Ims Operation Manual Water Division: Ivrcl Limited, Hyderabad
Ims Operation Manual Water Division: Ivrcl Limited, Hyderabad
CONTENTS
Status
Sl No Name of Document Identification Page No
Rev No Date
AMENDMENT RECORD
PROCESS PROCEDURE
1.0.0 OBJECTIVE
1.1.0 Objective is to establish a process & define responsibility/authorities for achieving set targets of Division, in
close co-ordination with Region Heads.
2.0.0 SCOPE
2.1.0 BUSINESS DEVELOPMENT
2.1.1 Based on various business development activities and study of market, find out optimum possible business
opportunities for any financial year and inform Management about the target & profitability of the Division.
2.1.2 Business Development is carried out in collaboration with BD&CS department and Regional Offices through
market survey, scrutiny of bid notices in newspapers/internet, follow up with customers for getting repeated
orders, exploring business opportunities with new customers, etc.
2.1.3 All possible details about various contracts are maintained in Data Bank for use as guideline in future
business.
2.2.0 TENDERING
2.2.1 Receive information regarding tender notices and business opportunities from BD&CS department and Head
Regions.
2.2.2 Study and decide about participation in the Bid.
2.2.3 Purchase Bid Document; send to BD&CS for arranging required PQ documents.
2.2.4 Study the Bid carefully on various important points pertaining to specifications/Technical & commercial
aspects, etc. for preparation of best possible Offer.
2.2.5 Obtain all possible information for Bid preparation through Site Investigation/Pre-bid meeting from Regional
Offices.
2.2.6 Work out rates & other details, obtain approval from COC and arrange for submission through Regional
Offices.
2.2.7 Depute representative while opening of the tender to note the offer of competitors, record and store the same
in Data Bank for future guidance.
3.0.0 RESPONSIBIILITY
3.1.0 Division Head with Division Office team is responsible for obtaining various information pertaining to Project
execution from Sites/Regions, compile the same and submit reports to PM&C Department/ COC, as required.
3.2.0 Division Heads may also visit Sites/Regions in connection with execution of Projects, for
coordination/monitoring/meeting with Clients, extending required guidance, etc., as required.
TARGET SET BY
MANAGEMENT
MARKET STUDY
APPRAISE CUSTOMERS
OF NEW AVENUES/
SEND
PROPOSAL ERIODIC
L NEWS LETTER
START
INVITATION TO TENDER
TYPES OF TENDERS
ITEM RATE, PERCENTAGE, LUMP SUM, TURNKEY, BOT, BOOT,
ANNUITY, BOS, EPC, FEED, ETC
SELECTION OF TENDER
- TYPE OF WORK
- AREA OF WORK
- VOLUME OF WORK
- CORPORATE STRATEGY
PRE QUALIFICATION
QUALIFIED
CHECK FOR OUR
QUALIFICATION
ANALYSE
ANALYSIS
END
OBTAIN
DOCUMENT
ANALYSE
– PREPARE SYNOPSIS.
END – SUBMIT TO HOD FOR APPROVAL FORFLOATING OF ENQUIRIES FOR GETTING THE
SITE INFORMATION AND ENTERING IN T-2 FOR SITE INVESTIGATION REPORT.
– SENDING REP. OF DIV. OFFICE.
– SENDING REP.OF NEARBY SITE.
ANALYSE – ANY EXTERNAL CONSULTANTS FOR SPECIALISED WORK.
– DESIGNS DEPARTMENT REP IF REQUIRED FORMAT-1)
END
B
YES
ANALYSE
END
DOCUMENTATION
– PREPARATION OF OFFER LETTER, TERMS & CONDITIONS
AND INCORPORATION OF TECH. SPECIFICATIONS
– ENCLOSURE OF OTHER PAPERS / CREDENTIALS/
FORMATS AS PER TENDER DOCUMENTS
NEGOTIATION
YES
1.0.0 ACTIVITY DURING THE PERIOD WE BECAME L1 & RECEIPT OF WORK ORDER FROM CLIENTS:
1.1.0 Immediately on our becoming L1, concerned Regional Head has to identify the Site In-charge for that Project
in consultation with concerned Division Head and send him to Site, with a complete set of Bid documents.
