Parryware, India 1¼" - 1¼"
Connection Pipe, Wall Flange & Washer, etc.
3.01.c CP Half Thread Waste Coupling 32 mm size 32 mm # T9910A1 Parryware, India - - 1¼"
3.01.d CP Pillar Cock for Wash Basin - # G3402A1 "AMBER" ½" - -
Parryware, India
3.01.e CP Regulating (Angle) Valve Long Thread with - # G3453A1 "AMBER" ½" - ½"
CP Wall Flange for Health Faucet Parryware, India
PA G E | 16 2
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S S AN I T A R Y S C H E D U L E
3.01.f CP Flexible Connection Hose 450 mm long # T991299 Parryware, India ½" - ½"
3.01.g CP Robe Hook - # T6006A1 Parryware, - - -
India
3.01.h CP Soap Dish - # T6003A1 Parryware, - - -
India
PA G E | 16 3
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S S AN I T A R Y S C H E D U L E
3.02.e CP Regulating (Angle) Valve Long Thread with - # G3453A1 "AMBER" ½" - ½"
CP Wall Flange for Health Faucet Parryware, India
3.02.f CP Flexible Connection Hose 450 mm long # T991299 Parryware, India ½" - ½"
3.02.g CP Robe Hook - # T6006A1 Parryware, - - -
India
3.02.h CP Soap Dish - # T6003A1 Parryware, - - -
India
3.03 Type: 'WB-3' (for Persons with Physical Limitations) consisting of:
3.03.a White Glazed Vitreous China Porcelain Wall 520 x 465 "PAL" # C8441 Parryware, India - - 40 mm
hung Lavatory Basin including fixing Bolts
3.03.b CP Bottle Trap with Internal Partition, 32 mm 250 x 190 # ALD-769 Jaquar, India 40 mm - 40 mm
size with 250 mm & 190 mm long Wall
Connection Pipe, Wall Flange & Washer
3.03.c CP Half Thread Waste Coupling 32 mm size, - # ALD-709L130 Jaquar, India 40 mm - 40 mm
3.03.d CP Pillar Cock for Wash Basin - # CQT-23021 Jaquar, India ½" - -
3.03.e CP Regulating Valves CP Regulating Valve - # CQT-23059 Jaquar, India ½" - ½"
Long Thread with CP Wall Flange for Water
Feeder Pipe Line
3.03.f Flexible Braided Connector Tube with Nut & 450 mm long # ALD-805B Jaquar, India ½" - ½"
Washer
3.03.g CP Hand Towel Rail for Wash Basin 300 mm long # ACN-1101N Jaquar, India - - -
3.03.h CP Soap Dish - # ACN-1131N Jaquar, India - - -
3.03.i Bath Room Accessories for WC (for the Persons with Physical Limitations):
a. Drop Down Support Arm Type: 'SA-1' having:
- A Pair of ABS / Stainless Steel Foldable Hinged 600 mm long # C8153 Parryware, India - - -
Arms (Drop Down Support Arm)
4.00 Hand Wash Trough (HWT) Set:
4.01 Type: 'HWT-1' consisting of:
4.01.a Rectangular Masonry Hand Wash Trough (HWT) Local Fabricated (Civil Work) as per Drawing
(as per Drawing) having 1¼" dia outlet for Waste
Coupling
PA G E | 16 4
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S S AN I T A R Y S C H E D U L E
4.01.b CP Bib Cock Long Body with CP Wall Flange x 2 - # G3406A1 "AMBER" ½" - -
sets Parryware, India
4.01.c CP Bottle Trap, 32 mm size with Wall 250 x 190 mm # T3201A1 Parryware, India 1¼" - 1¼"
Connection Pipe, Wall Flange & Washer, etc.
