RnA Power Industrial Sdn Bhd provided a daily work progress report for their 415 MCC Upgrade Project at Petronas Gas Berhad in the UK. According to the report:
1. 16 workers were on site today and worked 8 hours each to prepare for the project, including conducting a safety induction and preparing work packs.
2. Planned work for tomorrow includes inspection of tools and equipment, applying for permits, preparing for delivery of 27 new drawers, and removing existing timers from a redundant MCC.
3. Overall actual progress of the project is currently at 8% according to the report.
RnA Power Industrial Sdn Bhd provided a daily work progress report for their 415 MCC Upgrade Project at Petronas Gas Berhad in the UK. According to the report:
1. 16 workers were on site today and worked 8 hours each to prepare for the project, including conducting a safety induction and preparing work packs.
2. Planned work for tomorrow includes inspection of tools and equipment, applying for permits, preparing for delivery of 27 new drawers, and removing existing timers from a redundant MCC.
3. Overall actual progress of the project is currently at 8% according to the report.
RnA Power Industrial Sdn Bhd provided a daily work progress report for their 415 MCC Upgrade Project at Petronas Gas Berhad in the UK. According to the report:
1. 16 workers were on site today and worked 8 hours each to prepare for the project, including conducting a safety induction and preparing work packs.
2. Planned work for tomorrow includes inspection of tools and equipment, applying for permits, preparing for delivery of 27 new drawers, and removing existing timers from a redundant MCC.
3. Overall actual progress of the project is currently at 8% according to the report.
RnA Power Industrial Sdn Bhd provided a daily work progress report for their 415 MCC Upgrade Project at Petronas Gas Berhad in the UK. According to the report:
1. 16 workers were on site today and worked 8 hours each to prepare for the project, including conducting a safety induction and preparing work packs.
2. Planned work for tomorrow includes inspection of tools and equipment, applying for permits, preparing for delivery of 27 new drawers, and removing existing timers from a redundant MCC.
3. Overall actual progress of the project is currently at 8% according to the report.
Progress Status Equipment/Machinery Unit Qty (%) Total Today Prev. Acc. complete Site Activities Hand tools no 0 1. Mobilize & Preparation 0.40 1 Lot 20% 0% 20% 20% Inspection Tools no 0 2. Gemstart 5 New drawer delivery 0.20 27 nos. 0 0 0 0% Tritton no 1 3. Site verification ASU2 MCC data 0.10 36 nos. 0 0 0 0% Walkie-talkie no 0 4. Timer replacement 0.10 10 nos 0 0 0 0% 5. New drawer Calibration 0.20 27 nos. 0 0 0 0%
Total 1.0 Overall Progress 8%
Today Activities (Sunday 16/2017) 1. Manpower mobilize to site, safety induction conducted at MTC 2.Work pack preparation and approval 3. Preparation for permit to work
OVERAL ACTUAL PROGRESS: 8%
OVERAL PLANPROGRESS: 8%
Tomorrow Activities (Monday 17/7/2017)
1. Preparation work, tools and equipment inspection 2. Apply permit to work (vehicle entry, testing and calibration at sub 1, MCC site verification at sub3 ) 3. Preparation for receiving of 27 nos. new drawer 4. remove exisitng timer at redundant MCC ASU1 at Sub3
Site Issue 1. Nil
Prepared by : MOHD AZRUL RAIS Checked/ Verified by : M SALIM M IBRAHIM