Steps of ROB/RUB GAD Approval Process in RORACS on-line Application
Step Activity Responsibility
1 Creation of proposal by Sponsoring Organization (NHAI, etc.) Sponsoring Organization 2 Fixing of Joint Site Inspection Date in consultation with Sr.DEN/DEN Sponsoring of concerning railway division Organization 3 Joint Site Inspection by Sr.DEN/DEN and Sponsoring Organization Sponsoring Organization and Railway Division 4 Entry of Joint Site Inspection date, details of officials present in Sr.DEN/DEN Joint Site Inspection 5 Preparation of Joint Feasibility Report and signing by Railway Sr.DEN/DEN of Official Railway 6 Signing of Joint Feasibility Report by Sponsoring Organization Sponsoring Organization 7 Uploading of Joint Feasibility Report by Sr.DEN/DEN Sr.DEN/DEN of (In case Sponsoring Organization officials do not sign the Joint Railway Feasibility Report in reasonable time, Sr.DEN/DEN may upload without their signature duly giving the remark to this effect in Joint Feasibility Report) 8 Finalization of Span Arrangement by CBE CBE of a) He may approve with changes as deemed fit and send to concerning Zonal Sponsoring Organization for preparation of GAD Railway b) He may return the proposal to division for revision with necessary remarks 9 If Joint Feasibility Report is returned by CBE to division then Sr.DEN/DEN of division to take action as per step 5,6,7. Railway 10 Submission of GAD, etc by Sponsoring Organization to CBE as per Sponsoring Joint Feasibility Report and Span arrangement finalized by CBE Organization 11 Scrutiny of GAD, etc by CBE CBE of a) He may forward to division for signature concerning Zonal b) He may return to Sponsoring Organization for correction if any Railway 12 In case GAD, etc is returned by CBE, then Sponsoring Organization Sponsoring to revise the GAD accordingly and resubmit Organization 13 Signing of document by divisional officials and forwarding to CBE Sr.DEN/DEN 14 Approval of GAD by CBE CBE of a) He may approve the proposal concerning Zonal b) He may return to division for corrections if any Railway 15 If GAD is returned by CBE to division for correction then Sr.DEN/DEN Sr.DEN/DEN to do the correction, sign and send to CBE for approval