4.01.d CP Full Thread Waste Coupling 32 mm size 32 mm # T9911A1 Parryware, India - - 1¼"
4.01.e CP Towel Hook x 2 - # T6006A1 Parryware, - - -
India
4.01.f CP Soap Dish - # T6003A1 Parryware, - - -
India
4.02 Type: 'HWT-2' consisting of:
4.02.a Rectangular Masonry Hand Wash Trough (HWT) Local Fabricated (Civil Work) as per Drawing
(as per Drawing) having 1¼" dia outlet for Waste
Coupling
4.02.b CP Bib Cock Long Body with CP Wall Flange x 3 - # G3406A1 "AMBER" ½" - -
sets Parryware, India
4.02.c CP Bottle Trap, 32 mm size with Wall 250 x 190 mm # T3201A1 Parryware, India 1¼" - 1¼"
Connection Pipe, Wall Flange & Washer, etc.
4.02.d CP Full Thread Waste Coupling 32 mm size 32 mm # T9911A1 Parryware, India - - 1¼"
4.02.e CP Towel Hook x 3 - # T6006A1 Parryware, - - -
India
4.02.f CP Soap Dish - # T6003A1 Parryware, - - -
India
5.00 Urinal Set:
5.01 Type: 'UR-1' consisting of:
5.01.a White Glazed Vitreous China Porcelain Wall 305 x 305 x Flat Back Parryware, India ½" - 1¼"
Mounted Flat Back Urinal Basin having Top Inlet, 440 mm # C0501
CP anchorage Bolts/Brackets, etc.
5.01.b CP Regulating (Angle) Valve Long Thread with - # G3453A1 "AMBER" ½" - ½"
CP Wall Flange for Health Faucet Parryware, India
5.01.c CP Flexible Connection Hose 450 mm long # T991299 Parryware, India ½" - ½"
5.01.d CP Bottle Trap, 32 mm size with Wall 250 x 190 mm # T3201A1 Parryware, India 1¼" - 1¼"
Connection Pipe, Wall Flange & Washer, etc.
PA G E | 16 5
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S S AN I T A R Y S C H E D U L E
PA G E | 16 6
S P E CI FI C AT I O NS F OR S AN I T ARY W O RK S S AN I T A R Y S C H E D U L E
PA G E | 16 7
S P E C I F I C A T I O N S F O R E L E C T R I C AL W O R K S S E CT I ON E S- 0 1 0
GENERAL SPECIFICATIONS
1. GENERAL
This general technical specification covers the general technical requirements for the
complete supply and installation of the electrical system for the project including all
necessary supervision, labor, tools, equipment and accessories, miscellaneous
materials, testing, and putting in acceptable operation of the electrical system. The
electrical system shall be implied as the works related to lights, power sockets, fans,
telephone sockets, air-conditioning system, supply intake system, power cables etc.
Abbreviation used:
LT - Low Tension
HT - High Tension
MDB - Main Distribution Board
DB - Distribution Board
kV - Kilo Volt
kVA - Kilo Volt Amp
kA - Kilo Amp
PVC - Poly Vinyl Chloride
SWG - Standard Wire Gauge (British)
IS - Indian Standard
TPN - Three Phase Neutral
DP - Double Pole
MCB - Miniature Circuit Breaker
MCCB - Moulded Case Circuit Breaker
PA G E | 1 68
S P E C I F I C AT I O N S F O R E L E C T R I C AL W O R K S G E N E R A L S P E C I F I C AT I O N S
2. SCOPE OF WORK
The Contractor shall supply and install all the electrical system works as per BOQ
complete with all accessories including materials, fixtures, electrical equipment and
appliances etc.
All equipment shall be complete and operative in all details and shall be left in a
satisfactory working condition.
The miscellaneous materials include, but are not limited to, all conduit wires, sub
distribution boards, junction boxes, fittings, supports, main distribution panel, cables,
metal clad switch fuse unit, fans, call-bells, and other accessories required for the
complete installation and satisfactory operation of the lighting system.
The Contractor shall perform the following work in addition to furnishing and delivering
of the equipment, materials and accessories:
Assembling at the site
a. Erection and complete installation
b. Testing of all equipment
c. Commissioning of all equipment prior to trial operation
d. Trial operation and all necessary adjustments prior to initial operation.
e. Obtaining Owner's/Engineer's approval and written acceptance for satisfactory
operation.
