Professional Documents
Culture Documents
14.20022018 Paul Bussey-RIBA CDM PD Documentation - Universities Short Couse (171107) v1
14.20022018 Paul Bussey-RIBA CDM PD Documentation - Universities Short Couse (171107) v1
CDM 2015:
A Practical Guide
for Architects and
Designers
Risk Tolerability
Pre-construction Detailed Commercial
Information Design Decisions VE
(Initial Design
Risks) + Principal
Pre-construction Procurement
Contractor &
Information Tender subcontractors
(Developed
Design Risks) Significant Construction Contractor /
Risk /Benefit Planning Worker/ FM
Tolerability
Construction Construction &
Phase Plan & Handover
Site Risks
H&S File &
Maintenance
Risks
Principal Designer duties in CDM 2015
Your role is to plan, manage and monitor the
Pre-Construction Phase including P-C
Information by :-
• Ensuring client is aware of his duties
• Providing P-CI to all designers, Principal
Contractor & Contractors
• identifying, eliminating or controlling
foreseeable (significant) risks (P’s of P?)
• Ensuring (sfarp) all designers comply with
their duties
• Liaising with the PC for duration of your
appointment
• Preparing a Health and Safety file
(proportionate to risks and project) Appoint those most
appropriate to coordinate the
risks?
Not the same duties as a CDM-Coordinator
under 2007 but additional services can be
provided
All Designers must understand SFARP
(HASAWA 1974)
SFARP
“So Far As Reasonably Practicable”
In essence, it requires weighing the risk
?
against the resources needed to eliminate
or reduce the risk.
And the question, whether a measure is
or is not “reasonably practicable “is one
which requires no more than the making
of a value judgment in the light of all the
facts (not just H&S).ie:-
Empowerment of the team to make
properly informed project judgements,
without fear of prosecution.
Clause 81 states :-
Clause 83 states :-
‘Health and safety risks need to be considered alongside other factors that influence the
design, such as costs, fitness for purpose, aesthetics and environmental impact. Working with
contractors (including principal contractors) involved in the project can help identify the
potential risks and ways they may be controlled.’
Clause 84 states :-
‘ Once the risks have been considered , the level of detail in the information provided to those
who need it should be proportionate to the risks remaining.’
The General Principles of Prevention are only intended for Design
Stages “So far as is reasonably practicable”- They are Qualified Duties.
The Principles in L153
(a)avoid risks;
(b)evaluate the risks which cannot be
avoided;
(c)combat the risks at source;
(d)adapt the work to the individual, How would you explain the relevance of
especially regarding the design of workplaces these principles to a client, other designer or
etc. a student???
(e)adapt to technical progress;
(f)replace the dangerous by the non-
dangerous or the less dangerous; Why is it important that these principles are
(g)develop a coherent overall prevention understood by the project team??
policy which covers technology, organisation
of work etc.
(h) give collective protective measures
priority over individual protective measures;
(i)give appropriate instructions to employees.
30 mins
SFARP is the proportionate integration of safety and
health issues into innovative & creative design..sfarp
Company
Rating Risk Rating Information provided about the Designer/Constructor Status Manager of Control
Name &
Phase
Specific Action by Designer to residual hazards - Design Manager Discussion Date & Active/ responsible - Measures? Y/N Control Measures
Ref Location/Activity Potential Hazards L S R Eliminate/Reduce Risk Rating L S R Drawing/Document responsible - Name Comments Closed Name Control Measures required (by whom) identified in:
STRUCTURES
S.1 S01 piers C,M,D TAN Working in proximity to live 4 5 20 S01 crosses several major roads and 3 5 15 Note on drawing - method statement required Tim Nicholson 17/05/06 & 21/05/06 Active M Bell Works to be carried out with lane
(Jacobs) traffic impossible to configure within alignment to cover particular issues relating to the closures in accordance with Costain TM
constraints to avoid constructing near live complexity of the existing slip roads and phases. Provide proteced safety zone
traffic. Risk cannot be eliminated or A282 underneath and requirements for with barriers
significantly reduced. Position piers as far temporary road closures for pier construction.
away from live traffic as possible. Single span
S.2 S01 Working in A2 c.r. C,M,D TAN Working in proximity to live 4 5 20 S01 crosses several major roads and 4 5 20 Note on drawing - method statement required Tim Nicholson 17/05/06 & 21/05/06 Active M Bell Works to be carried out with lane
adjacent to live traffic (Jacobs) traffic impossible to configure within alignment to address the particular difficulty of working closures in accordance with Costain TM
constraints to avoid constructing near live in an island site phases. Provide proteced safety zone
traffic. Cannot be eliminated and therefore no with barriers
mitigation available to designer.