1.2.0 Site In-charge/Regional Head shall get acquainted with the Site conditions/prevailing cost parameters, etc.
Site In-charge, based on his study of Site conditions, Bid documents, etc., has to prepare the following and
submit to concerned Regional Head & Division:
“PCA for execution”
Detailed execution plan
Detailed Resource plan
Detailed Expenditure plan
Cash flow for execution of Contract within stipulated contractual period
All other relevant statements as indicated in the “Project Planning & Control System Manual (PPCS)”
1.3.0 Concerned Regional/Division to scrutinize the above details thoroughly and finalize with their
recommendations. Regional Head to send such finalized details to COC, for their scrutiny & vetting.
1.4.0 In case of Contracts decided for execution on total B2BSC basis after bidding, concerned Regional/Division
Head to take following actions on our becoming L1:
Proposal of B2BSC proposing our royalty fees
Proposed Site In-charge from our side
Scrutinize detailed execution plan, resource plan, expenditure plan, cash flow, etc., prepared by B2BSC
Indemnity bond to be executed by B2BSC
Send such details to Director Technical/COC for their scrutiny/study and approval
2.6.0 In case of Contracts to be executed on total B2BSC basis, details about our terms with B2BSC, our royalty
fees, proposed Site In-charge from our side, concluding B2BSC agreement, Indemnity bond to be executed by
the B2BSC, execution plan, resource plan, expenditure plan, cash flow, etc., as prepared by the B2BSC and
vetted by Division/Regional Heads, etc. are to be discussed in the “Kick-off” meeting and required decisions to
be given by COC, for starting the Contract Execution.
ST
3.0.0 ACTIVITY DURING 1ST MONTH OF RECEIPT OF WORK ORDER FROM CLIENTS:
3.1.0 Regional Head & Site In-charges shall start the activities at Site, within the time frame stipulated in the
contract, including for B2BSC projects.
3.2.0 Immediately on opening of Site, Regional Head to write our first letter to Clients informing
About our Company’s credentials in similar works, highlighting our special achievements
Brief introduction about Site In-charge, highlighting his achievements
Details of Contact persons at Regional Office, Division Office, PM&C Department and Director Resource,
with their telephone numbers for Clients to contact in case of important issues
3.3.0 Regional Head to arrange for a “kick-off” meeting with Clients for taking up major issues related to Clients
assistance such as release of work fronts, drawings to be issued by Clients, etc. Also based on our earlier
analysis/study of various BOQ items with reference to available margins in each item, we may appropriately
initiate in this “Kick-off” meeting about reduction or increase in scope wrt such loosing or profitable items,
respectively. All such points of discussions of this meeting are to be minuted by Clients. In case of Clients not
minuting this, Regional Head/Site In-charge has to write immediately about these points of discussion to
Clients, with the concurrence of PM&C Department. In case of larger projects of more than Rs. 15 to 20
crores, depending upon the importance of the projects in terms of Clients/Contract period/Nature of the
Contract, etc., on a case-to-case basis. Concerned Division Head may also attend such “kick-off” meeting with
Clients along with COO, PM&C Department.
3.4.0 Regional Head & Site In-charge, in close consultation with concerned Division Head/Head PM & C
Department, to ensure that full-fledged execution of works is reached within one month from the date of
receipt of Work Order. First Bill has to be submitted within one to two months from date of LOA, irrespective of
the bill amount. In case of Contracts where minimum billing amount is stipulated, this has to be achieved
within that period.
3.5.0 For each project, Site QMS Documents and Site HSE Documents shall be prepared:
Site QMS Documents, on a minimum basis, shall include:
1) Site organization chart
2) Roles and responsibilities, Resource programme for the project
3) Site Investigation Report
4) Project Implementation Schedule
5) Activity flow chart
6) QA checklists
Effective implementation
Health Safety & of reviewing the IMS in Data Sheet
As fixed during
4 Environment (HSE) MRM in order to reduce Monthly basis MSS/MIS
beginning of the year
Improvements the number of major and Sheet
fatal accidents