3. REQUIREMENTS
3.1.1 Workmanship:
All work shall be done in a first-class, neat and workmanlike manner by mechanics
skilled in the trade involved. They shall rectify then and there the defects pointed out by
the Engineer during the progress of work. The work shall be carried out in the best
workmanship and any defect or minor changes in design/construction if pointed out shall
be carried out by the contractor without any extra charges.
3.1.2 Materials:
All materials shall be new, of the best of their several kinds, and without imperfections
and blemishes. Where two or more units of the same class of equipment are required,
these units shall be of same manufacturer. Materials which are defective or damaged
during the progress of work shall be replaced or repaired in approved manner at the
expense of the contractor.
3.1.3 Quantities:
All quantities mentioned in the bill of quantities are close to actual quantities and the
contractor will get paid according to measurement of actual work. The schedule of
quantities is liable to alteration by deletion or addition as required.
3.1.4 Rates:
The rate quoted in the tender shall include all charges of materials, installation, testing,
commissioning, labor, tools and equipment, auxiliary materials required to complete the
particular item of work, shed for material store, transferring all material from place of
availability to the site, all taxes, contingencies, breakage, wastage and maintenance of
installation for one year. The rate in the original contract shall determine the values of
the extra work where such extra work is of a similar nature and has been executed
PA G E | 1 69
S P E CI FI C AT I O NS F OR E L E CT RI CAL W OR K S G E N E R AL S P E C I F I C AT I O N S
under similar conditions. Wherever the extra work is not of a similar nature, the rate for
the same shall be determined prior to the execution of work and established on the
approval of the Clint after recommendation by the Consultant.
3.1.5 Drawings:
The Drawings provided are design Drawings and generally are diagrammatic. They do
not show offsets, bends, pull box, which may be required for the installation. The
Contractor shall follow the Drawings as closely as possible and shall provide necessary
bends, pull box etc. The Contractor shall prepare and submit for approval detailed shop
Drawings of all installations not detailed on the Drawings provided. Some modification in
design, drawing can be done during the construction time in order to overcome practical
difficulties, provided the modification is approved by the Project Engineer. Prior to
commencing the electrical works, the Contractor shall provide to the Project Engineer a
set of drawings to the scale 1:50 showing detailed conduit layout and wiring drawings
showing all details such as the route and size of the duct, number and size of cables in
the conduit, location of outlet boxes, openings or duct outlets in civil works if required
etc. This Drawing shall be prepared in complete coordination with and understanding of
the civil and architectural works which will actually be undertaken. The Drawing shall be
immediately architect modified and approved if any changes in design are undertaken
and a record of such amendments shall be kept. A set of the up-dated and approved
Drawings shall be available at the site at all times for inspection by the Project Engineer.
Shop drawing: The work shall be carried in accordance with the drawing enclosed with
the tender and also in accordance with modification there to from time to time approved
by the Engineer. The contractor shall prepare the detail shop drawings of the following
items and get approval from the consultant before manufacturing/fabricating/installing of
the items.
Detail of main distribution boards & sub-distribution boards.
The run of various main & sub-main cables
Site Condition:
The equipment and materials to be installed should be suitable for the site conditions. It
is estimated that the maximum temperature at site will be 48 degree centigrade.
3.1.7 Sample:
Prior to commencing procurement, the Contractor shall submit for approval technical
description, related catalogue/brochures and a sample item each of all cable, conduit,
accessories, switches, power outlets, lamps, fluorescent tubes, fixtures etc. which are to
be procured and installed.
PAGE | 170
S P E CI FI C AT I O NS F OR E L E CT RI CAL W OR K S SE CT I O N- E S- 0 2 0
TECHNICAL SPECIFICATIONS
Equipment supplied and the construction work shall conform to the relevant IS (IS:732 -
Code of Practice of Electrical Wiring Installation - System voltage not exceeding 650 V),
BS, DIN and the latest National Code of Practice published by HMG/N, Ministry of
Water Resources. Notwithstanding the stipulation of above Standards, local electrical
codes for electrical services in buildings, where such exist Code (Nepal Standard) shall
also be followed. Adequate consideration shall be given to compliance of the equipment
and works with local environmental conditions such as temperature, altitude, humidity,
duct, vermin, attitude of personnel who will occupy the premises etc.