S.3 Pier bearing installation, M TAN Working in proximity to live 5 5 25 Design as integral bridges without bearings 5 5 25 Note on drawing - method statement required Tim Nicholson 17/05/06 & 25/05/06 Residual risks Active M Bell Provide protected safety zone with tvcbs
maintenance & (Jacobs) traffic. Working at height considered but structure too long for this. No addressing handling and installing of heavy to be noted in H&S plan - barrriesrs to mitigate traffic risk.
replacement (S01, S04, alternative mitigation available to designer in components at height with restrictive & TM required
S10(N) & S10(S) this respect. clearances. Log in H&S file.
S.4 Inspecting joints and M TAN Working at height. 3 5 15 Provide enclosed abutment galleries 2 2 4 RRR <6 - no further action required Tim Nicholson 17/05/06 & 21/05/06 Closed M Bell
bearings at abutments (Jacobs)
(S01, S04, S10(N) &
S10(S)
S.5 Painting of steelwork C,M TAN Working at height. 3 5 15 Use weathering steel 1 5 5 RRR <6 - no further action required Tim Nicholson 17/05/06 & 21/05/06 Closed M Bell
(S01, S04, S10(N) & (Jacobs)
S10(S)
S.6 Concrete impregnation C TAN Use of potentially toxic 4 2 8 Apply for Departure from Standards to use 4 1 4 RRR <6 - no further action required Tim Nicholson 17/05/06 & 21/05/06 Closed M Bell
(Jacobs) substance (silane) less toxic substance (Pavix) or to use
concrete additive.
S.7 Parapet installation C TAN Working at height, debris falls 3 5 15 No mitigation available to designer at 3 5 15 Note on drawing - method statement required Tim Nicholson 17/05/06 & 21/05/06 Active M Bell Cantilever formwork left in position until
(S01, S04, S10(N) & (Jacobs) installation stage. to address the particular dufficulty of providing parapet installation complete
S10(S) temporary edge protection while installing the
permanent edge protection at the same
location. Log in H&S file - maintenance
wpork on the outside of the parpap
S.7a Parapet maintenance M TAN Working at height, debris falls 3 5 15 Use aluminium parapet to minimise 1 5 5 RRR <6 - no further action required. Tim Nicholson 17/05/06 & 31/05/06 Residual risks Closed M Bell
(S01, S04, S10(N) & (Jacobs) maintenance to be noted in H&S plan
S10(S)
S.8 Placing deck formwork C TAN Working at height. 5 5 25 No mitigation available to designer. 3 5 15 Note on drawing - method statement Tim Nicholson 17/05/06 & 21/05/06 Active M Bell Permanent formwork placed where
(S01, S04, S10(N) & (Jacobs) required. Consider placing deck formwork at possible at ground level and lifted into
S10(S) ground level and lifting into place with beams. place with main steel.
Otherwise special precautions e.g.netting,
harnesses, will be required to ensure safety of
operatives while working on bare st
S.9 Placing deck formwork C TAN Debris falling onto motorway 5 5 25 No mitigation available to designer 3 5 15 Note on drawing - method statement required Tim Nicholson 17/05/06 & 21/05/06 Active M Bell Any formwork erected at height to be
(S01, S04, S10(N) & (Jacobs) and construction site. - see above - but addressing containment of carried out wijt lane closures in place or
S10(S) materials by use of netting or similar. area beneath enclosed
S.10 Site splicing of steelwork C TAN Working at height. 3 5 15 Minimise number of splice positions. 2 5 10 Note on drawing - method statement required Tim Nicholson 17/05/06 & 21/05/06 Active M Bell All work at height to be carried out wijt
(S01, S04, S10(N) & (Jacobs) to address handling of heavy components at lane closures in place or area beneath
S10(S) height. enclosed
Review the concept design- Identify significant design risks
Significant Risks “only” identified on Plans and numbered
Significant
Risks
identified
on
Sections &
Elevations
A simple “Architectural Project” Risk Register
CDM - Intelligent Drawing Annotation
Legend to Identify
Risk’s by what’s
annotated on each
Revit Sheet
Go Safely