Professional Documents
Culture Documents
Chapters 234 PDF
Chapters 234 PDF
FINANCIAL STUDY
by first making a complete and conservative estimate of the total cost for
the accomplishment of the project. Since the project was owned by the
High School, every peso has given much priority and mindful analysis to
A. MAJOR ASSUMPTIONS
fund method:
Dn = d (F/A, i%, n)
Cn = Co – Dn
Co = Initial Cost
CL = Salvage Cost
annually.
all aspects.
a. Footing
Portland Cement 1753 bags 260.00 455,780.00 159,523.00
Fine Sand 97.5 cu.m. 560.00 54,600.00 19,110.00
Crushed Gravel 194.8 cu.m. 640.00 124,672.00 43,635.20
b. Column
Portland Cement 1151 bags 260.00 299,260.00 104,741.00
Fine Sand 64 cu.m. 560.00 35,840.00 12,544.00
Crushed Gravel 127.9 cu.m. 640.00 81,856.00 28,649.60
c. Beams
Portland Cement 1900 bags 260.00 494,000.00 172,900.00
Fine Sand 105.6 cu.m. 560.00 59,136.00 20,697.60
Crushed Gravel 211.1 cu.m. 640.00 135,104.00 47,286.40
d. Slab
Portland Cement 1341 bags 260.00 348,660.00 122,031.00
Fine Sand 74.5 cu.m. 560.00 41,720.00 14,602.00
Crushed Gravel 149 cu.m. 640.00 95,360.00 33,376.00
e. Stair and
Landing
Portland Cement 285 bags 260.00 74,100.00 25,935.00
Fine Sand 15.9 cu.m. 560.00 8,904.00 3,116.40
Crushed Gravel 31.7 cu.m. 640.00 20,288.00 7,100.80
a. FOOTING
20 mm Dia.
528 pcs 460.00 242,880.00 85,008.00
Vertical bars
#16 Tie wire 44 kgs 75.00 3,300.00 1,155.00
b. COLUMN
16 mm Dia. RSB
1488 pcs 300.00 446,400.00 156,240.00
deformed bars
#16 Tie wire 39 kgs 75.00 2,925.00 1,023.75
c. BEAM
16 mm Dia. RSB
6136 pcs 300.00 1,840,800.00 644,280.00
deformed bars
#16 Tie wire 302 kgs 75.00 22,650.00 7,927.50
d. SLAB
16 mm DIA.
DEFORMED 4576 pcs 300.00 1,372,800.00 480,480.00
BARS
#16 TIE WIRE 484 kgs 75.00 36,300.00 12,705.00
e. STAIR AND
LANDING
10 mm Dia. RSB
170 pcs 135.00 22,950.00 8,032.50
deformed bars
12 mm Dia. RSB
257 pcs 188.00 48,316.00 16,910.60
deformed bars
#16 Tie wire 30 kgs 75.00 2,250.00 787.50
f. RAILINGS
2"x3" Structural
46 pcs 1,750.00 80,500.00 28,175.00
Steel Tube
5" dia. steel pipe 12 pcs 380.00 4,560.00 1,596.00
12 mm steel
356 pcs 225.00 80,100.00 28,035.00
square bar
MASONRY
III.
WORKS
PLASTERING
IV
WORKS
PORTLAND
892 bags 260.00 231,920.00 81,172.00
CEMENT
FINE SAND 47 cu.m. 560.00 26,320.00 9,212.00
ROOF FRAMING
V.