2. RELEVANT STANDARDS
Following Specifications and Codes or their latest revision shall apply under all
circumstances.
Low Voltage Moulded Case Circuit Breaker - IS 2516, 1977
Transformer - IS 2026, 1962
Earthing - IS 3043, 1966
Wiring installation - IS 732, 1963
PVC Cable - IS 1554, 1964
Distribution boards - IS 2675, 1966
3. STANDARD MAKE
The standard make of the light fixtures, switch, socket, circuit breaker etc shall be as
indicated below or equivalent as approved by the Engineer.
MCCB Legrand/ Siemens/ L&T
MCB Legrand/Siemens/ L&T
Wiring cable Nepalese cable with NS Mark
Light switch Unbreakable Legrand Modular
Switch socket Unbreakable Legrand Modular
PAGE | 171
S P E CI FI C AT I O NS F OR E L E CT RI CAL W OR K S T E C H N I C AL S P E C I F I C AT I O N
4. COLOR CODE
Color codlings, as per internationally accepted rule, shall be followed for phases
(Red/Yellow/Blue), neutral (Black) and earth wire (Green) everywhere, even including
inside the main panel board, distribution board, main switch.
The Contractor shall propose two complete, new and unused sets of all special tools
and gauges which will be required for normal operation and maintenance. The
Contractor shall furnish the list of tools and appliances and their prices under price
schedule of the tender document. To the greatest extent possible, the tools for each
specific operation shall be stored in a single, lockable, portable steel box suitably and
clearly marked for convenient identification.
6.1.1 General
The electric cable shall be of 650/1100 volt insulation grade armoured / unarmoured
power cables. The cables shall be used for mains supply, walkway lighting, garden
lighting or facade lighting etc. The cables shall be of 4, 3 1/2, 2 or 1 core copper
conductors for LT application and 3 core aluminum conductor for HT application.
PAGE | 172
S P E C I F I C AT I O N S F O R E L E C T R I C AL W O R K S T E C H N I C A L S P E C I F I C AT I O N S
6.1.3 Tests
Cable shall be tested for insulation resistance before and after installation. The
insulation resistance between each conductor and against earth shall be more than 20
M-ohm
7.1.1 General
The LT main distribution board shall be suitable for alternating current 3-phase 4-wire
400/230V, 50 Hz supply. It shall be pad-mounted. All the incoming and outgoing feeders
shall have appropriate sizes of MCCB & MCB's mentioned as per BOQ. The board
shall also consist of CT's, voltmeter, ammeter, indicating lamp assembly, fuses with fuse
blocks, copper terminal blocks etc. It shall also in-house the copper earth terminal with
multi-way provisions.
PA G E | 1 73
S P E CI FI C AT I O NS F OR E L E CT RI CAL W OR K S T E C H N I C AL S P E C I F I C AT I O N S
Clearance
The minimum clearance of the power terminal lug from the bottom plate shall be
maintained as 200 mm. The minimum gap between two MCCB shall be 40mm.
Arrangement shall be made at the bottom of the control panel for receiving incoming
cable. Space for outgoing cables shall be properly designed as per requirement.
PAGE | 174
S P E C I F I C AT I O N S F O R E L E C T R I C AL W O R K S T E C H N I C A L S P E C I F I C AT I O N S
The miniature circuit breaker shall be magnetic short circuit and thermal overload trip
low voltage automatic circuit breaker. Miniature circuit breaker shall have short circuit
breaking capacity of 9kA or higher. The body of circuit breaker shall be made of
fiberglass reinforced nylon pouring. The mechanism of the MCB shall be trip free also it
shall ensure opening of contacts under fault condition even if the operating knob is held
in `ON' position. In case of multiple units of MCB's, tripping of one pole should
automatically open the other poles.
