Rescue Plan: Hot Oil Drain Drum
Rescue Plan: Hot Oil Drain Drum
Hot oil drain drum
1 Work description : scaffolding erection and dismantling installing insulation and jacketing for pipe and equipment
1.1 TEAM: Competent supervisor Hole watcher ,HSE supervisor ,workers and operator rigger.
Rescue team containing from four people will take the patient out by using a stretcher with the help of SECL nurse
1.3
1.5 Ensure assigning competent and trained people for doing this job
2 Rescue plan and Emergency procedure in case of exposing the work team to falling from height
2.1 After hearing the alarm the work shall directly stopped
2.2 The team rescue leader will be moved to the guy exposed to falling directly .
2.4 Assists SECL nurse to transfer the IP (injured person)to the stretcher and take out of the confined space.
2.6 Rescue team containing from four people will take a patient out by using a stretcher
2.7 Ramp ladder( which already erected )inside if scaffolding shall be used as an evacuation rout to transport the patient out
3 Emergency procedure in case of exposing the work team to electrical shock :
3.1 Directly turn the power off by using an isolated materials from the main source supplier after hearing the alarm .
3.2 Carefully remove the sores of contact from the injured worker
Rescue team containing from four people will take a patient out by using a stretcher
3.3
Ramp ladder( which already erected )inside if scaffolding shall be used as an evacuation rout to transport the patient out
3.4
3.5 First AID treatment to be given by trained /approved first aider by following the step below.
a Establish and maintain an open air way
b If injured is not breathing assists ventilation shall be started (using mouth - to mouth ) breathing .
c The injured to be warm and rest .
d In case of vomiting the injured shall be turned on side to insure clearance of air way
3.6 Transport the patient to the ambulance then to medical aid center .