WORKS
a. Truss
Assembly
150x50x20x1.5m
150 pcs 980.00 147,000.00 51,450.00
m C-purlins x 6m
2"x10"x1.2mm
20 pcs 1,025.00 20,500.00 7,175.00
Facia board x 6m
3"x3"x6mm angle
68 pcs 760.00 51,680.00 18,088.00
bar x 6m
2.5"x2.5"x6mm
64 pcs 680.00 43,520.00 15,232.00
angle bar x 6m
b. Painting of
Truss Assembly
Rust converter 4 gal 510.00 2,040.00 714.00
Red Oxide 7 gal 450.00 3,150.00 1,102.50
Paint Thinner 3 gal 180.00 540.00 189.00
Paint Brush 1 lot 950.00 950.00 332.50
c. Hardwares
Grinding Disc 15 pcs 70.00 1,050.00 367.50
Cutting Disc 30 pcs 450.00 13,500.00 4,725.00
6011 welding rod 20 kgs 120.00 2,400.00 840.00
6013 welding rod 20 kgs 100.00 2,000.00 700.00
TINSMITHRY
VI
WORKS
a. Roofing Sheet
Pre-painted rib
240 sheets 380.00 91,200.00 31,920.00
type roofing sheet
Pre-painted end
44 pcs 178.00 7,832.00 2,741.20
wall flashing
b. Miscellaneous
GUTTER 43 pcs 178.00 7,654.00 2,678.90
Pre painted
263 pcs 120.00 31,560.00 11,046.00
spandrel (6")
Silicone sealant 2 gals 1,800.00 3,600.00 1,260.00
Neoprene
26 kgs 200.00 5,200.00 1,820.00
tekscrew
Touch-up paint 48 gals 1,200.00 57,600.00 20,160.00
5mm thk
10 rolls 1,250.00 12,500.00 4,375.00
insulation foam
HardiFlex Ceiling
Board (1/4 x 4' x 320 pcs 270.00 86,400.00 30,240.00
8')
Finishing nail 18 kgs 80.00 1,440.00 504.00
Wood Adhesive
3 gal 1,500.00 4,500.00 1,575.00
Stickwell
PAINTING
VIII
WORKS
A. EXTERIOR
MASONRY PUTTY 30 gal 350.00 10,500.00 3,675.00
PRIMER PAINT 30 gal 480.00 14,400.00 5,040.00
PLEXIBOND 149 gal 950.00 141,550.00 49,542.50
TOPCOAT PAINT 60 gal 470.00 28,200.00 9,870.00
THINNER 23 gal 180.00 4,140.00 1,449.00
ROLLER 1 lot 1,000.00 1,000.00 350.00
BRUSH 1 lot 950.00 950.00 332.50
SAND PAPER 1 lot 600.00 600.00 210.00
B. INTERIOR
MASONRY PUTTY 822 gal 350.00 287,700.00 100,695.00
PRIMER PAINT 329 gal 480.00 157,920.00 55,272.00
LATEX PAINT 549 gal 470.00 258,030.00 90,310.50
ROLLER 1 1 1,000.00 1,000.00 350.00
BRUSH 1 1 600.00 600.00 210.00
SAND PAPER 1 1 600.00 600.00 210.00
C. CEILING
PAINT
PUTTY 132 gal 350.00 46,200.00 16,170.00
SCREEN TAPE 1 lot 500.00 500.00 175.00
PRIMER PAINT 80 gal 470.00 37,600.00 13,160.00
SEMIGLOSS
127 gal 650.00 82,550.00 28,892.50
ENAMEL
THINNER 68 gal 470.00 31,960.00 11,186.00
ROLLER 1 lot 1,000.00 1,000.00 350.00
BRUSH 1 lot 600.00 600.00 210.00
SAND PAPER 1 lot 600.00 600.00 210.00
IX TILE WORKS
FLOOR TILES
60x60cm ceramic
1219 pcs 229.00 279,151.00 97,702.85
tiles
DOORS &
X
WINDOW WORKS
a. DOORS
D1, 1m x 2.1
24 sets 8,000.00 192,000.00 67,200.00
Solid Panel Door
D2, 0.9m x 2.1
16 sets 2,000.00 32,000.00 11,200.00
Hollow Core Door
FORMWORKS
XI. AND
SCAFFOLDINGS
FORMS AND
STAGING
1/2"x 4ft x 8 ft
678 pcs 460.00 311,880.00 109,158.00
phenolic plywood
2"x3"10" good
3518 bd.ft. 60.00 211,080.00 73,878.00
lumber
CWN 2 1/2" 171 kgs 110.00 18,810.00 6,583.50
FINISHING NAILS
127 kgs 80.00 10,160.00 3,556.00
1 1/2"
160,000.0
GI PIPES 1 lot 160,000.00 56,000.00
0
ELECTRICAL
XII
WORKS
PLUMBING
XIII.