7.1.5 Accessories
The separate chamber of the main panel board shall consist of the accessories:
Voltmeter (0-500 Volt)
Ammeter with selector switch
Indicating lamps
Fuse blocks
The CT's shall be in-housed in the bus bar chamber. The CT's shall be plain ring type
with round windows. It shall be wound with the best non-ageing material. The windings
of ring transformer shall be evenly distributed around the core. The cores of current
transformers shall be either silicon steel stamping, grain oriented steels or high
permeability alloys. The ratings and features for CT's are:
rated voltage: 400 Volt
maximum system voltage : 660 Volt
rated frequency: 50 Hz
rated secondary output: 5 Amp
rated output: 10 VA
accuracy class: BM refer to BS 81
rated short time current (thermal,1 sec): 40 x In A
rated continuous thermal current: 1.2 x In A
polarity: subtractive
applicable standard: BS 81 and BS 2046, IEC, or
7.1.6 Tests
Routine tests of main panel board shall be conducted in accordance with IS
specifications. Type test certificates and results, as per relevant IS specification for the
main panel board shall be furnished. The panel board shall be completely assembled,
wired adjusted and tested for operation under simulated conditions to ensure
correctness of wiring and proper functioning of all equipment. All component parts such
as MCCB, MCB's, meters, etc. shall be tested in accordance with relevant IS
specifications. Type test result of identical equipment shall be acceptable.
7.1.7 Installation
A trench of appropriate dimension shall be made to lead the cable from the
bottom of panel board. Sufficient space shall be provided to avoid sharp bending
and for easy connection.
The main panel board shall be ground mounted with all necessary accessories.
PA G E | 1 75
S P E CI FI C AT I O NS F OR E L E CT RI CAL W OR K S T E C H N I C AL S P E C I F I C AT I O N S
All the outgoing feeders shall be brought out from the top of the board.
Necessarily dust and other foreign particles shall not enter into the board from
the holes.
Interior wiring should be neat and handy.
The location of the main panel board shall be in the ground floor and for specific
location the site engineer shall be consulted.
The drawings in general are diagrammatic only and whilst every effort is made to show
the full extent of the work, proper allowance must be made when measuring from these
drawings to allow for rises and falls in the runs.
The Contractor will be held responsible for the accuracy of all measurements and for the
quantities of materials required in connection with the work. Any discrepancies must be
referred to the Consultants before submitting a tender, and claims later for extra
payment on account of misinterpretation of the specification or drawings will not be
allowed.
The following drawing with details shall be furnished along with the tender: Drawing of
the main panel board with:
space required in the front and back
power cable entry/exit points
bus bar clearance between phase to phase and phase to neutral
configuration of bus bars
location of MCCB and MCB's
compartments for metering/indicating accessories
PAGE | 176
S P E C I F I C AT I O N S F O R E L E C T R I C AL W O R K S S EC T I ON - E S - 0 3 0
DISTRIBUTION BOARD
1. GENERAL
The low-tension distribution board shall be suitable for alternating current 3-phase
4-wire 400/230 V, 50 Hz and 1-phase 230 V supply. For the line isolation and circuit
protection MCB's shall be employed. All the distribution boards shall be flush mounted.
2. CONSTRUCTION
Distribution board shall be made with 16 SWG mild steel-sheet cubical, concealed
mounting with double cover having openable hinges and locking arrangement. The mild
steel sheet shall be painted with two coats of red oxide primer, and the two final coats of
enamel of approved color. The bus bar used shall be made from highly conductive
electrolytically pure copper bar strips of sufficient cross sectional area so that maximum
current density of 1.2 Amp/sq mm shall not be exceeded. Neutral bus bar shall not be
less than 50 % of the phase bus cross section. The interconnection of cable inside SDB
shall be done with crimping type cable shoe of appropriate size. The incomer MCCB
shall have breaking capacity as indicated in the BOQ at 400 volts and the outgoing
MCBs shall have breaking capacity of 9 kA or higher at 230 volts. All the outgoing MCB
shall be properly marked on the inner cover.
PA G E | 1 77
S P E C I F I C A T I O N S F O R E L E C T R I C AL W O R K S S EC T I ON - E S - 0 4 0
1. GENERAL
The scope of this specification is the design and constructional aspects of electrical
wiring including the accessories. Wiring for lights, convenience outlets, fans, call bells,
telephones, etc. shall be carried out by distribution and looping tem as shown in the
electrical drawings. Accessories shall be of best quality.
No alteration which shall affect the structural building shall be done unless sanction of
the site-engineer in charge. All chassis, holes etc required in connection with the
electrical works shall be provided when the building is in progress.
2. WIRES
All the wiring conductors hall be of soft drawn annealed copper with PVC insulation
rated for 600 Volts. The sizes of the wires shall as per following:
Circuit conductors shall extend to the outlets shown. Circuiting basically shall be as
shown in the electrical drawings provided. An arrow indicating to sub-distribution board is
a complete circuit i.e. consisting of one phase conductor, one neutral conductor and one
earthing. .
PA G E | 1 78
S P E C I F I C AT I O N S F O R E L E C T R I C AL W O R K S W I R I N G A N D AC C E S S O R I E S
conductor with color codes (if necessary), in a suitable conduit with wire sizes defined
by the type of circuits.
Request for deviations in methods of circuiting and conduit branch circuit distribution
shall be submitted in shop drawings for approval to the engineer. The capacity of circuits
shall be such that a light circuit shall not have the load more than 1000 watts and a
power circuit shall not have more than three points i.e. 3000 watts unless otherwise
specified.
All wiring and conducting of cable shall be concealed inside ceiling slab and wall.
All the wiring conductors shall be of soft drawn annealed copper with PVC
insulation rated for 600 Volts. The cable shall be drawn in HDPE conduits of size
mentioned in the bill of quantity. The minimum wall thickness of HDPE conduit
shall be 2 mm.
Maximum 4 nos of 3/22 PVC insulated copper wire along with an earth wire
shall be allowed through a 16 mm internal dia PVC conduit and maximum of 2
nos 7/22 PVC insulated copper wire along with an earth wire shall be
allowed through a 16-mm internal dia PVC conduit.
All the PVC conduits shall be single lengths without joint except in the junction
box and pull-box. Single conduit length above 15m shall be provided with
a conveniently located pull-box. Pull-box also shall be provided at the sharp
bending of conduit.
The outlet box for light point shall be made of rigid HDPE and the 16mm internal
dia conduit shall be tightly fixed to this box.
All the wiring conductors shall be single length without joint except in the
junction box. No cable joint shall be allowed in the pull box.
5. INSTALLATION
Switches shall be fixed at the wall 1.5 m above the finished floor and at the locations
shown in the drawings.
Power, telephone and call-bell sockets shall be fixed at the walls 20 cm above the
finished floor and they shall be as shown in the drawings.
PA G E | 1 79
S P E CI FI C AT I O NS F OR E L E CT RI CAL W OR K S SE CT I O N- E S- 0 5 0
1. GENERAL
This specification shall cover the lighting fixtures and the lamps including all necessary
accessories. The contractor shall furnish and install all the fixtures with lamps and
accessories as per following specifications and drawings. The location of the fixture
shall be as per electrical layout plan drawings and as per the instruction of the Engineer.
The quality of the materials and installation shall be up to the satisfaction of the
supervisor in charge.
Fixture shall be provided on ceilings, walls carefully aligned and leveled. Adequacy of
support system and alignment shall be approved. Fixtures shall be left clean at the time
of final completion of work; every item shall be in proper working order. Fixtures shall be
protected from dirt, dust, paint, debris, etc.
Manufacture's catalogue number and/or description in the "Fixture Schedule" shall
establish quality, style, finish etc; similar fixture, which shall meet the exact specification,
or quality features and alike appearance shall be submitted for prior approval.
Fitting shall be designed for continuous trouble free operation under tropical climate. All
outdoor fittings shall be weatherproof and rainproof type. - The fittings shall be
designed so as to facilitate easy maintenance, including cleaning, replacement of
lamps/starters etc.