WORKS
SEPTIC VAULT
1. Concrete Slab
Portland Cement 194 bags 260.00 50,440.00 17,654.00
Fine Sand 11.2 cu.m 560.00 6,272.00 2,195.20
Crushed Gravel 23.4 cu.m 640.00 14,976.00 5,241.60
10 mm ᴓ RSB
deformed bar x 182 pcs 135.00 24,570.00 8,599.50
6m
#16 Tie Wire 24 kgs 75.00 1,800.00 630.00
2. Masonry
Works
4" thick CHB 1052 pcs 10.00 10,520.00 3,682.00
Portland Cement 43 bags 260.00 11,180.00 3,913.00
Fine Sand 3.6 cu.m 560.00 2,016.00 705.60
Crushed Gravel 2 cu.m 640.00 1,280.00 448.00
10mm ᴓ RSB
deformed bar x 29 pcs 135.00 3,915.00 1,370.25
6m
#16 Tie Wire 2 kgs 75.00 150.00 52.50
3. Plastering
works
Portland Cement 24 bags 260.00 6,240.00 2,184.00
Fine sand 1.4 cu.m 560.00 784.00 274.40
Sahara
waterproofing 5 bags 600.00 3,000.00 1,050.00
compound
4. Earthworks
Excavation 76 cu.m 235.00 17,860.00 6,251.00
Forms, stagging
8,000.00 2,800.00
and hardware
EARTH WORKS
XIV.
& FILLS
XVI. EQUIPMENTS
One bagger mixer
2 unit 172.00 17,200.00
(50 days)
Dump trucks (30
1 unit 1,420.00 42,600.00
days)
Concrete vibrator
3 unit 91.25 2,737.50
(10 days)
Welding machine
5 unit 371.00 27,825.00
(15 days)
Bar cutter (50
5 unit 219.75 54,937.50
days)
Bar bender (50
3 unit 351.50 52,725.00
days)
Back hoe (12
1 unit 1,537.00 18,444.00
days)
Plate compactor (3
2 unit 123.00 738.00
days)
Transit mixer (30
1 unit 1,318.00 39,540.00
days)
Water truck (30
1 unit 2,450.00 73,500.00
days)
Electric drill (50
5 unit 201.00 50,250.00
days)
SCHOOL EQUIPMENT,
XVII. FIXTURES AND
FURNITURES
ARM CHAIR 500 unit 400.00 200,000.00
MONOBLOCK
50 unit 250.00 12,500.00
CHAIR
STOOL 100 unit 500.00 50,000.00
TABLES 25 unit 2,500.00 62,500.00
LABORATORY
100 unit 2,000.00 200,000.00
APARATUS
SPEAKERS 4 unit 1,500.00 6,000.00
MICROPHONE 3 unit 30,000.00 90,000.00
ITEM MATERIAL
DESCRIPTION LABOR COST
NO. COST
I CONCRETE WORKS ₱2,329,280.00 ₱815,248.00
II STEEL WORKS ₱4,206,731.00 ₱1,472,355.85
III MASONRY WORKS ₱760,955.00 ₱266,334.25
IV PLASTERING WORKS ₱258,240.00 ₱90,384.00
V ROOF FRAMING WORKS ₱288,330.00 ₱100,915.50
VI TINSMITHRY WORKS ₱217,146.00 ₱76,001.10
VII CEILING WORKS ₱92,340.00 ₱32,319.00
VIII PAINTING WORKS ₱1,108,200.00 ₱387,870.00
IX TILE WORKS ₱306,671.00 ₱107,334.85
DOORS & WINDOW
X ₱618,400.00 ₱216,440.00
WORKS
FORMWORKS AND
XI ₱711,930.00 ₱249,175.50
SCAFFOLDINGS
XII ELECTRICAL WORKS ₱148,054.00 ₱51,818.90
XIII PLUMBING WORKS ₱629,689.00 ₱220,391.15
XIV EARTH WORKS & FILLS ₱324,050.00 ₱113,417.50
XV SITE WORKS ₱12,500.00 ₱4,375.00
XVI EQUIPMENTS ₱380,497.00
SCHOOL EQUIPMENT,
XVII FIXTURES AND ₱621,000.00
FURNITURES
₱12,915,813.00 ₱17,120,193.60
= Php 162,000.00
E. DEPRECIATION COST
𝒊
𝒅 = (𝑪𝑶 − 𝑪𝑳 )
(𝟏 + 𝒊)𝒏 − 𝟏
A. Building Cost
0.08
𝑑 = (22,598,655.55)(1 − 0.1)
(1 + 0.08) −1
0.08
𝑑 = (621,000.00)(1 − 0.1)
(1 + 0.08) −1
A. BENEFITS
donations.
B. COST
, , .
= 𝑃ℎ𝑝 1,040,237.21
( . )
Capitalized Cost
Cc = Php 25,898,758.31
1 − (1 + 𝑖)
𝑃𝑟𝑒𝑠𝑒𝑛𝑡 𝑊𝑜𝑟𝑡ℎ = 𝐴 𝑥
𝑖
1 − (1 + 0.08)
25,898,758.31 = 𝐴 𝑥
0.08
C. BENEFIT-COST RATIO
𝐵 6,172,000.00 − 540,353.35
= = 𝟐. 𝟓𝟗
𝐶 2,171,874.06
National High School, the people who will be part of the project, their job
Also, to the specific schedules from the preparatory stage start of operation
enough to provide the necessary needs of the students and at the same
the equipment, high skilled and experienced human resource the project
generally will be providing the necessary technical and financial needs for
the strategic role that the new Academic Building, as part of the main
Hon. Mayor Alfredo Ortega, the City mayor of San Fernando, together with
operation of the on-going construction since the mayor’s office will be the
a. Operation
correlate its operation and function to the current condition and parameter
b. Operation Analysis
Order No. 1 of 2018 and the needs of the current students who deserve
A. Construction Phase
1. Owner
2. Engineer
Functions:
in the NBCP.
Qualifications:
3. Safety Officer
Functions:
workplace.
4. Electrician
Functions:
PEC.
Qualifications:
drawing plans.
5. Plumber
Qualifications:
drawing plans.
6. Timekeeper
progress report.
Qualifications:
7. Foreman
Functions:
not around.
Qualifications:
in the field.
Functions:
construction works.
9. Skilled workers
a. Steelman
Functions:
Qualifications:
Functions:
Qualifications:
c. Mason
mixes.
Qualifications:
10. Laborer
Functions:
11. Painter
Functions:
works.
of experience in painting.
B. Operational Phase
1. Principal
Functions:
school.
c) Ensures that providing quality education is the highest
students.
Qualifications:
Secondary Educations.
Functions:
knowledge.
Qualifications:
3. Laboratory Custodian
Functions:
4. Medical Staff
Qualifications:
5. Janitor
Functions:
National High School. In this chapter shows the different impacts and
Introduction
generated, but also from the social and economic benefits offered to the
union. The proposed building will surely increase literacy rate and will
employment, taxes, and income are guaranteed. Which would increase the
revenue of the City of San Fernando, La Union. Upon the completion of the
help in uplifting the literacy rate of the students of La Union National High
School.
National High School there are many manpower and professionals needed
which will increase the rate of employment and help the people for their
to earn income for their families. Upon completion of the project teachers
and non-teaching staff are also needed in the school. Therefore, increase
National High School will provide facilities for the students to acquire
comfortable and healthy environment for them. It will also provide quality
education that its students need in order to achieve their goals and become
generate much taxes and revenues. Public schools are being funded by the
government which means that the government pays all the expenses of the
school from the salary of their employees down to the expenses on the
facilities and other resources needed by the school. In addition, during the
can contribute to the taxes and revenues if they are not earning minimum
wage.
The civil engineer should be in charge for the materials needed for the
hardware. The civil engineer will then choose the standard materials
needed for the construction and the local hardware will offer supplies for
the proposed project. The civil engineer or materials engineer that was in
V. ENVIRONMENTAL IMPACT
utility workers should adopt easily by the students so that they will be
carried out from the school that will lead to cleanliness and healthier
lifestyle. With this, awareness on the proper disposal of garbage inside the
will also take part of the various programs, projects and activities
implemented by the school. The school will adopt Waste Management and
Disposal Program wherein there will be at least two garbage cans labeled
environment and health of the students. The knowledge being learned and
acquired by the students will then be carried out from the school to their
own home. And will lead to more vigorous result of cleanliness and healthy
lifestyle which is then the start of more improved and higher state of