Connections between different components shall be made in such a way that they will
not work loose by small vibration. For each type fluorescent type and mercury type of
lightning fitting the contractor shall supply the utilization factor to indicate the proportion
of the light emitted by the bare lamps which falls on the working plane.
All fittings shall be supplied complete with lamps suitable for operation on a supply
voltage and the variation in supply voltage up to +/- 10%. Normal supply voltage shall be
3 phase, four wire 400/230 volt 50HZ neutral solidly grounded system.
The fittings and accessories shall be designed to have low temperature rise. The
temperature rise above the ambient temperature shall be as indicated in the relevant
standards. All mercury vapor lamp fittings shall be complete with accessories like lamps,
ballasts, power factor improvement capacitors, starters wherever applicable etc. These
shall be mounted as far as possible in the fitting assembly only. If these cannot be
accommodated inside then a separate metal enclosed box shall be included to
accommodate the accessories and in addition with a fuse and a terminal block suitable
for loop-in, loop-out connections. Outdoor type fittings shall be provided with outdoor
type weatherproof box.
PAGE | 180
S P E C I F I C AT I O N S F O R E L E C T R I C AL W O R K S S EC T I ON - E S - 0 6 0
EARTHING
GI rod grid earthing shall be carried out as per drawing with 2m long 50mm dia GI solid
rod electrodes buried vertically with their tops 1m below the general ground level.
50mm4mm GI strip with welded joint shall be used for the interconnection of electrodes
and 25mm3mm GI strip shall be used to connect the grounding grid to the equipment.
The earthing grid should be at least 2 meters away from the building foundation. The
earth resistance in no case shall exceed 10 Ohms. Contractor shall be responsible to
bring down the value of earth resistance in case measured value comes more than 10
Ohms.
Plate earthing shall be made of 600mm600mm3mm copper plate buried vertically 1.5
m below the general ground level. 10 SWG bare copper wire shall be used to connect
the plate and the equipment. The 10 SWG bare copper wire shall be connected to the
plate by heat joint. Provision of watering chamber shall be provide as per drawing.
Separate earthing electrode shall be provided for the following system and equipment:
Transformer Neutral
Transformer body
DG body
DG neutral
Main control Panel
PA G E | 1 81
S P E CI FI C AT I O NS F OR E L E CT RI CAL W OR K S SE CT I O N- E S- 0 7 0
The steel tubular poles for LT lines and HT lines shall confirm to IS 2713 (Part I and II)
1980. The poles shall be swaged type and made from steel having breaking load of 451
Kg. The dimension of the pole shall be as described below. The pole shall be complete
with a cast iron, beset type cap with 3 Nos. of equally spaced screws. The poles shall be
complete with 6 mm thick 300 mm x 300 mm mild steel base plate welded at the larger
end. The poles shall be painted throughout inside with a bituminous preservative
compound and outside shall be painted with a coat of zinc chromate primer and two
coats of aluminum paint. At the bottom of the pole 2 m coal tar vanish shall be painted
over the outer surface.
PAGE | 182
S P E C I F I C AT I O N S F O R E L E C T R I C AL W O R K S S EC T I ON - E S - 0 8 0 0
METHOD OF MEASUREMENT
All the items of work shall be measured in the unit specified in the BOQ.
A set shall be considered as a complete set of the item of work described in the
BOQ including all the necessary fixing accessories to complete that item of work.
A light point wiring includes the cost of HDPE conduit, wire, junction box, pull
box, other fixing accessories to complete the wiring from DB to a light point via
junction box and switch. A light fixture set shall be counted as a point, which
shall include the wiring to junction box and switch. Junction box and switch shall
not be counted as a point wiring.
A power socket point wiring includes the cost of PVC conduit, wire, junction box,
pull box, other fixing accessories to complete the wiring from DB to a socket
point via pull box. A power socket shall be counted as a point.
All the main cables, except point wiring, shall be running meter.
PA G E | 1 83